Engineering monitoring management system based on 5G application
By analyzing weather and date factors, combining project progress, and calculating the daily standard progress of the construction site, the problem of inaccurate prediction in the existing technology is solved, and the accuracy and trust of project management are improved.
Patent Information
- Application Number
- CN202411138509.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
When obtaining the total amount of pre-completed, the existing engineering monitoring and management system ignores the impact of weather information, remaining time of the project and progress, resulting in inaccurate prediction of the total amount of project completion, and the impact of the progress of the working day in the future has not been considered, resulting in Management hassle and reduced trust.
By obtaining weather information, date conditions and target information of the detection area, we analyze the weather efficiency factor, date incentive factor and first progress incentive factor, calculate the daily standard progress of the construction site, and use this to allocate the differential amount of the engineering team to ensure that The project is completed on schedule.
It improves the accuracy of project completion forecasts, ensures that the engineering team completes tasks on schedule, and enhances the trust and efficiency of the management system.
Smart Images

Figure CN119090066A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of smart construction sites and relates to engineering monitoring and management technology, specifically an engineering monitoring and management system based on 5G applications. Background Art
[0002] With the promotion of the concept of smart cities, smart construction sites, as an important part of smart city construction, need to improve the intelligence level of engineering construction through advanced communication technologies and management methods. 5G networks, as a transmission method with high transmission speed and low latency, provide better communication infrastructure for real-time monitoring of data. At the same time, with the development of the economy and the advancement of science and technology, the scale and complexity of construction projects are also increasing. How to build an engineering monitoring and management system that can intelligently monitor the construction site and enable the engineering team to complete the work tasks on schedule has been widely studied.
[0003] At present, most engineering monitoring and management systems find it difficult to adjust the progress of engineering teams according to the remaining time and the expected total amount of project completion in engineering monitoring and management, resulting in the engineering teams being unable to complete their work tasks on schedule and causing economic losses. At the same time, most engineering monitoring and management systems ignore the impact of weather information, the remaining time of the project, and the progress of the project on the total amount of project completion when obtaining the expected total amount of project completion. They only mechanically analyze the total amount of project completion, resulting in inaccurate prediction of the total amount of project completion. When analyzing the impact of the progress on the total amount of project completion, they ignore the fact that there is no actual progress in the upcoming working days, resulting in inaccurate prediction of the total amount of project completion. This brings management troubles to managers and reduces the trust of the using companies in the system.
[0004] Therefore, the present invention discloses an engineering monitoring and management system based on 5G applications to solve the above technical problems. Summary of the invention
[0005] The present invention aims to solve at least one of the technical problems existing in the prior art; to this end, the present invention proposes an engineering monitoring and management system based on 5G applications, which is used to solve the technical problems that when obtaining the pre-completed total amount in engineering monitoring and management, the influence of weather information, remaining project time and progress status on the total project completion amount is ignored, and when analyzing the influence of progress status on the total project completion amount, the lack of actual progress on the upcoming working days is ignored, resulting in inaccurate prediction of the total project completion amount. The present invention obtains weather information, date conditions and target information of each detection area, analyzes the weather information to obtain the weather efficiency factor of each date; analyzes the date conditions to obtain the date incentive factor of each date; obtains the first progress incentive factor of each detection area based on the target information; and obtains the subsequent daily standard progress of the construction site through the weather efficiency factor, the date incentive factor and the first progress incentive factor to solve the above problems.
[0006] To achieve the above-mentioned object, a first aspect of the present invention provides an engineering monitoring and management system based on 5G applications, comprising: a data analysis module, and an information collection module, a monitoring and management module and a database connected thereto;
[0007] The information collection module is used to plan the construction site into several detection areas, and obtain basic information and target information of each detection area; wherein the basic information includes weather information and date conditions; weather information includes daily maximum temperature and daily rainfall; date conditions include the proportion of the current date, working days and rest days; target information includes the amount of building materials used, the height of the built building and the proportion of the built building area;
[0008] The data analysis module is used to analyze weather information to obtain weather efficiency factors for each date, analyze date conditions to obtain date incentive factors for each date; obtain the first progress incentive factor for each detection area based on target information; and obtain the subsequent daily standard progress of the construction site through the weather efficiency factor, date incentive factor and first progress incentive factor;
[0009] The monitoring and management module is used to calculate the daily standard progress to obtain the total engineering variance, and to allocate the variance to the engineering teams based on the total engineering variance.
[0010] Preferably, the data analysis module communicates and / or is electrically connected to the information collection module, the monitoring management module and the database respectively; the database communicates and / or is electrically connected to the information collection module, the data analysis module and the monitoring management module respectively.
[0011] Preferably, the construction site is planned into several detection areas, including:
[0012] Use drones equipped with high-resolution cameras and 5G communication technology to obtain the digital surface model of the construction site in real time. Use 3D modeling technology to process the digital surface model and input the digital surface model as design data into the BIM software to obtain a 3D model of the construction site.
[0013] Select important building points in the three-dimensional model, obtain the center position and area ZMi of each important building point, and obtain the predetermined area YDi based on the formula YDi=ZMi×BL; delineate the area circle of each important building point with the center position of each important building point as the center and the predetermined area YDi as the range size; wherein BL is the ratio adjustment coefficient, and i is the number of important building points;
[0014] Get whether there are overlapping areas in the area circles of each important building point; if yes, divide the overlapping areas equally to obtain evenly divided areas, obtain the center distance between the center point of each evenly divided area and the center position of each important building point, and assign each evenly divided area to the area circle of the corresponding important building point with the smallest center distance; if no, do nothing;
[0015] The construction site area corresponding to the area circle of each important building point is marked as the detection area of each important building point.
[0016] It is worth noting that in this step, the construction site is planned into several detection areas, and the detection areas are analyzed and then the construction site is managed comprehensively. This is because different areas of the construction site may have different progress of construction. If the construction site is directly analyzed and then managed, it is very likely that several construction works will interfere with each other, making the analysis results inaccurate.
[0017] Preferably, the obtaining of basic information and target information of each detection area includes:
[0018] Get the ratio of the current date to the entire project cycle, and mark the value of the ratio as the ratio position;
[0019] Obtain statutory holidays in the current project cycle, mark the statutory holidays as rest days, obtain the daily maximum temperature and daily rainfall of each day within the project period through a computer, and determine whether the daily maximum temperature or daily rainfall of each day exceeds the corresponding set threshold; if yes, mark the corresponding date as a rest day; if no, mark the corresponding date as a working day; wherein the set threshold is obtained through experience;
[0020] The amount of building materials used is obtained through the registration form, and the height and area of built buildings are obtained in real time through surveillance cameras connected to 5G signals. The ratio of the built building area to the area of the detection area is marked as the built building area ratio.
[0021] It should be noted that built buildings are buildings that have been completed or are under construction by the engineering team.
[0022] Preferably, the weather information is analyzed to obtain the weather efficiency factor for each date, including:
[0023] Extract the daily maximum temperature RZW and daily rainfall RY of each day within the project period, extract the set optimum daily maximum temperature ZRZW, and judge whether the daily maximum temperature RZW of each day exceeds the optimum daily maximum temperature ZRZW; if yes, obtain the weather efficiency factor TLY of each day based on the formula TLY=β1×exp(-|α1×(RZW-ZRZW) / ZRZW|)+β2 / exp(RY / BRY); if no, obtain the weather efficiency factor TLY of each day based on the formula TLY=β1×exp(-|α2×(RZW-ZRZW) / ZRZW|)+β2 / exp(RY / BRY); wherein, the optimum daily maximum temperature is the daily maximum temperature corresponding to the highest daily work efficiency, BRY is the standard rainfall that does not affect construction, α1 and α2 are both amplitude adjustment coefficients, and β1 and β2 are both proportional adjustment coefficients greater than 0.
[0024] It is worth noting that the curve obtained by combining the functions exp(-|α1×(RZW-ZRZW) / ZRZW|) and exp(-|α2×(RZW-ZRZW) / ZRZW|) is the influence curve of the daily maximum temperature RZW on the weather efficiency factor TLY. This curve presents a shape with low sides and high middle. The farther the daily maximum temperature RZW is from the optimum daily maximum temperature ZRZW, the greater the influence on the weather efficiency factor TLY, which in turn leads to a smaller value of the weather efficiency factor TLY. When the daily maximum temperature RZW is equal to the daily maximum temperature ZRZW, it indicates that the daily maximum temperature of the day is suitable for construction and the construction efficiency is the highest. The value of the weather efficiency factor TLY obtained without considering the influence of daily rainfall RY is also the largest.
[0025] Preferably, the step of analyzing the date conditions to obtain the date incentive factors for each date includes:
[0026] Get the ratio of working days after the current date to the project cycle, and mark the ratio as the workable ratio GBL; extract the ratio position BLW of the current date, and obtain the date incentive factor RLY of each date based on the formula RLY=γ×BLW / exp(GBL); wherein γ is the ratio adjustment coefficient.
[0027] It should be noted that the larger the BLW of the current date, the smaller the number of days remaining in the project cycle, which means that the incentive for the engineering team's work efficiency is greater, which in turn leads to an increase in the value of the date incentive factor; the larger the workable proportion GBL, the higher the proportion of subsequent working days. When there are more workable days, the incentive for the engineering team's work efficiency is smaller, which in turn leads to a decrease in the value of the date incentive factor.
[0028] Preferably, obtaining the first progress incentive factor of each detection area based on the target information includes:
[0029] Extract the usage of building materials CYL, the height of built buildings YZG, and the proportion of built building area YMB in each area; obtain the first progress incentive factor YDLZ of each detection area based on the formula YDLZ=1-δ×ln(ρ1×CYL / YCYL+ρ2×YZG / BYZG+ρ3×YMB / BYMB); among which YCYL is the estimated usage of building materials in each area, BYZG is the estimated total height of buildings in each area, and BYMB is the estimated total area of buildings in each area; δ is an amplitude adjustment factor greater than 0, ρ1, ρ2, and ρ3 are all proportion adjustment factors, and ρ1+ρ2+ρ3=1.
[0030] It should be noted that the first progress incentive factor obtained in this step represents the progress incentive situation obtained by analyzing the construction progress on site on that day. The first progress incentive factor obtained through actual survey can be used as a basic data to predict the progress of subsequent dates.
[0031] Preferably, obtaining the subsequent daily standard progress of the construction site through the weather efficiency factor, the date incentive factor and the first progress incentive factor includes:
[0032] A1: Number each working day between the current date and the project deadline from the earliest to the latest according to the time, extract the working days in sequence according to the number n, and determine whether the number n of the working day is 1; if yes, jump to A2; if no, jump to A3;
[0033] A2: Extract the first progress incentive factor YDLZ of each region on the current date, extract the daily preset progress YJD1 of each region on the working day with label n=1, and the weather efficiency factor TLY and date incentive factor RLY of the working day with label n=1; obtain the daily standard progress RJD1 of each region on the working day with label n=1 based on the formula RJD1=(σ1×YDLZ+σ2×TLY+σ3×RLY)×YJD1; where σ1, σ2, and σ3 are all proportional adjustment factors, and σ1+σ2+σ3=0;
[0034] A3: Based on the formula DLZ n =1-δ×ln(RJD n-1 / YJD n-1 ) Get the progress incentive factor DLZ of each region on day n n , extract the weather efficiency factor TLY of the nth day n and date incentive factor RLY n , based on the formula RJD n =(σ1×DLZ n +σ2×TLY+σ3×RLY)×YJD n Get the daily standard progress RJD of each region on the nth day n; Among them, the daily preset progress YJD n obtained through digital project logs stored in a database;
[0035] A4: Repeat step A3 until the daily standard progress of all remaining working days in the project deadline is obtained and then stop calculating.
[0036] It is worth noting that this step obtains the daily standard progress of the first working day after the current date by analyzing the first progress incentive factor and the weather efficiency factor and date incentive factor of the first working day after the current date. The daily standard progress obtained at this time is obtained by analyzing the actual project completion situation, which can be used to calculate the daily standard progress to obtain the total project difference, and can also be used to analyze the progress incentive factor of the second working day after the current date. The progress incentive factor can be reflected by the current completed progress or the daily completed progress of the previous day. Because when n is greater than 1, the n-1th working day after the current date has not yet arrived, so the actual completed progress or the daily completed progress of the previous day cannot be obtained. Therefore, the progress incentive factor of the nth working day after the current date can be obtained by the daily standard progress and the daily preset progress of the n-1th working day after the current date; if the daily standard progress of the n-1th working day after the current date is less than the daily preset progress, it means that the current task volume will not be completed, which will further improve the work efficiency of the engineering team in the next working day. Doing so ensures that the standard progress for each day predicted by the system is based on the previous working day, thus improving the accuracy of the system's predictions.
[0037] Preferably, the total engineering difference is obtained by calculating the daily standard progress, including:
[0038] The daily standard progress of each area on each working day in the remaining working days of the project is RJD n Perform regional summation calculation to obtain the total daily standard progress of the construction site for each working day in the remaining working days of the project;
[0039] The total daily standard progress of the construction site on each working day in the remaining working days of the project is added up to obtain the total estimated progress ZYD of the construction site on the remaining working days of the project, and the total engineering difference ZCL is obtained based on the formula ZCL=ZYD-SZD; wherein SZD is the set total progress, which is obtained by summing up the daily preset progress of each area on each working day in the remaining working days of the project.
[0040] Preferably, the method of allocating the difference amount to the engineering teams based on the total engineering difference amount includes:
[0041] B1: extract the total engineering difference ZCL, and determine whether the total engineering difference ZCL is less than 0; if yes, jump to B2; if no, do not allocate the difference;
[0042] B2: Extract the total engineering difference ZCL and the number of remaining working days n of the project, and obtain the average distribution PL of each working day in the remaining working days of the project based on the formula PL = ZCL / n;
[0043] B3: Calculate the average allocation amount PL into each of the remaining working days of the project to obtain the final daily work schedule.
[0044] Compared with the prior art, the present invention has the following beneficial effects:
[0045] 1. The present invention obtains weather information, date conditions and target information of each detection area, analyzes the weather information to obtain the weather efficiency factor of each date; analyzes the date conditions to obtain the date incentive factor of each date; obtains the first progress incentive factor of each detection area based on the target information; obtains the subsequent daily standard progress of the construction site through the weather efficiency factor, the date incentive factor and the first progress incentive factor, thereby solving the problem that when obtaining the total amount of pre-completion in engineering monitoring and management, the influence of weather information, the remaining time of the project and the progress conditions on the total amount of project completion are ignored, and when analyzing the influence of the progress conditions on the total amount of project completion, the non-existence of the actual progress on the upcoming working days is ignored, resulting in inaccurate prediction of the total amount of project completion. The present invention improves the accuracy of the prediction of the total amount of project completion.
[0046] 2. The present invention obtains the daily standard progress of the first working day after the current date by analyzing the first progress incentive factor and the weather efficiency factor and date incentive factor of the first working day after the current date. The daily standard progress obtained at this time is obtained by analyzing the actual project completion situation, which can be used to calculate the daily standard progress to obtain the total project difference, and can also be used to analyze the progress incentive factor of the second working day after the current date. The progress incentive factor can be reflected by the current completed progress or the daily completed progress of the previous day. Because when n is greater than 1, the n-1th working day after the current date has not yet arrived, so the actual completed progress or the daily completed progress of the previous day cannot be obtained. Therefore, the progress incentive factor of the nth working day after the current date can be obtained by the daily standard progress of the n-1th working day after the current date and the daily preset progress; if the daily standard progress of the n-1th working day after the current date is less than the daily preset progress, it indicates that the current task volume will not be completed, and the work efficiency of the engineering team in the next working day will be further improved. In this way, the standard progress of each day predicted by the system can be obtained on the basis of the previous working day, which improves the accuracy of the system prediction. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0048] Figure 1 It is a schematic diagram of the operation steps of the present invention;
[0049] Figure 2 It is a schematic diagram of the system module of the present invention;
[0050] Figure 3 The figure is a schematic diagram of the operation steps for obtaining the subsequent daily standard progress of the construction site according to the present invention. DETAILED DESCRIPTION
[0051] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0052] See also Figure 1-Figure 2 , the first aspect of the present invention provides an engineering monitoring and management system based on 5G applications, including: a data analysis module, and an information collection module, a monitoring management module and a database connected thereto;
[0053] Information collection module: used to plan the construction site into several detection areas, obtain basic information and target information of each detection area; basic information includes weather information and date conditions; weather information includes daily maximum temperature and daily rainfall, date conditions include the current date's proportion position, working days and rest days; target information includes the amount of building materials used, the height of the built building and the proportion of the built building area;
[0054] Data analysis module: used to analyze weather information to obtain weather efficiency factors for each date, analyze date conditions to obtain date incentive factors for each date; obtain the first progress incentive factor for each detection area based on target information; obtain the subsequent daily standard progress of the construction site through the weather efficiency factor, date incentive factor and first progress incentive factor;
[0055] Monitoring and management module: used to calculate the daily standard progress to obtain the total engineering variance, and allocate variances to engineering teams based on the total engineering variance.
[0056] For example, in this embodiment, the construction site is planned into 6 detection areas, the project cycle is 100 days, the current date is the 20th day, and the working days in the remaining cycle of the project are 60 days;
[0057] Get the scale position of the current date BLW=20 / 100=0.2;
[0058] Through the analysis of statutory holidays and the maximum daily temperature and daily rainfall on each day during the project period, it is determined that there will be 60 working days and 20 rest days in the remaining period of the project;
[0059] The amount of building materials used is obtained through the registration form, and the height and area of the built buildings are obtained in real time through the surveillance cameras connected to the 5G signal. The ratio of the built building area to the area of the detection area is marked as the built building area ratio;
[0060] Extract the daily maximum temperature RZW and daily rainfall RY for each day within the project period, and extract the set optimum daily maximum temperature ZRZW=29℃;
[0061] When the daily maximum temperature RZW of each day exceeds 29°C, the weather efficiency factor TLY of each day is obtained by the formula TLY=β1×exp(-|α1×(RZW-29) / 29|)+β2 / exp(RY / BRY);
[0062] When the daily maximum temperature RZW does not exceed 29°C, the weather efficiency factor TLY of each day is obtained by the formula TLY=β1×exp(-|α2×(RZW-29) / 29|)+β2 / exp(RY / BRY); where BRY is the standard rainfall that does not affect construction and is obtained by manual setting;
[0063] Get the workable ratio GBL=60 / 100=0.6, extract the ratio position BLW=0.2 of the current date, and obtain the date incentive factor RLY of each date based on the formula RLY=γ×0.2 / exp(0.6);
[0064] Extract the building material usage CYL, the built building height YZG, and the built building area ratio YMB of each area; obtain the first progress incentive factor YDLZ of each detection area based on the formula YDLZ=1-δ×ln(ρ1×CYL / YCYL+ρ2×YZG / BYZG+ρ3×YMB / BYMB); where YCYL is the estimated building material usage of each area, BYZG is the estimated total height of the buildings in each area, and BYMB is the estimated total area of the buildings in each area;
[0065] Number each working day between the current date and the project deadline from the earliest to the latest according to the time, and extract the working days in sequence according to the number n; wherein, in this embodiment, the value range of n is [1,60];
[0066] When the number n of the working day is 1, extract the first progress incentive factor YDLZ of each area on the current date, extract the daily preset progress YJD1 of each area on the working day with number n=1, and extract the weather efficiency factor TLY and date incentive factor RLY of the working day with number n=1; based on the formula RJD1=(σ1×YDLZ+σ2×TLY+σ3×RLY)×YJD1, obtain the daily standard progress RJD1 of each area on the working day with number n=1; wherein, in this embodiment, number n=1 represents the 21st day in the project cycle;
[0067] When the number n of the working day is not 1, the progress incentive factor DLZn of each area on the nth day is obtained based on the formula DLZn=1-δ×ln(RJDn-1 / YJDn-1), the weather efficiency factor TLYn and the date incentive factor RLYn of the nth day are extracted, and the daily standard progress RJDn of each area on the nth day is obtained based on the formula RJDn=(σ1×DLZn+σ2×TLY+σ3×RLY)×YJDn; wherein the daily preset progress YJDn is obtained through the digital project log stored in the database;
[0068] The total engineering variance ZCL is calculated for the daily standard progress. When the total engineering variance ZCL is less than 0, the total engineering variance ZCL and the number of remaining working days of the project are extracted as 60. Based on the formula PL=ZCL / 60, the average distribution PL of each working day in the remaining working days of the project is obtained; the average distribution PL is included in each working day in the remaining working days of the project to obtain the final daily work schedule;
[0069] When the total project difference ZCL is not less than 0, no difference allocation is made.
[0070] In this application, weather information is analyzed to obtain weather efficiency factors for each date, including:
[0071] Extract the daily maximum temperature RZW and daily rainfall RY of each day within the project period, extract the set optimum daily maximum temperature ZRZW, and judge whether the daily maximum temperature RZW of each day exceeds the optimum daily maximum temperature ZRZW; if yes, obtain the weather efficiency factor TLY of each day based on the formula TLY=β1×exp(-|α1×(RZW-ZRZW) / ZRZW|)+β2 / exp(RY / BRY); if no, obtain the weather efficiency factor TLY of each day based on the formula TLY=β1×exp(-|α2×(RZW-ZRZW) / ZRZW|)+β2 / exp(RY / BRY); wherein, the optimum daily maximum temperature is the daily maximum temperature corresponding to the highest daily work efficiency, BRY is the standard rainfall that does not affect construction, α1 and α2 are both amplitude adjustment coefficients, and β1 and β2 are both proportional adjustment coefficients greater than 0.
[0072] It should be noted that the function of the amplitude adjustment coefficients α1 and α2 is to adjust the amplitude change rate of the graph in the two cases where the daily maximum temperature RZW is greater than or less than the optimum daily maximum temperature ZRZW.
[0073] In this application, the first progress incentive factor of each detection area is obtained based on the target information, including:
[0074] Extract the usage of building materials CYL, the height of built buildings YZG, and the proportion of built building area YMB in each area; obtain the first progress incentive factor YDLZ of each detection area based on the formula YDLZ=1-δ×ln(ρ1×CYL / YCYL+ρ2×YZG / BYZG+ρ3×YMB / BYMB); among which YCYL is the estimated usage of building materials in each area, BYZG is the estimated total height of buildings in each area, and BYMB is the estimated total area of buildings in each area; δ is an amplitude adjustment factor greater than 0, ρ1, ρ2, and ρ3 are all proportion adjustment factors, and ρ1+ρ2+ρ3=1.
[0075] It should be noted that when the values of the amount of building materials used, the height of the built buildings and the proportion of the built building area are larger, the invisible pressure on the construction team will be smaller, which will cause a decrease in construction motivation, and therefore the first progress incentive factor will also be reduced.
[0076] See also Figure 3 In this application, the subsequent daily standard progress of the construction site is obtained through the weather efficiency factor, the date incentive factor and the first progress incentive factor, including:
[0077] A1: Number each working day between the current date and the project deadline from the earliest to the latest according to time, extract working days in sequence according to number n, and determine whether the working day number n is 1. If yes, jump to A2; if not, jump to A3.
[0078] A2: Extract the first progress incentive factor YDLZ of each region on the current date, extract the daily preset progress YJD1 of each region on the working day with label n=1, and the weather efficiency factor TLY and date incentive factor RLY of the working day with label n=1; obtain the daily standard progress RJD1 of each region on the working day with label n=1 based on the formula RJD1=(σ1×YDLZ+σ2×TLY+σ3×RLY)×YJD1; where σ1, σ2, and σ3 are all proportional adjustment factors, and σ1+σ2+σ3=0;
[0079] A3: Based on the formula DLZn=1-δ×ln(RJDn-1 / YJDn-1), the progress incentive factor DLZn of each region on the nth day is obtained, the weather efficiency factor TLYn and the date incentive factor RLYn of the nth day are extracted, and the daily standard progress RJDn of each region on the nth day is obtained based on the formula RJDn=(σ1×DLZn+σ2×TLY+σ3×RLY)×YJDn; wherein, the daily preset progress YJDn is obtained through the digital project log stored in the database;
[0080] A4: Repeat step A3 until the daily standard progress of all remaining working days in the project deadline is obtained and then stop calculating.
[0081] It should be noted that the working days between the current date and the project deadline can be understood as the remaining working days of the project.
[0082] It should be noted that the working day numbered n=1 can be understood as the first working day after the current date, and the progress incentive factor of the first working day after the current date can be reflected by the first progress incentive factor obtained from the existing building in reality.
[0083] In this application, the daily standard progress is calculated to obtain the total engineering variance, including:
[0084] The daily standard progress RJDn of each area on each working day in the remaining working days of the project is calculated by regional summation to obtain the total daily standard progress of the construction site on each working day in the remaining working days of the project;
[0085] The total daily standard progress of the construction site on each working day in the remaining working days of the project is added up to obtain the total estimated progress ZYD of the construction site on the remaining working days of the project, and the total engineering difference ZCL is obtained based on the formula ZCL=ZYD-SZD; wherein SZD is the set total progress, which is obtained by summing up the daily preset progress of each area on each working day in the remaining working days of the project.
[0086] It should be noted that SZD is the set total progress, which is obtained by summing up the daily preset progress of each area for each working day in the remaining working days of the project. The specific steps are: regionally summing up the daily preset progress of each area for each working day in the remaining working days of the project to obtain the total daily preset progress of the construction site on each working day in the remaining working days of the project; summing up the total daily preset progress of the construction site on each working day in the remaining working days of the project to obtain the set total progress SZD of the construction site in the remaining working days of the project.
[0087] Part of the data in the above formula is calculated by removing the dimension and taking its numerical value. The formula is a formula closest to the actual situation obtained by software simulation of a large amount of collected data; the preset parameters and preset thresholds in the formula are set by technical personnel in this field according to actual conditions or obtained through simulation of a large amount of data.
[0088] Working principle of the present invention:
[0089] The construction site is planned into several inspection areas, and weather information, date conditions and target information of each inspection area are obtained; the weather information is analyzed to obtain the weather efficiency factor of each date, and the date conditions are analyzed to obtain the date incentive factor of each date; the first progress incentive factor of each inspection area is obtained based on the target information; the subsequent daily standard progress of the construction site is obtained through the weather efficiency factor, the date incentive factor and the first progress incentive factor; the daily standard progress is calculated to obtain the total project difference, and the difference is allocated to the engineering team based on the total project difference.
[0090] The above embodiments are only used to illustrate the technical method of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical method of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the present invention.
Claims
1. An engineering monitoring and management system based on 5G applications, characterized in that: include: Data analysis module, and the information collection module, monitoring management module and database connected thereto; The information collection module is used to plan the construction site into several detection areas, and obtain basic information and target information of each detection area; wherein the basic information includes weather information and date conditions; weather information includes daily maximum temperature and daily rainfall; date conditions include the proportion of the current date, working days and rest days; target information includes the amount of building materials used, the height of the built building and the proportion of the built building area; The data analysis module is used to analyze weather information to obtain weather efficiency factors for each date, analyze date conditions to obtain date incentive factors for each date; obtain the first progress incentive factor for each detection area based on target information; and obtain the subsequent daily standard progress of the construction site through the weather efficiency factor, date incentive factor and first progress incentive factor; The monitoring and management module is used to calculate the daily standard progress to obtain the total engineering variance, and to allocate the variance to the engineering teams based on the total engineering variance.
2. According to claim 1, the engineering monitoring and management system based on 5G application is characterized in that: The data analysis module communicates and / or is electrically connected to the information collection module, the monitoring management module and the database respectively; the database communicates and / or is electrically connected to the information collection module, the data analysis module and the monitoring management module respectively.
3. According to the 5G application-based engineering monitoring and management system of claim 1, it is characterized in that: The construction site is planned to be divided into several detection areas, including: Use drones equipped with high-resolution cameras and 5G communication technology to obtain the digital surface model of the construction site in real time. Use 3D modeling technology to process the digital surface model and input the digital surface model as design data into the BIM software to obtain a 3D model of the construction site. Select important building points in the three-dimensional model, obtain the center position and area ZMi of each important building point, and obtain the predetermined area YDi based on the formula YDi=ZMi×BL; delineate the area circle of each important building point with the center position of each important building point as the center and the predetermined area YDi as the range size; wherein BL is the ratio adjustment coefficient, and i is the number of important building points; Get whether there are overlapping areas in the area circles of each important building point; if yes, divide the overlapping areas equally to obtain evenly divided areas, obtain the center distance between the center point of each evenly divided area and the center position of each important building point, and assign each evenly divided area to the area circle of the corresponding important building point with the smallest center distance; if no, do nothing; The construction site area corresponding to the area circle of each important building point is marked as the detection area of each important building point.
4. According to the 5G application-based engineering monitoring and management system of claim 1, it is characterized in that: The obtaining of basic information and target information of each detection area includes: Get the ratio of the current date to the entire project cycle, and mark the value of the ratio as the ratio position; Obtain statutory holidays in the current project cycle, mark the statutory holidays as rest days, obtain the daily maximum temperature and daily rainfall of each day within the project period through a computer, and determine whether the daily maximum temperature or daily rainfall of each day exceeds the corresponding set threshold; if yes, mark the corresponding date as a rest day; if no, mark the corresponding date as a working day; The amount of building materials used is obtained through the registration form, and the height and area of built buildings are obtained in real time through surveillance cameras connected to 5G signals. The ratio of the built building area to the area of the detection area is marked as the built building area ratio.
5. According to claim 4, the engineering monitoring and management system based on 5G application is characterized in that: The weather information is analyzed to obtain the weather efficiency factor of each date, including: Extract the daily maximum temperature RZW and daily rainfall RY of each day within the project period, extract the set optimum daily maximum temperature ZRZW, and judge whether the daily maximum temperature RZW of each day exceeds the optimum daily maximum temperature ZRZW; if yes, obtain the weather efficiency factor TLY of each day based on the formula TLY=β1×exp(-|α1×(RZW-ZRZW) / ZRZW|)+β2 / exp(RY / BRY); if no, obtain the weather efficiency factor TLY of each day based on the formula TLY=β1×exp(-|α2×(RZW-ZRZW) / ZRZW|)+β2 / exp(RY / BRY); wherein, the optimum daily maximum temperature is the daily maximum temperature corresponding to the highest daily work efficiency, BRY is the standard rainfall that does not affect construction, α1 and α2 are both amplitude adjustment coefficients, and β1 and β2 are both proportional adjustment coefficients greater than 0.
6. According to claim 5, the engineering monitoring and management system based on 5G application is characterized in that: The date incentive factors of each date are obtained by analyzing the date conditions, including: Get the ratio of working days after the current date to the project cycle, and mark the ratio as the workable ratio GBL; extract the ratio position BLW of the current date, and obtain the date incentive factor RLY of each date based on the formula RLY=γ×BLW / exp(GBL); wherein γ is the ratio adjustment coefficient.
7. According to claim 6, the engineering monitoring and management system based on 5G application is characterized in that: The obtaining of the first progress incentive factor of each detection area based on the target information includes: Extract the usage of building materials CYL, the height of built buildings YZG, and the proportion of built building area YMB in each area; obtain the first progress incentive factor YDLZ of each detection area based on the formula YDLZ=1-δ×ln(ρ1×CYL / YCYL+ρ2×YZG / BYZG+ρ3×YMB / BYMB); among which YCYL is the estimated usage of building materials in each area, BYZG is the estimated total height of buildings in each area, and BYMB is the estimated total area of buildings in each area; δ is an amplitude adjustment factor greater than 0, ρ1, ρ2, and ρ3 are all proportion adjustment factors, and ρ1+ρ2+ρ3=1.
8. According to claim 7, the engineering monitoring and management system based on 5G application is characterized in that: The subsequent daily standard progress of the construction site is obtained by using the weather efficiency factor, the date incentive factor and the first progress incentive factor, including: A1: Number each working day between the current date and the project deadline from the earliest to the latest according to the time, extract the working days in sequence according to the number n, and determine whether the number n of the working day is 1; if yes, jump to A2; if no, jump to A3; A2: Extract the first progress incentive factor YDLZ of each region on the current date, extract the daily preset progress YJD1 of each region on the working day with label n=1, and the weather efficiency factor TLY and date incentive factor RLY of the working day with label n=1; obtain the daily standard progress RJD1 of each region on the working day with label n=1 based on the formula RJD1=(σ1×YDLZ+σ2×TLY+σ3×RLY)×YJD1; where σ1, σ2, and σ3 are all proportional adjustment factors, and σ1+σ2+σ3=0; A3: Based on the formula DLZ n =1-δ×ln(RJD n-1 / YJD n-1 ) Get the progress incentive factor DLZ of each region on day n n , extract the weather efficiency factor TLY of the nth day n and date incentive factor RLY n , based on the formula RJD n =(σ1×DLZ n +σ2×TLY+σ3×RLY)×YJD n Get the daily standard progress RJD of each region on the nth day n ; Among them, the daily preset progress YJD n obtained through digital project logs stored in a database; A4: Repeat step A3 until the daily standard progress of all remaining working days in the project deadline is obtained and then stop calculating.
9. The engineering monitoring and management system based on 5G application according to claim 8 is characterized in that: The total engineering difference obtained by calculating the daily standard progress includes: The daily standard progress of each area on each working day in the remaining working days of the project is RJD n Perform regional summation calculation to obtain the total daily standard progress of the construction site for each working day in the remaining working days of the project; The total daily standard progress of the construction site on each working day in the remaining working days of the project is added up to obtain the total estimated progress ZYD of the construction site on the remaining working days of the project, and the total engineering difference ZCL is obtained based on the formula ZCL=ZYD-SZD; wherein SZD is the set total progress, which is obtained by summing up the daily preset progress of each area on each working day in the remaining working days of the project.
10. The engineering monitoring and management system based on 5G application according to claim 9 is characterized in that: The method of allocating the difference amount to the engineering team based on the total engineering difference amount includes: B1: extract the total engineering difference ZCL, and determine whether the total engineering difference ZCL is less than 0; if yes, jump to B2; if no, do not allocate the difference; B2: Extract the total engineering difference ZCL and the number of remaining working days n of the project, and obtain the average distribution PL of each working day in the remaining working days of the project based on the formula PL = ZCL / n; B3: Calculate the average allocation amount PL into each of the remaining working days of the project to obtain the final daily work schedule.