Coal seam sampling-while-drilling equipment, sampling method and gas loss measuring and calculating method

Through the sample equipment and methods of coal seam drilling, coal samples were collected and gas loss was calculated using a closed pressure-keeping environment, which solved the problems of low sampling efficiency, high cost and inaccurate gas content in the existing technology, and achieved the gas content of coal seam High accuracy determination.

CN119086161AActive Publication Date: 2024-12-06CHINA COAL TECH & ENG GRP SHENYANG ENG CO
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202411594886.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-11
Publication Date
2024-12-06
Estimated Expiration
2044-11-11

AI Technical Summary

Technical Problem

There are problems in the existing coal seam gas measurement technology, such as low sampling efficiency, high cost and inaccurate measurement of gas loss. Especially due to the errors and human factors during the gas desorption process, there are large errors in the determination of gas content of coal samples.

Method used

The coal seam drilling sampling equipment and methods are adopted, including outer drilling structure, closed pressure-keeping sample storage device, sampling drill bit, dual-powered drilling rig, outer drilling rod and inner drilling rod, coal sample collection through closed pressure-keeping environment and Gas loss measurement, gas loss is calculated using gas outflow speed sensor to reduce gas desorption and readsorption, and improve measurement accuracy.

Benefits of technology

High accuracy measurement of coal seam gas content is achieved, the drilling construction volume and man-made errors are reduced, the sampling efficiency and the authenticity of gas parameters are improved, and the measurement error of gas loss is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119086161A_ABST
    Figure CN119086161A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of coal seam sampling and gas measurement, and particularly provides coal seam sampling while drilling equipment, a sampling method and a gas loss measuring and calculating method.The coal seam sampling while drilling equipment comprises an outer layer drilling structure, a closed pressure maintaining sample storage device, a sampling drill bit, a dual-power drilling machine, an outer layer drilling rod, an inner layer drilling rod and a closed pressure maintaining adjusting device; a coal seam sampling while drilling method comprises the following specific steps that a dual-power drilling machine is arranged in a working area, and equipment assembling is carried out; non-sampling section drilling construction is conducted on the coal seam; drilling a coal sample from the coal seam; and taking out the coal sample, and replacing the closed pressure-maintaining sample storage device. Coal samples are continuously drilled through construction while drilling, the one-hole multi-section continuous sampling technology is achieved, and the drilling sampling utilization rate is increased; a coal sample drilling process of an original coal seam in a closed pressure-maintaining environment is realized by utilizing a closed pressure-maintaining sample storage device; the gas loss amount can be measured and calculated with high precision by using the measurement device for the gas emission speed of the confined space while drilling.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of coal seam sampling and gas measurement, and in particular provides a coal seam sampling while drilling device, a sampling method and a gas loss amount measuring method. Background Art

[0003] At present, most of the technologies and equipment used in the market for determining coal seam gas parameters adopt drilling rigs for drilling construction, use slag drill rods or sampling drill rods to transport coal samples from the bottom of the hole to the hole mouth, and use coal sample tanks to complete the direct sampling method of hole mouth sampling. Gas loss is difficult to avoid in this process, and considering that different media, different time periods, different coal qualities and other factors will affect the gas desorption law, therefore, due to the escape problem, the final extrapolated data may have large errors, which directly affects the reliability of laboratory measurement results.

[0004] In addition, in the direct sampling method, the coal sample taken at the borehole mouth is not necessarily the coal cuttings at the predetermined depth of the coal seam, and the sampling depth is subject to technical limitations. During the drilling process, the coal cuttings will desorb gas that is adsorbed on the surface of the borehole cracks, causing gas loss problems. At the same time, there is also the characteristic that a single borehole can only collect a single coal sample, resulting in low sampling efficiency and high cost.

[0005] The current method of directly measuring coal seam gas content underground in coal mines is affected by human factors. There are errors in coal sample exposure time in the process of determining gas loss, and errors in reading values ​​in the process of measuring underground gas desorption values. These results in inaccurate measurements of coal sample gas loss and desorption, and ultimately, large errors in the measurement of coal sample gas content.

[0006] Therefore, it is necessary to develop a new technology, device and method to solve the shortcomings of the traditional drill cuttings method, such as low sampling efficiency, high cost, collection of a single coal sample by a single drill and inaccurate measurement of gas content parameters at each stage, and to optimize the construction method of long-distance continuous coal sampling in complex environments and a new method for determining the gas content in coal seams. Summary of the invention

[0007] In order to solve the above technical problems, the technical solution adopted by the present invention is: a coal seam sampling while drilling equipment, including an outer drilling structure, a closed pressure-maintaining sample storage device, a sampling drill bit, a dual-power drilling rig, an outer drill rod, an inner drill rod and a closed pressure-maintaining adjustment device. The inner drill rod is coaxially assembled inside the outer drill rod, and the outer drill rod and the inner drill rod are both assembled on the dual-power drilling rig. The outer drilling structure and the sampling drill bit are respectively assembled at the front ends of the outer drill rod and the inner drill rod. The front end of the outer drilling structure is provided with a drilling bit, and the front port of the drilling bit is provided with a center valve plate. The closed pressure-maintaining sample storage device is arranged at the front end of the inner drill rod and is connected to the sampling drill bit. The sample cut by the sampling drill bit falls into the closed pressure-maintaining sample storage device. The rear part of the side wall of the sampling drill bit is equipped with a closed pressure-maintaining device, and the closed pressure-maintaining device is connected to the closed pressure-maintaining adjustment device through a pipeline.

[0008] Furthermore, the sealed pressure maintaining device is composed of a plurality of high-pressure sealed pressure maintaining capsules, which are mounted on the rear part of the side wall of the sampling drill bit. A second air duct is disposed inside the inner drill rod, one end of the second air duct is connected to the sealed pressure maintaining adjustment device, and the other end of the second air duct is provided with a plurality of branch ports, which are connected to the plurality of high-pressure sealed pressure maintaining capsules one by one.

[0009] Furthermore, the closed pressure-maintaining sample storage device is composed of a closed sample storage air chamber and an elastic pressure-maintaining capsule. The closed sample storage air chamber is a cylindrical structure. The front end of the closed sample storage air chamber is equipped with a sample storage air chamber valve plate, and the rear end of the outer surface of the closed sample storage air chamber is equipped with an elastic pressure-maintaining capsule. A first air duct is deployed inside the inner drill rod, and both ends of the first air duct are respectively connected to the closed pressure-maintaining regulating device and the elastic pressure-maintaining capsule.

[0010] A coal seam sampling while drilling method is provided, which uses a coal seam sampling while drilling device in the first embodiment, and the specific steps are as follows: Step 1: Arrange the dual-power drilling rig in the work area and assemble the equipment; Step 2: Drilling a non-sampling section into the coal seam; Step 3: Drilling coal samples from the coal seam; Open the central valve plate of the drilling bit, operate the outer dynamic load device, retreat the outer drilling structure to the rear of the closed pressure-maintaining device, operate the closed pressure-maintaining regulating device, inflate the elastic pressure-maintaining capsule and the high-pressure closed pressure-maintaining capsule, and when the elastic pressure-maintaining capsule and the high-pressure closed pressure-maintaining capsule are fully expanded, adjust the closed pressure-maintaining regulating system to maintain the gas pressure in the capsule to form a closed pressure-maintaining sampling space, open the valve plate of the sample storage air chamber, start the drilling function of the inner dynamic load device, start the sampling section drilling and sampling operation, and use the sampling drill bit to drill the coal sample through the valve plate of the sample storage air chamber into the closed sample storage air chamber. After the sampling section drilling and sampling construction are completed, close the valve plate of the sample storage air chamber, stop the drilling function of the inner dynamic load device, and complete the single sampling operation; Step 4: Take out the coal sample and replace the sealed pressure-maintaining sample storage device; Step 5: Repeat the operations of steps 3 and 4 to complete multiple consecutive samplings for a single borehole.

[0011] Furthermore, the specific method of step four is to operate the closed pressure maintaining adjustment device to relieve the pressure of the elastic pressure maintaining capsule and the high-pressure closed pressure maintaining capsule. After the pressure is completely relieved, the outer dynamic load device is operated to send the outer drilling structure to the front section of the drilling hole, and at the same time, the inner dynamic load device is operated to withdraw the sampling drill bit and the closed pressure maintaining sample storage device containing the coal sample into the outer drilling structure, and then the center valve plate is closed to continue to retract the closed pressure maintaining sample storage device until it passes through the outer drill rod and completely exits the drilling hole.

[0012] A method for calculating gas loss, based on a coal seam sampling while drilling method in Embodiment 2; A gas outflow velocity measuring sensor is embedded in the front end of the inner wall of the sampling drill bit, and a gas outflow velocity measuring sensor is embedded in the front end of the inner wall of the closed sample storage chamber; The gas outflow velocity measuring sensor can identify conventional parameters such as pressure and temperature of gas in the borehole and the sample gas storage chamber, and has a built-in timing module and a storage module. The gas outflow velocity data in the sample gas storage chamber can be obtained through calculation according to the identified parameters, and the data is recorded in the storage module; The specific process is as follows: When the rotation function of the outer power load device of the dual-power drilling rig is stopped, the time t1 is recorded, and when the drilling function of the inner power load device is stopped, the time t2 is recorded; When exiting the inner layer pressure-maintaining drilling sampling structure, remove the gas outflow velocity measuring sensor on the inner side wall of the sampling drill bit. After the laboratory measures the gas desorption and residual amount of the coal sample, remove the gas outflow velocity measuring sensor on the inner side wall of the closed sample storage chamber. The gas outflow velocity is measured by a computer reading measuring device, that is, at time t1, the gas outflow velocity of the sampling section is K1, and the inflow velocity of the sample storage chamber is K2. At time t2, the gas outflow velocity of the sampling section is K3, and the inflow velocity of the sample storage chamber is K4. The calculation formula of gas loss in hole sampling is: Formula 1: V 损 =V 钻 -V 气室 ; Formula 2: V 钻 =Q 钻 Δt=(K3-K1)S 钻 (t2-t1); Formula 3: V 气室 =Q 气室 Δt=(K4-K2)S 钻 (t2-t1); Where: V 损 is the sampling gas loss (m³); V 钻 is the gas outflow volume of the sampling section (m³); V 气室 is the gas inflow into the sample storage chamber (m³); Q 钻 is the amount of gas passing through the sampling section borehole per unit time (m³ / min); Q 气室 is the amount of gas passing through the sample storage chamber per unit time (m³ / min); S 钻 is the cross-sectional area of ​​the borehole in the sampling section, m2; S 气室 is the cross-sectional area of ​​the sample storage chamber, m2; K1 is the gas outflow velocity at sampling section t1 (m³ / min·㎡); K2 is the gas inflow rate of the sample storage chamber at t1 (m³ / min·㎡); K3 is the gas outflow rate at the sampling section t2 (m³ / min·㎡); K4 is the gas inflow rate of the sample storage chamber at t2 (m³ / min·㎡); Through theoretical calculation, the coal seam gas loss V during sampling is determined 损 .

[0013] Furthermore, the operation flow is encoded into the firmware device according to the calculation formula of the gas loss amount of the hole sampling.

[0014] The beneficial effects of using the present invention are: The present invention utilizes continuous drilling and sampling of coal samples while drilling to realize the process of continuous drilling and sampling of coal samples in the original coal seam while drilling, greatly reduces the exposure time of the drilled coal samples, eliminates the moving drilling distance of the drilled coal samples, eliminates the work of traditional hole drilling and sampling and the hidden dangers of human operation errors, reduces the drilling construction volume, avoids the problem of drilling trajectory deviation caused by complete drill withdrawal, realizes a one-hole multi-segment continuous sampling technology, and improves the utilization rate of drilling sampling; The elastic pressure-maintaining function of the sealed pressure-maintaining sample storage device and the high-pressure sealed pressure-maintaining capsule of the sealed pressure-maintaining device are used to maintain the pressure in the drilling coal sample environment, so as to realize the original coal seam coal sampling process under the sealed pressure-maintaining environment, ensure the sealed isolation of the sampling space from the outside world, reduce the loss of gas desorption amount of the drilling coal sample, improve the accuracy of gas desorption amount measurement, and improve the authenticity of gas parameters of the original coal seam; The gas outburst velocity measuring device for enclosed space while drilling is used to measure the gas flow velocity in the borehole and the gas flow velocity in the enclosed sample storage chamber during the sampling process. The gas loss amount during the sampling process can be determined by calculation, eliminating the orifice loss of gas desorption in drill cuttings sampling, the re-adsorption loss in the hole wall cracks, and the human error value of the loss amount, thereby improving the accuracy of coal seam gas content. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the sampling drill bit of the present invention being stored inside the outer drilling structure; Figure 2 It is a schematic diagram of the sampling drill bit of the present invention in a sampling operation state; The reference numerals in the drawings include: 1. outer drilling structure; 2. closed pressure-maintaining sample storage device; 3. drilling drill bit; 4. sampling drill bit; 5. dual-power drilling rig; 501. outer power load device; 502. inner power load device; 6. closed pressure-maintaining device; 601. high-pressure closed pressure-maintaining capsule; 7. elastic pressure-maintaining capsule; 801. first air duct; 802. second air duct; 9. central valve plate; 10. sample storage air chamber valve plate; 11. closed sample storage air chamber; 1201. first gas outflow rate measuring sensor; 1202. second gas outflow rate measuring sensor; 13. outer drill pipe; 14. inner drill pipe; 15. coal sample; 16. coal seam; 17. closed pressure-maintaining regulating device. DETAILED DESCRIPTION

[0016] The present invention is described in detail below with reference to the accompanying drawings.

[0017] Embodiment 1

[0018] Reference Figure 1 and Figure 2 A coal seam sampling while drilling equipment comprises an outer drilling structure 1, a sealed pressure-maintaining sample storage device 2, a sampling drill bit 4, a dual-power drilling rig 5, an outer drill rod 13, an inner drill rod 14 and a sealed pressure-maintaining adjustment device 17, wherein the inner drill rod 14 is coaxially assembled inside the outer drill rod 13, and the outer drill rod 13 and the inner drill rod 14 are assembled on the dual-power drilling rig 5, and the outer drilling structure 1 and the sampling drill bit 4 are respectively assembled on the outer drill rod 13 and the inner drill rod 14. At the front end of the rod 14, the front end of the outer drilling structure 1 is provided with a drilling bit 3, the front port of the drilling bit 3 is provided with a central valve plate 9, the closed pressure-maintaining sample storage device 2 is provided at the front end of the inner drill rod 14, and is connected to the sampling drill bit 4, the sample cut by the sampling drill bit 4 falls into the closed pressure-maintaining sample storage device 2, the rear part of the side wall of the sampling drill bit 4 is equipped with a closed pressure-maintaining device 6, and the closed pressure-maintaining device 6 is connected to the closed pressure-maintaining regulating device 17 through a pipeline.

[0019] Specifically, annular track frames are arranged at equal intervals inside the outer drill rod 13 , and the inner drill rod 14 is slidably assembled inside the outer drill rod 13 through the annular track frames.

[0020] Preferably, the sealed pressure-maintaining regulating device 17 uses nitrogen as the gas source and a high-pressure air pump as the pressurized gas supply equipment.

[0021] The sealed pressure-maintaining device 6 is composed of a plurality of high-pressure sealed pressure-maintaining capsules 601, which are mounted on the rear part of the side wall of the sampling drill bit 4. A second air duct 802 is disposed inside the inner drill rod 14. One end of the second air duct 802 is connected to the sealed pressure-maintaining adjustment device 17. The other end of the second air duct 802 is provided with a plurality of branch ports, which are connected to the plurality of high-pressure sealed pressure-maintaining capsules 601 in a one-to-one correspondence.

[0022] The sealed pressure-maintaining sample storage device 2 is composed of a sealed sample storage air chamber 11 and an elastic pressure-maintaining capsule 7. The sealed sample storage air chamber 11 is a cylindrical structure. The front end of the sealed sample storage air chamber 11 is equipped with a sample storage air chamber valve plate 10, and the rear end of the outer surface of the sealed sample storage air chamber 11 is equipped with an elastic pressure-maintaining capsule 7. A first air duct 801 is deployed inside the inner drill rod 14, and both ends of the first air duct 801 are respectively connected to the sealed pressure-maintaining adjustment device 17 and the elastic pressure-maintaining capsule 7.

[0023] An outer power load device 501 and an inner power load device 502 are provided in the dual-power drilling rig 5 . The outer power load device 501 and the inner power load device 502 are connected to the outer drill rod 13 and the inner drill rod 14 respectively.

[0024] Embodiment 2

[0025] A coal seam sampling while drilling method is provided, which uses a coal seam sampling while drilling device in the first embodiment, and the specific steps are as follows: Step 1: Arrange the dual-power drilling rig 5 in the working area and assemble the equipment; Specifically, at the drilling site, the drilling bit 3 with an adjustable central valve plate 9 is connected to the outer drilling rod 13 to form an outer drilling structure 1; The sampling drill bit 4 is connected to the inner drill rod 14, and the closed sample storage chamber 11 containing the sample storage chamber valve plate 10 is connected to the elastic pressure-maintaining capsule 7 to form a closed pressure-maintaining sample storage device 2; The sealed pressure-maintaining sample storage device 2 is connected to the sampling drill bit 4 through the track groove to be assembled into an inner layer pressure-maintaining drilling sampling structure.

[0026] Step 2: Drilling a non-sampling section into the coal seam 16; Specifically, the dual-power drilling rig 5 is started, the drilling function of the outer power load device 501 is turned on, and at the same time, the propulsion function of the inner power load device 502 is turned on to push the inner pressure-maintaining drilling sampling structure into the borehole along with the outer drilling structure.

[0027] Step 3, drilling a coal sample 15 from the coal seam; Specifically, when the outer drilling structure 1 is constructed to the designed non-sampling section position in front of the sampling section, the rotation function of the outer power load device 501 of the dual-power drilling rig 5 is stopped, the central valve plate 9 of the drilling drill bit 3 is opened, the outer power load device 501 is operated, and the outer drilling structure 1 is retreated to the rear of the closed pressure maintaining device, and the closed pressure maintaining regulating device 17 is operated to inflate the elastic pressure maintaining capsule 7 and the high-pressure closed pressure maintaining capsule 601. When the elastic pressure maintaining capsule 7 and the high-pressure closed pressure maintaining capsule 601 are fully expanded, the regulating device 17 is operated. The closed pressure-maintaining regulating system 17 is opened to maintain the gas pressure in the capsule to form a closed pressure-maintaining sampling space, the sample storage air chamber valve plate 10 is opened, the drilling function of the inner layer dynamic load device 502 is started, and the sampling section drilling and sampling operations are started. The coal sample 15 is drilled by the sampling drill bit 4 and passes through the sample storage air chamber valve plate 10 into the closed sample storage air chamber 11. After the sampling section drilling and sampling construction are completed, the sample storage air chamber valve plate 10 is closed, the drilling function of the inner layer dynamic load device 502 is stopped, the single sampling operation is completed, and the time t2 is recorded.

[0028] Step 4: Take out the coal sample 15 and replace the sealed pressure-maintaining sample storage device 2; Specifically, the closed pressure-maintaining regulating device 17 is operated to relieve the pressure of the elastic pressure-maintaining capsule 7 and the high-pressure closed pressure-maintaining capsule 601. After the pressure is completely relieved, the outer layer dynamic loading device 501 is operated to send the outer layer drilling structure 1 to the front section of the drilling hole. At the same time, the inner layer dynamic loading device 502 is operated to withdraw the sampling drill bit 4 and the closed pressure-maintaining sample storage device 2 containing the coal sample 15 into the outer layer drilling structure 1. Then, the central valve plate 9 is closed, and the closed pressure-maintaining sample storage device 2 is continuously withdrawn until it passes through the outer layer drill rod 13 and completely exits the drilling hole. Replace the new sealed pressure-maintaining sample storage device 2, and then send it to the front position of the outer drilling structure 1 through the inner dynamic load device 502 to prepare for the next sampling.

[0029] Step 5, repeat the operations of step 3 and step 4 to complete multiple continuous sampling of a single borehole; Specifically, during the operation of step 4, the operation of step 2 is simultaneously implemented to perform the non-sampling section drilling construction, that is, the implementation of step 4 does not affect the implementation of step 2.

[0030] Embodiment 3

[0031] A method for calculating gas loss, based on a coal seam sampling while drilling method in Embodiment 2; A first gas outflow velocity measuring sensor 1201 is embedded in the front end of the inner wall of the sampling drill bit 4 , and a second gas outflow velocity measuring sensor 1202 is embedded in the front end of the inner wall of the sealed sample storage gas chamber 11 .

[0032] When the propulsion function of the inner layer dynamic load device 502 is turned on, the first gas outflow velocity measuring sensor 1201 and the second gas outflow velocity measuring sensor 1202 are turned on.

[0033] The gas outflow rate measuring sensor can identify conventional parameters such as pressure and temperature of gas in the borehole and the closed sample storage chamber 11, and has a built-in timing module and storage module. It can obtain the gas outflow rate data in the sample storage chamber through calculation based on the identified parameters and record the data in the storage module.

[0034] A method for calculating gas loss, the specific process is as follows: When the rotation function of the outer power load device 501 of the dual-power drilling rig 5 is stopped, the time t1 is recorded, and when the drilling function of the inner power load device 502 is stopped, the time t2 is recorded; When exiting the inner layer pressure-maintaining drilling sampling structure, remove the first gas outflow velocity measuring sensor 1201, and after the laboratory measures the desorption amount and residual amount of the coal sample gas, remove the second gas outflow velocity measuring sensor 1202, and measure the gas outflow velocity by reading the measuring device through a computer, that is, at time t1, the gas outflow velocity of the sampling section is K1, and the inflow velocity of the sample storage chamber is K2, and at time t2, the gas outflow velocity of the sampling section is K3, and the inflow velocity of the sample storage chamber is K4; The calculation formula of gas loss in hole sampling is: Formula 1: V 损 =V 钻 -V 气室 ; Formula 2: V 钻 =Q 钻 Δt=(K3-K1)S 钻 (t2-t1); Formula 3: V 气室 =Q 气室 Δt=(K4-K2)S 钻 (t2-t1); Where: V 损 is the sampling gas loss (m³); V 钻 is the gas outflow volume of the sampling section (m³); V 气室 is the gas inflow into the sample storage chamber (m³); Q 钻is the amount of gas passing through the sampling section borehole per unit time (m³ / min); Q 气室 is the amount of gas passing through the sample storage chamber per unit time (m³ / min); S 钻 is the cross-sectional area of ​​the borehole in the sampling section, m2; S 气室 is the cross-sectional area of ​​the sample storage chamber, m2; K1 is the gas outflow velocity at sampling section t1 (m³ / min·㎡); K2 is the gas inflow rate of the sample storage chamber at t1 (m³ / min·㎡); K3 is the gas outflow rate at the sampling section t2 (m³ / min·㎡); K4 is the gas inflow rate of the sample storage chamber at t2 (m³ / min·㎡); Through theoretical calculation, the coal seam gas loss V during sampling is determined 损 ; By encoding the above calculation process into the firmware device (which can be achieved using the mature single-chip microcomputer coding method on the market), the gas loss amount in the hole can be determined.

[0035] The above contents are only preferred embodiments of the present invention. For ordinary technicians in this field, many changes can be made in the specific implementation methods and application scopes based on the ideas of the present invention. As long as these changes do not deviate from the concept of the present invention, they all belong to the protection scope of the present invention.

Claims

1. A coal seam sampling while drilling equipment, Features: The utility model comprises an outer drilling structure, a closed pressure-maintaining sample storage device, a sampling drill bit, a dual-power drilling rig, an outer drill rod, an inner drill rod and a closed pressure-maintaining regulating device. The inner drill rod is coaxially assembled inside the outer drill rod, and both the outer drill rod and the inner drill rod are assembled on the dual-power drilling rig. The outer drilling structure and the sampling drill bit are respectively assembled at the front ends of the outer drill rod and the inner drill rod. The front end of the outer drilling structure is provided with a drilling bit, and the front port of the drilling bit is provided with a center valve plate. The closed pressure-maintaining sample storage device is arranged at the front end of the inner drill rod and is connected to the sampling drill bit. The sample cut by the sampling drill bit falls into the closed pressure-maintaining sample storage device. The rear part of the side wall of the sampling drill bit is provided with a closed pressure-maintaining device, and the closed pressure-maintaining device is connected to the closed pressure-maintaining regulating device through a pipeline.

2. A coal seam sampling while drilling device according to claim 1, Features: The sealed pressure maintaining device is composed of a plurality of high-pressure sealed pressure maintaining capsules, which are mounted on the rear part of the side wall of the sampling drill bit. A second air duct is disposed inside the inner drill rod, one end of the second air duct is connected to the sealed pressure maintaining adjustment device, and the other end of the second air duct is provided with a plurality of branch ports, which are connected to the plurality of high-pressure sealed pressure maintaining capsules one by one.

3. According to the coal seam sampling while drilling device described in claim 1, Features: The sealed pressure-maintaining sample storage device is composed of a sealed sample storage air chamber and an elastic pressure-maintaining capsule. The sealed sample storage air chamber is a cylindrical structure. The front end of the sealed sample storage air chamber is equipped with a sample storage air chamber valve plate, and the rear end of the outer surface of the sealed sample storage air chamber is equipped with an elastic pressure-maintaining capsule. A first air guide tube is deployed inside the inner drill rod, and both ends of the first air guide tube are respectively connected to the sealed pressure-maintaining adjustment device and the elastic pressure-maintaining capsule.

4. A coal seam sampling while drilling method, using a coal seam sampling while drilling device as claimed in claim 1, Features: The specific steps are as follows: Step 1: Arrange the dual-power drilling rig in the work area and assemble the equipment; Step 2: Drilling a non-sampling section into the coal seam; Step 3: Drilling coal samples from the coal seam; Open the central valve plate of the drilling bit, operate the outer dynamic load device, retreat the outer drilling structure to the rear of the closed pressure-maintaining device, operate the closed pressure-maintaining regulating device, inflate the elastic pressure-maintaining capsule and the high-pressure closed pressure-maintaining capsule, and when the elastic pressure-maintaining capsule and the high-pressure closed pressure-maintaining capsule are fully expanded, adjust the closed pressure-maintaining regulating system to maintain the gas pressure in the capsule to form a closed pressure-maintaining sampling space, open the valve plate of the sample storage air chamber, start the drilling function of the inner dynamic load device, start the sampling section drilling and sampling operation, and use the sampling drill bit to drill the coal sample through the valve plate of the sample storage air chamber into the closed sample storage air chamber. After the sampling section drilling and sampling construction are completed, close the valve plate of the sample storage air chamber, stop the drilling function of the inner dynamic load device, and complete the single sampling operation; Step 4: Take out the coal sample and replace the sealed pressure-maintaining sample storage device; Step 5: Repeat the operations of steps 3 and 4 to complete multiple consecutive samplings for a single borehole.

5. A coal seam sampling while drilling method according to claim 4, Features: The specific method of step four is to operate the closed pressure maintaining adjustment device to relieve the pressure of the elastic pressure maintaining capsule and the high-pressure closed pressure maintaining capsule. After the pressure is completely relieved, operate the outer dynamic load device to send the outer drilling structure to the front section of the drilling hole, and at the same time operate the inner dynamic load device to withdraw the sampling drill bit and the closed pressure maintaining sample storage device containing the coal sample into the outer drilling structure, then close the center valve plate, and continue to retract the closed pressure maintaining sample storage device until it passes through the outer drill rod and completely exits the drilling hole.

6. A method for calculating gas loss, based on a coal seam sampling while drilling method as claimed in claim 4; A gas outflow velocity measuring sensor is embedded in the front end of the inner wall of the sampling drill bit, and a gas outflow velocity measuring sensor is embedded in the front end of the inner wall of the closed sample storage chamber; The gas outflow velocity measuring sensor can identify conventional parameters such as pressure and temperature of gas in the borehole and the sample gas storage chamber, and has a built-in timing module and a storage module. The gas outflow velocity data in the sample gas storage chamber can be obtained through calculation according to the identified parameters, and the data is recorded in the storage module; The specific process is as follows: When the rotation function of the outer power load device of the dual-power drilling rig is stopped, record the time t 1 , when the inner layer dynamic load device drilling function is stopped, record the time t 2 ; When exiting the inner pressure-maintaining drilling sampling structure, remove the gas outflow velocity measuring sensor on the inner wall of the sampling drill bit. After the laboratory measures the gas desorption and residual amount of the coal sample, remove the gas outflow velocity measuring sensor on the inner wall of the closed sample storage chamber. The gas outflow velocity is measured by the computer reading measuring device, that is, t 1 At time , the gas outflow speed K in the sampling section 1 , the influx velocity of the sample chamber is K 2 , t 2 At the moment, the gas outflow speed in the sampling section is K 3 , the influx velocity of the sample chamber is K 4 ; The calculation formula of gas loss in hole sampling is: Formula 1: V 损 =V 钻 -V 气室 ; Formula 2: V 钻 =Q 钻 ·Δt=(K 3 -K 1 )·S 钻 ·(t 2 -t 1 ); Formula 3: V 气室 =Q 气室 ·Δt=(K 4 -K 2 )·S 钻 ·(t 2 -t 1 ); Where: V 损 is the sampling gas loss (m³); V 钻 is the gas outflow volume of the sampling section (m³); V 气室 is the gas inflow into the sample storage chamber (m³); Q 钻 is the amount of gas passing through the sampling section borehole per unit time (m³ / min); Q 气室 is the amount of gas passing through the sample storage chamber per unit time (m³ / min); S 钻 is the cross-sectional area of ​​the borehole in the sampling section, m2; S 气室 is the cross-sectional area of ​​the sample storage chamber, m2; K 1 t 1 Gas outflow rate in sampling section (m³ / min·㎡); K 2 t 1 Gas inflow rate of sample storage chamber (m³ / min·㎡); K 3 t 2 Gas outflow rate in sampling section (m³ / min·㎡); K 4 t 2 Gas inflow rate of sample storage chamber (m³ / min·㎡); Through theoretical calculation, the coal seam gas loss V during sampling is determined 损 .

7. According to the method for calculating gas loss amount described in claim 6, Features: According to the calculation formula of the gas loss amount of the hole sampling, the operation process is encoded into the firmware device.

Citation Information

Patent Citations

  • Underground reverse circulation sampling gas desorption process simulation test device and test method

    CN106093338A

  • Pressure-maintaining airtight coal sample collecting device and method

    CN108547614A

  • Sealed sampling device for coal seam while drilling

    CN110646236A

  • Underground direct determination method for coal seam gas content

    CN113049440A

  • Near-bit coal seam gas parameter while-drilling comprehensive measurement device and method

    CN113266347A