Modular building construction scaffold and mounting method thereof
The modular building construction scaffold addresses inefficiencies in existing scaffolding by using folding unit frames and reinforcement members for rapid assembly and disassembly, enhancing stability and safety with integrated protection components.
Patent Information
- Application Number
- CN202411300944.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2024-12-13
AI Technical Summary
Existing scaffolding systems face challenges with low disassembly and assembly efficiency, poor support, large usage volume, and height restrictions, making them cumbersome and unsafe for construction applications.
A modular building construction scaffold comprising folding unit frames with axial swivel seats, connecting rods, and transverse connection assemblies, allowing for quick assembly and disassembly, enhanced support through reinforcement members, and integrated protection components.
The modular scaffold enables efficient construction with high assembly and disassembly rates, improved stability, and reduced storage volume, while ensuring safety through integrated protection features.
Smart Images

Figure CN119122240A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of scaffolds, in particular to a modular building construction scaffold and an installation method thereof, and in particular to a modular building construction scaffold and an installation method thereof which are convenient and quick to assemble and disassemble to improve construction efficiency and reduce construction costs. Background Art
[0002] In the modern construction process, in order to facilitate workers to carry out construction at high places of buildings, it is often necessary to set up scaffolding inside and outside the wall. In the past, scaffolding was mostly temporarily built with on-site pipe fittings. Although this method can effectively control costs, it is not convenient due to the primitive bundling and connection methods, and the use effect is not good, which can easily cause complete accidents such as collapse.
[0003] At present, scaffolding is mainly constructed with prefabricated standard rods. There are two main construction modes of scaffolding. One is to connect through connectors, that is, fasteners; the other is to connect through an integrated frame to the wall. Both of the above methods have the problems of low disassembly and assembly efficiency, poor support and large usage volume.
[0004] CN 108149911 B discloses a modular scaffold and a method for erecting the same. A plurality of connecting pipes are connected by connecting pieces through connecting pipes, and finally a scaffold with a limited internal space in a three-dimensional space is formed for operators to stand. In this form, during the erection of the scaffold, the entire scaffold is erected with the connecting pieces as the radiation. However, this method requires the connection and locking of the connecting pieces and the pipes during the erection of the scaffold. The locking method adopted is that each pipe is locked independently with the connecting piece, which is not separated from the previous fastener connection method. This connection method also requires the pipes to be disassembled for storage during use. Therefore, the steps of retracting and releasing are cumbersome, resulting in low efficiency of disassembly and assembly. CN 103321397 B discloses a folding scaffolding, which improves the convenience of the scaffolding by folding a frame forming a parallelogram and storing it. However, the folding structure adopted by the scaffolding relies on a straight ladder for installation and cannot be connected up and down. Therefore, it is subject to height restrictions when used and cannot be used in multi-story construction.
[0005] Therefore, it is of great practical significance to develop a modular building construction scaffold with good applicability and high disassembly and assembly efficiency. Summary of the invention
[0006] Due to the above-mentioned defects in the prior art, the present invention provides a modular construction scaffold with good applicability and high disassembly and assembly efficiency, so as to overcome the defects of the existing construction scaffold that it is difficult to balance high disassembly and assembly efficiency, low construction cost, small storage volume and good applicability.
[0007] In order to achieve the above object, the present invention provides the following technical solutions:
[0008] A modular building construction scaffold, comprising a plurality of mutually connected folding unit frames and scaffolding boards used in conjunction with the folding unit frames;
[0009] A single folding unit frame includes an axial swivel seat, two connecting rods, a transverse connection assembly and a node reinforcement fixing member. The axial swivel seat is a cubic structure. The two connecting rods are movably connected to the two vertical surfaces of the axial swivel seat respectively. The two surfaces of the axial swivel seat opposite to the connecting surface of the connecting rod are provided with fixed connection seats matching the connecting rods. The other surface of the axial swivel seat is fixedly connected to the transverse connection assembly and the transverse connection assembly is perpendicular to the contact surface.
[0010] A plurality of folding unit frames are connected to each other to form a frame structure. Two horizontally adjacent folding unit frames are connected by a transverse assembly or a connecting rod. Two vertically adjacent folding unit frames are connected by a connecting rod. The frame structure uses an axis rotation seat as a connection node. Two connecting rods connected to the same axis rotation seat and perpendicular to each other are connected by a node reinforcement fixing member.
[0011] The scaffolding planks are laid on the horizontal plane of the frame structure.
[0012] The modular construction scaffolding of the present invention has a reasonable structural design. The folding unit frame is used as a single body, and the columnar rods can be folded for easy transportation and disassembly. A plurality of folding unit frames can be connected to each other to form a frame structure, and then the modular scaffolding boards are laid on the plane of the frame structure to complete the installation of the scaffolding. The scaffolding can be quickly erected and disassembled, and the operation is easy and the structure is simple. The folding unit frame can be used as a single body for rapid storage and installation, which can significantly improve the construction efficiency and has great application prospects.
[0013] As the preferred technical solution:
[0014] A modular building construction scaffold as described above, further comprising a wall connection member and a protective assembly;
[0015] The frame structure is fixedly connected to the wall through a wall connecting piece;
[0016] The outer facade of the frame structure is hung with vertically arranged protective components.
[0017] A modular building construction scaffold as described above, wherein the wall connection member comprises a reinforcing rib seat, a counter-tension rod and a counter-tension screw, the reinforcing rib seat comprises a wall connection seat and a fixed steel bar fixed on the wall connection seat, the reinforcing rib seat is fixed to the wall body by the fixed steel bar, the counter-tension rod is connected to the wall connection seat by a rotating pair, the counter-tension rod is threadedly connected to the counter-tension screw at an end away from the wall connection seat, and the reinforcing rib seat is counter-tensioned by the counter-tension effect of the counter-tension rod;
[0018] The protection assembly includes an upper protection rod, a lower protection rod, a protection mesh and a protection plate. The upper protection rod and the lower protection rod are parallel to each other and are respectively fixed on the upper and lower sides of the protection mesh. A protection plate is fixed on the lower side of the lower protection rod and is parallel to the protection mesh. The protection mesh serves to increase the protection area.
[0019] A modular building construction scaffold as described above, wherein the upper protection bar and the lower protection bar are rigidly connected by a cross bar to improve the structural strength of the protection assembly;
[0020] Both ends of the upper protection rod and the lower protection rod are provided with fixing grooves, and the fixing grooves are fixedly connected to the side walls of the connecting rod by screws;
[0021] The protective plate is fitted with the edge of the scaffolding board to prevent the fallen workpiece from falling out from the two sides of the protective plate.
[0022] A modular building construction scaffold as described above, further comprising supporting channel steel;
[0023] The supporting channel steels are arranged below the frame structure, and the frame structure is supported on the installation surface by the supporting channel steels. The supporting channel steels are configured in pairs and arranged in parallel on the installation surface.
[0024] In the modular building construction scaffold as described above, the shaft swivel seat is movably connected to the connecting rod member via a movable adapter;
[0025] The movable adapter comprises a rotary joint, which is fixed on the shaft swivel seat, and a rotary rod is mounted on the rotary joint. A rotary groove is provided on the rotary rod away from the rotary joint. The rotary groove is movably connected to one end of the connecting rod through a pin. The rotary joint and the rotary rod are connected in a movable connection manner, so that the rotary rod can be axially rotated 360° in the rotary joint. A rotary groove is provided at the end of the rotary rod for movably connecting to the connecting rod. The connecting rod can be further rotated in the rotary groove, and the adjustment of the orientation is convenient for use.
[0026] The fixed connection seat includes a fixed joint, which is fixed on the other side of the shaft rotating seat opposite to the rotating joint. The fixed joint is connected to a fixed sleeve at the end away from the shaft rotating seat. A locking ring matching the end of the connecting rod is provided on the fixed sleeve to lock the end of the connecting rod, that is, to fix the fixed sleeve and the connecting rod.
[0027] The transverse connection assembly includes a pair of transverse link buckles, which are symmetrically arranged on both sides of one side of the shaft swivel seat, and the transverse link buckles are provided with slots, and the transverse link buckles are connected to the transverse connecting rods, and both ends of the transverse connecting rods are provided with plug-in cards matching the slots, and the slots are provided with locking holes, and the locking holes are equipped with locking bolts threadedly connected to the plug-in cards. The pair of transverse link buckles adopt a single-side opening structure, and when the relative folding unit frames are transversely connected, the transverse connecting rods connected with the transverse link buckles are staggered, that is, the two ends of the transverse connecting rods are respectively connected to the transverse link buckles of the symmetrical pair of folding unit frames; and then by inserting the plug-in card into the slot, the plug-in card and the slot are radially limited, and the plug-in card is reversely threadedly connected to the plug-in card by the reversely installed locking bolt, so as to realize reverse pull fixation.
[0028] A modular building construction scaffold as described above, further comprising a rotating fixture;
[0029] The rotating fixing member includes a rotating groove provided at both ends of the connecting rod, a rotating rod is movably connected in the rotating groove through a pin shaft, the rotating rod is an external threaded rod, a back-pull sleeve is threadedly connected to the rotating rod, a rotating knob is arranged on the outer circumference of the back-pull sleeve, and the back-pull sleeve is threadedly connected to the back-pull screw. The rotating rod is loaded through the rotating groove, and when the rotating rod is used, the back-pull sleeve is adjusted to have different extension lengths by rotating the rotating rod out of the rotating groove and adjusting the back-pull sleeve to be threadedly engaged with the rotating rod, and the back-pull sleeve is threadedly connected to the wall connecting member or the temporary reinforcement member by using the back-pull sleeve to form a stable connection with the temporary reinforcement member and the wall connecting member, and the back-pull sleeve is conveniently rotated by using the rotating knob.
[0030] A modular building construction scaffold as described above, wherein the transverse connecting rod is provided with a plurality of transverse connecting rod vertical through rods;
[0031] The scaffolding board includes a support plate, on which a plurality of through holes arranged in a matrix and matching with the vertical through rods of the horizontal connecting rods are provided, and the vertical through rods of the horizontal connecting rods are inserted into the through holes to realize the fixed connection between the horizontal connecting rods and the support plate;
[0032] One end of the support plate is provided with a plurality of parallel arranged transverse connecting blocks, and the other end is provided with a plurality of transverse connecting grooves matching the transverse connecting blocks. When the scaffolding boards are connected, the transverse connecting blocks on the support plate are connected with the transverse connecting grooves to realize the lateral limitation of the support plate, and the through-holes on the support plate are connected with the vertical through-rods of the transverse connecting rods to further limit the connection of the support plate.
[0033] In a modular building construction scaffold as described above, the node reinforcement fixing part includes a reinforcement rod, a reinforcement joint arranged on a connecting rod connected to the shaft swivel, and a reinforcement pin arranged on another connecting rod connected to the shaft swivel, and the two ends of the reinforcement rod are respectively movably connected to the reinforcement joint and the reinforcement pin, and the reinforcement joint and the reinforcement pin are threadedly connected with a limit nut. One end of the reinforcement rod is movably connected through the reinforcement pin, and the reinforcement rod adopts a threaded structure and is adjustable in length. By adjusting the reinforcement rod to a suitable length, the other end of the reinforcement rod is sleeved on the reinforcement joint, and the reinforcement joint and the reinforcement joint both limit the outer end of the reinforcement rod through the limit nut, so that a pair of adjacent connecting rods on the same shaft swivel and the reinforcement rod form a triangular reinforcement frame, thereby improving the support and limit capability.
[0034] In addition, the present invention also provides a method for installing a modular building construction scaffold as described above, comprising the following steps:
[0035] (1) Construct a support foundation and lay support channel steel on the support foundation. Specifically, construct a support foundation on one side of the building. The support foundation adopts a ground foundation of a precast concrete structure. Lay support channel steel on the precast concrete. The support channel steel is arranged in pairs and anti-corrosion treatment must be carried out before use;
[0036] (2) Measure and lay out the support and installation points of the scaffolding vertical bars and horizontal bars, which must be completed before laying the channel steel and erecting the scaffolding;
[0037] (3) Transport the folding unit frame to be used to the construction site, check whether there are problems such as pipe bending, and replace and repair the rods in time;
[0038] (4) Prefabricate a temporary support base at a distance of at least two vertical poles on the outside of the supporting channel steel, and install a temporary bracket on the temporary support base for standby use;
[0039] (5) Two folding unit frames are arranged in parallel on a double-row installation foundation of the scaffolding. After adjusting the spacing, the lateral connection components are used in conjunction with the connecting rods for lateral connection. The folding unit frames are arranged in groups of two, and the folding unit frames are connected end to end, and fixed by connecting the shaft swivel, the connecting rods and the lateral connection components;
[0040] (6) Connect the rotating fixings on the vertical connecting rods in the folding unit frame to the temporary brackets on the outside to support the folding unit frame, and then strengthen the nodes through the node strengthening fixings;
[0041] (7) Prefabricate a concrete base for connecting the wall on the building ground, set a wall connecting piece on the concrete base, and connect the wall connecting piece to the rotating fixing piece;
[0042] (8) Install the scaffolding boards, butt-jointly lay them on the horizontal connecting rods and horizontal connecting components, and use positioning bolts to pass through the through holes to pull the scaffolding boards in opposite directions to fix the scaffolding boards;
[0043] (9) Install the protection assembly. The protection assembly adopts an integrated structural design, with a pair of parallel protection rods carrying a hard protection net and X-shaped reinforcement ribs. The protection assembly is installed and fixed by connecting the protection rods with the connecting rods;
[0044] (10) Disassembly and maintenance: from high to low, first release the connection of the wall connecting parts, then release the connection between the reinforcing rod and the reinforcing joint, take a folding unit frame as the basic unit, release the lock of the fixed connecting seat on the connecting rod, remove the folding unit frame and fold it for storage. The above installation method is easy to operate, has high construction efficiency, low construction cost and good applicability.
[0045] The above technical solution is only a feasible technical solution of the present invention, and the protection scope of the present invention is not limited thereto. Those skilled in the art can reasonably adjust the specific design according to actual needs.
[0046] The above invention has the following advantages or beneficial effects:
[0047] (1) The modular building construction scaffold of the present invention uses a folding unit frame as a basic unit, which can achieve efficient folding, has a small storage volume and can meet the needs of fast and efficient assembly;
[0048] (2) The modular construction scaffold of the present invention is based on a folding unit frame as a basic unit. The folding unit frames are connected to each other to form the main frame of the scaffold. One end of the connecting rod is pre-installed on the folding unit frame, which is convenient for connecting and installing the connecting rod. On the other hand, it can be quickly disassembled, stored and folded, and the construction efficiency is higher.
[0049] (3) The modular construction scaffolding of the present invention is also provided with a pre-installed reinforcement member on the folding unit frame to improve the stability of the folding unit frame, making the connection more secure, and cooperating with the pre-installed rotating fixing member to connect with the external wall connecting member or temporary bracket, further improving the stability of the folding unit frame;
[0050] (4) The modular construction scaffolding of the present invention is used with modular scaffolding boards and protective components in conjunction with the folding unit frame, which is easy and quick to install, and while assisting in fixing the folding unit frame, it also improves the overall scaffolding construction efficiency;
[0051] (5) The modular building construction scaffolding installation method of the present invention is easy to operate, has high construction efficiency, low construction cost and good applicability, and has great application prospects. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] The present invention and its features, aspects and advantages will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings, in which like reference numerals indicate like parts throughout the drawings, with emphasis placed on illustrating the gist of the present invention.
[0053] Figure 1 and Figure 2 They are schematic diagrams of the three-dimensional structure of the modular building construction scaffold of the present invention at different viewing angles;
[0054] Figure 3 for Figure 2 Schematic diagram of the three-dimensional structure after removing the protective components;
[0055] Figure 4 and Figure 5 They are three-dimensional structural schematic diagrams of modular building construction scaffolding connection nodes from different perspectives;
[0056] Figure 6 It is a structural schematic diagram when the shaft swivel seat is connected to the connecting rod;
[0057] Figure 7 It is a three-dimensional structural schematic diagram of the shaft swivel;
[0058] Figure 8 is a structural schematic diagram of the connecting rod;
[0059] Fig. 9 It is a structural diagram of the scaffolding board;
[0060] Fig.10 and 11 They are schematic diagrams of the structure of the protection component from different perspectives;
[0061] Among them, 1-support channel steel, 2-folding unit frame, 3-scaffolding board, 4-wall connection, 5-protection component, 6-temporary reinforcement, 21-connecting rod, 22-axis swivel seat, 23-cross-connection component, 24-rotation fixing part, 31-support plate, 32-through hole, 33-positioning bolt, 34-cross-connection plug block, 35-cross-connection groove, 41-reinforcement rib seat, 42-anti-pull rod, 43-anti-pull screw, 51-upper protection rod, 52-lower protection rod, 53-protection mesh plate, 54-protection plate, 212-reinforcement rod, 213-reinforcement joint , 214-reinforcement pin, 215-limiting nut, 221-movable adapter, 222-fixed connecting seat, 231-horizontal link buckle, 232-insertion card, 233-locking bolt, 234-slot, 235-horizontal connecting rod, 241-rotation groove, 242-rotation rod, 243-reverse pull sleeve, 244-rotation knob, 2211-rotation joint, 2212-rotation rod, 2213-rotation groove, 2221-fixed joint, 2222-fixed sleeve, 2223-locking ring, 2351-horizontal connecting rod vertical through rod. DETAILED DESCRIPTION
[0062] The structure of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but is not intended to limit the present invention.
[0063] Example 1
[0064] A modular building construction scaffolding, such as Figures 1 to 11 As shown, it comprises a supporting channel steel 1, a plurality of mutually connected folding unit frames 2, a scaffolding board 3 used in conjunction with the folding unit frames 2, a plurality of wall connecting members 4 and a protective assembly 5. Specifically, the folding unit frames 2 are mutually connected to form the main body of the construction scaffolding, and the scaffolding board 3 is laid on the folding unit frames 2 to form a walking channel of the scaffolding. The wall connecting members 4 can provide a pulling and anchoring position during the construction of the folding unit frames 2.
[0065] The support channel steel 1 is used as the ground support. Before the scaffold is erected, the support channel steel 1 is used to support the ground, and a certain support foundation is set. The number of support channel steels 1 is configured in pairs and arranged in parallel on the ground. A construction scaffold is set on the support channel steel 1. A number of steel bar connectors for fixing the construction scaffold are correspondingly arranged on the support channel steel 1 and inserted into the bottom of the construction scaffold to achieve fixed connection and support for the construction scaffold.
[0066] The above-mentioned single folding unit frame 2 is composed of a connecting rod 21 and a fixed connecting member, wherein the number of the connecting rods 21 is two and the wall thickness and diameter are the same. The two connecting rods 21 are the most basic configuration. The two connecting rods 21 are respectively installed on the two axial directions of the fixed connecting member, and are connected with adjacent folding unit frames 2 to form the skeleton of the construction scaffolding together;
[0067] The fixed connection member is composed of a cross-structured shaft seat 22 and a transverse connection component 23 perpendicular to the cross-axis surface of the shaft seat 22. The shaft seat 22 is a cross structure and is used to install its own connecting rod 21 and connect the connecting rods 21 of other folding unit frames 2. The transverse connection component arranged in a direction perpendicular to the shaft seat 22 is used to connect the remaining connecting rod 21, serving as the installation basis of the scaffolding board 3.
[0068] A pair of movable adapters 221 are provided at the adjacent two ends of the shaft rotating seat 22. The pair of movable adapters 221 are connected to one end of a pair of connecting rods 21. The movable connecting members are movably connected to the shaft rotating seat 22. The movable connecting members are further movably connected to the connecting rods 21, so that the connecting rods 21 can rotate in any direction, which is convenient for installation on the one hand and convenient for effective folding and storage of the folding unit frame 2 on the other hand.
[0069] In order to fix the ends of the connecting rods 21, a pair of fixed connecting seats 222 are provided at the other two ends of the shaft rotating seat 22 corresponding to the pair of movable adapters 221, and the pair of fixed connecting seats 222 are adapted to the other ends of the pair of connecting rods 21. By connecting the connecting rods 21, a fixed connecting seat 222 is further provided at one end of the shaft rotating seat 22 corresponding to the movable adapter 221. The fixed connecting seat 222 adopts a buckle structure, and the opening of the buckle faces upward when in use. When connecting and fixing the connecting rods 21, after adjusting the posture of the connecting rods 21 through the movable adapter 221, the head end of the connecting rod 21 of another folding unit frame 2 is installed into the fixed connecting seat 222 of the shaft rotating seat 22 for fixed locking, thereby realizing the basic fixation of the folding unit, so that the unit frames matched in pairs can form a complete rectangular frame as a unit cell of the scaffolding;
[0070] A transverse connecting assembly 23 is integrally arranged on the vertical plane of the cross axis of the shaft rotating seat 22. The transverse connecting assembly 23 serves as a supporting base for the scaffolding board 3 and a limiting device for determining the spacing of the double-row frames. The transverse connecting assembly 23 includes a pair of transverse connecting ring buckles 231, which are symmetrically arranged on both sides of one side of the shaft rotating seat 22. A slot 234 is arranged on the transverse connecting ring buckle 231, and the transverse connecting ring buckle 231 is connected to a transverse connecting rod 235. Both ends of the transverse connecting rod 235 are provided with a plug-in card 232 matching the slot 234. A locking hole is opened on the slot 234, and a locking bolt 233 threadedly connected to the plug-in card 232 is assembled in the locking hole.
[0071] The pair of transverse link buckles 231 are both single-side open structures. When the opposite folding unit frames 2 are transversely connected, the transverse connecting rods 235 connected to the transverse link buckles 231 are arranged in a staggered manner, that is, the two ends of the transverse connecting rods 235 are respectively connected to the transverse link buckles of the symmetrical pair of folding unit frames 2; and then the plug-in card 232 is inserted into the slot 234, so that the plug-in card 232 and the slot 234 are radially limited, and the locking bolt 233 installed in the opposite direction is reversely threadedly connected to the plug-in card 232, so that the plug-in card 232 is reversely pulled and fixed;
[0072] A connecting rod 21 connected to the movable adapter 221 is provided with at least one pair of rotating fixing members 24, and the rotating fixing members 24 are used to connect the wall connecting member 4. The rotating fixing members 24 can be connected to the wall connecting member 4. The wall connecting member 4 is installed based on the building body. The connection between the rotating fixing members 24 and the wall connecting member 4 plays a role in installing and fixing the folding unit frame 2.
[0073] The movable adapter 221 includes a rotary joint 2211; a rotary joint 2211 is provided on the cross shaft end of the shaft swivel seat 22, a rotary rod 2212 is sleeved on the rotary joint 2211, a rotary groove 2213 is provided at the end of the rotary rod 2212, and the rotary groove 2213 is movably connected to the head end of the connecting rod 21 through a pin shaft;
[0074] The rotating joint 2211 and the rotating rod 2212 are connected in an active connection manner, so that the rotating rod 2212 can be axially rotated 360° in the rotating joint 2211. A rotating groove 2213 is provided at the end of the rotating rod 2212 for active connection to the connecting rod 21. The connecting rod 21 can further rotate in the rotating groove 2213, and the orientation can be adjusted for easy use.
[0075] The fixed connection seat 222 includes a fixed joint 2221; the fixed joint 2221 is assembled on one side of the corresponding rotary joint 2211, and the end of the rotary joint 2211 is connected to a fixed sleeve 2222, and a locking ring 2223 corresponding to the head end of the connecting rod 21 is provided on the fixed sleeve 2222 for fixing the head end of the connecting rod 21;
[0076] The fixed sleeve 2222 on the fixed joint 2221 is used as a space for accommodating the connecting rod 21. One side of the fixed sleeve 2222 is open. A locking ring 2223 is provided on the fixed sleeve 2222. The locking ring 2223 is buckled on the end of the connecting rod 21 in the form of a ring buckle, and is used to limit the connection rod 21 and fix the head end.
[0077] The scaffolding board 3 comprises a support plate 31, on which a plurality of through holes 32 arranged in a matrix are provided, and the vertical through rods 2351 of the horizontal connecting rods are inserted into the through holes 32;
[0078] The support plate 31 adopts a cold-rolled steel plate structure. The through-holes 32 on the support plate 31 correspond to the vertical through-rods 2351 of the transverse connecting rods, so that the through-holes 32 limit the axial position of the vertical through-rods 2351 of the transverse connecting rods. A plurality of transverse connecting blocks 34 arranged in parallel are provided at one end of the support plate 31, and a plurality of transverse connecting grooves 35 are correspondingly provided at the other end of the support plate 31. When the scaffolding boards 3 are docked, the transverse connecting blocks 34 on the support plate 31 are plugged into the transverse connecting grooves 35 to realize the lateral limitation of the support plate 31. The through-holes 32 on the support plate 31 are docked with the vertical through-rods 2351 of the transverse connecting rods to further limit the connection of the support plate 31.
[0079] A reinforcing rod 212 is provided on one of the connecting rods 21 installed on the pair of movable adapters 221, and a reinforcing joint 213 is provided on the other connecting rod 21 installed on the pair of movable adapters 221. The reinforcing joint 213 and the reinforcing rod 212 form a triangle structure to limit and support the connecting rod 21.
[0080] A pair of reinforcing pins 214 extend from one side of the middle outer periphery of one of the connecting rods 21 on the same shaft swivel 22. The number of reinforcing rods 212 is two pairs, and two pairs are movably mounted on the pair of reinforcing pins 214. A reinforcing joint 213 extends from one side of another connecting rod 21 on the same shaft swivel 22. A connecting groove is provided at the end of the reinforcing rod 212, and the connecting groove is sleeved on the reinforcing joint 213. The end of the reinforcing rod 212 is movably connected to the reinforcing pin 214. The ends of the reinforcing pin 214 and the reinforcing joint 213 are sleeved with limiting nuts 215.
[0081] One end of the reinforcing rod 212 is movably connected through a reinforcing pin 214. The reinforcing rod 212 adopts a threaded structure and has an adjustable length. By adjusting the reinforcing rod 212 to a suitable length, the other end of the reinforcing rod 212 is sleeved on the reinforcing joint 213. The reinforcing joint 213 and the reinforcing joint 213 both limit the outer end of the reinforcing rod 212 through a limiting nut 215, so that a pair of adjacent connecting rods 21 on the same shaft swivel 22 and the reinforcing rod 212 form a triangular reinforcing frame, thereby improving the support and limiting capabilities.
[0082] The rotating fixing member 24 can be used to connect the wall connecting member 4 and the temporary reinforcement member 6. The rotating fixing member 24 includes a rotating groove 241, which is provided on the outer circumference of the connecting rod 21. A rotating rod 242 is movably connected to the rotating groove 241 through a pin. The rotating rod 242 is an externally threaded rod. A reverse pull sleeve 243 is threadedly connected to the rotating rod 242. The reverse pull sleeve 243 is connected to the wall connecting member 4. A rotating knob 244 is provided on the outer circumference of the reverse pull sleeve 243.
[0083] The rotating rod 242 is loaded through the rotating groove 241. When the rotating rod 242 is used, the rotating rod 242 is rotated out of the rotating groove 241, and the reverse pull sleeve 243 is adjusted to be threadedly engaged with the rotating rod 242, so that the extended length of the reverse pull sleeve 243 is different. The reverse pull sleeve 243 is threadedly connected to the wall connecting member 4 or the temporary reinforcement member 6, so that the reverse pull sleeve 243 forms a stable connection with the temporary reinforcement member 6 and the wall connecting member 4, and the reverse pull sleeve 243 is conveniently rotated by using the rotating knob 244;
[0084] The wall connecting member 4 is composed of a reinforcing rib seat 41 based on the building setting, a wall connecting seat installed on the reinforcing rib seat 41, and a back-pull rod 42 movably connected to the wall connecting seat. The head end of the back-pull rod 42 is provided with a back-pull screw 43, and the back-pull screw 43 is threadedly connected to the back-pull sleeve 243;
[0085] The reinforcing rib seat 41 is connected to the building by a steel bar structure, and the anti-pull rod 42 is movably installed and limited by the wall connecting seat on the reinforcing rib seat 41, and the anti-pull screw rod 43 is threadedly connected with the anti-pull sleeve 243, and the reinforcing rib seat 41 is reversely pulled by the reverse pull action of the reverse pull rod 42, so as to fix the connecting rod 21;
[0086] The above-mentioned protection assembly 5 is composed of an upper protection rod 51 and a lower protection rod 52 arranged in parallel, and the upper protection rod 51 and the lower protection rod 52 are connected by a protection mesh plate 53, and a protection plate 54 extends from the bottom of the lower protection rod 52 to fit the edge of the scaffolding board 3;
[0087] The upper protective rod 51 and the lower protective rod 52 are arranged in parallel and rigidly connected to each other by a cross rod. While achieving a reinforcement effect, both ends of the upper protective rod 51 and the lower protective rod 52 are provided with fixing grooves and connected to the side walls of the connecting rod 21 by screws. The upper protective rod 51 and the lower protective rod 52 are connected by a protective mesh plate 53 to increase the protection area. Under the effect of the adhesion between the protective plate 54 and the edge of the scaffolding board 3, it prevents the fallen workpiece from falling out from the two sides of the protective plate 54.
[0088] Example 2
[0089] A method for installing modular building construction scaffolding, comprising the following steps: support construction, measurement and setting out, folding unit frame standby, temporary support installation, scaffolding connection, scaffolding reinforcement, wall connection member reinforcement, scaffolding board laying and protection installation;
[0090] Support construction: construct a support foundation on one side of the building. The support foundation adopts a ground foundation of precast concrete structure. Support channel steel is laid on the precast concrete. The support channel steel is arranged in pairs and anti-corrosion treatment must be carried out before use;
[0091] Measurement and layout: Before laying the channel steel and erecting the scaffolding, use the layout equipment to find the support and installation points of the vertical and horizontal bars of the scaffolding;
[0092] Folding unit frame standby: transport the folding unit frame to be used to the construction site, check whether there are problems such as pipe bending, and replace and repair the rods in time;
[0093] Temporary support installation: prefabricate a temporary support base at least two poles apart on the outside of the supporting channel steel, and install temporary supports on the temporary support base for standby use:
[0094] Scaffolding connection: two folding unit frames are set up in parallel to form a double-row installation foundation of the scaffolding. After adjusting the spacing, the cross-connection components are used to cooperate with the connecting rods for horizontal connection. The folding unit frames are set up in pairs to connect the head and tail. The connection is achieved by fixing the two ends of the connecting rods through the movable adapter and the fixed connection seat;
[0095] Scaffold reinforcement: Connect the rotating fixings on the vertical connecting rods in the folding unit frame with the temporary brackets on the outside to support the folding unit frame, and then fix and connect the adjacent longitudinal and horizontal connecting rods through the reinforcement rods and reinforcement joints;
[0096] Wall tie reinforcement: prefabricate a concrete base for wall ties on the building ground, set wall ties on the concrete base, and connect the wall ties with the rotating fixings on the inner side of the folding unit;
[0097] Laying of scaffolding boards: Lay the scaffolding boards end to end on the horizontal connecting rods of the folding unit, and connect the scaffolding boards by pulling them in opposite directions through the through holes with positioning bolts to fix the scaffolding boards;
[0098] Protection installation: The protection component adopts an integrated structural design, with a pair of parallel protection rods carrying a hard protection net and X-shaped reinforcement ribs. The protection component is installed and fixed by connecting the protection rods with the connecting rods;
[0099] Disassembly and maintenance: From high to low, first release the connection of the wall connection parts, then release the connection between the reinforcement rod and the reinforcement joint, use a folding unit frame as the basic unit, release the lock of the fixed connection seat on the connecting rod, remove the folding unit frame and fold it for storage.
[0100] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.
[0101] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.
Claims
1. A modular building construction scaffolding, Features: It includes a plurality of mutually connected folding unit frames and a scaffolding board used in conjunction with the folding unit frames; A single folding unit frame includes an axial swivel seat, two connecting rods, a transverse connection assembly and a node reinforcement fixing member. The axial swivel seat is a cubic structure. The two connecting rods are movably connected to the two vertical surfaces of the axial swivel seat respectively. The two surfaces of the axial swivel seat opposite to the connecting surface of the connecting rod are provided with fixed connection seats matching the connecting rods. The other surface of the axial swivel seat is fixedly connected to the transverse connection assembly and the transverse connection assembly is perpendicular to the contact surface. A plurality of folding unit frames are connected to each other to form a frame structure. Two horizontally adjacent folding unit frames are connected by a transverse assembly or a connecting rod. Two vertically adjacent folding unit frames are connected by a connecting rod. The frame structure uses an axis rotation seat as a connection node. Two connecting rods connected to the same axis rotation seat and perpendicular to each other are connected by a node reinforcement fixing member. The scaffolding planks are laid on the horizontal plane of the frame structure.
2. A modular building construction scaffold according to claim 1, It is characterized in that It also includes wall connecting parts and protective components; The frame structure is fixedly connected to the wall through a wall connecting piece; The outer facade of the frame structure is hung with vertically arranged protective components.
3. A modular building construction scaffold according to claim 2, It is characterized in that The wall connection member includes a reinforcing rib seat, a back-pull rod and a back-pull screw. The reinforcing rib seat includes a wall connection seat and a fixed steel bar fixed on the wall connection seat. The reinforcing rib seat is fixed to the wall body by the fixed steel bar. The back-pull rod is connected to the wall connection seat through a rotating pair. The back-pull rod is threadedly connected to the back-pull screw at an end away from the wall connection seat. The protection assembly includes an upper protection rod, a lower protection rod, a protection mesh and a protection plate. The upper protection rod and the lower protection rod are parallel to each other and are respectively fixed on the upper and lower sides of the protection mesh. A protection plate is fixed on the lower side of the lower protection rod and is parallel to the protection mesh.
4. A modular building construction scaffold according to claim 3, It is characterized in that The upper protection bar and the lower protection bar are rigidly connected via a cross bar; Both ends of the upper protection rod and the lower protection rod are provided with fixing grooves, and the fixing grooves are fixedly connected to the side walls of the connecting rod by screws; The protective plate is fitted with the edge of the scaffolding board.
5. A modular building construction scaffold according to claim 1, It is characterized in that It also includes supporting channels; The supporting channel steel is arranged below the frame structure, and the frame structure is supported on the installation surface by the supporting channel steel.
6. A modular building construction scaffold according to claim 1, It is characterized in that The shaft swivel seat is movably connected to the connecting rod through a movable adapter; The movable adapter comprises a rotary joint, which is fixed on the shaft swivel seat, and a rotary rod is sleeved on the rotary joint. A rotary groove is formed on the rotary rod away from the rotary joint, and the rotary groove is movably connected to one end of the connecting rod through a pin shaft; The fixed connection seat includes a fixed joint, which is fixed to the other side of the shaft rotating seat opposite to the rotating joint, and the fixed joint is connected to a fixed sleeve at the end away from the shaft rotating seat, and a locking ring matching the end of the connecting rod is provided on the fixed sleeve; The transverse connection assembly includes a pair of transverse connecting rings, which are symmetrically arranged on both sides of one side of the shaft swivel seat. The transverse connecting rings are provided with slots, and the transverse connecting rings are connected to the transverse connecting rods. Both ends of the transverse connecting rods are provided with plug-in cards matching the slots. The slots are provided with locking holes, and the locking holes are equipped with locking bolts threadedly connected to the plug-in cards.
7. A modular building construction scaffold according to claim 3, It is characterized in that Also included is a rotating fixture; The rotating fixing part includes a rotating groove opened at both ends of the connecting rod, a rotating rod is movably connected in the rotating groove through a pin shaft, the rotating rod is an externally threaded rod, a back-pull sleeve is threadedly connected to the rotating rod, a rotating knob is arranged on the outer peripheral ring of the back-pull sleeve, and the back-pull sleeve is threadedly connected to the back-pull screw.
8. A modular building construction scaffold according to claim 1, It is characterized in that The transverse connecting rod is provided with a plurality of transverse connecting rod vertical through rods; The scaffolding board includes a support plate, on which a plurality of through holes arranged in a matrix and matching with the vertical through rods of the horizontal connecting rods are provided, and the vertical through rods of the horizontal connecting rods are inserted into the through holes to realize the fixed connection between the horizontal connecting rods and the support plate; One end of the support plate is provided with a plurality of parallel arranged transverse connecting blocks, and the other end is correspondingly provided with a plurality of transverse connecting grooves matching with the transverse connecting blocks.
9. A modular building construction scaffold according to claim 1, It is characterized in that The node reinforcement fixing member includes a reinforcement rod, a reinforcement joint arranged on a connecting rod connected to the shaft swivel, and a reinforcement pin arranged on another connecting rod connected to the shaft swivel, the two ends of the reinforcement rod are respectively movably connected to the reinforcement joint and the reinforcement pin, and the reinforcement joint and the reinforcement pin are threadedly connected with a limiting nut.
10. A method for installing a modular building construction scaffold according to any one of claims 1 to 9, It is characterized in that The steps include: (1) Construct the support foundation and lay the support channel steel on the support foundation; (2) Measure and lay out the support and installation points of the scaffolding vertical and horizontal bars; (3) transporting the folding unit frame to be used to the construction site; (4) Prefabricate a temporary support base at a distance of at least two vertical poles on the outside of the supporting channel steel, and install a temporary bracket on the temporary support base for standby use; (5) Two folding unit frames are arranged in parallel on a double-row installation foundation of the scaffolding. After adjusting the spacing, the lateral connection components are used in conjunction with the connecting rods for lateral connection. The folding unit frames are arranged in groups of two, and the folding unit frames are connected end to end, and fixed by connecting the shaft swivel, the connecting rods and the lateral connection components; (6) Connect the rotating fixings on the vertical connecting rods in the folding unit frame to the temporary brackets on the outside to support the folding unit frame, and then strengthen the nodes through the node strengthening fixings; (7) Prefabricate a concrete base for connecting the wall on the building ground, set a wall connecting piece on the concrete base, and connect the wall connecting piece to the rotating fixing piece; (8) Install scaffolding; (9) Install protective components; (10) Disassembly and maintenance.
Citation Information
Patent Citations
Erecting method of ring lock type scaffold
CN117306831A
Scaffold convenient to build for indoor construction
CN210316424U
Node structure for scaffold and scaffold
CN211341721U
Scaffold transverse support positioning device
CN212897478U
Safety supporting system of ring lock type scaffold
CN215212203U
Cited By
Folding type formwork support
CN120175126A