Quick positioning and fixing device and method for prefabricated prestressed beam and frame column with column cap
By using fast positioning and fixing devices for components such as columns, column caps, and force beams in construction, and using electric push rods to drive lifting mechanisms and clamps to position the force beams, the construction process in the prior art and the formwork is not fixed in a firm manner. Problem, efficient and rapid fixation and stable forming of prefabricated prestressed beams and frame columns are achieved.
Patent Information
- Application Number
- CN202411460098.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-18
- Publication Date
- 2024-12-06
AI Technical Summary
In the existing construction technology, the connection process between prefabricated prestressed beams and frame columns is complicated, the formwork is difficult to fix and is not firm, and the molding effect is poor, especially in the lifting environment of large-span factory buildings.
Using a quick positioning and fixing device including columns, column caps, force beams, positioning holes, fixing frames, limit frames, clamps and electric push rods, the lifting mechanism and clamps are driven by the electric push rod to position and fix the force beams to ensure concrete Stability and firmness during pouring.
The rapid positioning and fixation of prefabricated prestressed beams and column-capped frame columns is achieved, the construction efficiency is improved, the stability and firmness of concrete forming is ensured, the installation and disassembly process is simplified, and the complexity of traditional formwork fixation is avoided. Instability.
Smart Images

Figure CN119083749A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a device and method for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap. Background Art
[0002] Prefabricated prestressed beam components of large-span factories are very heavy and are generally hoisted on the floor by cranes, which greatly restricts the hoisting environment. When connecting existing beams and frame columns, most of them are first connected with steel bars, and then prefabricated formwork is used to cast concrete on concrete beams and concrete frame columns. In addition, the frame columns are equipped with column caps, resulting in a large variable cross-section, which is quite different from the cross-section of prestressed beams. In addition, the traditional construction process is to cast concrete by splicing wooden formworks and fixing them with tension screws. This process reinforcement method is cumbersome, and the formwork is difficult to fix, the inclined tension is not firm, and the forming effect is not good. Summary of the invention
[0003] The purpose of the present invention is to solve the problems in the prior art of pouring concrete by splicing wooden formworks and fixing them with tension screws. This process reinforcement method is cumbersome, the formwork is difficult to fix, the diagonal tension is not firm, and the forming effect is not good. A quick positioning and fixing device and method for prefabricated prestressed beams and frame columns with column caps are proposed.
[0004] In order to achieve the above object, the present invention adopts the following technical solutions:
[0005] A quick positioning and fixing device for prefabricated prestressed beams and frame columns with column caps, comprising a plurality of columns, column caps arranged at the tops of the columns and a plurality of force beams, wherein the corresponding four force beams are arranged at the tops of the column caps, four groups of positioning columns are fixedly arranged at the tops of the column caps, positioning holes used in conjunction with the positioning columns are provided at the bottoms of the force beams, a fixing frame and a limiting frame are sequentially sleeved on the outer walls of the column caps, and a positioning groove for positioning the force beams is provided on the outer walls of the limiting frames;
[0006] Four groups of first clamping plates, which are respectively arranged around the limiting frame and used for clamping and fixing the force beam;
[0007] A fixing mechanism, arranged on the fixing frame, for clamping the fixing frame on the column cap;
[0008] A lifting mechanism is provided on the fixed frame to drive the limit frame to move up and down, can be used in conjunction with the first clamping plate to clamp the force beam during the lifting process, and can also be used in conjunction with the fixing mechanism to clamp the fixed frame on the column cap;
[0009] An electric push rod is arranged on one side of the fixed frame and is used to provide power for the lifting mechanism.
[0010] In a possible design, the lifting mechanism includes a rectangular hole opened on the outside of the fixed frame, four inner screw sleeves are rotatably provided through the top of the fixed frame, the bottom ends of the inner screw sleeves respectively extend into the corresponding rectangular holes, the inner wall of the inner screw sleeve is threaded with a stud, the top of the stud is fixed with a first fixed block, and the first fixed block is fixed on the outside of the limit frame.
[0011] In a possible design, a fixing plate corresponding to the first clamping plate is fixedly provided on the top of the fixing frame, at least two first guide rods are slidably provided through one side of the fixing plate, one end of the two first guide rods are fixedly connected to the corresponding first clamping plate, a rotating seat is fixedly provided on one side of the first clamping plate, a connecting rod is rotatably provided on one side of the rotating seat, and the other end of the connecting rod is rotatably provided on the outside of the limit frame.
[0012] In a possible design, the outer wall fixing sleeve of the inner screw sleeve is provided with a synchronous wheel, the outer walls of the four synchronous wheels are transmission-connected with the same double-sided synchronous belt, a connecting block is fixedly provided on one side of the double-sided synchronous belt, and the output end of the electric push rod is fixedly connected to the connecting block.
[0013] In a possible design, two guide wheels are rotatably provided on the top wall of the rectangular hole. The two guide wheels are respectively located on both sides of the synchronous wheel to increase the wrap angle between the double-sided synchronous belt and the synchronous wheel.
[0014] In a possible design, a receiving groove is provided on the outer wall of the fixing frame, and the double-sided synchronous belt is located in the receiving groove to protect the double-sided synchronous belt.
[0015] In a possible design, the fixing mechanism includes two second fixing blocks fixedly arranged on the inner walls on both sides of the rectangular hole, a second guide rod is slidably provided through one side of the second fixing block, the same second clamping plate is fixedly arranged at one end of the two second guide rods, a protrusion is fixedly arranged on one side of the second clamping plate, the outer wall of the stud is provided with a conical portion and a transition portion used in conjunction with the protrusion, for driving the second clamping plate to approach the column cap, the outer wall of the second guide rod is provided with a spring, and the two ends of the spring are respectively fixedly connected to the outer wall of the second guide rod and one side of the second fixing block.
[0016] A method for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap comprises the following steps:
[0017] S1. First, pre-fix the column on the ground and install the column cap on the column. Then, put the fixing frame on the column cap and start the electric push rod to drive the second clamping plate to move and clamp the column cap.
[0018] S2. Then, position the force beam on the two column caps and make the force beam located in the positioning groove;
[0019] S3, secondly, start the electric push rod again to drive the limit frame to move upward until the bottom of the positioning groove contacts the force beam, and at the same time, the two first clamping plates on the same side can be driven to move closer to each other to clamp and fix the force beam;
[0020] S4. Finally, pour concrete in the limit frame until the concrete solidifies, and then remove the fixing frame from the column cap.
[0021] In the present application, first, the column is pre-fixed on the ground, and the column cap is installed on the column, and then the fixing frame is put on the column cap, and the electric push rod is started to drive the connecting block to move, and the movement of the connecting block can drive the double-sided synchronous belt to move in the storage groove, and at the same time, it can drive the synchronous wheel to rotate, and the rotation of the synchronous wheel can drive the inner screw sleeve to rotate, and the rotation of the inner screw sleeve can drive the stud to move upward, and the upward movement of the stud can drive the limit frame to move upward, and when the conical part contacts the convex block, it can drive the convex block to move, so as to drive the second clamping plate to move to clamp the column cap, until the transition part cooperates with the convex block to maintain the clamping state;
[0022] Then, position the force beam on the column cap, and make the force beam be located in the positioning groove and the positioning column be inserted into the positioning hole;
[0023] Secondly, the electric push rod is started again to drive the limit frame to move upward until the bottom of the positioning groove contacts the force beam. When the limit frame moves, it can drive one end of the connecting rod to move upward and rotate, and can drive the first clamping plate to move through the rotating seat, so that the two first clamping plates on the same side are close to each other to clamp and fix the force beam;
[0024] Finally, pour concrete in the limit frame until the concrete solidifies, and then start the electric push rod to reset. During the resetting process, the limit frame can be driven to move downward through the studs. At the same time, when the studs move downward, the protrusions can move to the tapered portion. At this time, the second clamping plate can be reset and moved under the action of the spring. At this time, the fixed frame is removed from the column cap, and then the fixation between the ground and the column is released, and the entire frame is lifted to the final installation position by a crane.
[0025] In the present invention, the prefabricated prestressed beam and the frame column with column cap quick positioning and fixing device can drive the second clamping plate to approach each other and clamp the fixing frame on the column cap by starting the electric push rod, without the need to use additional bolts for fixing, so that it is easy to install and disassemble, and the installation efficiency can be improved;
[0026] In the present invention, the prefabricated prestressed beam and the frame column with column cap quick positioning and fixing device can drive the limit frame to move upward by starting the electric push rod, so that the force beam can be further positioned after it is moved into place, and during the movement, the first clamping plate on the same side can be driven to clamp the force beam, so that the fixation is more firm, and the force beam will not move during the pouring process;
[0027] In the present invention, the prefabricated prestressed beam and the frame column with column cap quick positioning and fixing device, by opening a positioning groove corresponding to the force beam on the outer side of the limit frame, can be used as a template after the force beam is positioned, without the need for additional support of the template for pouring, and is more convenient to use.
[0028] In the present invention, by starting the electric push rod, not only the fixing frame can be fixed on the column cap, but also the force beam can be further fixed on the column cap, so that the force beam and the column cap will not move during the pouring process, and can be quickly disassembled and assembled, which is more convenient to use than traditional prefabricated formwork. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 A schematic diagram of the three-dimensional structure of the device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap proposed by the present invention;
[0030] Figure 2 A schematic diagram of the column cap and force beam positioning structure of the prefabricated prestressed beam and the frame column with column cap quick positioning and fixing device proposed by the present invention;
[0031] Figure 3 A schematic diagram of the three-dimensional structure of a fixing frame of a device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap proposed by the present invention;
[0032] Figure 4 A schematic diagram of the local structure of a fixing frame of a device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap proposed by the present invention;
[0033] Figure 5 This is a schematic diagram of the first clamping plate connection structure of the device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap proposed by the present invention;
[0034] Figure 6 A schematic diagram of the second clamping plate connection structure of the prefabricated prestressed beam and the frame column with column cap quick positioning and fixing device proposed by the present invention;
[0035] Figure 7 This is a schematic diagram of the stud structure of the device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap proposed by the present invention.
[0036] In the figure: 1. column; 2. force beam; 3. fixing frame; 4. limiting frame; 5. first clamping plate; 6. column cap; 7. positioning column; 8. positioning hole; 9. fixing plate; 10. rotating seat; 11. first guide rod; 12. connecting rod; 13. positioning groove; 14. first fixing block; 15. stud; 16. connecting block; 17. electric push rod; 18. inner screw sleeve; 19. synchronous wheel; 20. guide wheel; 21. double-sided synchronous belt; 22. rectangular hole; 23. second fixing block; 24. second guide rod; 25. spring; 26. second clamping plate; 27. protrusion; 28. tapered part; 29. transition part; 30. storage groove. DETAILED DESCRIPTION
[0037] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0038] Example 1
[0039] Reference Figure 1-Figure 7 , a quick positioning and fixing device for prefabricated prestressed beams and frame columns with column caps, which is used in the field of building construction, comprises: a plurality of columns 1, column caps 6 arranged at the tops of the columns 1, and a plurality of force beams 2, wherein the corresponding four force beams 2 are all arranged at the tops of the column caps 6, four groups of positioning columns 7 are fixedly arranged at the tops of the column caps 6, positioning holes 8 used in conjunction with the positioning columns 7 are opened at the bottoms of the force beams 2, a fixing frame 3 and a limiting frame 4 are sequentially sleeved on the outer walls of the column caps 6, and a positioning groove 13 for positioning the force beams 2 is opened on the outer walls of the limiting frame 4;
[0040] Four groups of first clamping plates 5, which are respectively arranged around the limiting frame 4 and are used to clamp and fix the force beam 2;
[0041] A fixing mechanism, provided on the fixing frame 3, for clamping the fixing frame 3 on the column cap 6;
[0042] The lifting mechanism is arranged on the fixed frame 3 to drive the limit frame 4 to move up and down, and can be used in conjunction with the first clamping plate 5 to clamp the force beam 2 during the lifting process, and can also be used in conjunction with the fixing mechanism to clamp the fixed frame 3 on the column cap 6;
[0043] The electric push rod 17 is arranged on one side of the fixed frame 3 and is used to provide power for the lifting mechanism. By starting the electric push rod 17, the lifting mechanism can be driven to move upward. During the movement, the limit frame 4 can be driven to contact the bottom of the force beam 2, and the first clamping plate 5 can be driven to clamp the force beam 2, so that the force beam 2 can be quickly fixed on the column cap 6, so that it will not move during the pouring process.
[0044] The lifting mechanism includes a rectangular hole 22 opened on the outside of the fixed frame 3, four inner screw sleeves 18 are rotatably provided on the top of the fixed frame 3, and the bottom ends of the inner screw sleeves 18 extend into the corresponding rectangular holes 22 respectively. The inner wall of the inner screw sleeve 18 is threaded with a stud 15, and the top of the stud 15 is fixedly provided with a first fixed block 14, and the first fixed block 14 is fixedly provided on the outside of the limit frame 4. By rotating the four inner screw sleeves 18 at the same time, the stud 15 can be driven to move upward, and the upward movement of the stud 15 can drive the limit frame 4 to move upward, so that it can limit the bottom of the force beam 2.
[0045] A fixing plate 9 corresponding to the first clamping plate 5 is fixedly provided on the top of the fixing frame 3, and at least two first guide rods 11 are slidably provided on one side of the fixing plate 9, and one end of the two first guide rods 11 are fixedly connected to the corresponding first clamping plate 5, and a rotating seat 10 is fixedly provided on one side of the first clamping plate 5, and a connecting rod 12 is rotatably provided on one side of the rotating seat 10, and the other end of the connecting rod 12 is rotatably provided on the outside of the limit frame 4. When the limit frame 4 moves upward, the rotating seat 10 can be driven to move through the connecting rod 12. During the movement of the rotating seat 10, the first clamping plate 5 can be driven to approach the force beam 2, so that it can clamp the force beam 2, and the moving direction of the first clamping plate 5 can be guided by the setting of the first guide rod 11, and no lifting or lowering movement will occur.
[0046] The outer wall fixed sleeve of the inner screw sleeve 18 is provided with a synchronous wheel 19, and the outer walls of the four synchronous wheels 19 are transmission-connected with the same double-sided synchronous belt 21. A connecting block 16 is fixedly provided on one side of the double-sided synchronous belt 21. The output end of the electric push rod 17 is fixedly connected to the connecting block 16. By starting the electric push rod 17, the connecting block 16 can be driven to move, and the movement of the connecting block 16 can drive the double-sided synchronous belt 21 to move. The double-sided synchronous belt 21 can drive the synchronous wheel 19 to rotate during the movement, thereby driving the inner screw sleeve 18 to rotate, so that the stud 15 can be lifted and moved. At the same time, the pitch of the stud 15 is large, which avoids the number of rotations of the synchronous wheel 19 and cannot drive the stud 15 to be lifted and lowered.
[0047] The fixing mechanism includes two second fixing blocks 23 fixedly arranged on the inner walls on both sides of the rectangular hole 22, a second guide rod 24 is slidably provided on one side of the second fixing block 23, one end of the two second guide rods 24 is fixedly provided with the same second clamping plate 26, one side of the second clamping plate 26 is fixedly provided with a protrusion 27, the outer wall of the stud 15 is provided with a conical portion 28 and a transition portion 29 used in conjunction with the protrusion 27, which is used to drive the second clamping plate 26 to approach the column cap 6, the outer wall of the second guide rod 24 is sleeved with a spring 25, the two ends of the spring 25 are respectively fixedly connected to the outer wall of the second guide rod 24 and one side of the second fixing block 23, when the stud 15 moves upward on the fixing frame 3, it can drive the protrusion 27 to move through the conical portion 28, thereby driving the second clamping plate 26 to approach the column cap 6, and when continuing to move upward, it can limit the protrusion 27 through the transition portion 29 so that it can maintain a clamped state.
[0048] Example 2
[0049] refer to Figure 1-Figure 7 , an improvement on the basis of Example 1: two guide wheels 20 are rotatably provided on the top wall of the rectangular hole 22, and the two guide wheels 20 are respectively located on both sides of the synchronous wheel 19, and are used to increase the wrap angle between the double-sided synchronous belt 21 and the synchronous wheel 19. By arranging the guide wheels 20 on both sides of the synchronous wheel 19, the double-sided synchronous belt 21 can be bent, and the wrap angle between the double-sided synchronous belt 21 and the synchronous wheel 19 can be increased to avoid insufficient friction.
[0050] A storage groove 30 is provided on the outer wall of the fixed frame 3, and the double-sided synchronous belt 21 is located in the storage groove 30 for protecting the double-sided synchronous belt 21. By providing the double-sided synchronous belt 21 on the outer wall of the fixed frame 3, the double-sided synchronous belt 21 can be hidden in the storage groove 30, which can effectively prevent foreign objects from colliding with the double-sided synchronous belt 21 and causing damage.
[0051] A method for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap comprises the following steps:
[0052] S1. First, pre-fix the column 1 on the ground and install the column cap 6 on the column 1. Then, put the fixing frame 3 on the column cap 6 and start the electric push rod 17 to drive the second clamping plate 26 to move and clamp the column cap 6.
[0053] S2, then, position the force beam 2 on the two column caps 6, and make the force beam 2 located in the positioning groove 13;
[0054] S3, secondly, the electric push rod 17 is started again to drive the limit frame 4 to move upward until the bottom of the positioning groove 13 contacts the force beam 2, and the two first clamping plates 5 on the same side are driven to move closer to each other to clamp and fix the force beam 2;
[0055] S4. Finally, pour concrete into the limiting frame 4 until the concrete solidifies, and then remove the fixing frame 3 from the column cap 6.
[0056] However, as is well known to those skilled in the art, the working principle and wiring method of the electric push rod 17 are commonplace, and are conventional means or common knowledge, and will not be elaborated here. Those skilled in the art can make any selection according to their needs or convenience.
[0057] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A quick positioning and fixing device for prefabricated prestressed beams and frame columns with column caps, characterized in that: The invention comprises a quick positioning and fixing device for prefabricated prestressed beams and frame columns with column caps, comprising a plurality of columns, column caps arranged at the tops of the columns and a plurality of force beams, wherein the corresponding four force beams are arranged at the tops of the column caps, four groups of positioning columns are fixedly arranged at the tops of the column caps, positioning holes used in conjunction with the positioning columns are provided at the bottoms of the force beams, a fixing frame and a limiting frame are sequentially sleeved on the outer walls of the column caps, and a positioning groove for positioning the force beams is provided on the outer walls of the limiting frames; Four groups of first clamping plates, which are respectively arranged around the limiting frame and used for clamping and fixing the force beam; A fixing mechanism, arranged on the fixing frame, for clamping the fixing frame on the column cap; A lifting mechanism is provided on the fixed frame to drive the limit frame to move up and down, can be used in conjunction with the first clamping plate to clamp the force beam during the lifting process, and can also be used in conjunction with the fixing mechanism to clamp the fixed frame on the column cap; An electric push rod is arranged on one side of the fixed frame and is used to provide power for the lifting mechanism.
2. The device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap according to claim 1 is characterized in that: The lifting mechanism includes a rectangular hole opened on the outside of the fixed frame, four inner screw sleeves are rotatably provided on the top of the fixed frame, the bottom ends of the inner screw sleeves extend into the corresponding rectangular holes respectively, the inner wall of the inner screw sleeve is threaded with a stud, the top of the stud is fixed with a first fixed block, and the first fixed block is fixed on the outside of the limit frame.
3. The device for quickly positioning and fixing prefabricated prestressed beams and frame columns with column caps according to claim 1 is characterized in that: A fixing plate corresponding to the first clamping plate is fixedly provided on the top of the fixing frame, at least two first guide rods are slidably provided through one side of the fixing plate, one end of the two first guide rods are fixedly connected to the corresponding first clamping plate, a rotating seat is fixedly provided on one side of the first clamping plate, a connecting rod is rotatably provided on one side of the rotating seat, and the other end of the connecting rod is rotatably provided on the outside of the limit frame.
4. The device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap according to claim 2, characterized in that: The outer wall fixed sleeve of the inner screw sleeve is provided with a synchronous wheel, the outer walls of the four synchronous wheels are transmission-connected with the same double-sided synchronous belt, a connecting block is fixedly provided on one side of the double-sided synchronous belt, and the output end of the electric push rod is fixedly connected to the connecting block.
5. The device for quickly positioning and fixing prefabricated prestressed beams and frame columns with column caps according to claim 2 is characterized in that: Two guide wheels are rotatably arranged on the top wall of the rectangular hole. The two guide wheels are respectively located on both sides of the synchronous wheel and are used to increase the wrap angle between the double-sided synchronous belt and the synchronous wheel.
6. The device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap according to claim 1, characterized in that: The outer wall of the fixing frame is provided with a receiving groove, and the double-sided synchronous belt is located in the receiving groove, so as to protect the double-sided synchronous belt.
7. The device for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap according to claim 1, characterized in that: The fixing mechanism includes two second fixing blocks fixedly arranged on the inner walls on both sides of the rectangular hole, a second guide rod slidingly provided through one side of the second fixing block, a same second clamping plate fixedly arranged at one end of the two second guide rods, a protrusion fixedly arranged at one side of the second clamping plate, an outer wall of the stud is provided with a conical portion and a transition portion used in conjunction with the protrusion, for driving the second clamping plate to approach the column cap, a spring is sleeved on the outer wall of the second guide rod, and two ends of the spring are respectively fixedly connected to the outer wall of the second guide rod and one side of the second fixing block.
8. The method for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap according to any one of claims 1 to 7, characterized in that , including the following steps: S1. First, pre-fix the column on the ground and install the column cap on the column. Then, put the fixing frame on the column cap and start the electric push rod to drive the second clamping plate to move and clamp the column cap. S2. Then, position the force beam on the two column caps and make the force beam located in the positioning groove; S3, secondly, start the electric push rod again to drive the limit frame to move upward until the bottom of the positioning groove contacts the force beam, and at the same time, the two first clamping plates on the same side can be driven to move closer to each other to clamp and fix the force beam; S4. Finally, pour concrete in the limit frame until the concrete solidifies, and then remove the fixing frame from the column cap.
9. The method for quickly positioning and fixing a prefabricated prestressed beam and a frame column with a column cap according to claim 1, characterized in that: First, the column is pre-fixed on the ground, and the column cap is installed on the column, and then the fixing frame is put on the column cap, and the electric push rod is started to drive the connecting block to move, and the movement of the connecting block can drive the double-sided synchronous belt to move in the storage groove, and at the same time, it can drive the synchronous wheel to rotate, and the rotation of the synchronous wheel can drive the inner screw sleeve to rotate, and the rotation of the inner screw sleeve can drive the stud to move upward, and the upward movement of the stud can drive the limit frame to move upward, and when the conical part contacts the convex block, it can drive the convex block to move, so as to drive the second clamping plate to move to clamp the column cap, until the transition part cooperates with the convex block to maintain the clamping state; Then, position the force beam on the column cap, and make the force beam be located in the positioning groove and the positioning column be inserted into the positioning hole; Secondly, the electric push rod is started again to drive the limit frame to move upward until the bottom of the positioning groove contacts the force beam. When the limit frame moves, it can drive one end of the connecting rod to move upward and rotate, and can drive the first clamping plate to move through the rotating seat, so that the two first clamping plates on the same side are close to each other to clamp and fix the force beam; Finally, pour concrete in the limit frame until the concrete solidifies, and then start the electric push rod to reset. During the resetting process, the limit frame can be driven to move downward through the studs. At the same time, when the studs move downward, the protrusions can move to the tapered portion. At this time, the second clamping plate can be reset and moved under the action of the spring. At this time, the fixed frame is removed from the column cap, and then the fixation between the ground and the column is released, and the entire frame is lifted to the final installation position by a crane.