Separating device for beam-column joint concrete pouring

By designing the partitioning devices of side frames, partition plates and positioning frames in the concrete pouring of beam and column nodes, and using water flow to push the push blocks and sealing plates, the problem of insufficient stability of the existing partitioning devices is solved, and more stable Separate effect and uniform concrete pouring.

CN119083728APending Publication Date: 2024-12-06CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411453077.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-17
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing beam-column node concrete pouring partitioning devices have insufficient installation stability, easy to move, and slurry leakage is easily generated during the pouring process, resulting in poor separation effect.

Method used

A partition device including side frame, partition plate, upper positioning frame and lower positioning frame is designed. Through structures such as clamping plate, locking bolts, flow guide cavity and docking tube, water flow pushing the push block and The closure plate enables stable installation and separation to prevent slippage and leakage.

Benefits of technology

Effectively improve the installation stability and separation effect of the partition device, avoid the displacement of the device during casting, and seal the gap between the beam formwork and the partition plate through the sealing plate and the avoidance groove, ensuring uniform pouring of concrete .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083728A_ABST
    Figure CN119083728A_ABST
Patent Text Reader

Abstract

The invention discloses a separation device for beam-column joint concrete pouring, and relates to the technical field of building construction, the separation device comprises a side frame, the inner wall of the side frame is connected with a separation plate in a clamping manner, the top of the side frame is provided with an upper positioning frame, and the bottom of the side frame is connected with a lower positioning frame in a clamping manner; two butt joint seats are rotationally connected to one side of the lower positioning frame, butt joint insertion pipes are fixedly connected to the two sides of the bottom of the side frame, and the bottoms of the two butt joint insertion pipes are connected with the two butt joint seats in a clamped mode respectively; through installation limiting of two positions of the upper positioning frame and the lower positioning frame, stable installation of the whole separation device is achieved, clamping plates and friction gaskets at the bottoms of locking bolts are used for friction with a beam mold, the upper positioning frame is prevented from sliding, and an abutting-pushing block is pushed to be pressed downwards and ejected out to make contact with the bottom face of the inner wall of the beam mold through structures such as a flow guide cavity and an abutting-joint insertion pipe; the motion resistance of the lower positioning frame is improved, and the position stability of the lower positioning frame is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, in particular to a partition device for pouring concrete at a beam-column node. Background Art

[0002] In cast-in-place reinforced concrete frame structures, sometimes the design concrete strength grades of frame beams and frame columns are different. In this case, the concrete strength grade of the column is generally higher than that of the beam, which is in line with the design concept of "strong column and weak beam" in structural seismic design. This also brings up a problem, namely the concrete pouring problem in the core area of ​​the beam-column joint.

[0003] The core area of ​​the beam-column joint is part of both the column and the beam, and its concrete strength grade should be determined according to the higher of the beam and column. According to the national standard "Concrete Structure Engineering Construction Code", when the design strength of column and wall concrete is two grades or more higher than that of beam and slab concrete, separation measures should be taken at the junction area;

[0004] In this case, after the reinforcement is tied, a wire mesh plate is used to separate the core area of ​​the node at the low-strength beam and slab positions around the core area of ​​the node. First, pour high-strength concrete in the core area of ​​the node. Before the concrete in the core area of ​​the node begins to set, remove the wire mesh plate and then pour low-strength concrete in the surrounding beams and slabs.

[0005] However, in this separation method, the wire mesh plate used as a separation device has insufficient installation stability and is very likely to shift during the subsequent pouring and cement vibration process. In addition, due to the gaps between the wire mesh plate and the beam mold, leakage is likely to occur during the pouring process, resulting in a poor separation effect. Therefore, it is necessary to propose improvements. Summary of the invention

[0006] The object of the present invention is to provide a partition device for pouring concrete at a beam-column joint, so as to solve the problem that the partition device of the prior art proposed in the above background technology has insufficient installation stability and is prone to displacement.

[0007] To achieve the above object, the present invention provides the following technical solutions:

[0008] A partition device for pouring concrete at a beam-column node comprises a side frame, the inner wall of the side frame is snap-connected with a partition plate, an upper positioning frame is arranged on the top of the side frame, a lower positioning frame is snap-connected with the bottom of the side frame, clamping plates are fixedly connected to both sides of the bottom of the upper positioning frame, locking bolts are threadedly connected to both sides of the top of the upper positioning frame, and friction pads are fixedly connected to the bottoms of the two locking bolts;

[0009] One side of the lower positioning frame is rotatably connected to two docking seats, and docking plugs are fixedly connected to both sides of the bottom of the side frame. The bottoms of the two docking plugs are respectively engaged with the two docking seats, and a docking cavity is opened in the middle of the docking seat. A guide cavity is opened inside the side frame, and the bottoms of the two guide cavities are respectively connected to the two docking plugs, and the tops of the two guide cavities are fixedly connected to water inlet pipes;

[0010] A push groove is provided on one side of the bottom of the lower positioning frame, a push block is slidably connected to the inner wall of the push groove, and the top of the push groove is connected to the docking cavity through a connecting pipe.

[0011] As a further solution of the present invention: a plurality of sliding grooves are provided at the edge of the partition plate, the inner walls of the plurality of sliding grooves are slidably connected with a closing plate, a closing pad is fixedly connected to the edge of the closing plate, and an avoidance groove is provided on one side of the closing plate.

[0012] As a further solution of the present invention: extension parts are fixedly connected to both sides of the partition plate, a snap-in groove is provided on the side of the side frame away from the lower positioning frame, the extension part is snap-connected with the snap-in groove, a through opening is provided in the middle of the extension part, the through opening is connected with the guide cavity, a conducting pipe is fixedly connected to one side of the through opening, and one end of the conducting pipe is fixedly connected to one side of several snap-in grooves.

[0013] As a further solution of the present invention: the bottom of the upper positioning frame is fixedly connected to a mounting frame, both sides of the inner wall of the mounting frame are rotatably connected with mounting bolts, both sides of the top of the side frame are provided with threaded holes, and one end of the two mounting bolts are respectively threadedly connected to the two threaded holes.

[0014] As a further solution of the present invention: a baffle is fixedly connected to the middle of the mounting frame.

[0015] As a further solution of the present invention: the top of the upper positioning frame is fixedly connected to a diversion water tank, the top of the water inlet pipe is connected to the diversion water tank, both ends of the diversion water tank are fixedly connected to a return pipe, and a regulating valve is fixedly installed in the middle of the return pipe.

[0016] As a further solution of the present invention: a sprinkler pipe is fixedly connected to the middle of one side of the diversion water tank, a plurality of sprinkler holes are opened on both sides of the sprinkler pipe, and a control valve is fixedly installed in the middle of the sprinkler pipe.

[0017] As a further solution of the present invention: the push groove is inclined toward a side away from the side frame, and a friction pad is fixedly connected to the bottom of the push groove.

[0018] As a further solution of the present invention: both ends of the lower positioning frame are threadedly connected with clamping bolts, and one end of the two clamping bolts is respectively in tight contact with one side of the two docking seats.

[0019] As a further solution of the present invention: the installation and use method of the partition device comprises the following steps:

[0020] Step 1: Place the lower positioning frame into the bottom of the beam mold cavity;

[0021] Step 2: Insert the side frames from both sides of the beam mold and respectively plug and engage the two docking pipes with the two docking seats;

[0022] Step 3: Push the upper positioning frame to move until the bottom surface of the upper positioning frame is stably fitted with the top surface of the beam mold, then turn and tighten the mounting bolts to fix the side frame to the upper positioning frame, and then tighten the locking bolts to increase the sliding resistance of the upper positioning frame;

[0023] Step 4: Place the partition plate into the side frame and engage the extension part with the snap-in groove;

[0024] Step 5: Slide each closing plate so that each avoidance groove is aligned with the steel bar position;

[0025] Step six: Fill the diversion water tank with water through the return pipe, and then send water into the diversion cavity through the water inlet pipe. Part of the water flow is sent into the card-jointing groove through the diversion of the conducting pipe to push the closing plate out, thereby realizing the tight limit of the closing plate and the separation of the beam mold; part of the water flow is sent into the connecting pipe through the docking pipe, and then enters the push groove to push the push block out to realize the limit fixation of the lower positioning frame and improve the position stability of the lower positioning frame, thereby completing the installation operation of the separation device.

[0026] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention realizes the stable installation of the partition device as a whole through the installation limit of the upper positioning frame and the lower positioning frame, and utilizes the friction gasket at the bottom of the clamping plate and the locking bolt to rub against the beam mold to prevent the upper positioning frame from sliding, thereby improving the installation stability of the upper positioning frame; utilizes the structure such as the diversion cavity and the docking plug to guide the water flow into the push groove, and pushes the push block downward to contact with the bottom surface of the inner wall of the beam mold, thereby increasing the contact pressure between the side of the lower positioning frame away from the docking seat and the beam mold, thereby increasing the movement resistance of the lower positioning frame, ensuring the stable position of the lower positioning frame, thereby effectively avoiding the displacement of the partition device during the pouring process;

[0027] The present invention realizes separation of the beam mold by setting a partition plate, and blocks and seals the gap between the partition edge and the beam mold by a closing plate slidably set on the partition plate; and avoidance grooves aligned with the position of the steel bars are provided on one side of the closing plate to avoid the steel bars and block and seal the gap between the partition plate and the beam mold. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a schematic diagram of the installation position of the partition device of the present invention;

[0029] Figure 2 It is a schematic structural diagram of the side frame of the present invention;

[0030] Figure 3 It is a schematic diagram of the docking position of the side frame and the lower positioning frame of the present invention;

[0031] Figure 4 is a cross-sectional view of a closing plate of the present invention;

[0032] Figure 5 The present invention is a flowchart of the method for installing and using the separation device.

[0033] In the figure: 1. upper positioning frame; 2. side frame; 3. partition plate; 4. closing plate; 5. avoidance groove; 6. water inlet pipe; 7. docking pipe; 8. lower positioning frame; 9. docking seat; 10. push groove; 11. push block; 12. diversion cavity; 13. conduction pipe; 14. sliding groove; 15. diversion water tank; 16. return pipe; 17. sprinkler pipe; 18. locking bolt; 19. mounting frame; 20. baffle; 21. beam form; 22. column form. DETAILED DESCRIPTION

[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] See also Figure 1-Figure 5 In the embodiment of the present invention, a partition device for pouring concrete at a beam-column node includes a side frame 2, and the inner wall of the side frame 2 is snap-connected with a partition plate 3. During installation, the side frame 2 is located on the outside of the steel cage, and the partition plate 3 is located inside the steel cage, and is used to play a major role in partitioning. The edge of the side frame 2 is arranged in affixed relation to both sides of the inner wall of the beam mold 21, and the top of the side frame 2 is fixedly connected with an upper positioning frame 1, and the fixed connection method is as follows: a mounting frame 19 is fixedly connected to the bottom of the upper positioning frame 1, and both sides of the inner wall of the mounting frame 19 are rotatably connected with mounting bolts, and both sides of the top of the side frame 2 are provided with threaded holes, and one end of the two mounting bolts are respectively threadedly connected with the two threaded holes; in the transportation stage before installation, the mounting bolts connect the mounting frame 19 to the threaded holes, but do not lock them, so as to maintain the connection between the upper positioning frame 1 and the side frame 2, and facilitate the overall handling and movement;

[0036] In order to reduce the gap between the bottom of the mounting frame 19 and the partition plate 3, a baffle 20 is fixedly connected to the middle of the mounting frame 19. The baffle 20 is tilted, and the inclination angle between the baffle 20 and the ground of the beam mold 21 is between 30 degrees and 60 degrees.

[0037] In order to ensure the stable combination and installation of the upper positioning frame 1 and the beam mold 21, the bottom of the side frame 2 is connected with the lower positioning frame 8, and the bottom two sides of the upper positioning frame 1 are fixedly connected with clamping plates, and the distance between the two clamping plates is consistent with the width of the beam mold 21. The friction between the clamping plates and the outer walls of the beam mold 21 on both sides is used to prevent the upper positioning frame 1 from sliding; in order to further improve the installation stability of the upper positioning frame 1, the top two sides of the upper positioning frame 1 are threadedly connected with locking bolts 18, and the bottoms of the two locking bolts 18 are fixedly connected with friction pads;

[0038] See also Figure 3 In order to improve the installation stability of the lower positioning frame 8, one side of the lower positioning frame 8 is rotatably connected to two docking seats 9, and docking plugs 7 are fixedly connected to both sides of the bottom of the side frame 2. The bottoms of the two docking plugs 7 are respectively engaged with the two docking seats 9. A docking cavity is opened in the middle of the docking seat 9, and a guide cavity 12 is opened inside the side frame 2. The bottoms of the two guide cavities 12 are respectively connected to the two docking plugs 7, and the tops of the two guide cavities 12 are fixedly connected to the water inlet pipes 6; the lower positioning frame 8 A push groove 10 is provided on one side of the bottom, and a push block 11 is slidably connected to the inner wall of the push groove 10, and the top of the push groove 10 is connected to the docking cavity through a connecting pipe; the water flow is guided into the push groove 10 by means of the flow guide cavity 12 and the docking plug 7 and other structures, and the push block 11 is pushed down and pushed out to contact the bottom surface of the inner wall of the beam mold 21, thereby increasing the contact pressure between the side of the lower positioning frame 8 away from the docking seat 9 and the beam mold 21, thereby increasing the movement resistance of the lower positioning frame 8, and ensuring the position stability of the lower positioning frame 8;

[0039] In order to change the pushing direction of the push block 11 and improve the push effect of the push block 11 , the push groove 10 is inclined toward the side away from the side frame 2 , and a friction pad is fixedly connected to the bottom of the push groove 10 .

[0040] In order to prevent the docking seat 9 from rotating freely during use, causing the side frame 2 and the entire device to shake and shift, both ends of the lower positioning frame 8 are threadedly connected with clamping bolts, and one end of the two clamping bolts is respectively in tight contact with one side of the two docking seats 9.

[0041] See also Figure 2A plurality of sliding grooves 14 are provided at the edge of the partition plate 3, and the inner walls of the plurality of sliding grooves 14 are slidably connected with closing plates 4, and the gap between the partition edge and the beam mold 21 is blocked and blocked by the sliding closing plates 4; in order to improve the blocking effect, a closing pad is fixedly connected to the edge of the closing plate 4, and the closing pad is made of a flexible material. An avoidance groove 5 is provided on one side of the closing plate 4, and the position of the avoidance groove 5 is aligned with the position of the steel bar, thereby achieving avoidance of the steel bar.

[0042] In order to facilitate the installation of the partition plate 3 and the side frame 2, the two sides of the partition plate 3 are fixedly connected with extension parts, and a clamping groove is provided on the side of the side frame 2 away from the lower positioning frame 8, and the extension part is clamped and connected with the clamping groove. When the partition plate 3 is poured, the impact and extrusion force of the concrete will press against the partition plate 3, making the connection contact between the partition plate 3 and the side frame 2 more stable;

[0043] See also Figure 4 In order to achieve access to the water flow, a through opening is opened in the middle of the extension part, which is connected to the diversion cavity 12. A conducting pipe 13 is fixedly connected to one side of the through opening, and one end of the conducting pipe 13 is fixedly connected to one side of several clamping grooves.

[0044] See also Figure 1 In order to achieve water access to the entire device, a diversion water tank 15 is fixedly connected to the top of the upper positioning frame 1, and the top of the water inlet pipe 6 is connected to the diversion water tank 15. Both ends of the diversion water tank 15 are fixedly connected to a return pipe 16, and a regulating valve is fixedly installed in the middle of the return pipe 16. In the specific implementation, in order to facilitate the layout of the water inlet pipe 6, multiple beam-column nodes located around the same column can adopt multiple separation devices provided by the present application. The diversion water tanks 15 on each separation device are connected through the return pipe 16, so that a local linkage pipeline, and then only one external water inlet pipeline is needed to meet the use needs of multiple beam-column nodes around the same column.

[0045] To facilitate subsequent maintenance construction, a sprinkler pipe 17 is fixedly connected to the middle part of one side of the diversion water tank 15. A number of sprinkler holes are opened on both sides of the sprinkler pipe 17. A control valve is fixedly installed in the middle of the sprinkler pipe 17. When maintenance of the beams and columns is required, water is sent out from the sprinkler holes by opening the control valve.

[0046] The present invention completes the support installation of the column form 22 and the beam form 21 before installation. For the installation and use method of the present invention, please refer to Figure 5 First, install the lower positioning frame 8. According to the installation angle of the partition device required in advance, first rotate and adjust the installation angle corresponding to the docking seat 9, then rotate the clamping bolt to lock the docking seat 9, and then put the lower positioning frame 8 into the bottom of the inner cavity of the beam mold 21, and adjust the lower positioning frame 8 to make it fit stably with the beam mold 21;

[0047] Insert the side frame 2 from both sides of the beam mold 21 and plug and engage the two docking pipes 7 with the two docking seats 9 respectively; then push the upper positioning frame 1 to move until the bottom surface of the upper positioning frame 1 is stably fitted with the edge of the top surface of the beam mold 21, then turn and tighten the mounting bolts to fix the side frame 2 to the upper positioning frame 1, and then tighten the locking bolts 18 to increase the sliding resistance of the upper positioning frame 1; put the partition plate 3 into the side frame 2, and engage the extension part with the clamping groove; slide each closing plate 4 so that each avoidance groove 5 is aligned with the position of the steel bar;

[0048] The external water pump injects water into the diversion water tank 15 through the return pipe 16, and then the water is sent into the diversion cavity 12 through the water inlet pipe 6. Part of the water in the diversion cavity 12 is sent into the clamping groove through the conducting pipe 13 to push the closing plate 4 out, so as to achieve the tight position limit of the closing plate 4 and the separation of the beam mold 21; the other part of the water flow is sent into the docking cavity through the docking plug 7, and then sent into the push groove 10 through the connecting pipe to push the push block 11 out, so as to achieve the limit fixation of the lower positioning frame 8 and improve the position stability of the lower positioning frame 8, thereby completing the installation operation of the separation device;

[0049] Then, the pouring operation is carried out. After the pouring is completed, before the concrete in the core area of ​​the node is initially set, the device is dismantled. The specific disassembly method is to open the control valve to discharge the water flow in the device to release the pressure, push the closing plate 4, separate the avoidance groove 5 from the steel bar, and then loosen the installation bolts and locking bolts 18, slide and pull the side frame 2, so that the docking plug 7 is separated from the docking seat 9, and the partition plate 3 is out of contact with the concrete in the core area of ​​the node, and then remove the partition plate 3 first, then pull out the side frame 2 as a whole, and finally remove the lower positioning frame 8;

[0050] After the device is dismantled, the mounting bolts can be rotated to completely separate the side frame 2 from the upper positioning frame 1, and the upper positioning frame 1 and the diverter water tank 15 and the pipeline part thereon are retained, so as to facilitate water extraction during subsequent maintenance and other construction.

[0051] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still fall within the scope of the technical solution of the present invention.

Claims

1. A separation device for pouring concrete at a beam-column joint, characterized in that: It comprises a side frame (2), the inner wall of the side frame (2) is snap-connected with a partition plate (3), the top of the side frame (2) is provided with an upper positioning frame (1), and the bottom of the side frame (2) is snap-connected with a lower positioning frame (8); One side of the lower positioning frame (8) is rotatably connected to two docking seats (9); both sides of the bottom of the side frame (2) are fixedly connected to docking pipes (7); the bottoms of the two docking pipes (7) are respectively engaged with the two docking seats (9); a docking cavity is provided in the middle of the docking seat (9); a flow guide cavity (12) is provided inside the side frame (2); the tops of the two flow guide cavities (12) are fixedly connected to water inlet pipes (6); one side of the bottom of the lower positioning frame (8) is provided with a push groove (10); the inner wall of the push groove (10) is slidably connected to a push block (11); the top of the push groove (10) is connected to the docking cavity through a connecting pipe.

2. A beam-column joint concrete pouring separation device according to claim 1, characterized in that: The edge of the partition plate (3) is provided with a plurality of sliding grooves (14), the inner walls of the plurality of sliding grooves (14) are slidably connected to a closing plate (4), the edge of the closing plate (4) is fixedly connected to a closing pad, and a side of the closing plate (4) is provided with an avoidance groove (5).

3. A beam-column joint concrete pouring separator according to claim 2, characterized in that: Both sides of the partition plate (3) are fixedly connected with extension parts, one side of the side frame (2) is provided with a snap-in groove, the extension part is snap-connected with the snap-in groove, a through opening is provided in the middle of the extension part, the through opening is communicated with the guide cavity (12), one side of the through opening is fixedly connected with a conducting pipe (13), and one end of the conducting pipe (13) is fixedly connected with one side of a plurality of snap-in grooves.

4. A beam-column joint concrete pouring separator according to claim 1, characterized in that: The bottom of the upper positioning frame (1) is fixedly connected to a mounting frame (19), and mounting bolts are rotatably connected to both sides of the inner wall of the mounting frame (19). Threaded holes are provided on both sides of the top of the side frame (2), and one end of the two mounting bolts are respectively threadedly connected to the two threaded holes; a baffle (20) is fixedly connected to the middle of the mounting frame (19).

5. A beam-column joint concrete pouring separator according to claim 1, characterized in that: Clamping plates are fixedly connected to both sides of the bottom of the upper positioning frame (1), locking bolts (18) are threadedly connected to both sides of the top of the upper positioning frame (1), and friction pads are fixedly connected to the bottoms of the two locking bolts (18).

6. A beam-column joint concrete pouring separator according to claim 1, characterized in that: The push groove (10) is arranged to be inclined toward a side away from the side frame (2), and a friction pad is fixedly connected to the bottom of the push groove (10).

7. A beam-column joint concrete pouring separator according to claim 1, characterized in that: Both ends of the lower positioning frame (8) are threadedly connected with clamping bolts, and one end of the two clamping bolts is respectively in tight contact with one side of the two docking seats (9).

8. A beam-column joint concrete pouring partition device according to claim 1, characterized in that: The top of the upper positioning frame (1) is fixedly connected to a diversion water tank (15), the top of the water inlet pipe (6) is in communication with the diversion water tank (15), both ends of the diversion water tank (15) are fixedly connected to a return pipe (16), and a regulating valve is fixedly installed in the middle of the return pipe (16).

9. A beam-column joint concrete pouring partition device according to claim 8, characterized in that: A watering pipe (17) is fixedly connected to the middle of one side of the diversion water tank (15), a plurality of watering holes are opened on both sides of the watering pipe (17), and a control valve is fixedly installed in the middle of the watering pipe (17).

10. A separation device for pouring concrete at a beam-column joint according to any one of claims 1 to 6, characterized in that: The installation and use method of the partition device comprises the following steps: Step 1: Place the lower positioning frame (8) into the bottom of the inner cavity of the beam mold (21); Step 2: insert the side frame (2) from both sides of the beam mold (21), and plug and engage the docking plug (7) with the docking seat (9); Step 3: Push the upper positioning frame (1) so that its bottom surface fits the top surface of the beam mold (21), then turn and tighten the mounting bolts to fix the side frame (2) to the upper positioning frame (1), and then tighten the locking bolts (18); Step 4: Place the partition plate (3) into the side frame (2), and engage the extension portion with the engaging groove; Step 5: Slide each closing plate (4) so ​​that each avoidance groove (5) is aligned with the position of the steel bar; Step 6: Fill the diversion water tank (15) with water through the return pipe (16), push the closing plate (4) and the push block (11) out, limit and fix the closing plate (4) and the lower positioning frame (8), and complete the installation of the partition device.