Multi-region carbon emission pre-evaluation method, system and medium
By automatically sorting out the relationship between the receiving end and the improved bubble method calculation in the multi-region power system, the problems of complexity and fairness of carbon emission transfer in the prior art are solved, and the carbon emission calculation efficiency of the multi-region power system is improved. and accuracy.
Patent Information
- Application Number
- CN202411107406.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2044-08-13
AI Technical Summary
The prior art is difficult to accurately calculate the carbon emission transfer amount in multi-region power systems, especially when the number of regions and connection lines is large and the proportion of electricity is complex, which affects the fairness and calculation efficiency of carbon emission accounting.
A multi-regional carbon emission pre-evaluation method and system is proposed. By automatically sorting out the relationship between the receiving end, the improved bubble method is used to calculate the net carbon emissions of the regional power grid, including obtaining the regional calculation order, determining the initial power generation matrix and carbon emission matrix, and successively Calculate the net carbon emission factors for each region.
The efficiency and accuracy of net carbon emission calculation in multi-regional power systems have been improved, ensuring the fairness and accuracy of carbon emission calculation.
Smart Images

Figure CN119106801A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power system planning, and in particular to a multi-region carbon emission pre-assessment method, system and medium. Background Art
[0002] The planning of future new power systems needs to comprehensively consider multiple factors such as safety, economy, and low carbon, and carbon emission analysis is often conducted in the form of carbon emission constraints. How to confirm the carbon emission constraint indicators for typical scenarios in future key years will have a huge impact on parameters such as the power structure, electricity proportion, and new energy consumption of the new power system.
[0003] There is a clear order in the calculation of inter-regional carbon transfer. It is necessary to first solve the carbon emissions of the sending area, the regional power grid carbon emission factor and other parameters before the carbon transfer can be calculated clearly. Some scholars have proposed a method for calculating carbon transfer between multiple regions, but the relationship between the sending and receiving ends of each region is often analyzed by drawing a system structure diagram and clearly marking the power and carbon emissions of each interconnection line. When the number of regions and interconnection lines is large, the analysis scenario becomes complicated, and it is difficult to clearly and accurately calculate and analyze the carbon emission transfer between regions. At the same time, when there are complex scenarios such as green electricity and interconnection line supporting power grids in the transmission line, using the regional power grid carbon emission factor to calculate the carbon emission transfer of other interconnection lines will affect the fairness of carbon emission accounting.
[0004] For the existing technology of carbon emission assessment and calculation for multi-regional power systems with interconnection lines, there are existing calculation models that can calculate the CO2 emissions generated by local coal-fired power and gas-fired power in each region, but there is less analysis on the carbon transfer effect brought by the transmission of electricity through interconnection lines between multiple regions. The existing inter-regional carbon emission transfer algorithm generally draws the system structure diagram between each region first, and sorts out the corresponding relationship between the sending end and the receiving end between each region. This will become complicated and difficult to calculate for scenarios with many regions and a large proportion of interconnection line electricity. Summary of the invention
[0005] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a multi-region carbon emission pre-assessment method and system, which can automatically sort out the relationship between the sending and receiving ends of each region, and calculate the net carbon emissions of the regional power grid after considering the carbon transfer of the interconnection line in each region, and at the same time propose an improved residual carbon emission factor calculation method based on the carbon emission characteristics of the interconnection line. The present invention is conducive to the software implementation of the net carbon emission calculation, and is conducive to improving the calculation efficiency and accuracy of the net carbon emissions of the multi-regional power system.
[0006] The present invention also provides a system and a medium having the above-mentioned multi-region carbon emission pre-assessment method.
[0007] The multi-region carbon emission pre-assessment method according to the first embodiment of the present invention is characterized by comprising the following steps:
[0008] According to the relationship between the sending end and the receiving end of the interconnection line, the regional calculation order is obtained;
[0009] Determine the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emission, incoming and outgoing carbon emission of the region;
[0010] Based on the calculation order of the regions and the local carbon emissions, incoming and outgoing carbon emissions of each region, the carbon emission factors of the electricity sent from each region are obtained one by one, and the net carbon emissions of each region are calculated based on the carbon emission factors.
[0011] The multi-region carbon emission pre-assessment method according to the embodiment of the present invention has at least the following beneficial effects:
[0012] This method uses a regional carbon transfer calculation sequence confirmation method based on an improved bubbling method, automatically sorts out the sending and receiving end relationships between regions, and calculates the regional power grid net carbon emissions of each region after considering the carbon transfer of the interconnecting lines. This is conducive to the software implementation of net carbon emissions calculation, while improving the calculation efficiency and accuracy of net carbon emissions of multi-regional power systems.
[0013] According to some embodiments of the present invention, the step of obtaining the region calculation order based on the improved bubbling method according to the relationship between the sending end and the receiving end of the interconnection line includes:
[0014] Sort by area number and analyze the corresponding relationship between the sending end and the receiving end of the ith tie line;
[0015] Determine whether the sequence number of the sending end region is before the sequence number of the receiving end region. If not, swap the receiving end region with the adjacent region on the left. Determine whether the sequence number of the sending end region is before the sequence number of the receiving end region. If not, continue to swap with the adjacent region on the left. Keep swapping the sending end region before the receiving end region. If yes, skip this contact line and proceed to the next step.
[0016] Analyze the corresponding relationship between the sending end and the receiving end of the i+1th tie line, and sort them according to the above steps;
[0017] The impact of several tie lines is analyzed one by one to form a sorting matrix that satisfies the sending and receiving end relationships of all tie lines.
[0018] According to some embodiments of the present invention, in the step of determining the initial power generation matrix, carbon emission matrix, and transfer power matrix for each region, if the interconnection line has a matching power source, it is also necessary to determine the transfer power matrix of the interconnection line with the matching power source.
[0019] According to some embodiments of the present invention, the step of calculating the carbon emission factor of the electricity delivered by each region one by one based on the calculation order of the regions and the local carbon emissions, incoming and outgoing carbon emissions of each region, and calculating the net carbon emissions of each region includes:
[0020] Based on the relationship between regional input and output, determine the carbon emissions received and the carbon emissions sent;
[0021] The net carbon emissions of the region are calculated by subtracting the carbon emissions sent out and adding the carbon emissions received.
[0022] Repeat the above steps for each region to obtain the net carbon emissions of each region.
[0023] According to some embodiments of the present invention, the received carbon emissions include the received carbon emissions with a clear supporting power supply and the received carbon emissions without a clear supporting power supply; the sent carbon emissions include the sent carbon emissions with a clear supporting power supply and the sent carbon emissions without a clear supporting power supply.
[0024] The regional carbon emission pre-assessment system according to the second aspect of the present invention is characterized by comprising:
[0025] The regional sorting module can obtain the regional calculation order based on the relationship between the sending and receiving ends of the interconnected lines;
[0026] The data collection module determines the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emission, incoming and outgoing carbon emission of the region;
[0027] The net emission calculation module can obtain the carbon emission factor of the electricity sent out by each region one by one based on the regional calculation order and the local carbon emissions, incoming and outgoing carbon emissions of each region, and calculate the net carbon emissions of each region based on the carbon emission factors.
[0028] According to some embodiments of the present invention, the region sorting module includes:
[0029] The first relationship corresponding element can be sorted according to the regional sequence number and analyze the corresponding relationship between the sending end and the receiving end of the i-th tie line;
[0030] The bubble sorting component can determine whether the sequence number of the sending end area is sorted before the sequence number of the receiving end area. If not, the receiving end area is exchanged with the adjacent area on the left. It is determined whether the sequence number of the sending end area is sorted before the sequence number of the receiving end area. If not, it continues to exchange with the adjacent area on the left; the sending end area is exchanged before the receiving end area; if so, this connection line is skipped to the next step;
[0031] The second relationship corresponding element can analyze the corresponding relationship between the sending end and the receiving end of the i+1th tie line and sort them according to the above steps;
[0032] The matrix generation element can analyze the influence of several tie lines one by one and form a sorting matrix that satisfies the relationship between the sending and receiving ends of all tie lines.
[0033] According to some embodiments of the present invention, in the data collection module, if the tie line has a matching power supply, it is also necessary to determine the transfer power matrix of the tie line with the matching power supply.
[0034] According to some embodiments of the present invention, the net emission calculation module includes:
[0035] The component analysis element can determine the carbon emissions received and the carbon emissions sent based on the regional input and output relationship;
[0036] The regional calculation component can calculate the net carbon emissions of the region by subtracting the outgoing carbon emissions and adding the incoming carbon emissions;
[0037] The loop element can repeat the above steps for each area to obtain the net carbon emissions of each area.
[0038] According to some embodiments of the present invention, the received carbon emissions include the received carbon emissions with a clear supporting power supply and the received carbon emissions without a clear supporting power supply; the sent carbon emissions include the sent carbon emissions with a clear supporting power supply and the sent carbon emissions without a clear supporting power supply.
[0039] According to a computer-readable storage medium of an embodiment of the third aspect of the present invention, the medium stores computer-executable instructions, and the computer-executable instructions are used to execute the above-mentioned multi-regional carbon emission pre-assessment method.
[0040] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0042] Figure 1 A schematic diagram of the steps of a multi-region carbon emission pre-assessment method according to an embodiment of the present invention;
[0043] Figure 2 for Figure 1 A schematic diagram of regional power generation of a multi-regional carbon emission pre-assessment method is shown;
[0044] Figure 3 for Figure 1 A schematic diagram of regional carbon emissions of a multi-regional carbon emissions pre-assessment method is shown;
[0045] Figure 4 This is a structural block diagram of a multi-region carbon emission pre-assessment system provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0046] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0047] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0048] In the description of the present invention, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0049] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0050] Reference Figure 1 , an embodiment of the present invention provides a multi-region carbon emission pre-assessment method. The method comprises at least the following steps:
[0051] Step S100: Obtain the regional calculation order according to the relationship between the sending end and the receiving end of the interconnection line.
[0052] Step S200: determine the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emission, incoming and outgoing carbon emission conditions of the region.
[0053] Step S300: based on the regional calculation order and the local carbon emissions, incoming and outgoing carbon emissions of each region, obtain the carbon emission factor of the outgoing electricity of each region one by one, and calculate the net carbon emissions of each region according to the carbon emission factor.
[0054] This method automatically sorts out the relationship between the sending and receiving ends of each region, and calculates the net carbon emissions of the regional power grid after considering the carbon transfer of the interconnecting lines in each region. It can be conducive to the software implementation of net carbon emissions calculation, which is beneficial to improving the calculation efficiency and accuracy of net carbon emissions of multi-regional power systems.
[0055] Embodiment 1
[0056] Furthermore, in order to describe the specific process and purpose of the present invention in more detail, the above steps are described in more detail.
[0057] Specifically, the multi-region carbon emission pre-assessment method provided by the present invention comprises the following steps:
[0058] Step S100: Obtain the regional calculation order according to the relationship between the sending end and the receiving end of the interconnection line.
[0059] Step S101, sorting according to the area serial number, and analyzing the corresponding relationship between the sending end and the receiving end of the i-th connecting line.
[0060] Step S102, determine whether the sequence number of the sending end area is sorted before the sequence number of the receiving end area. If not, exchange the receiving end area with the adjacent area on the left, and determine whether the sequence number of the sending end area is sorted before the sequence number of the receiving end area. If not, continue to exchange with the adjacent area on the left; keep exchanging the sending end area before the receiving end area; if so, skip this connection line and proceed to the next step.
[0061] Step S103, analyzing the correspondence between the sending end and the receiving end of the (i+1)th tie line, and sorting them according to the above steps S101 and S102.
[0062] Step S104, analyzing the influence of several tie lines one by one, and forming a sorting matrix that satisfies the relationship between the sending and receiving ends of all tie lines.
[0063] Step S200: determine the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emission, incoming and outgoing carbon emission conditions of the region.
[0064] Preferably, some areas can identify supporting power sources, while some areas cannot. In order to distinguish these supporting power sources, it is necessary to sort out the initial power generation matrix and carbon emission matrix of each area, the transfer power matrix of the interconnection lines with supporting power sources, and the carbon transfer matrix; the transfer power matrix without supporting power sources.
[0065] And get the following matrix:
[0066]
[0067] in, is the total power generation of local power sources in area m; is the total carbon emissions of local power sources in region m; It is the total power transmission from area m1 to area m2 with a clear supporting power line. If there is no corresponding line, the element value is 0; It is the total carbon emissions from area m1 to area m2 with a clear supporting power line. If there is no corresponding line, the element value is 0; It is the total power transmission from area m1 to area m2 without a clear supporting power connection line. If there is no corresponding connection line, the element value is 0; It is the total carbon emissions from area m1 to area m2 without a clear supporting power line, where the initial value of all elements is 0.
[0068] Step S300: based on the regional calculation order and the local carbon emissions, incoming and outgoing carbon emissions of each region, obtain the carbon emission factor of the outgoing electricity of each region one by one, and calculate the net carbon emissions of each region according to the carbon emission factor.
[0069] like Figure 2 , Figure 3 As shown, regional power generation needs to consider local carbon emissions, incoming and outgoing carbon emissions, and the carbon emission factors of the electricity delivered to each region one by one. Only then can the local net carbon emissions be calculated. Specifically, the following steps are included:
[0070] Step S301: Determine the carbon emissions received and the carbon emissions sent based on the regional input and output relationship.
[0071] Step S302: Subtract the outgoing carbon emissions from the local carbon emissions and add the incoming carbon emissions to obtain the net carbon emissions of the area.
[0072] Step S303: Repeat the above steps for each region to obtain the net carbon emissions of each region.
[0073] Step S304: Generate a carbon emission matrix based on the net carbon emissions of each region.
[0074]
[0075] in, Represents the net emissions of region m.
[0076] Preferably, since some areas cannot determine the clear supporting power source, the carbon emissions received include the carbon emissions received from areas with clear supporting power sources and the carbon emissions received from areas without clear supporting power sources; similarly, the carbon emissions sent out also include the carbon emissions sent out from areas with clear supporting power sources and the carbon emissions sent out from areas without clear supporting power sources.
[0077] Bringing the above situation into step S300, the specific calculation process becomes:
[0078]
[0079]
[0080] in, is the total carbon emissions of local power sources in region m1; is the regional net carbon emission of region m1; The total carbon emissions transferred for the interconnection lines with clear supporting power sources received by area m1; The total carbon emissions transferred by the interconnection line without clear supporting power supply received by area m1. According to the ranking, when calculating the power received by area m1, the carbon transfer amount sent by the sending end area corresponding to area m1 has been calculated before; The total carbon emissions transferred by the interconnection line with clear supporting power supply sent to area m1; The total carbon emissions transferred by the interconnection line without clear supporting power supply sent to area m1.
[0081]
[0082] according to Calculate the carbon emissions transferred in area m1 without supporting power supply interconnection lines.
[0083]
[0084] Repeat the above steps for each region to obtain the net carbon emissions of all regions.
[0085] Embodiment 2
[0086] In order to verify the effect of the present invention, a specific scenario is now introduced for verification.
[0087] Step S100: Obtain the regional calculation order according to the relationship between the sending end and the receiving end of the interconnection line.
[0088] 1) Select multiple regional scenarios across the country for analysis. The names and IDs of each region are shown in Tables 1 and 2.
[0089] Table 1 Name and ID of each area
[0090] Serial number Region Name Region ID 1 North China 1 2 East China 2 3 Central China 3 4 northeast 4 5 northwest 5 6 southwest 6 7 China Southern Power Grid 7
[0091] Table 2 Correspondence between the sending and receiving ends of each tie line
[0092] Contact line ID Receiver ID Receiver ID 1 1 2 2 1 3 3 1 4 4 5 1 5 3 3 6 6 2 7 5 2 8 4 2 9 6 3 10 5 3 11 6 5 12 7 1
[0093] 2) According to the regional IDs, sort them from left to right and from small to large, and analyze the corresponding relationship between the sending end and the receiving end of the i-th (i=1) tie line;
[0094] Constructing the initial sorting matrix
[0095] S = [1,2,3,4,5,6,7]
[0096] 3) Determine whether the sender ID is sorted before the receiver ID. If so, proceed to step 4); if not, swap the receiver region with the left adjacent region to determine whether the sender ID is sorted before the receiver ID. If still not, continue to swap with the left adjacent region; keep swapping the sender region until it is before the receiver region, and then proceed to step 4);
[0097] The corresponding relationship of the first tie line is sending end area 1 and sending end area 2. The sorting S satisfies the requirement that the sending end ID is before the receiving end ID, and step 4 is performed;
[0098] 4) Analyze the corresponding relationship between the sending end and the receiving end of the (i+1)th tie line, and adjust the sorting S according to step 3);
[0099] Analysis shows that the second and third tie lines have no effect on the sorting S. After the fourth tie line, the sorting S is adjusted:
[0100] S = [5, 1, 2, 3, 4, 6, 7];
[0101] After the 4th tie line, adjust the order S:
[0102] S = [5, 1, 3, 2, 4, 6, 7];
[0103] Carry out sorting adjustment in sequence
[0104] 5) Analyze the impact of n tie lines one by one and form a sorting matrix that satisfies the relationship between the sending and receiving ends of all tie lines.
[0105] After analyzing the 12 curves, the final sorting matrix S = [6, 7, 4, 1, 3, 5, 2] is formed.
[0106] Step S200: determine the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emission, incoming and outgoing carbon emission conditions of the region.
[0107] Sort out the initial power generation matrix and carbon emission matrix of each region, the transfer power matrix of the interconnection lines with supporting power sources, and the carbon transfer matrix; the transfer power matrix without supporting power sources.
[0108]
[0109] E0=[20649.30,22126.80,13241.80,16866.70,7789.90,9248.60,26530.90]
[0110]
[0111] C0=[751.30,1077.60,465.60,859.20,349.80,100.00,1196.30]
[0112] E su , C su All elements in it are 0;
[0113]
[0114] in, is the total power generation of local power sources in area m; is the total carbon emissions of local power sources in region m; It is the total power transmission from area m1 to area m2 with a clear supporting power line. If there is no corresponding line, the element value is 0; It is the total carbon emissions from area m1 to area m2 with a clear supporting power line. If there is no corresponding line, the element value is 0; It is the total power transmission from area m1 to area m2 without a clear supporting power connection line. If there is no corresponding connection line, the element value is 0; is the total carbon emissions from area m1 to area m2 without a clear supporting power line, where the initial value of all elements is 0;
[0115] Step S300: based on the regional calculation order and the local carbon emissions, incoming and outgoing carbon emissions of each region, obtain the carbon emission factor of the outgoing electricity of each region one by one, and calculate the net carbon emissions of each region according to the carbon emission factor.
[0116]
[0117] in, is the regional net carbon emission of region m1; The total carbon emissions transferred from the interconnection lines with clear supporting power sources received by area m1; The total carbon emissions transferred by the interconnection line without clear supporting power supply received by area m1. According to the ranking, when calculating the power received by area m1, the carbon transfer amount sent by the sending end area corresponding to area m1 has been calculated before; The total carbon emissions transferred by the interconnection line with clear supporting power supply sent to area m1; The total carbon emissions transferred by the interconnection line without clear supporting power supply sent to area m1;
[0118]
[0119] according to Calculate the carbon emissions transferred in area m1 without supporting power supply interconnection lines.
[0120]
[0121] By repeating the above process, the net carbon emissions of all regions are calculated.
[0122] Based on the net carbon emissions of each region, the regional net carbon emissions matrix is obtained
[0123]
[0124] Epure=[849.66,1230.39,564.64,97.67,844.93,76.69,1135.81]
[0125] Embodiment 3
[0126] Another embodiment of the present invention provides a multi-region carbon emission pre-assessment system, such as Figure 4 As shown, the system 40 includes:
[0127] The region sorting module 401 can obtain the region calculation order based on the improved bubbling method according to the relationship between the sending end and the receiving end of the interconnection line;
[0128] The data collection module 402 determines the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emission, incoming and outgoing carbon emission of the region;
[0129] The net emission calculation module 403 can calculate the carbon emission factor of the electricity sent out by each region one by one based on the regional calculation order and the local carbon emissions, incoming and outgoing carbon emissions of each region, and calculate the net carbon emissions of each region.
[0130] Furthermore, the region sorting module 401 includes:
[0131] The first relationship corresponding element can be sorted according to the regional sequence number and analyze the corresponding relationship between the sending end and the receiving end of the i-th tie line;
[0132] The bubble sorting component can determine whether the sequence number of the sending end area is sorted before the sequence number of the receiving end area. If not, the receiving end area is exchanged with the adjacent area on the left. It is determined whether the sequence number of the sending end area is sorted before the sequence number of the receiving end area. If not, it continues to exchange with the adjacent area on the left; the sending end area is exchanged before the receiving end area; if so, this connection line is skipped to the next step;
[0133] The second relationship corresponding element can analyze the corresponding relationship between the sending end and the receiving end of the i+1th tie line and sort them according to the above steps;
[0134] The matrix generation element can analyze the influence of several tie lines one by one and form a sorting matrix that satisfies the relationship between the sending and receiving ends of all tie lines.
[0135] Furthermore, in the data collection module 402, if the tie line has a matching power source, it is also necessary to determine the transfer power matrix of the tie line with the matching power source.
[0136] Furthermore, the net emission calculation module 403 includes:
[0137] The component analysis element can determine the carbon emissions received and the carbon emissions sent based on the regional input and output relationship;
[0138] The regional calculation component can calculate the net carbon emissions of the region by subtracting the outgoing carbon emissions and adding the incoming carbon emissions;
[0139] The loop element can repeat the above steps for each area to obtain the net carbon emissions of each area.
[0140] Furthermore, the received carbon emissions include the received carbon emissions with a clear supporting power source and the received carbon emissions without a clear supporting power source; the sent carbon emissions include the sent carbon emissions with a clear supporting power source and the sent carbon emissions without a clear supporting power source.
[0141] Another aspect of the present application provides a computer-readable storage medium storing computer-executable instructions for executing the above-mentioned Figure 1 The multi-regional carbon emissions pre-assessment method shown.
[0142] The embodiment of the present application automatically sorts out the relationship between the sending and receiving ends of each region, and calculates the net carbon emissions of the regional power grid after considering the carbon transfer of the interconnecting lines for each region one by one, which is conducive to the software implementation of the net carbon emissions calculation and improves the calculation efficiency and accuracy of the net carbon emissions of the multi-regional power system.
[0143] The device embodiments described above are only illustrative, and the units described as separate components may or may not be physically separated, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0144] It will be appreciated by those skilled in the art that all or some of the steps and systems in the disclosed method above may be implemented as software, firmware, hardware and appropriate combinations thereof. Some physical components or all physical components may be implemented as software executed by a processor, such as a central processing unit, a digital signal processor or a microprocessor, or may be implemented as hardware, or may be implemented as an integrated circuit, such as an application specific integrated circuit. Such software may be distributed on a computer-readable medium, which may include a computer storage medium (or a non-transitory medium) and a communication medium (or a temporary medium). As known to those skilled in the art, the term computer storage medium includes volatile and non-volatile, removable and non-removable media implemented in any method or technology for storing information (such as computer-readable instructions, data structures, program modules or other data). Computer storage media include, but are not limited to, RAM, ROM, EEPROM, flash memory or other memory technologies, CD-ROM, digital versatile disks (DVD) or other optical disk storage, magnetic cassettes, magnetic tapes, disk storage or other magnetic storage devices, or any other medium that may be used to store desired information and may be accessed by a computer. Furthermore, it is well known to those skilled in the art that communication media typically embodies computer readable instructions, data structures, program modules, or other data in a modulated data signal such as a carrier wave or other transport mechanism, and may include any information delivery media.
[0145] The above is a specific description of the preferred implementation of the present application, but the present application is not limited to the above-mentioned implementation mode. Technical personnel familiar with the field can also make various equivalent deformations or substitutions without violating the spirit of the present application. These equivalent deformations or substitutions are all included in the scope defined by the claims of the present application.
Claims
1. A multi-regional carbon emissions pre-assessment method, It is characterized in that The following steps are involved: According to the relationship between the sending end and the receiving end of the interconnection line, the regional calculation order is obtained; Determine the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emission, incoming and outgoing carbon emission of the region; Based on the calculation order of the regions and the local carbon emissions, incoming and outgoing carbon emissions of each region, the carbon emission factors of the electricity sent from each region are obtained one by one, and the net carbon emissions of each region are calculated based on the carbon emission factors.
2. The method according to claim 1, It is characterized in that The step of obtaining the region calculation order based on the improved bubbling method according to the relationship between the sending end and the receiving end of the interconnection line includes: Sort by area number and analyze the corresponding relationship between the sending end and the receiving end of the ith tie line; Determine whether the sequence number of the sending end region is before the sequence number of the receiving end region. If not, swap the receiving end region with the adjacent region on the left. Determine whether the sequence number of the sending end region is before the sequence number of the receiving end region. If not, continue to swap with the adjacent region on the left. Keep swapping the sending end region before the receiving end region. If yes, skip this contact line and proceed to the next step. Analyze the corresponding relationship between the sending end and the receiving end of the i+1th tie line, and sort them according to the above steps; The impact of several tie lines is analyzed one by one to form a sorting matrix that satisfies the sending and receiving end relationships of all tie lines.
3. The method according to claim 1, It is characterized in that In the step of determining the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emissions, incoming and outgoing carbon emissions of the region, if the interconnection line has a supporting power supply, it is also necessary to determine the transfer power matrix of the interconnection line with the supporting power supply.
4. The method according to claim 1, It is characterized in that The step of calculating the carbon emission factor of the electricity delivered by each region one by one based on the calculation order of the regions and the local carbon emissions, incoming and outgoing carbon emissions of each region, and calculating the net carbon emissions of each region includes: Based on the relationship between regional input and output, determine the carbon emissions received and the carbon emissions sent; The net carbon emissions of the region are calculated by subtracting the carbon emissions sent out and adding the carbon emissions received. Repeat the above steps for each region to obtain the net carbon emissions of each region.
5. The method according to claim 4, It is characterized in that The received carbon emissions include the carbon emissions received from a clear supporting power source and the carbon emissions received from a source without a clear supporting power source; the sent carbon emissions include the carbon emissions sent from a clear supporting power source and the carbon emissions sent from a source without a clear supporting power source.
6. A multi-regional carbon emission pre-assessment system, It is characterized in that include: The regional sorting module can obtain the regional calculation order based on the relationship between the sending and receiving ends of the interconnected lines; The data collection module determines the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region as the carbon emission, incoming and outgoing carbon emission of the region; The net emission calculation module can obtain the carbon emission factor of the electricity sent out by each region one by one based on the regional calculation order and the local carbon emissions, incoming and outgoing carbon emissions of each region, and calculate the net carbon emissions of each region based on the carbon emission factors.
7. The system according to claim 6, It is characterized in that The region sorting module comprises: The first relationship corresponding element can be sorted according to the regional sequence number and analyze the corresponding relationship between the sending end and the receiving end of the i-th tie line; The bubble sorting component can determine whether the sequence number of the sending end area is sorted before the sequence number of the receiving end area. If not, the receiving end area is exchanged with the adjacent area on the left. It is determined whether the sequence number of the sending end area is sorted before the sequence number of the receiving end area. If not, it continues to exchange with the adjacent area on the left; the sending end area is exchanged before the receiving end area; if so, this connection line is skipped to the next step; The second relationship corresponding element can analyze the corresponding relationship between the sending end and the receiving end of the i+1th tie line and sort them according to the above steps; The matrix generation element can analyze the influence of several tie lines one by one and form a sorting matrix that satisfies the relationship between the sending and receiving ends of all tie lines.
8. The system according to claim 6, It is characterized in that In the step of determining the initial power generation matrix, carbon emission matrix, and transfer power matrix of each region, if the interconnection line has a matching power source, it is also necessary to determine the transfer power matrix of the interconnection line with the matching power source.
9. The system according to claim 6, It is characterized in that The net emission calculation module comprises: The component analysis element can determine the carbon emissions received and the carbon emissions sent based on the regional input and output relationship; The regional calculation component can calculate the net carbon emissions of the region by subtracting the outgoing carbon emissions and adding the incoming carbon emissions; The loop element can repeat the above steps for each area to obtain the net carbon emissions of each area.
10. The system according to claim 6, It is characterized in that The received carbon emissions include the carbon emissions received from a clear supporting power source and the carbon emissions received from a source without a clear supporting power source; the sent carbon emissions include the carbon emissions sent from a clear supporting power source and the carbon emissions sent from a source without a clear supporting power source.
11. A computer-readable storage medium storing computer-executable instructions, wherein the computer-executable instructions are used to execute the method according to any one of claims 1 to 5.
Citation Information
Patent Citations
Method and device for determining electric power carbon emission factor, equipment and medium
CN115423386A
Apportioning and reducing data center environmental impacts, including a carbon footprint
US20100191998A1