Method for pushing steel box girder for expressway
By monitoring the vibration signals of temporary brackets and pushing facilities in real time during the pushing process of steel box girders, the possible safety hazards during the pushing process are solved, and the safety and precise pushing of steel box girders are achieved, and construction safety is improved. Sex and efficiency.
Patent Information
- Application Number
- CN202411458529.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-18
- Publication Date
- 2024-12-06
AI Technical Summary
In highway construction, due to the heavy box body during the pushing process of steel box girders, construction deviations may lead to safety hazards, and it is difficult for the existing technology to effectively monitor and reduce this risk.
A method of over-pushing for steel box girders for highways is adopted. By installing temporary brackets and over-pushing facilities, the vibration signals of temporary brackets and over-pushing facilities are monitored in real time, and at least two vibration sensors are used to detect the process of thrusting, pushing and returning positioning. If the vibration value exceeds the threshold, an early warning signal will be issued and the pushing will be stopped to ensure construction safety.
The safety and precise pushing of steel box girders are achieved, the construction safety and accuracy are improved, the cost is reduced, the occurrence of safety hazards is reduced, and different construction conditions are adapted through dynamic monitoring and specific anti-slip movement measures.
Smart Images

Figure CN119083326A_ABST
Abstract
Description
Technical Field
[0001] This scheme belongs to the field of jacking process technology, and specifically designs a jacking method for steel box girders for highways. Background Art
[0002] In modern highway construction, steel box girders, as an important form of bridge structure, are widely used in large bridge projects across rivers, canyons, roads and other obstacles due to their superior bearing capacity, good torsion resistance and fast construction characteristics. However, due to the large size and weight of steel box girders, traditional hoisting methods have certain limitations in complex construction environments. Therefore, a more efficient and safe construction technology, the steel box girder jacking technology, came into being. This technology sets a jacking device on the abutment or temporary pier to gradually push the steel box girder to the designed position along the preset trajectory, effectively solving the construction problems of bridges with large spans and complex environments, improving construction efficiency and safety, and is of great significance to promoting the development of highway bridge construction technology.
[0003] The invention patent with application number 202211676399.6 discloses a construction method for pushing a steel box girder across an existing highway, which belongs to the field of bridge construction technology; the construction method for pushing a steel box girder across an existing highway includes the steps of manufacturing a steel box girder box body, welding and assembling an integral steel box girder, constructing temporary piers, installing a guide beam, horizontally pushing the steel box girder, and dropping the beam; the construction method for pushing a steel box girder across an existing highway has the advantages of simple process, low cost, high efficiency, safety and reliability, and can effectively solve the problem of difficult construction of steel box girders on highways; whether it is on the main line bridge or the E ramp bridge, the construction method of pushing a steel box girder across an existing highway can improve construction efficiency and significantly reduce construction costs.
[0004] The above technology solves the problem of difficult construction. However, since the box of the top pile is heavy, if the construction deviates, it will cause irreversible consequences. Therefore, a technology is needed to monitor the top pile process and reduce the occurrence of safety hazards. Summary of the invention
[0005] The purpose of this scheme is to provide a method for jacking steel box girders for highways, which can monitor the jacking process and reduce safety hazards.
[0006] In order to achieve the above purpose, this scheme provides a A method for pushing a steel box girder for a highway comprises the following steps: S1: Install temporary supports and jacking facilities according to relevant requirements; S2: Assemble and weld the front steel guide beam and steel beam; S3: Conduct a trial push forward to detect the pressure of the temporary support and the pushing facilities. If the pressure exceeds the threshold, stop and then test; S4: After the test push is correct, push forward to assemble the steel beam and tail beam; check whether the pressure of the temporary support and the push facility exceeds the threshold; S5: Accumulate jacking to the designed mileage; during the jacking process, the steel guide beams and tail beams are dismantled in a distributed manner; after each jacking, the pressure on the temporary support and jacking facilities is checked to see if it exceeds the threshold; S6: Each beam drop height is 40-60mm as one round, and after multiple rounds, the beam is dropped to the designed height; S7: Dismantle the jacking and beam dropping facilities; The temporary support in step S3 is also provided with a vibration signal for detecting the temporary support, and the vibration signal includes P1 and P2, which are respectively from vibration sensors arranged on both sides of the jacking facility in the direction of travel, and the vibration sensors are installed on the temporary support. The data processing module obtains the real-time values of P1 and P2 during the jacking process and the pushing process of the jacking facility in real time, and compares the values of P1 and P2 during the jacking process and the pushing process, and compares the values of P1 during the jacking process and the pushing process, and the values of P2 during the jacking process and the pushing process, and compares the values of P1 during the jacking process and the pushing process, and compares ... return process of the jacking facility. The P1 and P2 values of the entire process are used to determine the upper limit value of vibration Pm. If the P1 or P2 value exceeds Pm in any process of jacking, pushing or returning, an early warning signal will be issued. If early warning signals are issued in the three consecutive processes of jacking, pushing or returning, the jacking work will be stopped and the work will be continued when the P1 and P2 values drop below Pm. If the difference between the values of P1 and P2 exceeds the threshold in any process, the structure of the temporary support will be detected after the current jacking is completed. If an early warning signal is issued in the resetting process, the vibration of the jacking process will be reduced and dropped below Pm, and the jacking work will continue.
[0007] The basic principle and beneficial effects of this scheme: safe and accurate jacking of steel box girders is achieved. The method first installs temporary supports and jacking facilities, then builds a jacking structure by welding guide beams and steel beams, and tests its stability by trial jacking. During the formal jacking process, real-time monitoring and adjustment ensure accurate alignment and synchronization of the structure, while adopting construction process simulation, precise control of jacking equipment, dynamic monitoring and specific anti-slip measures to adapt to different construction conditions. Finally, the beam body is smoothly lowered by dropping the beam in stages, and the facilities are removed after the jacking is in place. This method not only improves construction safety and accuracy, but also improves efficiency and adaptability, reduces costs, and reduces the generation of safety hazards by monitoring the facilities at each jacking completion. Furthermore, before jacking, the jacking process of the curved beam must be simulated, and the jacking construction process control table is set according to the vertex position and jacking step corresponding to each temporary support top and steel beam, and the actual construction of the jacking process is carried out according to the process control table.
[0008] This scheme detects the vibration of the temporary support by setting at least two vibration sensors at the jacking facility, and measures the two vibration signals of the temporary support during the jacking process (lifting the steel box girder), the pushing process (moving the steel box girder as a whole), and the return process (the jacking facility returns to its original position and waits for the next lifting) of the jacking facility, and compares the values of the same detection points in different stages (i.e., the separate comparison of the P1 value in each process and the separate comparison of the P2 value in each process), and the values of the two detection points in the same stage (i.e., the separate comparison of the P1 and P2 values in each stage), because the steel box girder is usually in the process of lifting. It is carried out at high altitude (a certain height from the ground, and the specific height is affected by the construction location), so in addition to the vibration caused by the lifting itself, there may also be vibration caused by the wind. Therefore, the vibration of the temporary support is detected in real time through the two vibration sensors installed on the temporary support. If the vibration value in any process exceeds the maximum limit Pm, it indicates that the vibration of the temporary support exceeds the preset value, that is, it may be dangerous to continue pushing. This may be caused by wind force. If the return process exceeds Pm, but the vibration is reduced in the subsequent pushing process, it means that the weight of the superimposed steel box girder can reduce the vibration value of the temporary support, so the construction can continue. If the difference between the P1 and P2 values at each stage exceeds the threshold, it may be caused by uneven force. Forced construction may cause the overturning of the facility. Therefore, through the vibration detection at two points, the stress condition of the temporary support can also be judged to prevent the problem of uneven force when the pressure is normal, and strictly ensure the safety performance of the construction.
[0009] Furthermore, when debugging and using the jacking equipment, the tolerance value of the position error of the jacking equipment in each direction is set to 5mm, so that the synchronization error of each point is controlled within 5mm.
[0010] Furthermore, it is necessary to conduct real-time dynamic monitoring of the jacking process: the axis is released on the top of the temporary pier, and the penetration synchronization and axis deviation value are measured by hanging a plumb line during the jacking process. When the center line is found to be deviated, it is corrected in time; after each round of jacking of the steel-concrete composite beam, the axis endpoints are measured with a total station to determine whether there is any deviation, and if it occurs, it is corrected in time.
[0011] Furthermore, when the pushing direction is opposite to the longitudinal slope direction, a high-pressure asbestos plate is provided on the contact surface between the movable pad and the steel beam, and the friction coefficient between the steel plates is 0.15.
[0012] Further, the operation steps of beam dropping are as follows: A1: Remove the front and rear guide beams and start the preparation work before dropping the beams. Before pushing the beams into place, reserve 80mm of pushing distance to ensure that they are inside the 160mm expansion joint. Before dropping the beams, make adjustments to the line shape and offset. A2: Lift the jacking equipment until the cushion beam is empty, take a 10cm cushion block, and then drop it to the cushion beam; weld the lifting lug at the bottom of the steel box beam, lift the cushion beam with a hand chain hoist, repeat the cycle twice and take two 10cm cushion blocks; A3: The steel box beam falls on the cushion beam, and the distribution beam on the jack is emptied; weld the lifting lugs at the bottom of the steel box beam, and use the hand chain hoist to lift the jacking equipment and the full-length distribution beam; take the 20cm cushion block under the jacking equipment, and re-weld the cushion platform; the height of the beam drop; A4: Cycle A1-A3 operations, drop the beam into place, measure and correct the deviation every 0.5m, confirm the jacking stroke when it is 5cm away from the support for the last time, correct the deviation, and drop the beam onto the support after the jacking stroke is in place. The system transformation is completed and the beam is dropped.
[0013] Furthermore, the beam is lifted up as a whole, and the reaction force of each support is calculated by the oil pressure of each jacking machine. On this premise, the elevation of each support is uniformly measured, and a height measurement scale is arranged to intuitively judge the synchronization error of each support.
[0014] Furthermore, the pushing facility adopts a walking jack.
[0015] Furthermore, the jacking of the walking jack adopts a first hydraulic cylinder, which includes a hydraulic cylinder wall, a hydraulic space inside the hydraulic cylinder wall, a liquid through hole on the hydraulic cylinder wall, a first push plate slidably connected in the hydraulic space, the first push plate fits the inner wall of the hydraulic cylinder wall, and divides it into two upper and lower spaces, a push shaft is fixedly connected to the first push plate, the push shaft extends out of the upper hydraulic cylinder wall and is slidably connected to the hydraulic cylinder wall, a lifting platform is fixedly connected to the upper end of the push shaft, an air bag is fixedly provided below the first push plate, and a second push plate is fixedly provided at the lower end of the air bag A push plate, a second push plate and a hydraulic cylinder wall are slidably connected, a plurality of second springs are fixed between the second push plate and the first push plate, and the airbag is in an expanded state when the second spring is in an initial state; a first air passage is opened on the push shaft, a second air passage is opened in the pushing platform, the first air passage and the second air passage are connected, the lower end of the first air passage is connected to the airbag, a plurality of air ports are opened on the lifting platform, each air port is connected to the second air port, and an air cap is arranged at each air port, and the air cap is made of rubber material and expands into a suction cup shape when inflated. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A schematic diagram of the steps of a method for pushing a steel box girder for a highway; Figure 2 It is a structural schematic diagram of a walking jack; Figure 3 It is a cross-sectional view of a walking jack; Figure 4 It is a cross-sectional view of the first hydraulic cylinder.
[0017] Description Figure Numbers: Base 1, mounting hole 11, support block 2, track 3, sliding block 4, first hydraulic cylinder 5, hydraulic cylinder wall 51, hydraulic space 52, liquid port 53, second push plate 54, second spring 55, air bag 56, first push plate 57, first air duct 571, second air duct 572, air cap 58, lifting platform 6, slag collecting trough 61, blowing tower 7, first air outlet 71, second air outlet 72, motor 8, screw 81, ball seat 82, push rod 83, push block 84, cylinder 9, first air cavity 91, second air cavity 92.
[0018] The following is further described in detail through specific implementation methods: DETAILED DESCRIPTION Embodiment 1 This solution is applied to the construction of a ring road in a certain city, where the traffic volume is large. According to the actual situation on site, it is not allowed to occupy the road for construction, and it is difficult to set up temporary brackets at the interface and use cranes for lifting, so this solution is used for construction.
[0019] Before formal construction, the following preparations should be completed: (1) According to the site environment, site and construction conditions, determine the work area, material storage area and living area. Ensure the safe entry and placement of construction equipment, materials and construction equipment. According to the site engineering volume and construction progress requirements, the corresponding power supply should be configured. (2) According to the lifting plan, the construction site roads and sites should be leveled and hardened in advance to ensure that the site conditions meet the requirements of transportation vehicles and crane operations. (3) According to the construction requirements, prepare the production of safety assurance facilities, temporary working platforms and safety protection facilities for steel bridge construction. (4) Check whether the number of the shipping section and the marking of the beam section direction meet the requirements, and protect the markings and the on-site butt welds. (5) Formulate rules and regulations such as the job responsibility system, safety system, and power supply system for the construction site.
[0020] After the preparation is completed, follow the steps below to complete the construction: A method for pushing a steel box girder for a highway, as shown in the attached Figure 1 As shown, the following steps are included: S1: Install temporary supports and jacking facilities according to design requirements; the layout of the jacking temporary supports is divided into two parts: one is the temporary supports at the top of the concrete T-beam column, which is arranged on the top of the permanent pier; the other is the jacking temporary supports on both sides of the highway. The layout of the temporary supports in this scheme can be adaptively selected according to the on-site construction conditions.
[0021] S2: Assemble and weld 20-25m front steel guide beams and 38-43m steel beams; in the top-pushing construction of the bridge, the length of the guide beam has an important influence on the span of the top-pushing. The various parameters of the guide beam have a great influence on the force of the main beam during the construction process. Appropriate selection of the various parameter values of the guide beam can reduce the internal force of the main beam during the construction process, thereby saving materials and reducing construction costs. In this scheme, the guide beam and the tail beam are composed of two pieces of I-shaped solid web steel plate main beams with equal height. The longitudinal length of the guide beam is 23.7m, the length of the tail beam is 10m, and the height corresponds to the webs on both sides of the steel box beam. In order to facilitate transportation and assembly, the guide beam is provided with a transverse connection composed of steel pipes and an upper and lower plane connection between the two main beams to form the entire guide beam as a whole. The root of the guide beam is reliably connected to the steel box beam, and the connection of the high-strength bolts of the guide beam is regularly checked. The requirements for steel guide beams are as follows: (1) After the guide beam modification is completed, the butt welds of the steel guide beams shall be non-destructively tested before leaving the factory and a report shall be issued; (2) The steel guide beams shall be assembled after the single-segment hoisting on the ground. (3) The guide beams and steel box beams shall be connected with equal strength by butt welds, and the butt weld grade shall be Grade 1; the web plates of the guide beams shall be connected by φ24 high-strength bolts, and the upper and lower flange plates shall be welded; the connection system and the guide beam segments shall be connected by φ16 high-strength bolts. (4) The guide beam is an important structure for top-pushing construction. The processing of the guide beams and the inspection and acceptance of the welds shall be strictly carried out in accordance with the "Steel Structure Welding Code" (GB 50661-2011), "Steel Structure Engineering Construction Code" (GB 50755-2012) and "Steel Structure Engineering Construction Quality Acceptance Standard" (GB 50205-2020). The guide beam weld should be cooled to ambient temperature before appearance inspection can be carried out. Non-destructive testing should be carried out after the appearance inspection is qualified. The specific inspection time and requirements should comply with the provisions of the current national standard "Steel Structure Welding Code" (GB 50661-2011).
[0022] S3: Push forward about 2-3 meters for trial pushing, and detect the pressure of temporary supports and pushing facilities. If the threshold is exceeded, stop and then test; This scheme adopts the adaptive multi-point walking pushing process of steel-concrete composite beam nodes. During the pushing process, each jack realizes the functions of synchronization on both sides, multi-point synchronization, single-point single movement and inching limit through the hydraulic pump station and computer automatic control system. The maximum speed of this pushing technology can reach 4m / h. Due to the use of multi-point pushing, the temporary support is subjected to small horizontal force during the pushing process. In theory, it can achieve pushing without horizontal force. The pushing process is stable, the linear shape is adjustable, the equipment is measurable and controllable, and an intelligent monitoring and detection system has been developed. Before pushing, the construction process of the curved beam must be simulated, and the pushing construction process control table is set according to the vertex position and pushing step corresponding to each temporary support top and steel beam, and the actual construction of the pushing process is carried out according to the process control table.
[0023] During the jacking process, each pump station is connected to two 300t jacks. The equipment and the cushion beam are fixed with limit plates around them. In this scheme, the steel box girder is assembled twice on the concrete deck of the bridge with large pile numbers, and then pushed to the small pile numbers after the assembly is completed.
[0024] The jacking process of this scheme: The jacking adopts the adaptive multi-point synchronous walking jacking process. During the jacking process, each jack realizes the functions of two-side synchronization, multi-point synchronization, single-point single movement and inching limit through the hydraulic pump station and computer automatic control system. The jacking device is installed on the top of each temporary support pier.
[0025] The jacking device is composed of a walking jack, a hydraulic pump station, a computer control system, etc.
[0026] (1) Walking push mechanical system The horizontal thrust force of a single jack of the walking jack is 60t, and the stroke is 530mm; The vertical lifting force is 300t and the lifting stroke is 130mm; The thrust of the lateral deviation correcting jack is 30t and the stroke is 100mm.
[0027] The mechanical system of the crawler jacking equipment mainly includes an upper sliding seat structure, a lifting support cylinder, a longitudinal jacking cylinder, a lateral adjustment cylinder, and a base. It is intelligently pushed through computer control and hydraulic drive to meet construction requirements.
[0028] The equipment uses four steps of "lifting", "pushing", "lowering" and "retracting" alternately. First, the steel box girder is lifted up as a whole; then the jacking and translation cylinder is pushed forward a stroke; then the steel box girder is lowered as a whole and placed on the vertical supporting structure; the jacking and translation cylinder is retracted to the bottom to complete a jacking stroke; and the next cycle is continued, through reciprocating jacking steps, the steel box girder is finally pushed to the designed position.
[0029] The push mechanism structure is installed on the longitudinal beam of the steel pipe column pier. When sliding, the entire walking push device remains stationary relative to the temporary pier. The sliding surface of the walking push device adopts a stainless steel plate and the MGE slide plate contact surface. The sliding surface parameters can be found in the sliding surface introduction of the transverse mechanical system.
[0030] The whole set of equipment has high adjustment accuracy and can well meet the control requirements of load and deformation; it is fully hydraulically driven, with small size and light weight, smooth pushing process, complete hydraulic protection measures and high safety.
[0031] The upper and lower parts of the jacking equipment are moved in the direction of the bridge through the oil cylinder. The thrust is the internal force of the equipment itself, which overcomes the horizontal thrust on the temporary piers caused by other methods of jacking. Through the control of the hydraulic system, it can automatically adapt to the deformation of the jacking main bridge, making the jacking safer and more reliable. The hydraulic pump station is the power source of the walking jacking and provides power for the actuator jack. The hydraulic pump station uses an electric motor as the power to drive the plunger pump to provide pressure oil for the system, and forms basic circuits such as pressure and flow with hydraulic components such as overflow valves and electromagnetic reversing valves. The hydraulic power output by the pump station is used to drive the jack to extend or retract the jack, thereby realizing the translation, jacking and other actions of the walking jacking.
[0032] The system consists of six identical but independent circuit systems, each of which controls a jack. Each circuit has an independent pump head oil port to output hydraulic oil, and an independent hydraulic valve and related hydraulic components to control the pressure and flow direction of the hydraulic oil. They form a single circuit without interfering with each other, simplifying the hydraulic circuit and making it easier to control.
[0033] Working principle: The motor drives a plunger pump to provide pressure oil for the system. The hydraulic oil output from each oil port of the plunger pump enters the electromagnetic reversing valve after passing through the one-way valve. The flow direction of the pressure oil is controlled by the switching of the electromagnetic reversing valve slide valve, thereby determining the extension or retraction of the jack. A hydraulic control one-way valve is set between the reversing valve and the jack to maintain pressure. The maximum pressure of the system is set by the overflow valve, and the pressure can be displayed by the pressure gauge. The control system adopts a distributed computer network control system, which consists of 1 main console, several field controllers, several sensors, several data lines and control lines. The control system of this project is planned to use 1 main console to control 5 pump stations and 10 walking jacking devices, and matching sensors. Each walking jacking device consists of 1-2 vertical jacking tops, 1 horizontal jacking top and 2 deviation correction tops, and corresponding displacement and pressure sensors. The main control computer can remotely control each field controller, display the oil pressure and displacement of each jack top; and display the jacking distance on both sides of each pier. The system has data saving and fault alarm functions, and it will automatically shut down when the preset travel or load limit is reached. The main console adopts the method of industrial computer + configuration software. It can remotely control each field controller, display the oil pressure and displacement of each jack; set the maximum travel and maximum pressure of the jack; the system can easily allow users to remotely start and stop the pump station, pressure and control the pump station to complete various actions. In the online state, all operations are completed by the main control computer, and the field controller only performs emergency stop operations. When the field controller switches to the "on-site" state, the field wireless handle controls each pier separately, and the main console can monitor various sensor data on site. The system has data saving and fault alarm functions, and it will automatically shut down when the preset travel or load limit is reached.
[0034] Since different levels of system management permissions are implemented in the software, operators can choose different operation modes, view trend curves and reports, etc. System engineers can modify the software according to actual conditions. Operators with permissions can operate any jack and pump station individually or online in the central control room.
[0035] Synchronous control of the longitudinal horizontal push control system: The control strategy of longitudinal horizontal jacking is mainly based on displacement control, supplemented by jacking force. The displacement is monitored by displacement sensors, and the longitudinal horizontal jacking on the same pier is synchronously controlled: the 1# jack is the active point and comparison benchmark (the cylinder extension speed is constant), and the 2# jack is the follower point and compared with the 1# jack. When the stroke of the 2# jack is greater than the 1# jack (the longitudinal horizontal displacement difference is set to 3mm), the flow rate of the jack is reduced. Otherwise, the corresponding flow rate is increased. The synchronous displacement requirement of the longitudinal horizontal jacking on both sides of the same pier is ≤5㎜.
[0036] Synchronous control of longitudinal horizontal jacking on different piers: 1# jack is the active point and comparison benchmark, and the jacks of other piers are compared with it. When the difference in displacement of the jacks of each pier exceeds the set value (longitudinal horizontal jacking displacement 3MM), the corresponding flow rate is reduced or increased. The synchronous requirement for longitudinal horizontal jacking displacement of each pier is ≤5MM.
[0037] The vertical jacking control strategy is a synchronous control with pressure control as the main control and displacement control as the auxiliary control.
[0038] The vertical jacking pushes the main beam away from the cushion beam, and when retracting, the main beam is lowered back to the cushion beam to maintain synchronization. Each jacking device has 2 sets of displacement sensors. The same pier is based on one side. The displacement sensor is installed between the slideway and the cushion beam to detect the jacking height. The synchronization accuracy of the vertical jacking process is controlled within 5MM.
[0039] Each jacking device (two vertical jacking jacks) is equipped with four pressure transmitters. The computer can monitor the load changes at each stress point and accurately coordinate the load distribution of the entire system. The maximum pressure at each stress point and the maximum pressure difference between stress points on the same pier can be set through the on-site controller and the main console. When the load reaches the set value, the system will automatically shut down and alarm.
[0040] The control core uses PLC to collect sensor data, perform logical operations, and output control signals to achieve coordinated control of the hydraulic jacks. The human-computer interaction uses an industrial touch screen to monitor the actions of each jack, set control parameters, and record data information in real time.
[0041] The main console has three operating modes: automatic, manual and adjustment.
[0042] S4: After the test push is correct, push forward 15-25 meters, corresponding to the assembly of 14-24 meter steel beams and 10 meter tail beams; check whether the pressure of temporary supports and push facilities exceeds the threshold; S5: Accumulate jacking to the designed mileage; during the jacking process, the steel guide beam and tail beam are dismantled in a distributed manner; after each jacking, the temporary support and jacking facilities are tested to see if the pressure exceeds the threshold; S6: Each beam drop height is 40-60mm as one round, and after multiple rounds, the beam is dropped to the designed height; S7: Dismantle the jacking and beam dropping facilities.
[0043] When the pushing direction is opposite to the longitudinal slope direction, a high-pressure asbestos plate is set on the contact surface between the movable pad and the steel beam, and the friction coefficient between the steel plates is 0.15.
[0044] After pushing to the designed position, the height of the beam is 4700mm. The beam-dropping and pushing equipment is arranged on the DL3 DL4# pushing bracket. The beam is dropped in an integral manner, and the beam is dropped 10cm each time. The operation steps of the beam drop are as follows: A1: Remove the front and rear guide beams and start the preparation work before dropping the beams. Before pushing the beams into place, reserve 80mm of pushing distance to ensure that they are inside the 160mm expansion joint. Before dropping the beams, adjust the line shape and offset. The drop height of the beams is 4700mm. A2: Use the jacking equipment to lift the cushion beam until it is empty, take a 10cm cushion block, and then drop it to the cushion beam; weld the lifting lugs at the bottom of the steel box beam, lift the cushion beam with a hand chain hoist, repeat the cycle twice and take two 10cm cushion blocks; the beam drop height is 4500mm; A3: The steel box beam falls on the cushion beam, and the distribution beam on the jack is emptied; the lifting lug is welded at the bottom of the steel box beam, and the hand chain hoist lifts the jacking equipment and the full-length distribution beam; the 20cm cushion block under the jacking equipment is taken out, and the cushion platform is re-welded; the beam drop height is 4500mm; A4: Cycle A1-A3 operations, drop the beam into place, measure and correct the deviation every 0.5m, confirm the jacking stroke when it is 5cm away from the support for the last time, correct the deviation, and drop the beam onto the support after the jacking stroke is in place. The system transformation is completed and the beam is dropped.
[0045] Lift the beam as a whole, and calculate the reaction force of each support through the oil pressure of each jacking machine. On this premise, measure the elevation of each support uniformly, and arrange a height measurement scale to intuitively judge the synchronization error of each support.
[0046] Preparation before beam drop Lift the beam as a whole, and calculate the reaction force of each support point through the oil pressure of each jacking machine. Under this premise, the elevation of each support point is uniformly measured, and a height measurement scale is arranged to intuitively judge the synchronization error of each support point.
[0047] Check the jacking machine and hydraulic system to ensure they are intact and reliable. Prepare the beam support piers.
[0048] Verify whether the communication and command system is intact, unify communication signals, unify operating procedures and practice them to familiarize yourself with them.
[0049] Embodiment 2 A walking jack according to an embodiment of the present invention is as shown in the attached Figure 2-3 As shown, it includes a base 1: the base 1 is detachably connected to the temporary support; a plurality of mounting holes 11 are provided on the surface of the base 1, and these mounting holes 11 enable the base 1 to be connected to the temporary support by bolts. Four mounting holes 11 are evenly distributed on the front and back of the base 1.
[0050] Support blocks 2: There are two support blocks 2, which are relatively arranged on the base 1 and fixedly connected to the upper surface of the base 1; the support blocks 2 are vertically arranged to provide support for the subsequent installation of the rails 3.
[0051] Track 3: There are two tracks 3, which are fixedly connected to the support block 2; the connection method is threaded connection.
[0052] Sliding blocks 4: There are two sliding blocks 4, which are respectively arranged on two rails 3 and form a sliding connection with the rails 3; the cooperation between the sliding blocks 4 and the rails 3 makes sliding convenient.
[0053] First hydraulic cylinder 5: A first hydraulic cylinder 5 is installed on the upper surface of each sliding block 4, and the fixed end of the first hydraulic cylinder 5 is fixed to the upper surface of the sliding block 4; in this solution, there are four first hydraulic cylinders 5, two of which are provided on each track 3. The number of sliding blocks 4 matches that of first hydraulic cylinders 5.
[0054] Lifting platform 6: The bottom of the lifting platform 6 is fixedly connected to the free end of the first hydraulic cylinder 5; the lifting platform 6 is composed of two pieces, and a slag collecting tank 61 is provided between the two lifting platforms 6. The two lifting platforms 6 are fixedly connected to form a whole and can move together.
[0055] Reciprocating mechanism: This mechanism is used to push the lifting platform 6 to reciprocate along the track 3; the reciprocating mechanism is arranged on the side of the base 1, and its free end is located between the two tracks 3 and parallel to the track 3; the reciprocating mechanism adopts a ball screw 81 structure, including a motor 8, a screw 81 and a ball seat 82, the motor 8 is installed on one side of the base 1, the output shaft of the motor 8 is coaxial with the symmetry axis between the tracks 3, the screw 81 is coaxially fixed with the output shaft and parallel to the track 3; the ball seat 82 is slidably connected to the screw 81, and its upper part is fixedly connected to the lower part of the lifting platform 6.
[0056] Blowing tower 7: installed at a position of the base 1 close to the reciprocating mechanism. When the reciprocating mechanism pushes the lifting platform 6 to move toward the fixed end, the blowing tower 7 blows air in the direction of the lifting platform 6.
[0057] Cylinder 9: fixed on the base 1, with a push block 84 slidably connected inside, and a push rod 83 fixedly connected to the push block 84, the other end of the push rod 83 extends out of the cylinder 9 and is slidably connected to the cylinder 9, and the extended push rod 83 is parallel to the lead screw 81; the ball seat 82 is fixed to the bottom of the lifting platform 6 and the push rod 83 respectively; one side of the cylinder 9 is connected to the blowing tower 7. The inside of the cylinder 9 is divided into two air cavities with different diameters, the first air cavity 91 close to the push rod 83 has a smaller diameter than the second air cavity 92, and the push block 84 cooperates with the first air cavity 91; it also includes a spacer, which is arranged at the junction of the two air cavities and is slidably connected to the second air cavity 92, and a first spring is fixed between the inner wall of the second air cavity 92 and the spacer, and the blowing tower 7 is provided with two air outlets, the first air outlet 71 is vertically upward, and the second air outlet 72 is toward the lifting platform 6; the first air cavity 91 is connected to the first air outlet 71, and the second air cavity 92 is connected to the second air outlet 72. The second air outlet 72 is tilted downward, and its height is higher than the lowest position of the lifting platform 6 lifted by the first hydraulic cylinder 5 .
[0058] The reciprocating mechanism drags the lifting platform 6 back and forth on a horizontal path. When it returns to the starting position, all the first hydraulic cylinders 5 are lifted to the bottom of the steel box girder and contact it, and then lifted synchronously to make the steel box girder suspended in the air, and then the reciprocating mechanism is driven to move linearly to the far end. Under the action of the reciprocating mechanism, the steel box girder is synchronously translated to the target area for a certain distance. Then the first hydraulic cylinder 5 descends, and the steel box girder is supported by the temporary support. The lifting platform 6 descends to the lowest position and is then dragged back to its original position in the direction of the reciprocating mechanism. During this process, the blowing tower 7 blows air in the direction of the lifting platform 6 to cool down the surface of the lifting platform 6 and the exposed reciprocating mechanism, the first hydraulic cylinder 5, etc.; during the reciprocating lifting process, the movement of the steel box girder is completed. In addition to cooling by blowing air, the blowing tower 7 can also blow off the impurities that fall from the steel box beam to the top of the lifting platform 6 when the lifting platform 6 leaves from under the steel box beam, to prevent the hard impurities from being compressed and damaging the surface of the lifting platform 6 when lifting again, and the hard impurities from being stuck between the lifting platform 6 and the steel box beam, which may cause dislocation during lifting, resulting in uneven force on the jack, damage to the jack, and may also cause the steel box beam to shift in position, unable to achieve the predetermined travel target, and even cause safety hazards during the lifting process. Through the blowing process, the equipment can be cooled down, impurities can be removed, and safety hazards can be reduced.
[0059] Embodiment 3 The difference between the third embodiment and the second embodiment is that: Figure 4As shown, the first hydraulic cylinder 5 includes a hydraulic cylinder wall 51, and the hydraulic cylinder wall 51 has a hydraulic space 52. The hydraulic cylinder wall 51 is provided with a liquid passage 53. A first push plate 57 is slidably connected to the hydraulic space 52. The first push plate 57 is in contact with the inner wall of the hydraulic cylinder wall 51, dividing it into two upper and lower spaces. A push shaft is fixedly connected to the first push plate 57, and the push shaft extends out of the upper hydraulic cylinder wall 51 and is slidably connected to the hydraulic cylinder wall 51. The upper end of the push shaft is fixedly connected to the lifting platform 6. The lifting platform 6 and the push shaft in this solution are integrally formed; an air bag 56 is fixed below the first push plate 57, and a second push plate 54 is fixed at the lower end of the air bag 56. The second push plate 54 and the hydraulic The cylinder wall 51 is slidably connected, and a plurality of second springs 55 are fixed between the second push plate 54 and the first push plate 57. When the second spring 55 is in the initial state, the airbag 56 is in an expanded state; a first air channel 571 is opened on the push shaft, and a second air channel 572 is opened in the pushing platform. The first air channel 571 and the second air channel 572 are connected, and the lower end of the first air channel 571 is connected to the airbag 56. A plurality of air ports are opened on the lifting platform 6, each of which is connected to the second air channel 572, and an air cap 58 is provided at each air port. The air cap 58 is made of rubber and expands into a suction cup shape (i.e., a circle with the center not expanding and the surroundings expanding) when inflated.
[0060] During lifting, hydraulic pressure enters from the liquid port 53, squeezing the second push plate 54, which moves upward and compresses the second spring 55. At this time, the airbag 56 is in a partially compressed state, and part of the gas is squeezed to the gas cap 58, so that the gas cap 58 expands into a suction cup shape. During the lifting process of the lifting platform 6 contacting and lifting the steel box beam, the second spring 55 between the second push plate 54 and the first push plate 57 is in an extreme compression state, and all the gas in the airbag 56 is transferred to the gas cap 58. During the lifting process of the steel box beam, the suction cup-shaped gas cap 58 will fix the steel box beam and prevent the steel box beam from slipping during the translation process, thereby ensuring the safety of construction.
[0061] Embodiment 4 The fourth embodiment is different from the above embodiment in that: the temporary support in step S3 is also provided with a vibration signal for detecting the temporary support, the vibration signal includes P1 and P2, which are respectively from vibration sensors arranged on both sides of the travel direction of the jacking facility, and the vibration sensors are installed on the temporary support, and the data processing module obtains the real-time values of P1 and P2 in the jacking process and the pushing process of the jacking facility in real time, and compares the values of P1 and P2 in the jacking process and the pushing process, and compares the values of P1 in the jacking process and the pushing process, and the values of P2 in the jacking process and the pushing process, and By comparing the P1 and P2 values of the jacking facility during the return process, the upper limit of vibration Pm is determined. If the P1 or P2 value exceeds Pm during any of the jacking, pushing or returning processes, a warning signal is issued. If warning signals are issued during the three consecutive processes of jacking, pushing or returning, the jacking work is stopped and the work is continued when the P1 and P2 values drop below Pm. If the difference between the values of P1 and P2 exceeds the threshold during any process, the structure of the temporary support is inspected after the current jacking is completed. If a warning signal is issued during the resetting process, the vibration of the jacking process is reduced and drops below Pm, and the jacking work is continued.
[0062] This scheme detects the vibration of the temporary support by setting at least two vibration sensors at the jacking facility, and measures the two vibration signals of the temporary support during the jacking process (lifting the steel box girder), the pushing process (moving the steel box girder as a whole), and the return process (the jacking facility returns to its original position and waits for the next lifting) of the jacking facility, and compares the values of the same detection points in different stages (i.e., the separate comparison of the P1 value in each process and the separate comparison of the P2 value in each process), and the values of the two detection points in the same stage (i.e., the separate comparison of the P1 and P2 values in each stage), because the steel box girder is usually in the process of lifting. It is carried out at high altitude (a certain height from the ground, and the specific height is affected by the construction location), so in addition to the vibration caused by the lifting itself, there may also be vibration caused by the wind. Therefore, the vibration of the temporary support is detected in real time through the two vibration sensors installed on the temporary support. If the vibration value in any process exceeds the maximum limit Pm, it indicates that the vibration of the temporary support exceeds the preset value, that is, it may be dangerous to continue pushing. This may be caused by wind force. If the return process exceeds Pm, but the vibration is reduced in the subsequent pushing process, it means that the weight of the superimposed steel box girder can reduce the vibration value of the temporary support, so the construction can continue. If the difference between the P1 and P2 values at each stage exceeds the threshold, it may be caused by uneven force. Forced construction may cause the overturning of the facility. Therefore, through the vibration detection at two points, the stress condition of the temporary support can also be judged to prevent the problem of uneven force when the pressure is normal, and strictly ensure the safety performance of the construction.
[0063] The above is only an embodiment of the present invention, and the common knowledge such as the known specific structure and characteristics in the scheme is not described in detail here. It should be pointed out that for those skilled in the art, several deformations and improvements can be made without departing from the structure of the present invention, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims
1. A method for pushing a steel box girder for a highway, characterized in that: The following steps are involved: S1: Install temporary supports and jacking facilities according to relevant requirements; S2: Assemble and weld the front steel guide beam and steel beam; S3: Conduct a trial push forward to detect the pressure of the temporary support and the pushing facilities. If the pressure exceeds the threshold, stop and then test; S4: After the test push is correct, push forward to assemble the steel beam and tail beam; check whether the pressure of the temporary support and the push facility exceeds the threshold; S5: Accumulate jacking to the designed mileage; during the jacking process, the steel guide beams and tail beams are dismantled in a distributed manner; after each jacking, the pressure on the temporary support and jacking facilities is checked to see if it exceeds the threshold; S6: Each beam drop height is 40-60mm as one round, and after multiple rounds, the beam is dropped to the designed height; S7: Dismantle the jacking and beam dropping facilities; Among them, the temporary support in step S3 is also provided with a vibration signal for detecting the temporary support, and the vibration signal includes P1 and P2, which are respectively from vibration sensors arranged on both sides of the travel direction of the jacking facility, and the vibration sensors are installed on the temporary support. The data processing module obtains the real-time values of P1 and P2 in the jacking process and the pushing process of the jacking facility in real time, and compares the values of P1 and P2 in the jacking process and the pushing process, and compares the P1 value in the jacking process and the pushing process, the P2 value in the jacking process and the pushing process, and compares the return of the jacking facility The P1 and P2 values of the process are used to determine the upper limit of vibration Pm. If the P1 or P2 value exceeds Pm in any process of jacking, pushing or returning, an early warning signal will be issued. If early warning signals are issued in the three consecutive processes of jacking, pushing or returning, the jacking work will be stopped and the work will be continued when the P1 and P2 values drop below Pm. If the difference between the values of P1 and P2 in any process exceeds the threshold, the structure of the temporary support will be detected after the current jacking is completed. If an early warning signal is issued in the resetting process, the vibration of the jacking process will be reduced and dropped below Pm, and the jacking work will continue.
2. A method for pushing a steel box girder for a highway according to claim 1, characterized in that: Before jacking, the construction process of the curved beam jacking must be simulated, and a jacking construction process control table must be set up according to the vertex position and jacking step distance corresponding to each temporary support top and steel beam, and the actual construction of the jacking process must be carried out according to the process control table.
3. A method for pushing a steel box girder for a highway according to claim 2, characterized in that: When debugging and using the jacking equipment, set the tolerance value of the position error of the jacking equipment in each direction to 5mm, so that the synchronization error of each point is controlled within 5mm.
4. The method for pushing a steel box girder for a highway according to claim 1, characterized in that: It is also necessary to carry out real-time dynamic monitoring of the jacking process: release the axis on the top of the temporary pier, and use the method of hanging plumb line to measure the synchronization of the advancement and the axis deviation value during the jacking process; when the center line is found to be deviated, correct it in time; after each round of jacking of the steel-concrete composite beam, use a total station to measure the axis end points to determine whether deviation occurs, and correct it in time if it occurs.
5. The method for pushing a steel box girder for a highway according to claim 1, characterized in that: When the pushing direction is opposite to the longitudinal slope direction, a high-pressure asbestos plate is set on the contact surface between the movable pad and the steel beam, and the friction coefficient between the steel plates is 0.
15.
6. The method for pushing a steel box girder for a highway according to claim 1, characterized in that: The steps of beam dropping are as follows: A1: Remove the front and rear guide beams and start the preparation work before dropping the beams. Before pushing the beams into place, reserve 80mm of pushing distance to ensure that they are inside the 160mm expansion joint. Before dropping the beams, make adjustments to the line shape and offset. A2: Lift the jacking equipment until the cushion beam is empty, take a 10cm cushion block, and then drop it to the cushion beam; weld the lifting lug at the bottom of the steel box beam, lift the cushion beam with a hand chain hoist, repeat the cycle twice and take two 10cm cushion blocks; A3: The steel box beam falls on the cushion beam, and the distribution beam on the jack is emptied; weld the lifting lugs at the bottom of the steel box beam, and use the hand chain hoist to lift the jacking equipment and the full-length distribution beam; take the 20cm cushion block under the jacking equipment, and re-weld the cushion platform; the height of the beam drop; A4: Cycle A1-A3 operations, drop the beam into place, measure and correct the deviation every 0.5m, confirm the jacking stroke when it is 5cm away from the support for the last time, correct the deviation, and drop the beam onto the support after the jacking stroke is in place. The system transformation is completed and the beam is dropped.
7. A method for pushing a steel box girder for a highway according to claim 6, characterized in that: Lift the beam as a whole, and calculate the reaction force of each support through the oil pressure of each jacking machine. On this premise, measure the elevation of each support uniformly, and arrange a height measurement scale to intuitively judge the synchronization error of each support.
8. The method for pushing a steel box girder for a highway according to claim 1, characterized in that: The jacking facility adopts a walking jack.
9. A method for pushing a steel box girder for a highway according to claim 8, characterized in that: The lifting of the walking jack adopts a first hydraulic cylinder, the first hydraulic cylinder includes a hydraulic cylinder wall, the hydraulic cylinder wall has a hydraulic space, the hydraulic cylinder wall has a liquid passage, a first push plate is slidably connected to the hydraulic space, the first push plate is in contact with the inner wall of the hydraulic cylinder wall, and it is divided into two upper and lower spaces, a push shaft is fixedly connected to the first push plate, the push shaft extends out of the hydraulic cylinder wall above and is slidably connected to the hydraulic cylinder wall, the upper end of the push shaft is fixedly connected to a lifting platform, an air bag is fixed below the first push plate, a second push plate is fixed at the lower end of the air bag, the second push plate and the hydraulic cylinder wall are slidably connected, a number of second springs are fixed between the second push plate and the first push plate, and the air bag is in an expanded state when the second spring is in an initial state; a first air channel is opened on the push shaft, a second air channel is opened in the lifting platform, the first air channel and the second air channel are connected, the lower end of the first air channel is connected to the air bag, a number of air ports are opened on the lifting platform, each air port is connected to the second air channel, and an air cap is arranged at each air port, the air cap is made of rubber material and expands into a suction cup shape when inflated.