Random failure-based joint optimization method and device for maintenance of various devices of transformer substation

By building a reliability and maintenance effectiveness model and a joint optimization model for maintenance of multiple equipment, and combining genetic algorithms to optimize the preventive maintenance cycle, the problem of difficult maintenance costs and reliability caused by random failure of multiple equipment in the substation is solved, and the problem of difficulty in taking into account both the maintenance costs and reliability caused by the random failure of multiple equipment in the substation is realized. Reasonable maintenance planning and cost control.

CN119090076AInactive Publication Date: 2024-12-06GUANGZHOU POWER SUPPLY BUREAU GUANGDONG POWER GRID CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411196917.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing substation maintenance strategy is difficult to improve reliability and reduce maintenance costs, especially in the face of random failures of multiple equipment, and there is a lack of reasonable planning and effectiveness control.

Method used

By obtaining random failure data of each equipment in the substation system, a reliability and maintenance effectiveness model is built, maintenance indicators are generated, and a preventive maintenance cycle is determined using a joint optimization model for maintenance of multiple equipments, combined with genetic algorithm optimization schemes to minimize the total maintenance cost. .

Benefits of technology

Reasonable maintenance planning and effectiveness control of various equipment of the substation is achieved, system reliability is improved, maintenance costs are reduced, and balanced between economy and reliability is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119090076A_ABST
    Figure CN119090076A_ABST
Patent Text Reader

Abstract

The invention provides a joint optimization method and device for maintenance of various devices of a transformer substation based on random failure, and relates to the technical field of transformer substations, and the method comprises the steps: firstly obtaining random failure data of each device in a transformer substation system; then processing the random failure data through a reliability and maintenance effectiveness model constructed based on a task scene to determine the maintenance effectiveness of each device; and processing the maintenance validity and random failure data of each device through a plurality of device maintenance joint optimization models, and determining a preventive maintenance period of each device in the transformer substation system. Through the method, the technical problem that it is difficult to give consideration to improvement of the reliability of a transformer substation system and reduction of maintenance cost in the prior art is solved, and reasonable planning and effective control for maintenance of various devices of the transformer substation are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of transformer substations, and in particular to a method and a device for joint optimization of maintenance of multiple equipment in transformer substations based on random failure. Background Art

[0002] Substations are an important part of the power system and serve as the main link between all levels of the power system. The reliability of a substation depends on the availability and efficiency of all substation equipment. The failure rate of substation equipment is not constant, but is affected by operating conditions. Substation equipment will age and damage with use and time. The aging of electrical equipment directly affects the operating cost, reliability and service life of the power system. Therefore, preventive measures need to be taken to extend the service life of the equipment.

[0003] Maintenance strategy is an important issue in power systems and restricts the economic efficiency of production activities. The general goal of maintenance strategy is to maximize reliability while minimizing life cycle costs. Maintenance of substation equipment is generally divided into corrective maintenance and preventive maintenance. Preventive maintenance is generally used as an effective strategy to improve reliability. Through preventive maintenance actions, the costs caused by failures can be reduced, but the costs of preventive maintenance actions will be incurred. When a system failure occurs, corrective maintenance needs to be performed in order to restore the system to normal operation.

[0004] The existing substation maintenance strategy is usually based on corrective maintenance and supplemented by preventive maintenance. However, since substations usually include a variety of equipment with random failures, the maintenance cost is high and the workload is huge. At present, there is a lack of reasonable plans and effectiveness control for the maintenance of various equipment in substations. In addition, when facing a variety of equipment with different failure patterns, the existing strategy needs to allocate a limited maintenance budget, which has the technical problem of being difficult to balance improving reliability and reducing maintenance costs. Summary of the invention

[0005] The purpose of the present invention is to provide a method and device for joint optimization of maintenance of multiple equipment in a substation based on random failure, so as to alleviate the technical problem existing in the prior art that it is difficult to balance improving reliability and reducing maintenance costs.

[0006] In the first aspect, an embodiment of the present invention provides a joint optimization method for maintenance of multiple equipment in a substation based on random failures, which is applied to a substation system, wherein the substation system includes multiple equipment; the method includes: obtaining random failure data of each equipment in the substation system; the random failure data includes: equipment number, probability density function obeyed by the failure time of the equipment, effectiveness of a single preventive maintenance, preventive maintenance cycle, minimum reliability of the equipment, single corrective maintenance cost, and single preventive maintenance cost; processing the random failure data of each equipment through a reliability and maintenance effectiveness model to determine the maintenance effectiveness of each equipment; the reliability and maintenance effectiveness model is constructed based on a task scenario to generate maintenance indicators for the equipment; processing the maintenance effectiveness of each equipment and the random failure data through a joint optimization model for maintenance of multiple equipment to determine the preventive maintenance cycle of each equipment in the substation system; the joint optimization model for maintenance of multiple equipment is constructed based on the maintenance indicators of the equipment.

[0007] In some optional implementations, the reliability and maintenance effectiveness model includes: a model without preventive maintenance and a model with preventive maintenance; the model without preventive maintenance includes: a failure function, a first reliability function, a first failure rate and a first mean failure time; the random failure data of each device is processed by the reliability and maintenance effectiveness model, including:

[0008] Based on the probability density function obeyed by the failure time of the above equipment, a failure function and a first reliability function are determined; based on the failure function and the first reliability function, a first failure rate is determined; based on the first reliability function, a first mean failure time is determined; the above preventive maintenance model includes: a second reliability function, a second failure rate and a second mean failure time; the above random failure data of each equipment is processed by the reliability and maintenance effectiveness model, and also includes:

[0009] Based on the first failure rate, determine the second failure rate; based on the probability density function obeyed by the failure time of the equipment and the second failure rate, determine the second reliability function; based on the second reliability function, determine the second mean failure time.

[0010] In some optional implementations, the above-mentioned reliability and maintenance effectiveness model also includes: maintenance-free life, maintenance life and maintenance effectiveness; the above-mentioned random failure data of each device is processed through the reliability and maintenance effectiveness model to determine the maintenance effectiveness of each device, and also includes: determining the maintenance-free life based on the above-mentioned first reliability function and the minimum reliability of the equipment; determining the maintenance life based on the above-mentioned second reliability function and the minimum reliability of the equipment; determining the maintenance effectiveness based on the above-mentioned maintenance-free life and the above-mentioned maintenance life.

[0011] In some optional implementations, the maintenance indicators of the above-mentioned equipment include: a first mean failure time, a second mean failure time, a first failure rate, a second failure rate, and minimum maintenance effectiveness; the above-mentioned method also includes: constructing a joint optimization model for maintenance of multiple equipment based on the maintenance indicators of the above-mentioned equipment; constructing a joint optimization model for maintenance of multiple equipment based on constraints and the maintenance indicators of the above-mentioned equipment; the above-mentioned constraints include: equipment's preventive maintenance cycle decision variable constraints, equipment's mean failure time constraints, equipment's preventive maintenance capacity constraints, equipment's minimum maintenance effectiveness constraints, and unit time preventive maintenance budget constraints.

[0012] In some optional implementations, the above-mentioned maintenance effectiveness and the above-mentioned random failure data of each equipment are processed through multiple equipment maintenance joint optimization models to determine the preventive maintenance period of each equipment in the above-mentioned substation system, including: using the above-mentioned constraints to constrain the maintenance indicators of the above-mentioned equipment to determine the corrective maintenance cost and the preventive maintenance cost of the above-mentioned substation system; based on the above-mentioned corrective maintenance cost and the above-mentioned preventive maintenance cost, determine the total maintenance cost of the above-mentioned substation system; and determine at least one group of preventive maintenance period plans for each equipment in the above-mentioned substation system on the condition that the above-mentioned total maintenance cost is minimized.

[0013] In some optional implementations, the method further includes: using a genetic algorithm to process multiple preventive maintenance cycle plans generated by the multiple equipment maintenance joint optimization model to determine an optimal preventive maintenance cycle plan.

[0014] In some optional implementations, a genetic algorithm is used to process multiple preventive maintenance cycle plans generated by the above-mentioned multiple equipment maintenance joint optimization model to determine the optimal preventive maintenance cycle plan, including:

[0015] S21, encoding a plurality of preventive maintenance cycle plans generated by the above-mentioned joint optimization model for maintenance of various equipments; each of the above-mentioned preventive maintenance cycle plans corresponds to an objective function value; the above-mentioned objective function value is the total maintenance cost of the above-mentioned substation system;

[0016] S22, randomly generating several feasible solutions of the above-mentioned joint optimization model for maintenance of multiple equipments as the initial population;

[0017] S23, determining whether each of the above preventive maintenance cycle plans is feasible, if feasible, determining the inverse of the corresponding objective function value as the fitness; otherwise, determining the fitness as -M, where M is a sufficiently large positive number;

[0018] S24, using the exponential sorting selection method to select individuals in the current population for replication, and randomly cross-pairing the selected individuals with the individuals generated by the replication;

[0019] S25, performing a mutation operation on the individuals after random cross-pairing with a first mutation probability;

[0020] S23 to S25 are repeatedly executed until the iteration reaches the Lth generation, and the maximum code of the current fitness is output and decoded to obtain the optimal preventive maintenance cycle plan.

[0021] In the second aspect, an embodiment of the present invention provides a joint optimization device for maintenance of multiple equipment in a substation based on random failures, the device comprising: a data acquisition module, used to obtain random failure data of each equipment in the substation system; the above-mentioned random failure data include: equipment number, probability density function obeyed by the failure time of the equipment, effectiveness of a single preventive maintenance, preventive maintenance cycle, minimum reliability of the equipment, single corrective maintenance cost, single preventive maintenance cost; a maintenance effectiveness determination module, used to process the above-mentioned random failure data of each equipment through a reliability and maintenance effectiveness model to determine the maintenance effectiveness of each equipment; the above-mentioned reliability and maintenance effectiveness model is constructed based on a task scenario and is used to generate maintenance indicators of the above-mentioned equipment; a preventive maintenance cycle determination module, used to process the above-mentioned maintenance effectiveness and the above-mentioned random failure data of each equipment through a joint optimization model for maintenance of multiple equipment to determine the preventive maintenance cycle of each equipment in the above-mentioned substation system; the above-mentioned joint optimization model for maintenance of multiple equipment is constructed based on the maintenance indicators of the above-mentioned equipment.

[0022] In a third aspect, an embodiment of the present invention provides an electronic device, comprising a memory and a processor, wherein the memory stores a computer program executable on the processor, and when the processor executes the computer program, the steps of any one of the methods described in the first aspect are implemented.

[0023] In a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium stores machine-executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions cause the processor to execute any method described in the first aspect above.

[0024] The present invention provides a method and device for joint optimization of maintenance of multiple equipment in a substation based on random failures, the method comprising: firstly obtaining random failure data of each equipment in the substation system, then processing the random failure data through a reliability and maintenance effectiveness model constructed based on a task scenario to determine the maintenance effectiveness of each equipment; then processing the maintenance effectiveness and random failure data of each equipment through a joint optimization model for maintenance of multiple equipment to determine the preventive maintenance cycle of each equipment in the substation system. This method solves the technical problem of the difficulty in balancing the improvement of the reliability of the substation system and the reduction of maintenance costs in the prior art, and realizes reasonable planning and effectiveness control for the maintenance of multiple equipment in the substation. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0026] Figure 1 A schematic diagram of a flow chart of a joint optimization method for maintenance of multiple equipment in a substation based on random failures provided by an embodiment of the present invention;

[0027] Figure 2 A schematic flow chart of a specific embodiment of a joint optimization method for maintenance of multiple equipment in a substation based on random failures provided by an embodiment of the present invention;

[0028] Figure 3 A schematic diagram of a task scenario provided by an embodiment of the present invention;

[0029] Figure 4 A schematic diagram of failure rate under regular preventive maintenance provided by an embodiment of the present invention;

[0030] Figure 5 A schematic diagram of failure rate under an optimal preventive maintenance cycle scheme provided by an embodiment of the present invention;

[0031] Figure 6 A schematic diagram of the structure of a joint optimization device for maintenance of multiple equipment in a substation based on random failures provided by an embodiment of the present invention;

[0032] Figure 7 A schematic diagram of the structure of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0033] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0034] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. Some embodiments of the present invention are described in detail below in conjunction with the drawings. The following embodiments and features in the embodiments can be combined with each other without conflict.

[0036] As an important part of the power system, the substation is responsible for the main connection between all levels of the power system. The reliability of the substation depends on the availability and efficiency of all substation equipment. The failure rate of substation equipment is not constant, but is affected by the operating conditions. Substation equipment will age and damage with use and time. The aging of electrical equipment directly affects the operating cost, reliability and service life of the power system. Therefore, preventive measures need to be taken to extend the service life of the equipment.

[0037] Maintenance of substation equipment is generally divided into corrective maintenance and preventive maintenance. Preventive maintenance is generally used as an effective strategy to improve reliability. Through preventive maintenance actions, the cost caused by failures can be reduced, but the cost of preventive maintenance actions will be incurred. When a system fails, corrective maintenance needs to be performed in order to restore the system to normal operation.

[0038] Since substations usually include a variety of equipment that fail randomly, the maintenance cost is high and the workload is huge. At present, there is a lack of reasonable plans and effectiveness control for the maintenance of various equipment in substations. In addition, when facing multiple equipment with different failure patterns, the existing strategy needs to allocate limited maintenance budgets, which has the technical problem of being difficult to balance improving reliability and reducing maintenance costs.

[0039] Based on this, the embodiment of the present invention provides a method and device for joint optimization of maintenance of multiple equipment in a substation based on random failures, so as to alleviate the technical problem existing in the prior art that it is difficult to balance improving reliability and reducing maintenance costs.

[0040] To facilitate understanding of this embodiment, firstly, a joint optimization method for maintenance of multiple equipment in a substation based on random failure disclosed in an embodiment of the present invention is described in detail. Figure 1 The flowchart of a joint optimization method for maintenance of multiple equipment in a substation based on random failure is shown. The method is applied to a substation system, and the substation system includes multiple equipment. The method mainly includes the following steps S110 to S130:

[0041] S110: Obtain random failure data of each device in the substation system;

[0042] Among them, random failure data include: equipment number, probability density function of equipment failure time, effectiveness of single preventive maintenance, preventive maintenance cycle, minimum reliability of equipment, single corrective maintenance cost, and single preventive maintenance cost.

[0043] S120: Processing the random failure data of each device through a reliability and maintenance effectiveness model to determine the maintenance effectiveness of each device;

[0044] The reliability and maintenance effectiveness model is constructed based on task scenarios and is used to generate maintenance indicators for the equipment.

[0045] Among them, the task scenario includes a set of equipment numbers and a probability density function obeyed by the equipment failure time; the reliability and maintenance effectiveness model is used to generate the maintenance index of the equipment.

[0046] In one embodiment, the task scenario may be a scenario in which corrective maintenance and preventive maintenance are performed on various devices in a substation, where preventive maintenance is regular maintenance, and the reliability of different devices is a random variable that obeys different probability distributions. As a specific example, the task scenario construction includes:

[0047] (1.1) Number the devices to form a device number set:

[0048] N = {1, 2, ..., i, ..., n} (1);

[0049] In formula (1), N represents the set consisting of the serial numbers of n devices;

[0050] (1.2) The single corrective maintenance cost of equipment numbered i is c i,c ,1≤i≤n;

[0051] (1.3) The single preventive maintenance of equipment numbered i is c i,p ,1≤i≤n;

[0052] (1.4) The preventive maintenance cycle of equipment numbered i is t i ,1≤i≤n;

[0053] (1.5) The probability density function of the failure time of equipment numbered i is f i (t),1≤i≤n;

[0054] (1.6) The effectiveness of a single preventive maintenance of equipment numbered i is α i ,1≤i≤n.

[0055] Based on the task scenarios constructed above, a function group for calculating indicators such as reliability and maintenance effectiveness of different equipment can be generated, namely, a reliability and maintenance effectiveness model. Through this reliability and maintenance effectiveness model, various maintenance indicators of the equipment can be calculated.

[0056] In one embodiment, the reliability and maintenance effectiveness model includes: a model without preventive maintenance and a model with preventive maintenance; the model without preventive maintenance includes: a failure function, a first reliability function, a first failure rate and a first mean failure time.

[0057] Then S120 processes the random failure data of each device through the reliability and maintenance effectiveness model, including: determining the failure function and the first reliability function based on the probability density function obeyed by the failure time of the equipment; determining the first failure rate based on the failure function and the first reliability function; determining the first mean failure time based on the first reliability function.

[0058] As a specific example, the steps include:

[0059] (2.1) When there is no preventive maintenance, the failure function of the equipment numbered i is:

[0060]

[0061] In formula (2), F i (t) represents the failure function of equipment numbered i when there is no preventive maintenance;

[0062] (2.2) When there is no preventive maintenance, the reliability function of equipment numbered i is:

[0063]

[0064] In formula (3), R i(t) represents the reliability function of the equipment numbered i when there is no preventive maintenance, that is, the first reliability function;

[0065] (2.3) Without preventive maintenance, the failure rate of equipment numbered i is:

[0066]

[0067] In formula (4), λ i (t) represents the failure rate of equipment numbered i when there is no preventive maintenance, i.e., the first failure rate;

[0068] (2.4) Without preventive maintenance, the average failure time of equipment numbered i is:

[0069]

[0070] In formula (5), MTTF i It represents the average failure time of equipment numbered i when there is no preventive maintenance, that is, the first average failure time.

[0071] In one embodiment, the preventive maintenance model includes: a second reliability function, a second failure rate, and a second mean time to failure;

[0072] S120 processes the random failure data of each device through the reliability and maintenance effectiveness model, and also includes: determining the second failure rate based on the first failure rate; determining the second reliability function based on the probability density function obeyed by the failure time of the equipment and the second failure rate; determining the second mean failure time based on the second reliability function.

[0073] As a specific example, the above steps include:

[0074] (2.5) When there is preventive maintenance, the failure rate of equipment numbered i is:

[0075]

[0076] In formula (6), λ i '(t) represents the failure rate of equipment numbered i when there is preventive maintenance, that is, the second failure rate. Indicates a round-down operation;

[0077] (2.6) When there is preventive maintenance, the reliability function of equipment numbered i is:

[0078]

[0079] In formula (7), R i'(t) represents the reliability function of the equipment numbered i when there is preventive maintenance, that is, the second reliability function;

[0080] (2.7) When there is preventive maintenance, the average failure time of equipment numbered i is:

[0081]

[0082] In formula (8), MTTF' i It indicates the average failure time of equipment numbered i when there is preventive maintenance, that is, the second average failure time.

[0083] In one embodiment, the reliability and maintenance effectiveness model further includes: life without maintenance, life with maintenance, and maintenance effectiveness;

[0084] S120 processes the random failure data of each device through the reliability and maintenance effectiveness model to determine the maintenance effectiveness of each device, and also includes: determining the maintenance-free life based on the first reliability function and the minimum reliability of the equipment; determining the maintenance life based on the second reliability function and the minimum reliability of the equipment; determining the maintenance effectiveness of the equipment based on the maintenance-free life and the maintenance life.

[0085] As a specific example, the steps may include:

[0086] (2.8) The maintenance-free life of equipment numbered i is:

[0087] T i =solve(R i (T i )= R i ) (9),

[0088] In formula (9), T i Represents the maintenance-free life of the equipment numbered i. R i represents the minimum reliability of the device numbered i, solve(·) means solving the equation in the brackets;

[0089] It should be noted that the ways to obtain the minimum reliability of equipment include: 1) conducting statistical analysis on historical fault records and maintenance records as well as data obtained from laboratory tests and field tests to identify potential failure modes and their impact on equipment performance, and setting minimum reliability requirements based on evaluation results and equipment application requirements; 2) setting minimum reliability requirements with reference to relevant industry standards and regulations.

[0090] (2.9) The maintenance life of equipment numbered i is:

[0091] T i '=solve(R i '(T i ')= R i ) (10),

[0092] In formula (10), T i 'Indicates the maintenance life of the equipment numbered i;

[0093] (2.10) The maintenance effectiveness of equipment numbered i is defined as:

[0094]

[0095] In formula (11), E i Indicates the maintenance effectiveness of the equipment numbered i.

[0096] In order to solve the problem of how to allocate limited maintenance budget when facing multiple equipment with different failure patterns, so that the entire system can achieve the minimum total maintenance cost while meeting the reliability requirements, it is necessary to further construct a joint optimization model for maintenance of multiple equipment. This model aims to minimize the total cost of corrective maintenance and preventive maintenance of the entire system, and is constrained by meeting the minimum mean failure time, minimum maintenance effectiveness and preventive maintenance budget per unit time. It can be used to calculate the preventive maintenance cycle of each equipment in the substation system.

[0097] In one embodiment, the method further includes: constructing a plurality of equipment maintenance joint optimization models based on the maintenance index of the equipment; and constructing a plurality of equipment maintenance joint optimization models based on the constraint conditions and the maintenance index of the equipment.

[0098] Among them, the constraints include: equipment preventive maintenance cycle decision variable constraints, equipment mean failure time constraints, equipment preventive maintenance capability constraints, equipment minimum maintenance effectiveness constraints, and unit time preventive maintenance budget constraints.

[0099] S130: Processing the maintenance effectiveness and random failure data of each device through a multi-device maintenance joint optimization model to determine the preventive maintenance cycle of each device in the substation system;

[0100] The joint optimization model for maintenance of various equipments is constructed based on the maintenance indexes of the equipments.

[0101] In one embodiment, S130 includes:

[0102] (S131) ​​using constraint conditions to constrain maintenance indicators of equipment and determine corrective maintenance costs and preventive maintenance costs of the substation system;

[0103] (S132) determining a total maintenance cost of the substation system based on the corrective maintenance cost and the preventive maintenance cost;

[0104] (S133) Determine a preventive maintenance cycle plan for each device in at least one group of substation systems on the condition that the total maintenance cost is minimized.

[0105] As a specific example, the method includes the following process:

[0106] (3.1) Constraints on the value of the preventive maintenance cycle decision variable for equipment numbered i:

[0107] t i >0,1≤i≤n (12);

[0108] (3.2) The average failure time constraint of the device numbered i is:

[0109] MTTF i ≥ MTTF i ,1≤i≤n (13),

[0110] In formula (13), MTTF i It represents the minimum mean failure time of the equipment numbered i;

[0111] (3.3) Preventive maintenance capability constraint for equipment numbered i:

[0112] λ i (t)-λ i (tt i )>α i ,1≤i≤n (14),

[0113] Formula (14) shows that preventive maintenance can only restore part of the reliability of the equipment, but cannot completely replace the equipment;

[0114] (3.4) Minimum maintenance effectiveness constraint for equipment numbered i:

[0115] E i ≥ E i ,1≤i≤n (15),

[0116] In formula (15), E i Indicates the minimum maintenance effectiveness of the equipment numbered i;

[0117] (3.5) Preventive maintenance budget constraint per unit time:

[0118]

[0119] In formula (16), B represents the budget for preventive maintenance per unit time;

[0120] (3.6) Calculate the preventive maintenance cost of the entire system:

[0121]

[0122] In formula (17), c p Represents the preventive maintenance cost of the entire system;

[0123] (3.7) Calculate the corrective maintenance cost of the entire system:

[0124]

[0125] In formula (18), c c represents the corrective maintenance cost of the entire system;

[0126] (3.8) The objective function is set to minimize the total cost of corrective maintenance and preventive maintenance of the entire system:

[0127] minc=c p +c c (19)

[0128] In formula (19), c represents the total cost of corrective maintenance and preventive maintenance of the entire system;

[0129] (3.9), and by summarizing equations (12) to (19), we can obtain a joint optimization model for maintenance of multiple equipments.

[0130] In one embodiment, the method may further include: using a genetic algorithm to process multiple preventive maintenance cycle plans generated by multiple equipment maintenance joint optimization models to determine an optimal preventive maintenance cycle plan.

[0131] Among them, the genetic algorithm is used to process multiple preventive maintenance cycle plans generated by the joint optimization model of multiple equipment maintenance to determine the optimal preventive maintenance cycle plan, including:

[0132] S21, encoding multiple preventive maintenance cycle plans generated by the joint optimization model for maintenance of multiple equipments; each preventive maintenance cycle plan corresponds to an objective function value; the objective function value is the total maintenance cost of the substation system;

[0133] S22, several feasible solutions of the randomly generated multi-equipment maintenance joint optimization model are used as the initial population;

[0134] S23, determining whether each preventive maintenance cycle plan is feasible, if feasible, determining the inverse of the corresponding objective function value as the fitness; otherwise, determining the fitness as -M, where M is a sufficiently large positive number;

[0135] S24, using the exponential sorting selection method to select individuals in the current population for replication, and randomly cross-pairing the selected individuals with the individuals generated by the replication;

[0136] S25, performing a mutation operation on the individuals after random cross-pairing with a first mutation probability;

[0137] S23 to S25 are repeatedly executed until the Lth generation is reached, and the maximum code of the current fitness is output and decoded to obtain the optimal preventive maintenance cycle plan.

[0138] As a specific example, a genetic algorithm is used to solve the optimal preventive maintenance cycle plan, including:

[0139] 1) Use real number coding to encode the preventive maintenance cycle plan; 2) Randomly generate K feasible solutions of the above optimization model as the initial population; 3) For each preventive maintenance cycle plan, if the plan is not feasible, its fitness is -M. Where M is a sufficiently large positive number; 4) If the plan is feasible, the inverse of the objective function value under the plan is taken, that is, as fitness; 5) Use the exponential sorting selection method to select individuals in the current population for replication; 6) Randomly cross-pair the individuals generated by the selection-copy operation, with a crossover probability of γ c ; 7) With mutation probability γ m Perform mutation operation; 8) The above 3) to 7) is one iteration. Repeat this iteration until it reaches the Lth generation, output the code with the maximum fitness at this time, and decode it to obtain the optimal preventive maintenance cycle plan.

[0140] The embodiment of the present invention provides a joint optimization method for maintenance of multiple equipment in a substation based on random failures, the method comprising: firstly obtaining random failure data of each equipment in the substation system, then processing the random failure data through a reliability and maintenance effectiveness model constructed based on a task scenario to determine the maintenance effectiveness of each equipment; then processing the maintenance effectiveness and random failure data of each equipment through a joint optimization model for maintenance of multiple equipment to determine the preventive maintenance cycle of each equipment in the substation system. This method solves the technical problem of the difficulty in balancing the improvement of the reliability of the substation system and the reduction of maintenance costs in the prior art, and realizes reasonable planning and effectiveness control for the maintenance of multiple equipment in the substation.

[0141] As a specific example, combining Figures 2 to 5, a specific embodiment of the joint optimization method for maintenance of multiple equipment in substations based on random failure is described in detail, see Figure 2 The flowchart of a specific embodiment of a joint optimization method for maintenance of multiple equipment in a substation based on random failure is shown, and the method includes:

[0142] (S01) Task scenario representation;

[0143] Corrective maintenance and preventive maintenance are performed on various equipment in the substation. Preventive maintenance is regular maintenance, and the reliability of different equipment is a random variable that obeys different probability distributions. This step includes the following processes:

[0144] <011> , After numbering the devices, form a device number set:

[0145] N={1,2,...,i,...,n} (20),

[0146] In formula (20), N represents a set of n device numbers. In this example, n = 4, and the devices are Figure 3 The square in the middle indicates that the device number is marked in the square;

[0147] <012> , the single corrective maintenance cost of equipment numbered i is c i,c ,1≤i≤n. In this example, c 1,c =c 2,c =8000,c 3,c =c 4,c =9000, Figure 3 The right side of the square in indicates the single corrective maintenance cost of the corresponding equipment;

[0148] <013> , the single preventive maintenance of equipment numbered i is c i,p ,1≤i≤n. In this example, c 1,p =c 3,p =4000, c 2,p =c 4,p =5000, Figure 3 The left side of the square in indicates the single preventive maintenance cost of the corresponding equipment;

[0149] <014> The preventive maintenance cycle of equipment numbered i is t i ,1≤i≤n;

[0150] <015> The probability density function of the failure time of the device numbered i is f i (t), 1≤i≤n. In this example, the failure time of all devices follows the Weibull distribution. The shape parameter of all devices is 2, and the proportion parameters of the four devices are as follows: μ1 =μ 2 =50,μ 3 =μ 4 =60, Figure 3 The scale parameters of the corresponding device are marked above the square in ;

[0151] <016> The effectiveness of a single preventive maintenance of equipment numbered i is α i ,1≤i≤n. In this example, α 1 =α 3 =0.005,α 2 =α 4 =0.007, Figure 3 The square below indicates the effectiveness of single preventive maintenance of the corresponding equipment;

[0152] (S02) Construct reliability and maintenance effectiveness model;

[0153] Calculate the reliability and maintenance effectiveness indicators of different equipment. This step includes the following processes:

[0154] <021> , when there is no preventive maintenance, the failure function of the equipment numbered i is:

[0155]

[0156] In formula (21), F i (t) represents the failure function of equipment numbered i when there is no preventive maintenance;

[0157] <022> , when there is no preventive maintenance, the reliability function of equipment numbered i is:

[0158]

[0159] In formula (22), R i (t) represents the reliability function of equipment numbered i when there is no preventive maintenance;

[0160] <023> , Without preventive maintenance, the failure rate of equipment numbered i is:

[0161]

[0162] In formula (23), λ i (t) represents the failure rate of equipment numbered i when there is no preventive maintenance;

[0163] <024> , Without preventive maintenance, the average failure time of equipment numbered i is:

[0164]

[0165] In formula (24), MTTF i It represents the average failure time of equipment numbered i without preventive maintenance;

[0166] <025> , When there is preventive maintenance, the failure rate of equipment numbered i is:

[0167]

[0168] In formula (25), λ i '(t) represents the failure rate of equipment numbered i when there is preventive maintenance. Indicates a floor operation. In this example, Figure 4 The preventive maintenance failure rate curves of the four types of equipment when the preventive maintenance cycle is 15 are shown;

[0169] <026> , when there is preventive maintenance, the reliability function of equipment numbered i is:

[0170]

[0171] In formula (26), R i '(t) represents the reliability function of equipment numbered i when there is preventive maintenance;

[0172] <027> , When there is preventive maintenance, the average failure time of equipment numbered i is:

[0173]

[0174] In formula (27), MTTF' i It indicates the mean failure time of equipment numbered i when there is preventive maintenance;

[0175] <028> The maintenance-free life of equipment numbered i is:

[0176] T i =solve(R i (T i )= R i ) (28),

[0177] In formula (28), T i Represents the maintenance-free life of the equipment numbered i. R i represents the minimum reliability of the device numbered i, and solve(·) means solving the equation in the brackets. In this example, the minimum reliability of all devices is 0.9;

[0178] <029> , the maintenance life of equipment numbered i is:

[0179] T i '=solve(R i '(T i ')= R i ) (29),

[0180] In formula (29), T i 'Indicates the maintenance life of the equipment numbered i;

[0181] <0210> The maintenance effectiveness of equipment numbered i is defined as:

[0182]

[0183] In formula (30), E i Indicates the maintenance effectiveness of the equipment numbered i.

[0184] (S03) Construct a joint optimization model for maintenance of multiple equipments;

[0185] The goal is to minimize the total cost of corrective maintenance and preventive maintenance of the entire system, and to meet the minimum mean failure time, minimum maintenance effectiveness and unit time preventive maintenance budget as constraints of multiple equipment maintenance joint optimization model, and use genetic algorithm to solve the optimal preventive maintenance cycle. This step includes the following processes:

[0186] <031> , the decision variable value constraints of the preventive maintenance cycle of equipment numbered i:

[0187] t i >0,1≤i≤n (31);

[0188] <032> , the average failure time constraint of the device numbered i:

[0189] MTTF i '≥ MTTF i ,1≤i≤n (32),

[0190] In formula (32), MTTF i Indicates the minimum mean failure time of the device numbered i. In this example, the minimum mean failure time of all devices is 80;

[0191] <033> , Preventive maintenance capability constraints for equipment numbered i:

[0192] λ i (t)-λ i (tt i )>α i ,1≤i≤n (33),

[0193] Formula (33) shows that preventive maintenance can only restore part of the reliability of the equipment, but cannot completely replace the equipment;

[0194] <034> , the minimum maintenance effectiveness constraint for equipment numbered i:

[0195] E i ≥ E i ,1≤i≤n (34),

[0196] In formula (34), E i Indicates the minimum maintenance effectiveness of the device numbered i. In this example, the minimum maintenance effectiveness of all devices is 2;

[0197] <035> , Preventive maintenance budget constraint per unit time:

[0198]

[0199] In formula (35), B represents the budget of preventive maintenance per unit time. In this example, B = 850;

[0200] <036> , Calculate the preventive maintenance cost of the entire system:

[0201]

[0202] In formula (36), c p Represents the preventive maintenance cost of the entire system;

[0203] <037> , Calculate the corrective maintenance cost of the entire system:

[0204]

[0205] In formula (37), c c represents the corrective maintenance cost of the entire system;

[0206] <038> , set the objective function to minimize the total cost of corrective maintenance and preventive maintenance of the entire system:

[0207] minc=c p +c c (38),

[0208] In formula (38), c represents the total cost of corrective maintenance and preventive maintenance of the entire system;

[0209] <039> , Summarize equations (31) to (38) to obtain a joint optimization model for maintenance of multiple equipments;

[0210] <0310> This embodiment uses a genetic algorithm to solve the optimal preventive maintenance cycle. The algorithm framework is as follows: (1) Use real number coding to encode the preventive maintenance cycle plan; (2) Randomly generate 100 feasible solutions of the above optimization model as the initial population; (3) For each preventive maintenance cycle plan, if the plan is not feasible, its fitness is -M. Wherein, M is a sufficiently large positive number. In this example, M = 100; (4) If the plan is feasible, then the inverse of the objective function value under the plan is taken, that is, as fitness; (5) use the exponential sorting selection method to select individuals in the current population for replication; (6) randomly cross-pair the individuals generated by the selection-copy operation, with a crossover probability of γ c In this case, γ c =0.9; (7) with mutation probability γ m Perform the mutation operation. In this case, γ m =0.4; (8) (3) to (7) above is one iteration. Repeat this iteration until the 30th iteration, output the code with the maximum fitness at this time, and decode it to obtain the optimal preventive maintenance cycle plan.

[0211] In this embodiment, the minimum value of the objective function is 682804.23, and the optimal preventive maintenance cycles of the four types of equipment are 17.2, 20.3, 20.5, and 25.3, respectively. The failure rates of the four types of equipment under the optimal preventive maintenance cycle are as follows: Figure 5 shown.

[0212] An embodiment of the present invention proposes a joint optimization method for maintenance of multiple equipment in a substation based on random failures. The method establishes a reliability and maintenance effectiveness model for a scenario in which corrective maintenance and preventive maintenance are performed on multiple equipment in the substation, preventive maintenance is regular maintenance, and the reliability of different equipment is a random variable that obeys different probability distributions.

[0213] Based on this reliability and maintenance effectiveness model, a joint optimization model for maintenance of multiple equipments was constructed with the goal of minimizing the total cost of corrective maintenance and preventive maintenance of the entire system and with the constraints of minimum mean failure time, minimum maintenance effectiveness and preventive maintenance budget per unit time. A genetic algorithm was used to solve the optimal preventive maintenance cycle plan.

[0214] Through the above method, the effectiveness index of preventive maintenance is introduced, which can assist maintenance personnel to more accurately measure the effectiveness of preventive maintenance; under the maintenance budget constraint, the optimal preventive maintenance cycle of various equipment is obtained. Under the premise of meeting the operating and economic cost constraints, the optimal preventive maintenance cycle plan can improve equipment reliability and minimize the total maintenance cost.

[0215] In addition, the embodiment of the present invention also provides a joint optimization device for maintenance of multiple equipment in a substation based on random failure, see Figure 6 , the device comprises:

[0216] The data acquisition module 610 is used to acquire random failure data of each device in the substation system; the random failure data includes: device number, probability density function of the failure time of the device, effectiveness of single preventive maintenance, preventive maintenance cycle, minimum reliability of the device, single corrective maintenance cost, and single preventive maintenance cost;

[0217] The maintenance effectiveness determination module 620 is used to process the random failure data of each device through a reliability and maintenance effectiveness model to determine the maintenance effectiveness of each device; the reliability and maintenance effectiveness model is constructed based on the task scenario and is used to generate maintenance indicators for the equipment;

[0218] The preventive maintenance cycle determination module 630 is used to process the maintenance effectiveness and random failure data of each device through a multi-device maintenance joint optimization model to determine the preventive maintenance cycle of each device in the substation system; the multi-device maintenance joint optimization model is constructed based on the maintenance indicators of the equipment.

[0219] The device for joint optimization of maintenance of multiple equipment in a substation based on random failures provided in the embodiment of the present application may be specific hardware on the equipment or software or firmware installed on the equipment, etc. The implementation principle and technical effect of the device provided in the embodiment of the present application are the same as those of the aforementioned method embodiment. For the sake of brief description, the parts not mentioned in the device embodiment can refer to the corresponding contents in the aforementioned method embodiment. Technical personnel in the relevant field can clearly understand that for the convenience and simplicity of description, the specific working processes of the systems, devices and units described above can all refer to the corresponding processes in the aforementioned method embodiment, and will not be repeated here. The device for joint optimization of maintenance of multiple equipment in a substation based on random failures provided in the embodiment of the present application has the same technical features as the method for joint optimization of maintenance of multiple equipment in a substation based on random failures provided in the aforementioned embodiment, so it can also solve the same technical problems and achieve the same technical effects.

[0220] An embodiment of the present application further provides an electronic device. Specifically, the electronic device includes a processor and a storage device. The storage device stores a computer program, and when the computer program is executed by the processor, it executes the method described in any one of the above-mentioned embodiments.

[0221] Figure 7A structural schematic diagram of an electronic device provided in an embodiment of the present application, the electronic device 400 includes: a processor 40, a memory 41, a bus 42 and a communication interface 43, wherein the processor 40, the communication interface 43 and the memory 41 are connected via the bus 42; the processor 40 is used to execute an executable module stored in the memory 41, such as a computer program.

[0222] The memory 41 may include a high-speed random access memory (RAM), and may also include a non-volatile memory, such as at least one disk memory. The communication connection between the system network element and at least one other network element is realized through at least one communication interface 43 (which may be wired or wireless), and the Internet, wide area network, local area network, metropolitan area network, etc. may be used.

[0223] The bus 42 may be an ISA bus, a PCI bus, or an EISA bus, etc. The bus may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 7 Only one bidirectional arrow is used in the diagram, but this does not mean that there is only one bus or only one type of bus.

[0224] Among them, the memory 41 is used to store programs, and the processor 40 executes the program after receiving the execution instruction. The method executed by the process definition device disclosed in any embodiment of the above-mentioned embodiment of the present invention can be applied to the processor 40 or implemented by the processor 40.

[0225] The processor 40 may be an integrated circuit chip with signal processing capabilities. In the implementation process, each step of the above method can be completed by the hardware integrated logic circuit or software instructions in the processor 40. The above processor 40 can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA), or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. The methods, steps and logic block diagrams disclosed in the embodiments of the present invention can be implemented or executed. The general-purpose processor can be a microprocessor or the processor can also be any conventional processor. The steps of the method disclosed in the embodiments of the present invention can be directly embodied as a hardware decoding processor to execute, or can be executed by a combination of hardware and software modules in the decoding processor. The software module can be located in a mature storage medium in the field such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory, or an electrically erasable programmable memory, a register, etc. The storage medium is located in the memory 41, and the processor 40 reads the information in the memory 41 and completes the steps of the above method in combination with its hardware.

[0226] Corresponding to the above method, an embodiment of the present application also provides a computer-readable storage medium, which stores machine-executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions prompt the processor to execute the steps of the above method.

[0227] In the embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. The device embodiments described above are merely schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some communication interfaces, and the indirect coupling or communication connection of the devices or units can be electrical, mechanical or other forms.

[0228] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0229] In addition, each functional unit in the embodiments provided in the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.

[0230] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product, which is stored in a storage medium and includes several instructions for enabling a computer device (which can be a personal computer, electronic device, or network device, etc.) to perform all or part of the steps of the methods described in each embodiment of the present invention. The aforementioned storage medium includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk.

[0231] It should be noted that similar numbers and letters represent similar items in the accompanying drawings. Therefore, once an item is defined in one drawing, it does not need to be further defined and explained in subsequent drawings. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.

[0232] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A joint optimization method for maintenance of multiple equipment in substations based on random failure, characterized in that: Applied to a substation system, the substation system includes multiple devices; the method includes: Obtain random failure data of each device in the substation system; the random failure data includes: device number, probability density function obeyed by the failure time of the device, effectiveness of single preventive maintenance, preventive maintenance cycle, minimum reliability of the device, single corrective maintenance cost, and single preventive maintenance cost; The random failure data of each device is processed by a reliability and maintenance effectiveness model to determine the maintenance effectiveness of each device; the reliability and maintenance effectiveness model is constructed based on a task scenario and is used to generate maintenance indicators of the device; The maintenance effectiveness and random failure data of each device are processed through a multiple equipment maintenance joint optimization model to determine the preventive maintenance cycle of each device in the substation system; the multiple equipment maintenance joint optimization model is constructed based on the maintenance indicators of the equipment.

2. The joint optimization method for maintenance of multiple equipment in substations based on random failure according to claim 1 is characterized in that: The reliability and maintenance effectiveness model includes: a model without preventive maintenance and a model with preventive maintenance; The non-preventive maintenance model includes: a failure function, a first reliability function, a first failure rate and a first mean failure time; The random failure data of each device is processed by the reliability and maintenance effectiveness model, including: Determining a failure function and a first reliability function based on a probability density function obeyed by the failure time of the device; determining a first failure rate based on the failure function and the first reliability function; Determining a first mean failure time based on the first reliability function; The preventive maintenance model includes: a second reliability function, a second failure rate and a second mean failure time; the random failure data of each device is processed by the reliability and maintenance effectiveness model, and further includes: Based on the first failure rate, determining a second failure rate; Determining a second reliability function based on the probability density function obeyed by the failure time of the device and the second failure rate; Based on the second reliability function, the second mean failure time is determined.

3. The joint optimization method for maintenance of multiple equipment in substations based on random failure according to claim 2 is characterized in that: The reliability and maintenance effectiveness model also includes: maintenance-free life, maintenance life and maintenance effectiveness; the random failure data of each device is processed by the reliability and maintenance effectiveness model to determine the maintenance effectiveness of each device, and also includes: determining a maintenance-free life based on the first reliability function and a minimum reliability of the equipment; determining a maintenance life based on the second reliability function and a minimum reliability of the equipment; The maintenance effectiveness of the equipment is determined based on the maintenance-free life and the maintenance-supported life.

4. The joint optimization method for maintenance of multiple equipment in substations based on random failure according to claim 1 is characterized in that: The maintenance index of the equipment includes: a first mean failure time, a second mean failure time, a first failure rate, a second failure rate, and a minimum maintenance effectiveness; the method also includes: Building a joint optimization model for maintenance of multiple equipment based on the maintenance indicators of the equipment; Based on the constraints and the maintenance index of the equipment, a joint optimization model for multiple equipment maintenance is constructed; the constraints include: the decision variable constraints of the equipment's preventive maintenance cycle, the mean failure time constraints of the equipment, the preventive maintenance capacity constraints of the equipment, the minimum maintenance effectiveness constraints of the equipment, and the preventive maintenance budget constraints per unit time.

5. The joint optimization method for maintenance of multiple equipment in substations based on random failure according to claim 4 is characterized in that: The maintenance effectiveness and random failure data of each device are processed by a plurality of equipment maintenance joint optimization models to determine the preventive maintenance cycle of each device in the substation system, including: Using the constraint condition to constrain the maintenance index of the equipment, and determining the corrective maintenance cost and preventive maintenance cost of the substation system; Determining a total maintenance cost of the substation system based on the corrective maintenance cost and the preventive maintenance cost; Based on the condition that the total maintenance cost is minimized, at least one group of preventive maintenance cycle plans for each device in the substation system is determined.

6. The joint optimization method for maintenance of multiple equipment in substations based on random failure according to claim 5 is characterized in that: The method further comprises: A genetic algorithm is used to process multiple preventive maintenance cycle plans generated by the multiple equipment maintenance joint optimization model to determine the optimal preventive maintenance cycle plan.

7. The joint optimization method for maintenance of multiple equipment in substations based on random failure according to claim 6 is characterized in that: The multiple preventive maintenance cycle plans generated by the multiple equipment maintenance joint optimization model are processed by using a genetic algorithm to determine the optimal preventive maintenance cycle plan, including: S21, encoding a plurality of preventive maintenance cycle plans generated by the plurality of equipment maintenance joint optimization model; each of the preventive maintenance cycle plans corresponds to an objective function value; the objective function value is the total maintenance cost of the substation system; S22, randomly generating several feasible solutions of the joint optimization model for maintenance of multiple equipment as the initial population; S23, determining whether each of the preventive maintenance cycle plans is feasible, and if so, determining the inverse of the corresponding objective function value as the fitness; otherwise, determining the fitness as -M, where M is a sufficiently large positive number; S24, using the exponential sorting selection method to select individuals in the current population for replication, and randomly cross-pairing the selected individuals with the individuals generated by the replication; S25, performing a mutation operation on the individuals after random cross-pairing with a first mutation probability; S23 to S25 are repeatedly executed until the iteration reaches the Lth generation, the maximum code of the current fitness is output and decoded, and the optimal preventive maintenance cycle plan is obtained.

8. A joint optimization device for maintenance of multiple equipment in a substation based on random failure, characterized in that: The device comprises: A data acquisition module is used to acquire random failure data of each device in the substation system; the random failure data includes: device number, probability density function of the failure time of the device, effectiveness of single preventive maintenance, preventive maintenance cycle, minimum reliability of the device, single corrective maintenance cost, and single preventive maintenance cost; A maintenance effectiveness determination module, used to process the random failure data of each device through a reliability and maintenance effectiveness model to determine the maintenance effectiveness of each device; the reliability and maintenance effectiveness model is constructed based on a task scenario and is used to generate maintenance indicators for the device; The preventive maintenance cycle determination module is used to process the maintenance effectiveness and random failure data of each device through a joint optimization model for maintenance of multiple equipment, and determine the preventive maintenance cycle of each device in the substation system; the joint optimization model for maintenance of multiple equipment is constructed based on the maintenance indicators of the equipment.

9. An electronic device comprising a memory and a processor, wherein the memory stores a computer program that can be run on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 7 are implemented.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores machine-executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions cause the processor to execute the method according to any one of claims 1 to 7.

Citation Information

Patent Citations

  • Economic effectiveness evaluation method of maintenance strategy

    CN111210032A

  • Maintenance strategy optimal value evaluation method and system based on equipment failure rate

    CN112329949A

  • Reliability-based preventive maintenance optimization method and device for electrical equipment

    CN112507516A

  • System maintenance strategy optimization method under uncertain background, equipment and medium

    CN114781729A

  • Selective maintenance decision-making method and system based on uncertain maintenance quality

    CN117350706A