Construction site tower crane management device and method thereof
By designing a construction site tower crane management device with multi-directional movement and automatic cleaning, the problems of inaccurate monitoring data and cumbersome installation are solved, and the accurate monitoring and efficient management of the tower crane movement trajectory are realized, and construction safety and efficiency are improved.
Patent Information
- Application Number
- CN202411376594.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-30
- Publication Date
- 2024-12-06
AI Technical Summary
The existing construction site tower crane management device is inaccurate in monitoring the tower crane movement trajectory due to fixed positions, and the installation method is cumbersome and needs to be improved.
A management device including mounting plate, transmission assembly, motor, limit block, threaded wheel and disassembly mechanism is designed. Through multi-directional movement and automatic cleaning mechanism, monitoring sensitivity and installation convenience are improved.
Accurate monitoring of the tower crane movement trajectory is achieved, the installation and maintenance process is simplified, the need for manual cleaning is reduced, and the clarity and convenience of the monitor are improved.
Smart Images

Figure CN119079821A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of management devices, and in particular to a construction site tower crane management device and method thereof. Background Art
[0002] The construction site tower crane management device is an integrated intelligent monitoring system. Through real-time monitoring and data analysis of the tower crane's operating status, it can effectively prevent safety accidents, improve construction efficiency, and realize the information and intelligent management of construction sites.
[0003] Currently, in the process of tower crane operation on construction sites, a management device is used to combine with the tower crane for real-time operation data, and then the management device needs to be applied to the monitor and display. However, when the monitor monitors the movement trajectory of the tower crane, it is in a fixed position, which leads to inaccurate detection data during the monitoring process, and the installation method is more cumbersome, so it needs to be improved. Summary of the invention
[0004] The object of the present invention is to provide a construction site tower crane management device and method thereof to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: A construction site tower crane management device comprises a mounting plate, one side of the mounting plate is respectively fixedly connected with a first bearing seat, a first support seat and a second bearing seat, a first screw is rotatably connected between the first bearing seat and the first support seat, one end of the first screw is provided with a transmission assembly, a rotating rod is rotatably connected between the second bearing seat and the first support seat, the first screw and the rotating rod are respectively fixedly connected to the output ends of the first motor and the second motor, a limiting block is fixedly connected to the outer side of the rotating rod, an active threaded wheel is provided on the outer side of the rotating rod, a longitudinal movable seat is threadedly connected to the outer side of the first screw, the top of the longitudinal movable seat is rotatably connected to the second screw, one end of the second screw is fixedly connected with a driven threaded wheel, the outer side of the second screw is threadedly connected to the lateral movable seat, a monitor is provided on one side of the lateral movable seat, a first disassembly and assembly mechanism is provided between the lateral movable seat and the monitor, a guard is provided on the top of the monitor, a second disassembly and assembly mechanism is provided on one side of the guard, and a cleaning mechanism is provided on the top of the guard.
[0006] Preferably, the transmission assembly consists of a driving wheel, a transmission belt and a driven wheel.
[0007] Preferably, the active threaded wheel is engaged and connected with the rotating rod via a limiting block.
[0008] Preferably, the active threaded wheel and the driven threaded wheel are connected by threads.
[0009] Preferably, the first disassembly and assembly mechanism includes an installation box and a bracket, the top of the bracket is fixedly connected to a third motor, one side of the bracket is symmetrically fixedly connected to a socket, the inside of the installation box is rotatably connected to a third screw, the outer side of the third screw is symmetrically threadedly connected to a movable plate, one side of the movable plate is symmetrically rotatably connected to a clamping block, and the bottom of the third screw is fixedly connected to a first knob.
[0010] Preferably, the output end of the third motor is fixedly connected with a monitor, the card block is slidably connected to the installation box via a first rotating shaft, and the card block and the card seat are adapted and snap-fitted.
[0011] Preferably, a fill light is fixedly connected to one side of the bottom of the monitor, and a BIM integration device is included inside the monitor.
[0012] Preferably, the second disassembly and assembly mechanism includes a locking box, a bidirectional screw is rotatably connected inside the locking box, a second knob is fixedly connected to one end of the bidirectional screw, a tightening seat is symmetrically threadedly connected to the outer side of the bidirectional screw, a support rod is provided at one end of the tightening seat, a slider is provided at one end of the support rod, a second rotating shaft is rotatably connected between the tightening seat, the support rod and the slider, and the slider is slidably connected to the inside of the splint.
[0013] Preferably, the cleaning mechanism includes a second rotating shaft, a filter screen is fixedly connected to the top of the water collecting tank, a micro pump body is fixedly connected to one side of the water collecting tank, one end of the micro pump body is fixedly connected to a delivery pipe, one end of the delivery pipe is fixedly connected to a nozzle, and one side of the monitor is symmetrically fixedly connected to a second support seat, and a fourth screw and a positioning rod are respectively rotatably connected between the two second support seats, the fourth screw is fixedly connected to the output end of the fourth motor, and a cleaning brush is threadedly connected to the outer side of the fourth screw.
[0014] A method for using a construction site tower crane management device comprises the following steps:
[0015] Step 1: First, when installing the shield to the top of the monitor, by turning the second knob, the tightening seat, the support rod and the slider push the clamp plate to clamp the outside of the monitor under the scissor-like movement, so that the effect of quick installation can be achieved. Then, the clamping seat provided on one side of the bracket is clamped to the inside of the installation box. By turning the first knob, the clamping block is locked under the movement of the moving plate and the positioning sliding of the first rotating shaft, so as to quickly locate the installation position of the monitor, so that the device can improve the convenience during maintenance by means of quick disassembly and assembly;
[0016] Step 2: During the monitoring of the monitor of the construction site tower crane management device, the monitor can be provided with a steering monitoring function by driving the third motor, and the two first screws can be synchronously rotated under the transmission connection of the transmission assembly by setting the first motor, so that the longitudinal moving seat drives the longitudinal displacement of the outer side of the transverse moving seat, and the second motor is driven to make the rotating rod and the limit block drive the active threaded wheel to rotate. Since the active threaded wheel and the driven threaded wheel are threadedly connected, the second screw is rotated to facilitate the transverse displacement of the outer side of the monitor, and then cooperate with each other in multiple moving modes, which can improve the sensitivity of the device during the monitoring process, so that the movement trajectory of the tower crane can be monitored, thereby improving the accuracy of the information during monitoring;
[0017] Step three: During the long-term use of the tower crane management device on the construction site, the water collecting tank provided in the cleaning mechanism is used to collect rainwater, and the filter provided can isolate debris. Then the rainwater is transported to the nozzle using a micro pump body and a delivery pipe to flush the mirror of the monitor, and by driving the fourth motor, the cleaning brush is raised and lowered under the rotation of the thread of the fourth screw to achieve the wiping effect, thereby improving the clarity of the monitor during monitoring by flushing and wiping at the same time. As a result, the device does not require manual regular cleaning, which improves safety while increasing ease of use.
[0018] The present invention has at least the following beneficial effects:
[0019] 1. When the present invention is in use, the monitor can have the function of steering monitoring by driving the third motor, and the two first screws can be synchronously rotated under the transmission connection of the transmission assembly by the first motor, so that the longitudinal moving seat drives the longitudinal displacement of the outer side of the transverse moving seat, and the second motor is driven to make the rotating rod and the limit block drive the active threaded wheel to rotate. Since the active threaded wheel and the driven threaded wheel are threadedly connected, the second screw is rotated to facilitate the transverse displacement of the outer side of the monitor, and then cooperate with each other in multiple moving modes, which can improve the sensitivity of the device in the monitoring process, so that the movement trajectory of the tower crane can be monitored, thereby improving the accuracy of information during monitoring.
[0020] 2. The present invention sets a first disassembly and assembly mechanism and a second disassembly and assembly mechanism. When the protective cover is installed to the top of the monitor, by turning the second knob, the tightening seat, the support rod and the slider push the clamp plate to be clamped on the outside of the monitor under the scissor-like movement, so that the effect of quick installation can be achieved. Then, the card seat provided on one side of the bracket is engaged with the inside of the installation box. By turning the first knob, the card block is locked under the movement of the moving plate and the positioning sliding of the first rotating shaft, so as to quickly locate the installation position of the monitor, so that the device can improve the convenience during maintenance by means of quick disassembly and assembly.
[0021] 3. The present invention provides a cleaning device, a water collecting tank is provided to collect rainwater, a filter is provided to isolate debris, and then a micro pump body and a delivery pipe are used to deliver rainwater to the nozzle to flush the mirror surface of the monitor, and by driving the fourth motor, the cleaning brush is lifted and moved under the thread rotation of the fourth screw to achieve a wiping effect, thereby improving the clarity of the monitor during monitoring by flushing and wiping at the same time, and the device does not need manual regular cleaning, which improves safety while increasing convenience of use. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the shaft side structure of one side of the present invention;
[0023] Figure 2 It is a schematic diagram of the axial structure of the other side of the present invention;
[0024] Figure 3 It is a schematic diagram of the support structure of the present invention;
[0025] Figure 4 It is a schematic diagram of the card holder structure of the present invention;
[0026] Figure 5 It is a schematic diagram of the structure of the installation box of the present invention;
[0027] Figure 6 It is a schematic diagram of the structure of the monitor of the present invention;
[0028] Figure 7 It is a schematic diagram of the water collecting tank structure of the present invention;
[0029] Figure 8 It is a schematic diagram of the cleaning brush structure of the present invention;
[0030] Fig. 9 It is a schematic diagram of the filter structure of the present invention;
[0031] Fig.10 It is a schematic diagram of the internal structure of the shield of the present invention.
[0032] In the figure: mounting plate 1, first bearing seat 2, first support seat 3, first screw rod 4, transmission assembly 5, first motor 6, second bearing seat 7, rotating rod 8, limit block 9, second motor 10, active threaded wheel 11, longitudinal moving seat 12, second screw rod 13, driven threaded wheel 14, transverse moving seat 15, mounting box 16, third screw rod 17, first knob 18, moving plate 19, block 20, first rotating shaft 21, bracket 22, seat 23, third motor 24, monitor 25, fill light 26, shield 27, locking box 28, bidirectional screw rod 29, second knob 30, tightening seat 31, support rod 32, slider 33, splint 34, second rotating shaft 35, water collecting box 36, filter screen 37, micro pump body 38, delivery pipe 39, nozzle 40, second support seat 41, fourth screw rod 42, positioning rod 43, cleaning brush 44, fourth motor 45. DETAILED DESCRIPTION
[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0034] See also Figure 1-10
[0035] Embodiment 1
[0036] A construction site tower crane management device comprises a mounting plate 1, wherein a first bearing seat 2, a first support seat 3 and a second bearing seat 7 are fixedly connected to one side of the mounting plate 1, a first screw rod 4 is rotatably connected between the first bearing seat 2 and the first support seat 3, a transmission assembly 5 is arranged at one end of the first screw rod 4, a rotating rod 8 is rotatably connected between the second bearing seat 7 and the first support seat 3, the first screw 4 and the rotating rod 8 are respectively fixedly connected to the output ends of the first motor 6 and the second motor 10, a limiting block 9 is fixedly connected to the outer side of the rotating rod 8, an active threaded wheel 11 is arranged on the outer side of the rotating rod 8, a longitudinal moving seat 12 is threadedly connected to the outer side of the first screw rod 4, a second screw rod 13 is rotatably connected to the top of the longitudinal moving seat 12, a driven threaded wheel 14 is fixedly connected to one end of the second screw rod 13, a transverse moving seat 15 is threadedly connected to the outer side of the second screw rod 13, a monitor 25 is arranged on one side of the transverse moving seat 15, and a control system 25 is arranged on the control system 25. The first motor 6 is arranged so that the two first screws 4 can rotate synchronously under the transmission connection of the transmission assembly 5, so that the longitudinal moving seat 12 drives the longitudinal displacement of the outer side of the transverse moving seat 15, and by driving the second motor 10, the rotating rod 8 and the limit block 9 drive the active threaded wheel 11 to rotate. Since the active threaded wheel 11 and the driven threaded wheel 14 are threadedly connected, the second screw 13 is rotated to facilitate the transverse displacement of the outer side of the monitor 25, and then cooperate with each other in multiple moving modes, which can improve the sensitivity of the device during the monitoring process, so that the movement trajectory of the tower crane can be monitored, thereby improving the accuracy of information during monitoring. A first disassembly and assembly mechanism is arranged between the transverse moving seat 15 and the monitor 25, a shield 27 is arranged on the top of the monitor 25, a second disassembly and assembly mechanism is arranged on one side of the shield 27, and a cleaning mechanism is arranged on the top of the shield 27.
[0037] Specific implementation process: the device drives two first screws 4 through the first motor 6, and uses the transmission component 5 to achieve the longitudinal displacement of the longitudinal moving seat 12, thereby driving the transverse moving seat 15 and the monitor 25 thereon to move longitudinally. At the same time, the second motor 10 drives the rotating rod 8 and the limit block 9 to rotate the active threaded wheel 11, and drives the second screw 13 to rotate through the threaded connection to achieve the transverse displacement of the monitor 25, thereby cooperating with multiple movement modes to improve the monitoring sensitivity and ensure the accuracy of the tower crane motion trajectory monitoring. The monitor 25 realizes steering monitoring through the third motor 24, and the bottom fill light 26 enhances the lighting. The internal integrated management device monitors and analyzes the tower crane status in real time, and combines it with the data model to improve the safety and efficiency of the construction site. The first disassembly and assembly mechanism and the second disassembly and assembly mechanism enable the monitor 25 to be quickly Quick positioning and installation, easy maintenance, the cleaning mechanism automatically collects rainwater, and delivers it to the nozzle 40 through the micro pump body 38 and the delivery pipe 39, and cooperates with the wiping of the cleaning brush 44 to keep the monitor 25 clear, without manual cleaning, which improves safety and convenience. Example 2 describes the composition of the transmission component 5, Example 3 describes the composition of the first disassembly and assembly mechanism, Example 4 describes the composition of the second disassembly and assembly mechanism, and Example 5 describes the composition of the cleaning mechanism. The monitor 25 contains a management device inside, which monitors and analyzes the operating status of the tower crane in real time and combines it with the model to improve the safety and efficiency of the construction site. In summary, the device realizes accurate monitoring and efficient management of the tower crane on the construction site through mechanisms such as multi-directional movement, rapid disassembly and assembly, and automatic cleaning, thereby improving construction safety and efficiency.
[0038] A method for using a construction site tower crane management device comprises the following steps:
[0039] Step 1: First, when installing the shield 27 to the top of the monitor 25, by turning the second knob 30, the tightening seat 31, the support rod 32 and the slider 33 move in a scissor-like manner to push the clamping plate 34 to clamp the outer side of the monitor 25, so that the effect of quick installation can be achieved. Then, the clamping seat 23 provided on one side of the bracket 22 is clamped to the inside of the installation box 16, and by turning the first knob 18, the clamping block 20 is locked under the movement of the moving plate 19 and the positioning sliding of the first rotating shaft 21, so as to quickly locate the installation position of the monitor 25, so that the device can be quickly disassembled and assembled to improve the convenience during maintenance;
[0040] Step 2: During the monitoring of the monitor 25 of the construction site tower crane management device, the monitor 25 can be provided with a steering monitoring function by driving the third motor 24, and the two first screws 4 can be synchronously rotated under the transmission connection of the transmission assembly 5 by the first motor 6 provided, so that the longitudinal moving seat 12 drives the longitudinal displacement of the outer side of the transverse moving seat 15, and the second motor 10 is driven to drive the active threaded wheel 11 to rotate by the rotating rod 8 and the limit block 9. Since the active threaded wheel 11 and the driven threaded wheel 14 are threadedly connected, the second screw 13 is rotated to facilitate the transverse displacement of the outer side of the monitor 25, and then cooperate with each other in multiple moving modes, which can improve the sensitivity of the device during the monitoring process, so that the movement trajectory of the tower crane can be monitored, thereby improving the accuracy of the information during monitoring;
[0041] Step three: During the long-term use of the construction site tower crane management device, the water collecting tank 36 provided in the cleaning mechanism is used to collect rainwater, and the filter screen 37 provided can isolate debris, and then the rainwater is transported to the nozzle 40 by the micro pump body 38 and the delivery pipe 39 to flush the mirror surface of the monitor 25, and by driving the fourth motor 45, the cleaning brush 44 is raised and lowered under the threaded rotation of the fourth screw 42 to achieve the wiping effect, so that the clarity of the monitor 25 during the monitoring period can be improved by the method of flushing and wiping at the same time, and the device does not need manual regular cleaning, which improves safety while increasing convenience of use.
[0042] Embodiment 2
[0043] Based on the first embodiment: the transmission assembly 5 is composed of a driving wheel, a transmission belt and a driven wheel, the driving threaded wheel 11 is engaged with the rotating rod 8 through a limit block 9, the driving threaded wheel 11 and the driven threaded wheel 14 are threadedly connected, a fill light 26 is fixedly connected to one side of the bottom of the monitor 25, and the monitor 25 contains a BIM integration device inside, which improves the safety and construction efficiency of the construction site by real-time monitoring and analysis of the operating status of the tower crane and combining it with the BIM model;
[0044] Embodiment 3
[0045] Based on the first embodiment: the first disassembly and assembly mechanism includes an installation box 16 and a bracket 22, the top of the bracket 22 is fixedly connected to a third motor 24, one side of the bracket 22 is symmetrically fixedly connected to a card seat 23, the inside of the installation box 16 is rotatably connected to a third screw rod 17, the outer side of the third screw rod 17 is symmetrically threadedly connected to a moving plate 19, one side of the moving plate 19 is symmetrically rotatably connected to a card block 20, the bottom of the third screw rod 17 is fixedly connected to a first knob 18, the output end of the third motor 24 is fixedly connected to a monitor 25, the card block 20 is slidably connected to the installation box 16 through a first rotating shaft 21, the card block 20 and the card seat 23 are adapted and are snap-fitted, the card seat 23 provided on one side of the bracket 22 is snapped into the inside of the installation box 16, by rotating the first knob 18, the card block 20 is locked under the movement of the moving plate 19 and the positioning slide of the first rotating shaft 21, so as to quickly locate the installation position of the monitor 25, so that the device improves the convenience during maintenance in a quick disassembly and assembly manner;
[0046] Embodiment 4
[0047] Based on Example 1: The second disassembly and assembly mechanism includes a locking box 28, a bidirectional screw 29 is rotatably connected inside the locking box 28, one end of the bidirectional screw 29 is fixedly connected to a second knob 30, the outer side of the bidirectional screw 29 is symmetrically threadedly connected to a tightening seat 31, one end of the tightening seat 31 is provided with a support rod 32, one end of the support rod 32 is provided with a slider 33, a second rotating shaft 35 is rotatably connected between the tightening seat 31, the support rod 32 and the slider 33, the slider 33 is slidably connected to the inside of the clamping plate 34, and by rotating the second knob 30, the tightening seat 31, the support rod 32 and the slider 33 are pushed to clamp the clamping plate 34 on the outside of the monitor 25 under the scissor-like movement, so that the effect of quick installation can be achieved.
[0048] Embodiment 5
[0049] Based on the first embodiment: the cleaning mechanism includes a second rotating shaft 35, a filter screen 37 is fixedly connected to the top of the water collecting tank 36, a micro pump body 38 is fixedly connected to one side of the water collecting tank 36, one end of the micro pump body 38 is fixedly connected to a delivery pipe 39, one end of the delivery pipe 39 is fixedly connected to a nozzle 40, and a second support seat 41 is symmetrically fixedly connected to one side of the monitor 25. A fourth screw 42 and a positioning rod 43 are rotatably connected between the two second support seats 41, and the fourth screw 42 is fixedly connected to the output end of the fourth motor 45. The outer side of the fourth screw 42 is threadedly connected to a cleaning brush 44, and there is The water collecting tank 36 collects rainwater, and the filter screen 37 is provided to isolate debris. Then, the rainwater is transported to the nozzle 40 by means of the micro pump body 38 and the delivery pipe 39 to flush the mirror surface of the monitor 25, and by driving the fourth motor 45, the cleaning brush 44 is lifted and moved under the threaded rotation of the fourth screw 42 to achieve the wiping effect, so that the clarity of the monitor 25 during monitoring can be improved by the method of flushing and wiping at the same time, and the device does not need manual regular cleaning, which improves safety while increasing convenience of use.
[0050] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0051] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction site tower crane management device, comprising a mounting plate (1), characterized in that: One side of the mounting plate (1) is respectively fixedly connected with a first bearing seat (2), a first support seat (3) and a second bearing seat (7); a first screw rod (4) is rotatably connected between the first bearing seat (2) and the first support seat (3); a transmission assembly (5) is provided at one end of the first screw rod (4); a rotating rod (8) is rotatably connected between the second bearing seat (7) and the first support seat (3); the first screw rod (4) and the rotating rod (8) are respectively fixedly connected to the output ends of the first motor (6) and the second motor (10); a limiting block (9) is fixedly connected to the outer side of the rotating rod (8); an active threaded wheel (11) is provided on the outer side of the rotating rod (8); The outer side of the first screw rod (4) is threadedly connected to a longitudinal movable seat (12); the top of the longitudinal movable seat (12) is rotatably connected to a second screw rod (13); one end of the second screw rod (13) is fixedly connected to a driven threaded wheel (14); the outer side of the second screw rod (13) is threadedly connected to a transverse movable seat (15); a monitor (25) is arranged on one side of the transverse movable seat (15); a first disassembly and assembly mechanism is arranged between the transverse movable seat (15) and the monitor (25); a protective cover (27) is arranged on the top of the monitor (25); a second disassembly and assembly mechanism is arranged on one side of the protective cover (27); and a cleaning mechanism is arranged on the top of the protective cover (27).
2. A construction site tower crane management device according to claim 1, characterized in that: The transmission assembly (5) consists of a driving wheel, a transmission belt and a driven wheel.
3. A construction site tower crane management device according to claim 1, characterized in that: The active threaded wheel (11) is snap-connected to the rotating rod (8) via a limiting block (9).
4. A construction site tower crane management device according to claim 1, characterized in that: The active threaded wheel (11) and the driven threaded wheel (14) are connected by threads.
5. A construction site tower crane management device according to claim 1, characterized in that: The first disassembly and assembly mechanism comprises an installation box (16) and a bracket (22); the top of the bracket (22) is fixedly connected to a third motor (24); one side of the bracket (22) is symmetrically fixedly connected to a holder (23); the inside of the installation box (16) is rotatably connected to a third screw rod (17); the outer side of the third screw rod (17) is symmetrically threadedly connected to a movable plate (19); one side of the movable plate (19) is symmetrically rotatably connected to a clamping block (20); and the bottom of the third screw rod (17) is fixedly connected to a first knob (18).
6. A construction site tower crane management device according to claim 5, characterized in that: The output end of the third motor (24) is fixedly connected to a monitor (25); the clamping block (20) is slidably connected to the installation box (16) via a first rotating shaft (21); the clamping block (20) and the clamping seat (23) are matched and are in a snap-fit connection.
7. A construction site tower crane management device according to claim 1, characterized in that: A fill light (26) is fixedly connected to one side of the bottom of the monitor (25), and a BIM integration device is included inside the monitor (25).
8. A construction site tower crane management device according to claim 1, characterized in that: The second disassembly and assembly mechanism comprises a locking box (28), a bidirectional screw (29) is rotatably connected inside the locking box (28), one end of the bidirectional screw (29) is fixedly connected to a second knob (30), the outer side of the bidirectional screw (29) is symmetrically threadedly connected to a tightening seat (31), one end of the tightening seat (31) is provided with a support rod (32), one end of the support rod (32) is provided with a slider (33), a second rotating shaft (35) is rotatably connected between the tightening seat (31), the support rod (32) and the slider (33), and the slider (33) is slidably connected to the inside of the clamping plate (34).
9. A construction site tower crane management device according to claim 1, characterized in that: The cleaning mechanism comprises a second rotating shaft (35), a filter screen (37) fixedly connected to the top of a water collecting tank (36), a micro pump body (38) fixedly connected to one side of the water collecting tank (36), a delivery pipe (39) fixedly connected to one end of the micro pump body (38), a nozzle (40) fixedly connected to one end of the delivery pipe (39), a second support seat (41) symmetrically fixedly connected to one side of the monitor (25), a fourth screw (42) and a positioning rod (43) rotatably connected between the two second support seats (41), the fourth screw (42) fixedly connected to the output end of a fourth motor (45), and a cleaning brush (44) threadedly connected to the outer side of the fourth screw (42).
10. A method for managing a construction site tower crane according to any one of claims 1 to 9, characterized in that: The following steps are involved: Step 1: First, when the protective cover (27) is installed on the top of the monitor (25), the second knob (30) is turned so that the tightening seat (31), the support rod (32) and the slider (33) push the clamping plate (34) to clamp the outer side of the monitor (25) in a scissor-like movement, so that the effect of quick installation can be achieved. Then, the clamping seat (23) provided on one side of the bracket (22) is clamped into the inside of the installation box (16), and the first knob (18) is turned so that the clamping block (20) performs a locking movement under the movement of the moving plate (19) and the positioning sliding of the first rotating shaft (21), so as to quickly locate the installation position of the monitor (25), so that the device can be quickly disassembled and assembled to improve the convenience during maintenance; Step 2: During the monitoring period of the monitor (25) of the construction site tower crane management device, the monitor (25) can be provided with a steering monitoring function by driving the third motor (24), and the two first screws (4) can be synchronously rotated under the transmission connection of the transmission assembly (5) by the first motor (6), so that the longitudinal moving seat (12) drives the longitudinal displacement of the outer side of the transverse moving seat (15), and the second motor (10) is driven to drive the rotating rod (8) and the limit block (9) to drive the active threaded wheel (11) to rotate. Since the active threaded wheel (11) and the driven threaded wheel (14) are threadedly connected, the second screw (13) is rotated to facilitate the transverse displacement of the outer side of the monitor (25), and then cooperate with each other in multiple moving modes, which can improve the sensitivity of the device during the monitoring process, so that the movement trajectory of the tower crane can be monitored, thereby improving the accuracy of the information during monitoring; Step 3: During the long-term use of the construction site tower crane management device, the water collecting tank (36) provided in the cleaning mechanism is used to collect rainwater, and the filter (37) provided can isolate debris. Then, the rainwater is transported to the nozzle (40) by using the micro pump body (38) and the delivery pipe (39) to flush the mirror surface of the monitor (25), and by driving the fourth motor (45), the cleaning brush (44) is lifted and moved under the thread rotation of the fourth screw (42) to achieve the wiping effect, thereby improving the clarity of the monitor (25) during the monitoring period by using the method of flushing and wiping at the same time, and the device does not need to be manually cleaned regularly, which improves safety and increases convenience of use.