Air conditioning system and control method thereof
By introducing energy storage air conditioning boxes and intelligent control methods into the air conditioning system, three-dip heat exchanger and phase change materials are used to store energy in the electric valley scene, and release energy in the electric peak scene, the air conditioning system is solved in the electric peak scene. The problems of high energy consumption and excessive grid load have achieved flexible energy transmission and distribution and energy efficiency improvement.
Patent Information
- Application Number
- CN202411431705.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-14
- Publication Date
- 2024-12-06
AI Technical Summary
The existing air conditioning system has high energy consumption in peak scenarios and may lead to excessive load in the power grid, which cannot effectively solve the problem of supply and demand mismatch between the heat energy supply source and the use load.
An air conditioning system was designed, using energy storage air conditioning box and auxiliary heating pipelines, and energy storage and release through three medium heat exchangers and phase change materials. Combined with intelligent control methods, energy storage in the electric valley scene, Release energy in the peak scene and adjust the temperature of the space to be adjusted.
It realizes flexible energy transmission and distribution, improves the stability and reliability of the system under the uncertainty of energy load, reduces energy consumption, reduces dependence on electricity, improves energy efficiency ratio, and solves the peak-cutting and valley filling of electricity. question.
Smart Images

Figure CN119085044A_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the technical field of air conditioning, and in particular to an air conditioning system and a control method thereof. Background Art
[0002] Air conditioning systems play an important role in people's lives and work. With the continuous advancement of technology, the performance and functions of air conditioning systems will continue to improve, providing people with a more comfortable, efficient, energy-saving and environmentally friendly indoor environment. At present, air conditioning systems usually rely on electricity to directly drive compressors for cooling or heating. This method consumes a lot of energy and may cause excessive load on the power grid in peak power scenarios. Summary of the invention
[0003] In view of this, in order to solve the technical problems in the prior art of high energy consumption and possible excessive load on the power grid in peak power scenarios, the present disclosure provides an air-conditioning system and a control method thereof.
[0004] According to a first aspect of an embodiment of the present disclosure, an air-conditioning system is provided, which includes an energy storage air-conditioning box, a heating device and an auxiliary heating pipeline. The energy storage air-conditioning box includes a three-medium heat exchanger, and the three-medium heat exchanger includes a first medium channel, a second medium channel and a third medium channel. The first medium channel is connected to a heat source output port of the heating device through the auxiliary heating pipeline, and the second medium channel is provided with a phase change material. Part of the air flow channel of the energy storage air-conditioning box constitutes the third medium channel, and the input port of the air flow channel is connected to a space where the gas to be treated is located, and the output port of the air flow channel is connected to a space to be adjusted.
[0005] In an optional embodiment, the air-conditioning system includes a first control pump and a control device, the first control pump is located in the auxiliary heating pipeline, the control device is electrically connected to the first control pump, and the control device is configured to control the opening and closing of the auxiliary heating pipeline through the first control pump based on the power consumption scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger.
[0006] In an optional embodiment, the three-medium heat exchanger includes at least one temperature detection device, the temperature detection device is electrically connected to the control device, and the temperature detection device is used to detect the temperature of the phase change material in the three-medium heat exchanger.
[0007] In an optional embodiment, the air conditioning system includes a main heat supply pipeline, and the heat source channel of the energy storage air conditioning box is connected to the heat source output port of the heating device through the main heat supply pipeline;
[0008] The air-conditioning system includes a second control pump and a control device, the second control pump is located in the main heating pipeline, the control device is electrically connected to the second control pump, and the control device is configured to control the on and off of the main heating pipeline through the second control pump based on the power consumption scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger.
[0009] In an optional embodiment, the air-conditioning system includes a third control pump, the heating device includes an air-cooled heat pump, the main heating pipeline is connected to the heat source output port of the heating device through the third control pump, the control device is electrically connected to the third control pump, and the control device is configured to control the opening of the third control pump based on the temperature of the space to be regulated if the temperature fluctuation of the space to be regulated is within a preset range when the auxiliary heating pipeline is in a conducting state.
[0010] In an optional embodiment, the heating device includes at least one of the following devices:
[0011] Compressed air heat recovery unit, air-cooled heat pump, medium temperature heat recovery chiller.
[0012] According to a second aspect of an embodiment of the present disclosure, a control method is provided. The control method is applied to the air conditioning system according to any one of claims 1 to 4. The control method includes:
[0013] Based on the electricity consumption scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger, the on-off of the auxiliary heating pipeline is controlled.
[0014] In an optional embodiment, the controlling of the on-off of the auxiliary heating pipeline based on the power consumption scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger includes at least one of the following:
[0015] When the power consumption scenario is a valley power scenario and the temperature of the three-medium heat exchanger is greater than a set temperature threshold, the auxiliary heating pipeline is controlled to be in an on state or an off state;
[0016] When the power consumption scenario is the power valley scenario and the temperature of the three-medium heat exchanger is lower than the set temperature threshold, controlling the auxiliary heating pipeline to be in a conducting state;
[0017] When the electricity consumption scenario is a peak electricity consumption scenario, the auxiliary heating pipeline is controlled to be in a closed state.
[0018] In an optional embodiment, the control method includes:
[0019] Based on the electricity usage scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger, the on-off of the main heating pipeline is controlled.
[0020] In an optional embodiment, the controlling of the on-off of the main heating pipeline based on the power consumption scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger includes at least one of the following:
[0021] When the power consumption scenario is a valley power scenario, controlling the main heating pipeline to be in a conducting state;
[0022] When the electricity consumption scenario is a peak electricity consumption scenario and the temperature of the three-medium heat exchanger is greater than a set temperature threshold, the main heating pipeline is controlled to be in a shut-off state;
[0023] When the electricity consumption scenario is the electricity peak scenario and the temperature of the three-medium heat exchanger is less than the set temperature threshold, the main heating pipeline is controlled to be in a conducting state.
[0024] In an optional embodiment, the air conditioning system includes a third control pump, the heating device includes an air-cooled heat pump, the main heating pipeline is connected to the heat source output port of the heating device through the third control pump, the control device is electrically connected to the third control pump, and the control method includes:
[0025] When the auxiliary heating pipeline is in a conducting state, if the temperature fluctuation of the space to be conditioned is within a preset range, the opening degree of the third control pump is controlled based on the temperature of the space to be conditioned.
[0026] The technical solution provided by the embodiments of the present disclosure may include the following beneficial effects: the energy storage air conditioning box of the present disclosure has a newly added three-medium heat exchanger, and has a newly added auxiliary heating pipeline that cooperates with the three-medium heat exchanger in the air conditioning system, which is used to connect the first medium channel of the three-medium heat exchanger with the heat source output port of the heating device, and the second medium channel of the three-medium heat exchanger is provided with a phase change material, and part of the air flow channel of the energy storage air conditioning box constitutes the third medium channel of the three-medium heat exchanger, and the input port of the air flow channel is connected to the space where the gas to be treated is located, and the output port of the air flow channel is connected to the space to be regulated. In the present disclosure, the heating device can provide a heat source for the three-medium heat exchanger through the heating pipeline, and exchange heat with the phase change material in the three-medium heat exchanger, thereby storing energy for the phase change material, and then, when needed, release energy through the phase change material, thereby heating the gas in the third medium channel, thereby assisting in the temperature regulation of the space to be regulated.
[0027] In the air-conditioning system disclosed in the present invention, in the case of a valley electricity scenario, the phase change material can be stored with a heating device. In the case of a peak electricity scenario, the phase change material releases energy to assist in regulating the temperature of the space to be regulated, which can solve the problem of a mismatch between the supply source of thermal energy and the load of thermal energy use, realize flexible energy transmission and distribution, improve the stability and reliability of system operation under energy-load uncertainty, improve energy efficiency, realize peak shaving and valley filling of electric energy, and reduce dependence on electric energy.
[0028] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the invention and, together with the description, serve to explain the principles of the invention.
[0030] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0031] One or more embodiments are exemplarily described by pictures in the corresponding drawings, and these exemplified descriptions do not constitute limitations on the embodiments. Elements with the same reference numerals in the drawings represent similar elements, and unless otherwise stated, the figures in the drawings do not constitute proportional limitations.
[0032] Figure 1 is a schematic diagram of an air conditioning system according to an exemplary embodiment.
[0033] Figure 2 is a partial schematic diagram of an air conditioning system according to an exemplary embodiment.
[0034] Figure 3 is a schematic diagram of an air conditioning system according to another exemplary embodiment.
[0035] Reference numerals:
[0036] 11. Energy storage air conditioning box; 111. Three-medium heat exchanger;
[0037] 21. Heating device; 211. Air-cooled heat pump; 212. Air-compressed heat recovery device; 213. Medium-temperature heat recovery chiller;
[0038] 31. Auxiliary heating pipeline; 32. Main heating pipeline;
[0039] 40. Shared pipelines;
[0040] 51, first control pump; 52, second control pump; 53, third control pump; 54, fourth control pump; 55, fifth control pump;
[0041] 60. Fan filter unit;
[0042] 70. Dry cooling coil;
[0043] 80. Cold tower. DETAILED DESCRIPTION
[0044] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0045] The disclosure below provides many different embodiments or examples to implement different schemes of the present invention. In order to simplify the disclosure of the present invention, the components and settings of specific examples are described below. Of course, they are only examples, and the purpose is not to limit the present invention. In addition, the present invention can repeat reference numbers and / or letters in different examples. This repetition is for the purpose of simplification and clarity, and does not itself indicate the relationship between the various embodiments and / or settings discussed.
[0046] For ease of description, spatial relative terms may be used herein to describe the relative positional relationship or movement of one element or feature relative to another element or feature as shown in the figure, such as "inside", "outside", "inner side", "outer side", "below", "below", "above", "above", "front", "back", etc. Such spatial relative terms are intended to include different orientations of the device in use or operation in addition to the orientation depicted in the figure. For example, if the device in the figure undergoes a position flip or a posture change or a motion state change, then these directional indications also change accordingly, for example: an element described as "below other elements or features" or "below other elements or features" will subsequently be oriented as "above other elements or features" or "above other elements or features". Therefore, the example term "below..." may include both upper and lower orientations. The device may be otherwise oriented (rotated 90 degrees or in other directions) and the spatial relative descriptors used herein are interpreted accordingly.
[0047] It should be noted that the illustrations provided in the following embodiments are only schematic illustrations of the basic concept of the present application, and thus the drawings only show components related to the present application rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed at will, and the component layout may also be more complicated.
[0048] The following will describe the implementation methods of the present application with reference to the accompanying drawings and preferred embodiments. Those skilled in the art can easily understand other advantages and effects of the present application from the contents disclosed in this specification. The present application can also be implemented or applied through other different specific implementation methods, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present application. It should be understood that the preferred embodiments are only for illustrating the present application, not for limiting the scope of protection of the present application.
[0049] In order to solve the technical problems in the prior art of high energy consumption and possible excessive load on the power grid in peak power scenarios, the present disclosure provides an air-conditioning system and a control method thereof.
[0050] Among them, the energy storage air-conditioning box of the present disclosure has added a three-medium heat exchanger, and has added an auxiliary heating pipeline that cooperates with the three-medium heat exchanger in the air-conditioning system, which is used to connect the first medium channel of the three-medium heat exchanger with the heat source output port of the heating device, and the second medium channel of the three-medium heat exchanger is provided with a phase change material, and part of the air flow channel of the energy storage air-conditioning box constitutes the third medium channel of the three-medium heat exchanger, and the input port of the air flow channel is connected to the space where the gas to be treated is located, and the output port of the air flow channel is connected to the space to be adjusted. In the present disclosure, the heating device can provide a heat source for the three-medium heat exchanger through the heating pipeline, and exchange heat with the phase change material in the three-medium heat exchanger, thereby storing energy for the phase change material, and then, when needed, release energy through the phase change material, thereby heating the gas in the third medium channel, thereby assisting in the temperature regulation of the space to be regulated.
[0051] In the air-conditioning system disclosed in the present invention, in the case of a valley electricity scenario, the phase change material can be stored with a heating device. In the case of a peak electricity scenario, the phase change material releases energy to assist in regulating the temperature of the space to be regulated, which can solve the problem of a mismatch between the supply source of thermal energy and the load of thermal energy use, realize flexible energy transmission and distribution, improve the stability and reliability of system operation under energy-load uncertainty, improve energy efficiency, realize peak shaving and valley filling of electric energy, and reduce dependence on electric energy.
[0052] In an exemplary embodiment, reference Figures 1 to 3As shown, an air conditioning system and a control method thereof are provided. The air conditioning system may include an energy storage air conditioning box 11 and a heating device 21. The energy storage air conditioning box 11 may be a combined external air conditioning box or other forms of energy storage air conditioning box 11, which is not limited.
[0053] It should be noted that the combined outdoor air conditioning box is referred to as MAU (Make-uD Air Unit), which is generally composed of a fan, a cold coil, a hot coil (or electric heating), an air filter (primary, intermediate, and advanced three-stage filtration), and a humidifier. After primary and intermediate efficiency filtration, preheating, enthalpy reduction, dehumidification, reheating, and high-efficiency filtration, it is sent to the return air layer. MAU can provide constant temperature, constant humidity, and positive pressure in the laboratory, and provide three-layer filtered clean air for the room.
[0054] The input port of the air flow channel of the energy storage air conditioning box 11 is connected to the space where the gas to be processed is located, and the output port of the air flow channel is connected to the space to be regulated.
[0055] In the related art, the energy storage air conditioning box 11 may include a main heating pipeline 32, and is connected to the heat source output port of the heating device 21 through the main heating pipeline 32. In the heating mode, the heating device 21 converts electrical energy into thermal energy, and provides thermal energy to the energy storage air conditioning box 11 through the main heating pipeline 32. The energy storage air conditioning box 11 heats the gas in the air flow channel through the thermal energy provided by the heating device 21, and then transports it to the space to be regulated, thereby heating the space to be regulated. The energy consumption of this related art is high, and it cannot solve the technical problem that the power grid may be overloaded in the peak power scenario.
[0056] In this embodiment, an auxiliary heat supply pipeline 31 is newly added, and the energy storage air conditioning box 11 may include a three-medium heat exchanger 111. The three-medium heat exchanger 111 includes a first medium channel, a second medium channel and a third medium channel. The first medium channel is connected to the heat source output port of the heating device 21 through the auxiliary heat supply pipeline 31, the second medium channel is provided with a phase change material, and part of the air flow channel of the energy storage air conditioning box 11 constitutes the third medium channel.
[0057] The heating device 21 can provide a heat source for the three-medium heat exchanger 111 through a heating pipeline, and exchange heat with the phase change material in the three-medium heat exchanger 111, thereby storing energy for the phase change material, and then, when needed, release energy through the phase change material to heat the gas in the third medium channel, thereby assisting in temperature regulation of the space to be regulated.
[0058] The on-off of the auxiliary heating pipeline 31 can be controlled based on the power consumption scenario of the heating device 21 and / or the temperature of the phase change material in the three-medium heat exchanger 111, thereby controlling the energy storage timing of the phase change material.
[0059] When the electricity consumption scenario is a valley scenario and the temperature of the three-medium heat exchanger 111 is greater than the set temperature threshold, the auxiliary heating pipeline 31 is controlled to be in an on state or an off state. It should be noted that if the temperature of the three-medium heat exchanger 111 is greater than the set temperature threshold, it means that the energy storage state of the phase change material is better at this time, and the auxiliary heating pipeline 31 can be controlled to be in an on state or an off state according to actual needs. For example, if the temperature of the current space to be adjusted is already relatively suitable, and it is expected that a large amount of heat energy will not be needed in the future, the auxiliary heating pipeline 31 can be controlled to be shut down to avoid excessive energy storage; if it is expected that there will be a large demand for temperature adjustment in the future, the auxiliary heating pipeline 31 can be kept on to continue to store energy for the phase change material.
[0060] When the electricity consumption scenario is a valley scenario and the temperature of the three-medium heat exchanger 111 is less than the set temperature threshold, the auxiliary heat supply pipeline 31 is controlled to be in a conducting state. It should be noted that if the temperature of the three-medium heat exchanger 111 is less than the set temperature threshold, it indicates that the energy storage of the phase change material is insufficient. At this time, the auxiliary heat supply pipeline 31 is controlled to be in a conducting state to ensure that the heating device 21 can provide a heat source for the three-medium heat exchanger 111 through the auxiliary heat supply pipeline 31 to store energy for the phase change material.
[0061] When the electricity consumption scene is a peak electricity scene, the auxiliary heating pipeline 31 is controlled to be in a closed state. It should be noted that when the electricity consumption scene is a peak electricity scene, in order to reduce energy consumption and reduce the load on the power grid, the auxiliary heating pipeline 31 is controlled to be in a closed state. At this time, the phase change material is mainly used to release energy to assist in regulating the temperature of the space to be regulated.
[0062] Among them, the peak and valley scenarios can be judged according to the peak and valley time periods announced by the power company. Power companies usually divide the peak and valley time periods according to local power consumption and announce them to users. For example, in some areas, the peak power consumption period during the day (such as 9 am to 5 pm) is defined as the peak scenario, while the low power consumption period at night (such as 10 pm to 6 am the next day) is defined as the valley scenario.
[0063] The control device of the air-conditioning system can pre-set these peak and valley periods, and then obtain the current time through the clock module, and compare it with the preset peak and valley periods to determine whether it is currently in a peak electricity scene or a valley electricity scene.
[0064] In addition, the peak and valley periods of electricity consumption may vary in different seasons and weekdays / holidays. For example, in summer, the peak period of electricity consumption (i.e., peak scenario) may be extended due to the increased use of electrical appliances such as air conditioners; while on weekends or holidays, the valley period of electricity consumption (i.e., valley scenario) may be extended due to the reduction of industrial electricity consumption. The control device can appropriately adjust the preset peak and valley periods according to the different seasons and weekdays / holidays to improve the accuracy of the judgment.
[0065] In addition, in this embodiment, the total power consumption of the power grid can also be monitored in real time through a smart meter or other monitoring equipment connected to the power grid. When the total power consumption of the power grid exceeds a certain threshold, it is judged as a peak power scenario; when the total power consumption of the power grid is lower than a certain threshold, it is judged as a valley power scenario. The above thresholds can be set according to actual conditions, and their specific values are not limited.
[0066] In addition, some regions implement a time-of-use electricity price system, where electricity prices are higher during peak hours and lower during valley hours. The control device of the air conditioning system can obtain real-time electricity price information through the communication interface with the power company. When the electricity price is higher than a certain threshold, it is judged as a peak scenario; when the electricity price is lower than a certain threshold, it is judged as a valley scenario.
[0067] It should be noted that, in addition to the above-mentioned method for determining the power valley scene and the power peak scene, other methods may also be used for determination, which is not limited thereto.
[0068] In this air-conditioning system, through the above-mentioned control method, the phase change material can be reasonably stored with energy according to the actual situation in the valley scene, while avoiding energy waste caused by excessive energy storage. In the valley scene, the phase change material can be stored with energy through the heating device 21. In the peak scene, the temperature regulation of the space to be regulated is assisted by the release of energy by the phase change material, thereby reducing energy consumption and solving the technical problem that the grid may be overloaded in the peak scene. This embodiment can solve the problem of a mismatch between the supply source of thermal energy and the load of thermal energy use, realize flexible transmission and distribution of energy, improve the stability and reliability of system operation under energy-load uncertainty, improve energy efficiency, and realize peak shaving and valley filling of electric energy, reducing dependence on electric energy.
[0069] In an exemplary embodiment, reference Figures 1 to 3 As shown, an air conditioning system and a control method thereof are provided.
[0070] The air conditioning system may include a first control pump 51 and a control device. The first control pump 51 is located in the auxiliary heating pipeline 31, and the control device is electrically connected to the first control pump 51. The control device is configured to control the on-off of the auxiliary heating pipeline 31 through the first control pump 51 based on the power usage scenario of the heating device 21 and / or the temperature of the phase change material in the three-medium heat exchanger 111.
[0071] When the control device controls the first control pump 51 to be turned on, the auxiliary heating pipeline 31 is connected. When the control device controls the first control pump 51 to be turned off, the auxiliary heating pipeline 31 is turned off.
[0072] In this embodiment, when the power consumption scene of the heating device 21 is a valley scene and the temperature of the three-medium heat exchanger 111 is greater than the set temperature threshold, the control device can make a judgment based on actual needs. If it is not necessary to continue to store energy at this time or it is expected that the heat energy supply will be sufficient in the future, the first control pump 51 can be controlled to turn on, so that the auxiliary heating pipeline 31 is turned off to avoid excessive energy storage. On the contrary, if there is a need for further energy storage, the first control pump 51 is kept off to make the auxiliary heating pipeline 31 conductive.
[0073] When the electricity usage scenario is a valley scenario and the temperature of the three-medium heat exchanger 111 is less than the set temperature threshold, the control device controls the first control pump 51 to remain closed, so that the auxiliary heating pipeline 31 is turned on, ensuring that the heating device 21 can store energy for the phase change material. When the electricity usage scenario is a peak scenario, in order to reduce energy consumption and reduce the load on the power grid, the control device controls the first control pump 51 to turn on, so that the auxiliary heating pipeline 31 is turned off, and the phase change material is relied on to release energy to assist in regulating the temperature of the space to be regulated.
[0074] This embodiment realizes intelligent control of the on-off of the auxiliary heating pipeline 31 through the synergistic effect of the control device and the first control pump 51. The heating strategy can be flexibly adjusted according to different power usage scenarios and phase change material temperatures, thereby improving energy utilization efficiency and reducing energy consumption. It effectively solves the problem of excessive power grid load that may be caused by peak power scenarios, realizes peak shaving and valley filling of electric energy, and improves the stability and reliability of the air-conditioning system.
[0075] The three-medium heat exchanger 111 may include at least one temperature detection device (not shown in the figure), which may be a temperature sensor or other device capable of detecting temperature, and is not limited thereto. The temperature detection device is electrically connected to the control device, and is used to detect the temperature of the phase change material in the three-medium heat exchanger 111.
[0076] The temperature detection device can monitor the temperature of the phase change material in the three-medium heat exchanger 111 in real time and transmit the temperature data to the control device. After receiving the temperature data, the control device analyzes and processes the data. The control device can make corresponding control decisions based on the phase change material temperature data provided by the temperature detection device and the power consumption scenario of the heating device 21.
[0077] For example, in the valley scenario, if the temperature of the phase change material is lower than the set temperature threshold, the control device will control the auxiliary heating pipeline 31 to be turned on, so that the heating device 21 can store energy for the phase change material; if the temperature of the phase change material is higher than the set temperature threshold, the control device will determine the on / off state of the auxiliary heating pipeline 31 according to the actual situation. In the peak scenario, the control device will reasonably use the energy released by the phase change material to adjust the temperature according to the temperature of the phase change material and the temperature requirements of the space to be adjusted, and at the same time control the auxiliary heating pipeline 31 to be turned off.
[0078] It should be noted that when the air conditioning system includes multiple temperature detection devices, the temperatures detected by the multiple temperature detection devices can be averaged, and the average temperature value is used as the temperature of the three-medium heat exchanger 111. In addition, under the premise of not affecting the operation of the heat exchanger, the more points used to detect the temperature of the three-medium heat exchanger 111 and the more temperature detection devices are set, the higher the reliability of the temperature of the three-medium heat exchanger 111 is finally obtained.
[0079] In this embodiment, through the cooperation of the temperature detection device and the control device, the temperature of the phase change material in the three-medium heat exchanger 111 is monitored in real time and accurately controlled, providing strong support for the optimized operation of the air-conditioning system. This embodiment can adjust the operating state of the air-conditioning system in time according to the temperature change of the phase change material, improving the stability and reliability of the system. It is helpful to achieve efficient use of energy and peak-shaving and valley-filling of electric energy, reduce the energy consumption of the air-conditioning system, and improve the energy efficiency ratio.
[0080] In an exemplary embodiment, reference Figures 1 to 3 As shown, an air conditioning system and a control method thereof are provided.
[0081] The air conditioning system may include a main heating pipeline 32, and the heat source channel of the energy storage air conditioning box 11 is connected to the heat source output port of the heating device 21 through the main heating pipeline 32. In the related art, in the heating mode, the heating device 21 converts electrical energy into thermal energy, and provides thermal energy to the energy storage air conditioning box 11 through the main heating pipeline 32. The energy storage air conditioning box 11 heats the gas in the air flow channel through the thermal energy provided by the heating device 21, and then transmits it to the space to be conditioned, thereby heating the space to be conditioned.
[0082] In this embodiment, the air conditioning system may further include a second control pump 52, the second control pump 52 is located in the main heating pipeline 32, and the control device is electrically connected to the second control pump 52. The control device is configured to control the on-off of the main heating pipeline 32 through the second control pump 52 based on the power usage scenario of the heating device 21 and / or the temperature of the phase change material in the three-medium heat exchanger 111.
[0083] When the control device controls the second control pump 52 to be turned off, the main heat supply pipeline 32 is shut off. When the control device controls the second control pump 52 to be turned on, the main heat supply pipeline 32 is turned on.
[0084] Among them, when the electricity consumption scenario is a valley electricity scenario, the second control pump 52 is controlled to be turned on, and the main heating pipeline 32 is in a conducting state. At this time, the heating device 21 provides heat energy to the energy storage air-conditioning box 11 through the main heating pipeline 32 to heat the indoor space, so as to make full use of the low electricity price and relatively low grid load during the valley electricity period.
[0085] At the same time, if the temperature of the three-medium heat exchanger 111 is greater than the set temperature threshold, it means that the energy storage state of the phase change material is good at this time, and the auxiliary heating pipeline 31 can be controlled to be in the on state or the off state according to actual needs. For example, if the temperature of the current space to be adjusted is already relatively suitable, and it is expected that a large amount of heat energy will not be needed in the future, the auxiliary heating pipeline 31 can be controlled to be turned off to avoid excessive energy storage; if it is expected that there will be a large demand for temperature adjustment in the future, the auxiliary heating pipeline 31 can be kept on to continue to store energy for the phase change material.
[0086] In addition, if the temperature of the three-medium heat exchanger 111 is lower than the set temperature threshold, it indicates that the energy storage of the phase change material is insufficient. At this time, the auxiliary heat supply pipeline 31 is controlled to be in a conducting state to ensure that the heating device 21 can provide a heat source for the three-medium heat exchanger 111 through the auxiliary heat supply pipeline 31 to store energy for the phase change material.
[0087] When the electricity consumption scenario is a peak electricity scenario, the control device further determines the temperature of the three-medium heat exchanger 111. When the temperature of the three-medium heat exchanger 111 is greater than the set temperature threshold, it means that the energy storage of the phase change material is sufficient and can meet the temperature regulation requirements within a certain period of time. At this time, the second control pump 52 is controlled to be turned off to control the main heating pipeline 32 to be in a shut-off state, reduce dependence on the heating device 21, and reduce the load on the power grid.
[0088] When the power consumption scenario is the peak power scenario, if the temperature of the three-medium heat exchanger 111 is less than the set temperature threshold, it indicates that the energy storage of the phase change material is insufficient and cannot meet the indoor temperature regulation requirement. At this time, the second control pump 52 is controlled to be turned on to control the main heating pipeline 32 to be in a conducting state, so that the heating device 21 provides heat energy to the energy storage air conditioning box 11 to ensure the stability of the indoor temperature.
[0089] This embodiment realizes the optimized operation of the air-conditioning system in different electricity usage scenarios through intelligent control of the main heating pipeline 32. In the electricity valley scenario, the low electricity price is fully utilized for energy storage to reduce the operating cost; in the electricity peak scenario, the main heating pipeline 32 is reasonably controlled according to the temperature of the phase change material to reduce the pressure on the power grid and improve the energy utilization efficiency. This embodiment improves the stability and reliability of the air-conditioning system, ensures that the indoor temperature is always kept within a comfortable range, and provides users with a good indoor environment.
[0090] In an exemplary embodiment, reference Figures 1 to 3 As shown, an air conditioning system and a control method thereof are provided. The heating device 21 of the air conditioning system may include at least one of the following devices:
[0091] Air compression heat recovery device 212, air-cooled heat pump 211, medium-temperature heat recovery chiller 213.
[0092] That is to say, the heating device 21 may include only one of the above three devices, or any two of the above three devices, or all three devices at the same time, and there is no limitation on this.
[0093] When the heating device 21 includes an air-cooled heat pump 211 , the air conditioning system may include a third control pump 53 , the main heating pipeline 32 is connected to the heat source output port of the heating device 21 through the third control pump 53 , and the control device is electrically connected to the third control pump 53 .
[0094] The control device may be configured to control the opening degree of the third control pump 53 based on the temperature of the space to be conditioned when the auxiliary heating pipeline 31 is in the conducting state and the temperature fluctuation of the space to be conditioned is within a preset range.
[0095] It should be noted that since it is relatively difficult to control the heating of the air-compressed heat recovery device 212 and the medium-temperature heat recovery chiller 213, this embodiment can more accurately realize the energy storage of the three-medium heat exchanger 111 by controlling the air-cooled heat pump 211, thereby better adjusting the temperature of the space to be adjusted.
[0096] When the difference of the temperature fluctuation of the space to be regulated reaches a preset range, the temperature sensor can detect the value, and the three-medium heat exchanger 111 will adapt to the fluctuation to perform heat regulation, thereby achieving a stable air outlet temperature. At the same time, the auxiliary heat dissipation pipeline can be controlled to be in a conducting state, and the opening of the third control pump 53 can be controlled according to the temperature of the space to be regulated, thereby adjusting the heat supply of the air-cooled heat pump 211 to the three-medium heat exchanger 111, so as to more accurately adjust the temperature of the space to be regulated through the three-medium heat exchanger 111.
[0097] In an exemplary embodiment, reference Figures 1 to 3 As shown, an air conditioning system and a control method thereof are provided. The air conditioning system may include an energy storage air conditioning box 11 and a heating device 21. The energy storage air conditioning box 11 may be a combined external air conditioning box.
[0098] The input port of the air flow channel of the energy storage air conditioning box 11 is connected to the space where the gas to be processed is located, and the output port of the air flow channel is connected to the space to be regulated.
[0099] The air conditioning system may include a main heat supply pipeline 32, and the heat source channel of the energy storage air conditioning box 11 is connected to the heat source output port of the heating device 21 through the main heat supply pipeline 32. The air conditioning system may also include a second control pump 52, the second control pump 52 is located in the main heat supply pipeline 32, and the control device is electrically connected to the second control pump 52. The control device is configured to control the on and off of the main heat supply pipeline 32 through the second control pump 52 based on the power consumption scenario of the heating device 21 and / or the temperature of the phase change material in the three-medium heat exchanger 111.
[0100] The air conditioning system in this embodiment may be newly provided with an auxiliary heat supply pipeline 31, and the energy storage air conditioning box 11 may include a three-medium heat exchanger 111. The three-medium heat exchanger 111 includes a first medium channel, a second medium channel and a third medium channel, the first medium channel is connected to the heat source output port of the heating device 21 through the auxiliary heat supply pipeline 31, the second medium channel is provided with a phase change material, and part of the air flow channel of the energy storage air conditioning box 11 constitutes the third medium channel.
[0101] The heating device 21 can provide a heat source for the three-medium heat exchanger 111 through a heating pipeline, and exchange heat with the phase change material in the three-medium heat exchanger 111, thereby storing energy for the phase change material, and then, when needed, release energy through the phase change material to heat the gas in the third medium channel, thereby assisting in temperature regulation of the space to be regulated.
[0102] The on-off of the auxiliary heating pipeline 31 can be controlled based on the power consumption scenario of the heating device 21 and / or the temperature of the phase change material in the three-medium heat exchanger 111, thereby controlling the energy storage timing of the phase change material.
[0103] The air conditioning system may include a first control pump 51 and a control device. The first control pump 51 is located in the auxiliary heating pipeline 31, and the control device is electrically connected to the first control pump 51. The control device is configured to control the on-off of the auxiliary heating pipeline 31 through the first control pump 51 based on the power usage scenario of the heating device 21 and / or the temperature of the phase change material in the three-medium heat exchanger 111.
[0104] The three-medium heat exchanger 111 may include at least one temperature detection device, which may be a temperature sensor or other device capable of detecting temperature, and is not limited thereto. The temperature detection device is electrically connected to the control device, and is used to detect the temperature of the phase change material in the three-medium heat exchanger 111.
[0105] The heating device 21 may include an air-compressed heat recovery device 212, an air-cooled heat pump 211, and a medium-temperature heat recovery chiller 213. The air-conditioning system may include a third control pump 53, a fourth control pump 54, and a fifth control pump 55. The main heating pipeline 32 and the auxiliary heating pipeline 31 may share a common pipeline 40. The air-cooled heat pump 211 is connected to the common pipeline 40 through the third control pump 53, the air-compressed heat recovery device 212 is connected to the common pipeline 40 through the fourth control pump 54, and the medium-temperature heat recovery chiller 213 is connected to the common pipeline 40 through the fifth control pump 55.
[0106] The control device is electrically connected to the third control pump 53. When the auxiliary heating pipeline 31 is in the on state, if the temperature fluctuation of the space to be regulated is within a preset range, the control device can control the opening degree of the third control pump 53 based on the temperature of the space to be regulated.
[0107] It should be noted that the overall structure of the three-medium heat exchanger 111 in this embodiment is a combination of a shell-and-tube heat exchanger and fins, and the innermost pipe constitutes the first medium channel, in which the medium is hot water. The channel in the outer tube constitutes the second medium channel, and the medium therein can be a material with high specific heat capacity and high phase change temperature, which is used to store and release thermal energy. The third medium is air, which is located in the third medium channel. The three-medium heat exchanger 111 can distribute the energy storage of the reheat section of the MAU. The air-conditioning system ensures the stable operation between the system heat source and the heat load and enables efficient and economical use of energy through intelligent control of different operating modes.
[0108] Among them, temperature detection points can be set in the three-medium heat exchanger for installing temperature sensors. It should be noted that, under the premise of not affecting the operation of the three-medium heat exchanger 111, the more temperature detection points are set, the better. The air conditioning system is heavy, and the energy storage state of the phase change material is monitored in real time through the temperature data fed back by the temperature sensor.
[0109] Assume that the set temperature threshold of the phase change process is T (in degrees Celsius), that is, the temperature threshold of the phase change material undergoing the phase change process is T, which is a temperature threshold determined by the phase change material itself. This embodiment needs to monitor the temperature of the phase change material (also referred to as the temperature of the three-medium heat exchanger 111). When it is detected that the temperature of the phase change material is greater than T (the temperature of the phase change material at this time can be recorded as t1), it indicates that the three-medium heat exchanger 111 has completed energy storage. When it is detected that the temperature of the phase change material is less than T (the temperature of the phase change material at this time can be recorded as t2), it indicates that the three-medium heat exchanger 111 has completed energy release. When the temperature of the phase change material is at T, it indicates that the phase change material is undergoing a phase change, that is, it is storing or releasing energy.
[0110] In this embodiment, when the air conditioning system is started for the first time, the system can operate normally, the first control pump 51, the second control pump 52, the third control pump 53, the fourth control pump 54 and the fifth control pump 55 can be turned on at the same time, and the air-cooled heat pump 211, the air-compressed heat recovery device 212 and the medium-temperature heat recovery chiller 213 simultaneously supply heat to the three-medium heat exchanger 111. When it is detected that the temperature of the three-medium heat exchanger (i.e., the temperature of the phase change material in the three-medium heat exchanger 111) t1 is greater than T, the three-medium heat exchanger 111 completes energy storage, and the first control pump 51 can be controlled to be turned off, and the air-compressed heat recovery device 212, the air-cooled heat pump 211 and the medium-temperature heat recovery chiller 213 no longer supply heat to the three-medium heat exchanger 111.
[0111] In this implementation, when in the valley scene, the control device of the air conditioning system can control the first control pump 51 and the second control pump 52 to be turned on, and then decide whether to turn on the three devices of the air-compressed heat recovery device 212, the air-cooled heat pump 211 and the medium-temperature heat recovery chiller 213 according to the required environmental conditions of the space to be regulated (such as indoors), and heat and store energy for the three-medium heat exchanger 111 while supplying heat to the indoor space. It should be noted that since it is currently in the valley scene, storing energy for the three-medium heat exchanger 111 at this time can better and reasonably utilize electrical energy.
[0112] When in the peak power scenario, if the temperature t1 of the three-medium heat exchanger 111 is greater than T, the first control pump 51, the second control pump 52, the third control pump 53, the fourth control pump 54 and the fifth control pump 55 can be controlled to be closed, the three-medium heat exchanger 111 can release energy, and the fresh air temperature adjustment of the MAU is completed independently by the three-medium heat exchanger 111. When it is detected that the temperature t2 of the three-medium heat exchanger 111 is less than T, the three-medium heat exchanger 111 completes the energy release. At this time, the states of the three devices of the air-compressed heat recovery device 212, the air-cooled heat pump 211 and the medium-temperature heat recovery chiller 213 can be determined according to the required indoor environmental conditions. When the required indoor environmental conditions indicate that heating needs to continue, the three devices of the air-compressed heat recovery device 212, the air-cooled heat pump 211 and the medium-temperature heat recovery chiller 213 can be controlled to be turned on to achieve indoor heating. It should be noted that, since the current power peak scenario is in progress, the first control pump 51 may be controlled to be turned off to prevent the three-medium heat exchanger 111 from consuming electricity in the power peak scenario, thereby saving electrical energy.
[0113] In this embodiment, when the indoor ambient temperature fluctuates within a preset range, the three-medium heat exchanger 111 can intelligently release heat according to the indoor temperature change, thereby better ensuring indoor demand. At the same time, the first control pump 51 and the third control pump 53 can be turned on, and the opening of the third control pump 53 can be adjusted accordingly to accurately control the heat supply to the three-medium heat exchanger 111, thereby better ensuring automatic adjustment of the indoor ambient temperature.
[0114] In addition, when the air-conditioning system suddenly loses power, or when the air-compressed heat recovery device 212, the air-cooled heat pump 211 and the medium-temperature heat recovery chiller 213 suddenly fail, the three-medium heat exchanger 111 of the air-conditioning system serves as the final heating guarantee to ensure indoor demand for a certain period of time.
[0115] When the heating device 21 needs to be turned on, the number of the air-compressed heat recovery device 212, the air-cooled heat pump 211, and the medium-temperature heat recovery chiller 213 to be turned on can be controlled according to actual needs. For example, if the indoor heat demand is large, the air-compressed heat recovery device 212, the air-cooled heat pump 211, and the medium-temperature heat recovery chiller 213 can all be turned on; if the indoor heat demand is small, only one or two of the devices can be turned on, and there is no limitation on this.
[0116] The air conditioning system may also include FFU (Fan Filter Units), i.e., fan filter unit 60, which is a terminal purification device that combines a fan and a filter (high efficiency filter (HEPA) or ultra high efficiency filter (ULPA)) to form a self-powered terminal purification device. More precisely, it is a modular terminal air supply device with self-power and filtering effect. The fan inhales air from the top of the FFU and filters it through the HEPA. The filtered clean air is evenly delivered at a wind speed of 0.45m / s±20% on the entire air outlet surface.
[0117] The number of the fan filter units 60 can be determined according to actual needs and is not limited thereto. For example, the air conditioning system may include three fan filter units 60 to better ensure the air intake. The gas discharged from the energy storage air conditioning box 11 can enter the room through the fan filter unit 60 to better ensure the comfort of air supply.
[0118] In addition, it should be noted that the medium-temperature heat recovery chiller 213 can be used not only for heating but also for cooling. The air conditioning system may also include a cold tower 80 and a dry cooling coil 70 (DCC) that cooperate with the medium-temperature heat recovery chiller 213. The cold tower 80 can store cold water. The cold tower 80 is connected to the medium-temperature heat recovery chiller 213. The medium-temperature heat recovery chiller 213 is connected to the dry cooling coil 70. The cold tower 80 can provide low-temperature cold water to the dry cooling coil 70 through the medium-temperature heat recovery chiller 213. When it is necessary to cool the room, the outdoor gas can be cooled by the dry cooling coil 70 and then enter the room through the fan filter unit 60, thereby providing refrigeration gas for the room.
[0119] In this embodiment, the settings can be initialized before using the air-conditioning system, that is, the operating parameters of the system can be set according to user needs and indoor and outdoor environmental conditions. And the operating mode selected by the system can be controlled according to the temperature difference between indoor and outdoor (the operating mode may include heating mode and cooling mode, for example). In the heating mode, when the indoor temperature is lower than the set demand value, if the phase change material completes energy storage, the phase change material can be used to release energy, and the air is heated through the three-medium heat exchanger 111 to provide hot air for the room. In addition, the control device of the air-conditioning system can monitor the indoor temperature in real time, and adjust the power and operating time of the heating device 21 according to the temperature difference. It should be noted that during the operation of the air-conditioning system, the control algorithm can be continuously optimized by collecting its operating data to improve the energy efficiency and stability of the system.
[0120] In this embodiment, the traditional water tank in the computer room can be eliminated to solve the problems of long water tank transmission and distribution distance and occupied computer room space. In addition, in this embodiment, in the case of electricity valley scenario, the heating device 21 can be used to store energy for the phase change material. In the case of electricity peak scenario, the phase change material releases energy to assist in temperature regulation of the space to be regulated. This embodiment can solve the problem of mismatch between the supply source of thermal energy and the load of thermal energy use, realize flexible transmission and distribution of energy, improve the stability and reliability of system operation under energy-load uncertainty, improve energy efficiency, realize peak shaving and valley filling of electric energy, and reduce dependence on electric energy.
[0121] The professionals should also be further aware that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented with electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in terms of function in the above description. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0122] It should be noted that the phrases "one implementation", "an embodiment", "an exemplary embodiment", "some embodiments", etc. mentioned in the specification indicate that the described embodiments may include certain features, structures or characteristics, but not every embodiment may include the certain features, structures or characteristics. In addition, such phrases do not necessarily refer to the same embodiment. In addition, when describing certain features, structures or characteristics in conjunction with an embodiment, it is within the knowledge of those skilled in the art to implement such features, structures or characteristics in conjunction with other embodiments, whether explicitly or not explicitly described.
[0123] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of more limiting values, the elements defined by the sentence "comprise a..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0124] The above embodiments are only preferred embodiments for fully illustrating the present application, and the protection scope of the present application is not limited thereto. Any equivalent substitution or change made by a person skilled in the art based on the present application is within the protection scope of the present application.
Claims
1. An air conditioning system, characterized in that: The air-conditioning system includes an energy storage air-conditioning box, a heating device and an auxiliary heating pipeline. The energy storage air-conditioning box includes a three-medium heat exchanger. The three-medium heat exchanger includes a first medium channel, a second medium channel and a third medium channel. The first medium channel is connected to the heat source output port of the heating device through the auxiliary heating pipeline. The second medium channel is provided with a phase change material. Part of the air flow channel of the energy storage air-conditioning box constitutes the third medium channel, and the input port of the air flow channel is connected to the space where the gas to be treated is located, and the output port of the air flow channel is connected to the space to be adjusted.
2. The air conditioning system according to claim 1, characterized in that: The air-conditioning system includes a first control pump and a control device, the first control pump is located in the auxiliary heating pipeline, the control device is electrically connected to the first control pump, and the control device is configured to control the on and off of the auxiliary heating pipeline through the first control pump based on the power consumption scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger.
3. The air conditioning system according to claim 2, characterized in that: The three-medium heat exchanger includes at least one temperature detection device, which is electrically connected to the control device and is used to detect the temperature of the phase change material in the three-medium heat exchanger.
4. The air conditioning system according to claim 1, characterized in that: The air conditioning system comprises a main heat supply pipeline, and the heat source channel of the energy storage air conditioning box is connected to the heat source output port of the heating device through the main heat supply pipeline; The air-conditioning system includes a second control pump and a control device, the second control pump is located in the main heating pipeline, the control device is electrically connected to the second control pump, and the control device is configured to control the on and off of the main heating pipeline through the second control pump based on the power consumption scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger.
5. The air conditioning system according to claim 4, characterized in that: The air-conditioning system includes a third control pump, the heating device includes an air-cooled heat pump, the main heating pipeline is connected to the heat source output port of the heating device through the third control pump, the control device is electrically connected to the third control pump, and the control device is configured to control the opening of the third control pump based on the temperature of the space to be regulated if the temperature fluctuation of the space to be regulated is within a preset range when the auxiliary heating pipeline is in a conducting state.
6. The air conditioning system according to any one of claims 1 to 4, characterized in that: The heating device comprises at least one of the following devices: Compressed air heat recovery unit, air-cooled heat pump, medium temperature heat recovery chiller.
7. A control method, characterized in that: The control method is applied to the air conditioning system according to any one of claims 1 to 4, and the control method comprises: Based on the electricity consumption scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger, the on-off of the auxiliary heating pipeline is controlled.
8. The control method according to claim 7, characterized in that: The controlling of the on-off of the auxiliary heating pipeline based on the electricity usage scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger includes at least one of the following: When the power consumption scenario is a valley power scenario and the temperature of the three-medium heat exchanger is greater than a set temperature threshold, the auxiliary heating pipeline is controlled to be in an on state or an off state; When the power consumption scenario is the power valley scenario and the temperature of the three-medium heat exchanger is lower than the set temperature threshold, controlling the auxiliary heating pipeline to be in a conducting state; When the electricity consumption scenario is a peak electricity consumption scenario, the auxiliary heating pipeline is controlled to be in a closed state.
9. The control method according to claim 7 or 8, characterized in that: The control method comprises: Based on the electricity usage scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger, the on-off of the main heating pipeline is controlled.
10. The control method according to claim 9, characterized in that: The controlling of the on-off of the main heating pipeline based on the electricity usage scenario of the heating device and / or the temperature of the phase change material in the three-medium heat exchanger includes at least one of the following: When the power consumption scenario is a valley power scenario, controlling the main heating pipeline to be in a conducting state; When the electricity consumption scenario is a peak electricity consumption scenario and the temperature of the three-medium heat exchanger is greater than a set temperature threshold, the main heating pipeline is controlled to be in a shut-off state; When the electricity consumption scenario is the electricity peak scenario and the temperature of the three-medium heat exchanger is less than the set temperature threshold, the main heating pipeline is controlled to be in a conducting state.
11. The control method according to claim 9, characterized in that: The air conditioning system includes a third control pump, the heating device includes an air-cooled heat pump, the main heating pipeline is connected to the heat source output port of the heating device through the third control pump, the control device is electrically connected to the third control pump, and the control method includes: When the auxiliary heating pipeline is in a conducting state, if the temperature fluctuation of the space to be conditioned is within a preset range, the opening degree of the third control pump is controlled based on the temperature of the space to be conditioned.