Stone dry hanging joint and construction method thereof
The stone dry hanging node allows for convenient keel position adjustments and secure stone fixation through a horizontal keel profile with movable adjustments and sliding grooves, enhancing flexibility and load-bearing capabilities.
Patent Information
- Application Number
- CN202411461993.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-18
- Publication Date
- 2024-12-10
AI Technical Summary
The existing stone dry hanging method is limited by the inability to adjust the position of keels conveniently, restricting its application scope and flexibility.
A stone dry hanging node comprising a horizontal keel profile with a movable adjustment opening and a first hanger with a movable sliding groove, allowing vertical and horizontal adjustments through connecting angle codes, adjusting bolts, and nuts, facilitating easy installation and disassembly.
Enables convenient adjustment of keel positions, improving load-bearing performance, and ensuring the stone is securely fixed, with easy installation and maintenance.
Smart Images

Figure CN119102347A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building construction, and in particular to a stone dry hanging node and a construction method thereof. Background Art
[0002] Stone dry hanging method, also known as empty hanging method, is a new type of construction technology in wall decoration. Compared with the traditional stone pasting method, stone dry hanging method has many advantages. First, it does not require grouting and pasting, which can reduce pollution and waste in the construction process. Secondly, the facing stone is directly hung on the wall or hung on the steel frame through metal hangers, which can effectively improve the beauty and decorative effect of the building. In addition, the stone dry hanging method can also reduce the dead weight of the building, reduce the load of the building, and improve the safety performance of the building.
[0003] In the stone hanging method, the stone hanging node refers to the connection point where the stone is fixed to the building structure by the stone hanging method. These nodes are usually composed of metal hangers, keels, etc. However, the keels in the related art can only slide in two directions through the opening, and cannot slide in multiple directions, so it is not convenient for users to adjust the position of the keel, which limits the application scope and flexibility of the stone hanging method. Summary of the invention
[0004] The present application provides a stone dry hanging node and a construction method thereof, so as to solve the problem that it is inconvenient for a user to adjust the position of a keel.
[0005] The first aspect of the present application provides a stone dry hanging node, comprising: a horizontal keel profile, a vertical keel profile, a first connecting angle code, a first fixing bolt, a first adjusting bolt, a first adjusting nut, a second adjusting nut, a second adjusting bolt, a first hanger and a first connecting member; the vertical keel profile is provided with a movable adjustment opening on a side close to the horizontal keel profile; the connecting portion of the first connecting angle code is fixedly connected to the top surface of the horizontal keel profile through the first fixing bolt; the fixing portion of the first connecting angle code is fixedly connected to the first adjusting bolt through the first adjusting nut, and the first adjusting bolt is slidably connected to the movable adjustment opening; a first movable sliding groove is provided on the top of the horizontal keel profile, and the first connecting member is fixedly connected to the second adjusting bolt through the second adjusting nut; the second adjusting bolt is slidably connected to the first movable sliding groove; a first back bolt is provided on the first hanger, and the first back bolt is plugged into a prefabricated hole of the stone; the first hanger is clamped with the first connecting member on a side away from the stone.
[0006] The horizontal keel profile of the stone dry hanging node of the present application can be adjusted vertically according to the movable adjustment port, and the first hanger can be adjusted horizontally according to the first movable slide slot, thereby adjusting the position of the stone. The first connecting angle code, the first fixing bolt, the first adjusting bolt, the first adjusting nut, the second adjusting nut, the second adjusting bolt, the first hanger and the first connecting member are used for fixing, so that it is easy to install and disassemble at any time, so as to solve the problem that it is inconvenient for users to adjust the position of the keel.
[0007] Optionally, the first hanger includes a first hanging plate, a second hanging plate and a third hanging plate; the first hanging plate and the third hanging plate are parallel to each other, and the second hanging plate and the first hanging plate are perpendicular to each other; the lower part of a side of the first hanging plate away from the stone is connected to a side of the second hanging plate; the bottom surface of the second hanging plate is connected to the top surface of the third hanging plate away from the side of the first hanging plate; a first positioning piece is provided on the bottom surface of the third hanging plate close to the first hanging plate, and the first positioning piece is used to clamp the first connecting piece.
[0008] The first hanging member of the above structure can improve the load-bearing performance and prevent the stone from falling off or shifting; the first connecting member and the first positioning member are used in combination, which is easy to install and disassemble.
[0009] Optionally, the first connecting member includes a first connecting plate, a first U-shaped plate and a second connecting plate; the first connecting plate and the second connecting plate are parallel to each other; one side of the bottom surface of the first U-shaped plate is connected to one side of the top surface of the first connecting plate; one side of the bottom surface of the second connecting plate is connected to a side of the top surface of the first U-shaped plate away from the first connecting plate; the first connecting plate is fixedly connected to the top surface of the transverse keel profile by the first adjusting bolt and the first adjusting nut; and the first positioning member is clamped to the first U-shaped plate.
[0010] The first connecting member of the above structure is more convenient to be used in conjunction with the first positioning member, and can not only effectively disperse weight and pressure to improve load-bearing performance, but is also easy to install and disassemble.
[0011] Optionally, it also includes a second hanger, a second connecting piece, a third adjusting nut and a third adjusting bolt; a second movable slide groove is provided at the bottom of the transverse keel profile, and the second connecting piece is fixedly connected to the third adjusting bolt through the third adjusting nut; the third adjusting bolt is slidably connected to the second movable slide groove; a second back bolt is provided on the second hanger, and the second back bolt is plugged into the prefabricated hole of the stone; the second hanger is clamped with the second connecting piece on the side away from the stone.
[0012] The transverse keel profile and the stone can be further connected by the second hanging member and the second connecting member, so that the stone is fixed more firmly.
[0013] Optionally, the second hanger includes a fourth hanger plate, a fifth hanger plate and a sixth hanger plate; the fourth hanger plate and the sixth hanger plate are parallel to each other; the fifth hanger plate and the fourth hanger plate are perpendicular to each other; the upper part of the fourth hanger plate away from the stone is connected to one side of the fifth hanger plate; the bottom surface of the fifth hanger plate away from the side of the fourth hanger plate is connected to the top surface of the sixth hanger plate; a second positioning piece is provided on the bottom surface of the sixth hanger plate close to the fourth hanger plate, and the second positioning piece is used to clamp the second connecting piece.
[0014] The second hanging member of the above structure can improve the load-bearing performance and prevent the stone from falling off or shifting; the second connecting member and the second positioning member are used in combination, which is easy to install and disassemble.
[0015] Optionally, the second connecting member includes a third connecting plate, a second U-shaped plate and a fourth connecting plate; the third connecting plate and the fourth connecting plate are parallel to each other; one side of the top surface of the second U-shaped plate is connected to one side of the bottom surface of the third connecting plate; one side of the bottom surface of the fourth connecting plate is connected to a side of the top surface of the second U-shaped plate away from the third connecting plate; the top surface of the third connecting plate is fixedly connected to the bottom surface of the transverse keel profile by the second adjusting nut and the second adjusting bolt; the second positioning member is clamped to the second U-shaped plate.
[0016] The second connecting member of the above structure is more convenient to be used in conjunction with the second positioning member, and can not only effectively disperse weight and pressure to improve load-bearing performance, but is also easy to install and disassemble.
[0017] Optionally, it also includes a second fixing bolt, a second connecting angle code and an expansion bolt; the fixing part of the second connecting angle code is fixedly connected to the wall through the expansion bolt; the connecting part of the second connecting angle code is fixedly connected to the vertical keel profile through the second fixing bolt.
[0018] The vertical keel profile can be quickly fixed to the wall through the second fixing bolt, the second connection angle code and the expansion bolt, making the stone mounting process simple and fast, and facilitating future maintenance and replacement.
[0019] Optionally, the depth of the prefabricated hole of the stone is less than or equal to half of the thickness of the stone; and stone structural adhesive is provided in the prefabricated hole to further fix the first back bolt.
[0020] The stone structural adhesive can fill the tiny gap between the first back bolt and the stone, provide additional bonding force, and ensure that the first back bolt will not loosen or fall off during long-term use. The depth of the prefabricated hole of the stone is less than or equal to half of the thickness of the stone, which helps to maintain the overall strength and stability of the stone, and the prefabricated hole can reduce the stress concentration area of the stone, thereby reducing the risk of stone cracking or damage.
[0021] The second aspect of the present application provides a construction method for a stone dry hanging node, which is applied to the stone dry hanging node described in the first aspect, and the method comprises:
[0022] Insert the head of the first adjusting bolt from the top of the movable adjusting port so that the movable adjusting port is slidably connected to the first adjusting bolt;
[0023] The fixing portion of the first connecting angle bracket is fixedly connected to the first adjusting bolt via a first adjusting nut;
[0024] The connecting portion of the first connecting angle bracket is fixedly connected to the transverse keel profile by a first fixing bolt, so that the first adjusting bolt drives the transverse keel profile to slide vertically;
[0025] The first connecting member is fixedly connected to the second adjusting bolt via the second adjusting nut;
[0026] Insert the head of the first adjusting bolt from one end of the first movable sliding groove, so that the first connecting member is slidably connected to the first movable sliding groove;
[0027] Inserting a first back bolt of a first hanging member into a prefabricated hole of a stone material, so that the first hanging member is fixedly connected to the stone material;
[0028] The side of the first hanging member away from the stone is clamped on the first connecting member, so that the first connecting member drives the stone to slide horizontally.
[0029] The horizontal keel profile is adjusted vertically according to the movable adjustment port, and the first hanging member is adjusted horizontally according to the first movable slide slot, thereby adjusting the position of the stone. The first connecting angle, the first fixing bolt, the first adjusting bolt, the first adjusting nut, the second adjusting nut, the second adjusting bolt, the first hanging member and the first connecting member are fixed to facilitate installation and disassembly at any time, so as to solve the problem that it is inconvenient for users to adjust the position of the keel.
[0030] Optionally, before inserting the head of the first adjusting bolt from the top of the movable adjusting opening, the method further includes:
[0031] Fix the fixing part of the second connecting angle bracket to the wall surface by using expansion bolts;
[0032] The connecting portion of the second connecting angle bracket is fixedly connected to the side surface of the vertical keel profile by a second fixing bolt.
[0033] It should be understood that there are multiple expansion bolts, multiple second connection angle codes and multiple second fixing bolts, and multiple second connection angle codes can be fixed on both sides of the vertical keel profile to improve the strength of the connected wall.
[0034] The vertical keel profile can be quickly fixed to the wall through the second fixing bolt, the second connection angle code and the expansion bolt, making the stone mounting process simple and fast, and facilitating future maintenance and replacement.
[0035] It can be seen from the above technical scheme that the present application provides a stone dry hanging node and a construction method thereof, wherein the stone dry hanging node comprises a horizontal keel profile, a vertical keel profile, a first connecting angle code, a first fixing bolt, a first adjusting bolt, a first adjusting nut, a second adjusting nut, a second adjusting bolt, a first hanging member and a first connecting member; a movable adjusting opening is provided on the side of the vertical keel profile close to the horizontal keel profile; the connecting portion of the first connecting angle code is fixedly connected to the top surface of the horizontal keel profile through the first fixing bolt; the fixing portion of the first connecting angle code is fixedly connected to the first adjusting bolt through the first adjusting nut, and the first adjusting bolt is slidably connected to the movable adjusting opening; a first movable sliding groove is provided on the top of the horizontal keel profile, and the first connecting member is fixedly connected to the second adjusting bolt through the second adjusting nut; the second adjusting bolt is slidably connected to the first movable sliding groove; a first back bolt is provided on the first hanging member, and the first back bolt is plugged into the prefabricated hole of the stone; the first hanging member is clamped with the first connecting member on the side away from the stone, so as to solve the problem that it is inconvenient for the user to adjust the position of the keel. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the technical solution of the present application, the drawings required for use in the embodiments are briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.
[0037] Figure 1 This is a schematic diagram of the structure of the stone dry hanging node described in the embodiment of the present application;
[0038] Figure 2 This is a cross-sectional view of the stone dry hanging nodes after connection according to the embodiment of the present application;
[0039] Figure 3 This is a cross-sectional view of the connected transverse keel profiles in the stone dry hanging node described in the embodiment of the present application;
[0040] Figure 4 This is a schematic diagram of the structure of the first hanger in the stone dry hanging node described in the embodiment of the present application;
[0041] Figure 5 This is a schematic diagram of the structure of the second hanger in the stone dry hanging node described in the embodiment of the present application;
[0042] Figure 6 This is a schematic structural diagram of the first connecting member in the stone dry hanging node described in the embodiment of the present application;
[0043] Figure 7 This is a schematic diagram of the structure of the second connecting member in the stone dry hanging node described in the embodiment of the present application;
[0044] Figure 8 This is a schematic diagram of the structure of the transverse keel profile in the stone dry hanging node described in the embodiment of the present application.
[0045] Illustration Description:
[0046] Among them, 1-first hanging part; 2-second hanging part; 3-first connecting part; 4-second connecting part; 5-transverse keel profile; 51-first movable slide groove; 6-vertical keel profile; 61-movable adjustment port; 7-first connecting angle code; 8-second connecting angle code; 9-stone. DETAILED DESCRIPTION
[0047] The embodiments will be described in detail below, and examples thereof are shown in the accompanying drawings. When the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The implementation methods described in the following embodiments do not represent all implementation methods consistent with the present application. They are only examples of systems and methods consistent with some aspects of the present application.
[0048] To solve the problem that it is inconvenient for users to adjust the position of the keel, see Figure 1-Figure 8, some embodiments of the present application provide a stone dry hanging node, including: a horizontal keel profile 5, a vertical keel profile 6, a first connecting angle code 7, a first fixing bolt, a first adjusting bolt, a first adjusting nut, a second adjusting nut, a second adjusting bolt, a first hanger 1 and a first connecting member 3; the vertical keel profile 6 is provided with a movable adjusting port 61 on the side close to the horizontal keel profile 5; the connecting portion of the first connecting angle code 7 is fixedly connected to the top surface of the horizontal keel profile 5 through the first fixing bolt; the fixing portion of the first connecting angle code 7 is fixedly connected to the first adjusting bolt through the first adjusting nut, and the first adjusting bolt is slidably connected to the movable adjusting port 61; a first movable slide groove 51 is provided on the top of the horizontal keel profile 5, and the first connecting member 3 is fixedly connected to the second adjusting bolt through the second adjusting nut; the second adjusting bolt is slidably connected to the first movable slide groove 51; a first back bolt is provided on the first hanger 1, and the first back bolt is plugged into the prefabricated hole of the stone 9; the first hanger 1 is clamped with the first connecting member 3 on the side away from the stone 9.
[0049] It should be understood that the transverse keel profile 5 and the vertical keel profile 6 are both aluminum alloy profiles, which are lighter than steel frames and reduce ground load. The first connection angle bracket 7 can be a 50×20 angle bracket.
[0050] The horizontal keel profile 5 of the stone dry hanging node of the present application can be adjusted vertically according to the movable adjustment port 61, and the first hanger 1 can be adjusted horizontally according to the first movable slide slot 51, thereby adjusting the position of the stone 9. The first connecting angle code 7, the first fixing bolt, the first adjusting bolt, the first adjusting nut, the second adjusting nut, the second adjusting bolt, the first hanger 1 and the first connecting member 3 are used for fixing, so as to facilitate installation and disassembly at any time, so as to solve the problem that it is inconvenient for users to adjust the position of the keel.
[0051] In some embodiments, see Figure 4 The first hanging member 1 includes a first hanging plate, a second hanging plate and a third hanging plate; the first hanging plate and the third hanging plate are parallel to each other, and the second hanging plate and the first hanging plate are perpendicular to each other; the lower part of the first hanging plate away from the stone 9 is connected to one side of the second hanging plate; the bottom surface of the second hanging plate is connected to the top surface of the third hanging plate away from the first hanging plate; a first positioning member is provided on the bottom surface of the third hanging plate close to the first hanging plate, and the first positioning member is used to clamp the first connecting member 3.
[0052] It should be understood that the above-mentioned hanging plates are all rectangular structures; the first hanging member 1 of the above-mentioned structure can improve the load-bearing performance and prevent the stone 9 from falling off or shifting; the first connecting member 3 and the first positioning member are used in combination, which is easy to install and disassemble.
[0053] In some embodiments, see Figure 6 The first connecting member 3 includes a first connecting plate, a first U-shaped plate and a second connecting plate; the first connecting plate and the second connecting plate are parallel to each other; one side of the bottom surface of the first U-shaped plate is connected to one side of the top surface of the first connecting plate; one side of the bottom surface of the second connecting plate is connected to a side of the top surface of the first U-shaped plate away from the first connecting plate; the first connecting plate is fixedly connected to the top surface of the transverse keel profile 5 by the first adjusting bolt and the first adjusting nut; the first positioning member is clamped with the first U-shaped plate.
[0054] The first connecting member 3 of the above structure is more convenient to be used in conjunction with the first positioning member, and can not only effectively disperse weight and pressure to improve load-bearing performance, but is also easy to install and disassemble.
[0055] In some embodiments, it also includes a second hanger 2, a second connecting member 4, a third adjusting nut and a third adjusting bolt; a second movable slide groove is opened at the bottom of the transverse keel profile 5, and the second connecting member 4 is fixedly connected to the third adjusting bolt through the third adjusting nut; the third adjusting bolt is slidably connected to the second movable slide groove; a second back bolt is provided on the second hanger 2, and the second back bolt is plugged into the prefabricated hole of the stone 9; the second hanger 2 is clamped with the second connecting member 4 on the side away from the stone 9.
[0056] The transverse keel profile 5 and the stone 9 can be further connected by the second hanging member 2 and the second connecting member 4, so that the stone 9 can be fixed more firmly.
[0057] In some embodiments, see Figure 5 The second hanger 2 includes a fourth hanger plate, a fifth hanger plate and a sixth hanger plate; the fourth hanger plate and the sixth hanger plate are parallel to each other; the fifth hanger plate and the fourth hanger plate are perpendicular to each other; the upper part of the fourth hanger plate away from the stone 9 is connected to one side of the fifth hanger plate; the bottom surface of the fifth hanger plate is connected to the top surface of the sixth hanger plate away from the side of the fourth hanger plate; a second positioning member is provided on the bottom surface of the sixth hanger plate close to the fourth hanger plate, and the second positioning member is used to clamp the second connecting member 4.
[0058] The second hanging member 2 of the above structure can improve the load-bearing performance and prevent the stone 9 from falling off or shifting; the second connecting member 4 and the second positioning member are used in combination, which is easy to install and disassemble.
[0059] In some embodiments, see Figure 7The second connecting member 4 includes a third connecting plate, a second U-shaped plate and a fourth connecting plate; the third connecting plate and the fourth connecting plate are parallel to each other; one side of the top surface of the second U-shaped plate is connected to one side of the bottom surface of the third connecting plate; one side of the bottom surface of the fourth connecting plate is connected to the side of the top surface of the second U-shaped plate away from the third connecting plate; the top surface of the third connecting plate is fixedly connected to the bottom surface of the transverse keel profile 5 by the second adjusting nut and the second adjusting bolt; the second positioning member is clamped with the second U-shaped plate.
[0060] The second connecting member 4 of the above structure is more convenient to be used in conjunction with the second positioning member, and can not only effectively disperse the weight and pressure to improve the load-bearing performance, but is also easy to install and disassemble.
[0061] In some embodiments, it also includes a second fixing bolt, a second connecting angle code 8 and an expansion bolt; the fixing part of the second connecting angle code 8 is fixedly connected to the wall through the expansion bolt; the connecting part of the second connecting angle code 8 is fixedly connected to the vertical keel profile 6 through the second fixing bolt.
[0062] It should be understood that the second connection angle code 8 can be a 50×50 angle code, and the spacing between the plurality of vertical keel profiles 6 is less than or equal to 1200 mm.
[0063] The vertical keel profile 6 can be quickly fixed to the wall through the second fixing bolts, the second connection angle code 8 and the expansion bolts, making the mounting process of the stone 9 simple and fast, and facilitating future maintenance and replacement.
[0064] In some embodiments, the depth of the prefabricated hole of the stone 9 is less than or equal to half the thickness of the stone 9; stone structural adhesive is provided in the prefabricated hole to further fix the first back bolt.
[0065] It should be understood that the stone structural adhesive is an adhesive specifically used for bonding and repairing stone 9, and has the advantages of high strength, weather resistance, waterproofness, corrosion resistance, and convenient construction.
[0066] The stone structural adhesive can fill the tiny gap between the first back bolt and the stone 9, provide additional bonding force, and ensure that the first back bolt will not loosen or fall off during long-term use. The depth of the prefabricated hole of the stone 9 is less than or equal to half the thickness of the stone 9, which helps to maintain the overall strength and stability of the stone 9, and the prefabricated hole can reduce the stress concentration area of the stone 9, thereby reducing the risk of the stone 9 breaking or being damaged.
[0067] Some embodiments of the present application also provide a construction method for a stone dry hanging node, which is applied to the stone dry hanging node described in the above embodiment, and the method includes:
[0068] Insert the head of the first adjusting bolt from the top of the movable adjusting port 61 so that the movable adjusting port 61 is slidably connected to the first adjusting bolt;
[0069] The fixing portion of the first connecting angle bracket 7 is fixedly connected to the first adjusting bolt via a first adjusting nut;
[0070] The connecting portion of the first connecting angle bracket 7 is fixedly connected to the transverse keel profile 5 through a first fixing bolt, so that the first adjusting bolt drives the transverse keel profile 5 to slide vertically;
[0071] The first connecting member 3 is fixedly connected to the second adjusting bolt via the second adjusting nut;
[0072] Insert the head of the first adjusting bolt from one end of the first movable sliding groove 51 to make the first connecting member 3 slidably connected to the first movable sliding groove 51;
[0073] Insert the first back bolt of the first hanging member 1 into the prefabricated hole of the stone 9, so that the first hanging member 1 is fixedly connected to the stone 9;
[0074] The side of the first hanging member 1 away from the stone 9 is clamped on the first connecting member 3, so that the first connecting member 3 drives the stone 9 to slide horizontally.
[0075] The horizontal keel profile 5 is adjusted vertically according to the movable adjustment opening 61, and the first hanging member 1 is adjusted horizontally according to the first movable slide groove 51, thereby adjusting the position of the stone 9. The first connecting angle code 7, the first fixing bolt, the first adjusting bolt, the first adjusting nut, the second adjusting nut, the second adjusting bolt, the first hanging member 1 and the first connecting member 3 are fixed to facilitate installation and disassembly at any time, so as to solve the problem that it is inconvenient for users to adjust the position of the keel.
[0076] In some embodiments, before inserting the head of the first adjusting bolt from the top of the movable adjusting opening 61, the method further includes:
[0077] Fix the fixing portion of the second connecting angle bracket 8 to the wall surface by using expansion bolts;
[0078] The connecting portion of the second connecting angle code 8 is fixedly connected to the side surface of the vertical keel profile 6 by a second fixing bolt.
[0079] The vertical keel profile 6 can be quickly fixed to the wall through the second fixing bolts, the second connection angle code 8 and the expansion bolts, making the mounting process of the stone 9 simple and quick, and facilitating future maintenance and replacement.
[0080] It can be seen from the above technical scheme that the embodiment of the present application provides a stone dry hanging node and a construction method thereof, wherein the stone dry hanging node includes a horizontal keel profile 5, a vertical keel profile 6, a first connecting angle code 7, a first fixing bolt, a first adjusting bolt, a first adjusting nut, a second adjusting nut, a second adjusting bolt, a first hanger 1 and a first connecting member 3; the vertical keel profile 6 is provided with a movable adjusting port 61 on a side close to the horizontal keel profile 5; the connecting portion of the first connecting angle code 7 is fixedly connected to the top surface of the horizontal keel profile 5 by the first fixing bolt; the fixing portion of the first connecting angle code 7 is fixedly connected to the top surface of the horizontal keel profile 5 by the first fixing bolt; An adjusting nut is fixedly connected to the first adjusting bolt, and the first adjusting bolt is slidably connected to the movable adjusting port 61; a first movable slide groove 51 is provided on the top of the transverse keel profile 5, and the first connecting member 3 is fixedly connected to the second adjusting bolt through the second adjusting nut; the second adjusting bolt is slidably connected to the first movable slide groove 51; a first back bolt is provided on the first hanging member 1, and the first back bolt is plugged into the prefabricated hole of the stone 9; the first hanging member 1 is clamped with the first connecting member 3 on the side away from the stone 9 to solve the problem that it is inconvenient for the user to adjust the position of the keel.
[0081] Similar parts between the embodiments provided in this application can be referenced to each other. The specific implementation methods provided above are only a few examples under the general concept of this application and do not constitute a limitation on the protection scope of this application. For those skilled in the art, any other implementation methods expanded based on the scheme of this application without creative work belong to the protection scope of this application.
Claims
1. A stone dry hanging node, characterized in that: include: A transverse keel profile (5), a vertical keel profile (6), a first connection angle code (7), a first fixing bolt, a first adjusting bolt, a first adjusting nut, a second adjusting nut, a second adjusting bolt, a first hanging member (1) and a first connecting member (3); The vertical keel profile (6) is provided with a movable adjustment opening (61) on one side close to the transverse keel profile (5); the connecting portion of the first connecting angle bracket (7) is fixedly connected to the top surface of the transverse keel profile (5) via the first fixing bolt; the fixing portion of the first connecting angle bracket (7) is fixedly connected to the first adjusting bolt via the first adjusting nut, and the first adjusting bolt is slidably connected to the movable adjustment opening (61); A first movable slide groove (51) is provided on the top of the transverse keel profile (5); the first connecting member (3) is fixedly connected to the second adjusting bolt via the second adjusting nut; the second adjusting bolt is slidably connected to the first movable slide groove (51); a first back bolt is provided on the first hanging member (1), and the first back bolt is plugged into a prefabricated hole of the stone (9); the first hanging member (1) is clamped with the first connecting member (3) on a side away from the stone (9).
2. The stone dry hanging node according to claim 1, characterized in that: The first hanging member (1) comprises a first hanging plate, a second hanging plate and a third hanging plate; The first hanging plate and the third hanging plate are parallel to each other, and the second hanging plate is perpendicular to the first hanging plate; the lower part of the first hanging plate away from the stone (9) is connected to one side of the second hanging plate; the bottom surface of the second hanging plate away from the first hanging plate is connected to the top surface of the third hanging plate; a first positioning member is provided on the side of the bottom surface of the third hanging plate close to the first hanging plate, and the first positioning member is used to clamp the first connecting member (3).
3. The stone dry hanging node according to claim 2, characterized in that: The first connecting member (3) comprises a first connecting plate, a first U-shaped plate and a second connecting plate; The first connecting plate and the second connecting plate are parallel to each other; one side of the bottom surface of the first U-shaped plate is connected to one side of the top surface of the first connecting plate; one side of the bottom surface of the second connecting plate is connected to one side of the top surface of the first U-shaped plate away from the first connecting plate; The first connecting plate is fixedly connected to the top surface of the transverse keel profile (5) via the first adjusting bolt and the first adjusting nut; and the first positioning member is clamped to the first U-shaped plate.
4. The stone dry hanging node according to claim 1, characterized in that: It also includes a second hanging member (2), a second connecting member (4), a third adjusting nut and a third adjusting bolt; A second movable slide groove is provided at the bottom of the transverse keel profile (5); the second connecting member (4) is fixedly connected to the third adjusting bolt via the third adjusting nut; the third adjusting bolt is slidably connected to the second movable slide groove; a second back bolt is provided on the second hanging member (2), and the second back bolt is plugged into the prefabricated hole of the stone (9); the side of the second hanging member (2) away from the stone (9) is clamped with the second connecting member (4).
5. The stone dry hanging node according to claim 4, characterized in that: The second hanging member (2) comprises a fourth hanging plate, a fifth hanging plate and a sixth hanging plate; The fourth hanging plate and the sixth hanging plate are parallel to each other; the fifth hanging plate and the fourth hanging plate are perpendicular to each other; the upper part of the fourth hanging plate away from the stone (9) is connected to one side of the fifth hanging plate; the bottom surface of the fifth hanging plate away from the side of the fourth hanging plate is connected to the top surface of the sixth hanging plate; a second positioning member is provided on the bottom surface of the sixth hanging plate on the side close to the fourth hanging plate, and the second positioning member is used to clamp the second connecting member (4).
6. The stone dry hanging node according to claim 5, characterized in that: The second connecting member (4) comprises a third connecting plate, a second U-shaped plate and a fourth connecting plate; The third connecting plate and the fourth connecting plate are parallel to each other; one side of the top surface of the second U-shaped plate is connected to one side of the bottom surface of the third connecting plate; one side of the bottom surface of the fourth connecting plate is connected to one side of the top surface of the second U-shaped plate away from the third connecting plate; The top surface of the third connecting plate is fixedly connected to the bottom surface of the transverse keel profile (5) via the second adjusting nut and the second adjusting bolt; and the second positioning member is clamped with the second U-shaped plate.
7. The stone dry hanging node according to claim 1, characterized in that: It also includes a second fixing bolt, a second connection angle code (8) and an expansion bolt; The fixing portion of the second connecting angle bracket (8) is fixedly connected to the wall surface by means of the expansion bolts; The connecting portion of the second connecting angle bracket (8) is fixedly connected to the vertical keel profile (6) via the second fixing bolt.
8. The stone dry hanging node according to claim 1, characterized in that: The depth of the prefabricated hole of the stone (9) is less than or equal to half the thickness of the stone (9); stone structural glue is provided in the prefabricated hole to further fix the first back bolt.
9. A construction method for stone dry hanging nodes, characterized in that: Applied to the stone dry hanging node according to any one of claims 1 to 8, the method comprises: Inserting the head of the first adjusting bolt from the top of the movable adjusting opening (61) so that the movable adjusting opening (61) is slidably connected to the first adjusting bolt; The fixing portion of the first connecting angle code (7) is fixedly connected to the first adjusting bolt via a first adjusting nut; The connecting portion of the first connecting angle bracket (7) is fixedly connected to the transverse keel profile (5) via a first fixing bolt, so that the first adjusting bolt drives the transverse keel profile (5) to slide vertically; The first connecting member (3) is fixedly connected to the second adjusting bolt via the second adjusting nut; Inserting the head of the first adjusting bolt from one end of the first movable sliding groove (51) so that the first connecting member (3) is slidably connected to the first movable sliding groove (51); Inserting the first back bolt of the first hanging member (1) into the prefabricated hole of the stone (9) so that the first hanging member (1) is fixedly connected to the stone (9); The side of the first hanging member (1) away from the stone (9) is clamped on the first connecting member (3), so that the first connecting member (3) drives the stone (9) to slide horizontally.
10. The construction method of stone dry hanging node according to claim 9, characterized in that: Before inserting the head of the first adjusting bolt from the top of the movable adjusting opening (61), the method further comprises: The fixing portion of the second connecting angle bracket (8) is fixed to the wall surface by means of expansion bolts; The connecting portion of the second connecting angle code (8) is fixedly connected to the side surface of the vertical keel profile (6) by means of a second fixing bolt.