Movable crossing frame with buffering energy absorption, lifting claw and track monitoring functions
By adding liftable sheep horns, buffered energy-absorbing devices and trajectory monitoring systems to the mobile umbrella span frame, the problem of inaccurate detection of safety distances of span frames in the prior art is solved, and safer power line construction is achieved.
Patent Information
- Application Number
- CN202411318287.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-20
- Publication Date
- 2024-12-13
- Estimated Expiration
- 2044-09-20
AI Technical Summary
The existing mobile umbrella span frame lacks precise detection methods during the arrangement and evacuation process, resulting in inaccurate detection of the safety distance between the span frame and the line being spanned, which may lead to the close or contact of the car crane boom and the live line, causing economic losses. and construction workers were injured and killed.
Added lifting horn device, main bearing roller buffer energy absorption device and mobile track safety monitoring system, including RTK high-precision measurement system and lidar ranging system to monitor and adjust the trajectory across the frame in real time to prevent misoperation.
The impact resistance of the span frame is improved by lifting the sheep horns and buffering energy-absorbing device, and the arrangement and evacuation trajectory are accurately controlled, so as to avoid proximity or contact with the power line and ensure construction safety.
Smart Images

Figure CN119134122A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a mobile crossing frame with buffering energy absorption, lifting cleats and track monitoring, and belongs to the technical field of mechanized equipment for power line crossing construction. Background Art
[0002] In the construction of power lines, it is inevitable to carry out three-span operations, that is, crossing roads, railways and power lines. In order to protect these facilities and ensure construction safety, a crossing frame must be erected to protect them. In the three-span operation, especially crossing the live line, the contradiction is the most prominent. Using ordinary crossing frame erection or layout technology, in order to ensure the construction safety of the crossing frame erection, network closure layout, network closure evacuation, and crossing frame dismantling, the crossed power line must be shut down. However, ensuring that the power supply line is not shut down is the social responsibility and service goal pursued by the power industry. The State Grid Corporation of China clearly stipulates in the "State Grid Corporation Power Supply Service Specifications" that the number of power outages for customers with a voltage level of 35 kV and above should not exceed 1 per year; for customers with a voltage level of 10 kV, it should not exceed 3 times per year; with the acceleration of my country's power grid construction and transformation and the world's most developed power supply network, the situation of crossing power lines during line construction is ubiquitous. Therefore, when the construction of power lines crosses over energized lines, ensuring power supply and ensuring safety are two irreconcilable contradictions, which makes it extremely difficult for the line construction department to approve power outage applications. In desperation, illegal crossing construction without power outages will occur.
[0003] In order to resolve this difficult-to-reconcile contradiction, a mobile automatic fast-deployable crossing frame is disclosed in the prior art, with the announcement number CN205452971U. The crossing frame realizes the protection of the object by supporting the umbrella-shaped crossing frame above the object to be crossed through a car crane. The mobile crossing frame is widely used for its safety, convenience, economy and solution to the problems of manual high-altitude and near-electrical operations. Later, its function was innovated and a mobile umbrella-shaped crossing frame with rotation and pitching functions was introduced, with the announcement number CN 216598743 U. It was improved from a simple mobile quick-deployment crossing frame using the umbrella principle to a mobile umbrella-shaped crossing frame with rotation and pitching functions. In order to meet the needs of construction use, the prior art has introduced a mobile umbrella-shaped crossing frame with three functions, namely, a near-electricity alarm system, a front and rear sealing device, and a state change alarm system after deployment, such as the patent application with the publication number CN 117335320 A. The mobile umbrella-shaped crossing frame can safely carry out completely non-power-off crossing construction when the construction site has a large space, the live lines and the surrounding environment are good, and the electromagnetic environment is good, and can adapt to most construction conditions. However, this type of mobile umbrella-shaped spanning frame also exposes its imperfections in the application of spanning construction without power outages. The reason is that the above technology does not have a safety monitoring system specifically for the layout and movement trajectory of the mobile umbrella-shaped spanning frame during evacuation. When used on site, it will be difficult to use due to design errors in the special spanning construction plan, on-site layout errors, inaccuracy of near-electric sensors in complex electromagnetic environments, inability to install near-electric sensors on the boom of the truck crane for near-electric monitoring, multiple parallel power supply lines leading to tight space for spanning frame layout, irregular operation of truck cranes and spanning frames, etc. In addition, in order to reduce the construction cost of the line tower, the power line design department The tower height is kept as low as possible while ensuring that the safety distance at the intersection of power lines is sufficient, so that in many cases the height difference between the newly installed line and the crossed line at the intersection does not exceed the safety distance by much. The height dimension from the top of the existing horn to the bottom of the sealing plane is close to 4 meters, which often results in the mobile umbrella-shaped crossing frame not being able to be safely removed from the upper and lower power lines, causing the boom of the truck crane and the crossing frame to be too close to or contact the live line, which may cause the crossed live line to trip at the least, causing significant economic losses to power users, and serious safety accidents such as personal injury to the truck crane operator and construction workers on nearby construction lines.
[0004] Therefore, in order to further ensure construction safety and facilitate safe and convenient use on site, it is necessary to add devices such as a liftable horn device, a main load-bearing roller buffer energy absorption device, and a safety monitoring system for the moving trajectory during arrangement and evacuation to the existing mobile umbrella-shaped crossing frame to ensure the safety of the mobile crossing frame during arrangement and evacuation without power outages on the crossed power lines, so that the advantages of the mobile umbrella-shaped crossing frame cannot be fully utilized. Summary of the invention
[0005] The purpose of the present invention is to provide a mobile crossing frame with buffering and energy absorption, lifting horns and trajectory monitoring in view of the deficiencies in the above-mentioned prior art; the mobile umbrella-shaped crossing frame is added with a liftable horn device, a buffering and energy absorption device of the main bearing roller, a safety monitoring system for the moving trajectory during arrangement and evacuation, and devices for detecting the switch umbrella state of the umbrella-shaped crossing frame body, rotation angle detection and pitch angle detection on the basis of the existing functions, so as to solve the problem that the horn device of the existing mobile umbrella-shaped crossing frame is a fixed structure, the main bearing roller is a rigid structure, and the mobile crossing frame has no accurate detection means during the on-site arrangement and evacuation process, resulting in inaccurate detection of the safety distance value between the crossing frame and the crossed line, causing the boom of the automobile crane and the crossing frame to be too close to or contact the live line, causing significant economic losses and casualties of construction personnel.
[0006] The present invention achieves the above-mentioned purpose through the following technical solutions: A mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring, which consists of a mobile umbrella-shaped crossing frame, an integrated control system for the crossing frame body, a remote operation and remote control system for the crossing frame, a liftable horn device, a buffering energy absorption device for the main bearing roller, a safety monitoring system for the moving trajectory during arrangement and evacuation, etc.; it is characterized in that the integrated control system for the umbrella-shaped crossing frame body is installed in the crossing frame base control box of the mobile umbrella-shaped crossing frame; the remote operation and remote control system for the crossing frame is operated by an operating personnel at a place with good communication; the liftable horn device is divided into two groups, which are symmetrically distributed and installed on the main bearing trusses on both sides of the umbrella-shaped crossing frame body of the mobile umbrella-shaped crossing frame; the buffering energy absorption device for the main bearing roller is divided into four groups, two of which are installed on the umbrella-shaped upper base of the mobile umbrella-shaped crossing frame, and the other two groups are respectively installed on the main bearing trusses of the mobile umbrella-shaped crossing frame; the safety monitoring system for the moving trajectory during arrangement and evacuation includes an RTK high-precision control system. The RTK high-precision measurement system comprises a satellite positioning system, an RTK reference station, an RTK mobile station for the umbrella-shaped spanning frame body, an RTK mobile station for the rotation center of the crane boom, an RTK mobile station for the crossing point of the spanned wire and an RTK mobile station for the direction of the spanned wire. The RTK reference station is installed in a safe position at the work site and fixed. The RTK mobile station for the umbrella-shaped spanning frame body is installed on the umbrella-shaped lower base of the spanning frame. The RTK mobile station for the crane boom is installed at the rotation center position of the turntable of the crane. The RTK mobile station for the crossing point of the spanned wire and the RTK mobile station for the direction of the spanned wire are installed directly below the spanned wire. The laser radar ranging system comprises a front laser radar ranging device and a rear laser radar ranging device. The front laser radar ranging device is installed on the umbrella-shaped lower base of the umbrella-shaped spanning frame body, and the rear laser radar ranging device is installed on the umbrella-shaped upper base of the umbrella-shaped spanning frame body.
[0007] The control system of the crossing frame body is composed of a body control system circuit board, a data integration processing unit, a body wired communication module, a body wireless communication module, a wireless cellular communication module and a SIM card. The data integration processing unit, the body wired communication module, the body wireless communication module, the wireless cellular communication module and the SIM card are installed on the body control system circuit board; the control system of the crossing frame body collects various parameter values required by the switch umbrella status detection sensor, the rotation angle detection sensor, the pitch angle detection sensor, the safety monitoring system of the moving trajectory during the layout and evacuation process, and the special plan for crossing operations.
[0008] The remote operation remote control system of the crossing frame is composed of a remote control circuit board, a remote data processing module, a remote control operation button, a display screen, a USB data interface, a buzzer alarm and a remote control wireless communication module; the remote data processing module, the remote control operation button, the display screen, the USB data interface, the buzzer alarm and the remote control wireless communication module are installed on the remote control circuit board; the operation data of the mobile umbrella crossing frame required by the special crossing construction plan and the minimum allowable distance value between the mobile umbrella crossing frame and the crossed line or the newly built wire are input through the USB data interface, and are processed by the remote data processing module and transmitted to the crossing frame body control system via the remote control wireless communication module.
[0009] The liftable horn device consists of a lifting drive module, a pin, a horn rod and a horn support rod. The lifting drive module is installed on the main load-bearing truss by installing bolts. The screw nut in the lifting drive module is hinged to one end of the horn support rod, and the other end of the horn support rod is hinged to one end of the horn rod through the pin. The other end of the horn rod is hinged to the middle part of the main load-bearing truss through the pin. The screw nut, the horn rod and the horn support rod are hinged at the head and tail to form a triangular structure that can be lifted and lowered.
[0010] The lifting drive module is composed of a module drive motor, a planetary reducer, a screw bearing seat, a T-shaped screw, a double-row tapered roller bearing, a screw nut, a screw nut guide plate and a deep groove ball bearing. The module drive motor is connected to one end of the planetary reducer, and the other end of the planetary reducer is installed on the screw bearing seat. The screw bearing seat is installed on the main bearing truss through mounting bolts. A double-row tapered roller bearing is installed in the screw bearing seat. The double-row tapered roller bearing is mounted on the bearing position at the right end of the T-shaped screw. The end of the T-shaped screw is connected to the planetary reducer. The outer surface of the screw bearing seat is connected to the screw nut guide plate through a screw. The end is connected, and the other end of the screw nut guide plate is connected to the end support plate of the main load-bearing truss by screws. The end support plate of the main load-bearing truss is installed with a deep groove ball bearing, and the deep groove ball bearing is mounted on the left end of the T-shaped screw. The T-shaped screw is mounted with a screw nut, and a guide shaft is processed on the screw nut. The guide shaft cooperates with the guide groove of the screw nut guide plate, and the guide shaft can slide freely in the guide groove when the T-shaped screw rotates; the guide shaft is hingedly installed with one end of the horn support rod, and the module driving motor drives the T-shaped screw to rotate forward and reverse through the planetary reducer, so that the screw nut moves back and forth, thereby realizing the swing of the horn support rod to adjust the height of the horn rod.
[0011] The buffering energy absorbing device of the main load-bearing roller is composed of a buffering energy absorbing device, a roller connecting device, a latch, a rubber-coated roller and a bearing. Bearings are installed at the two inner ends of the rubber-coated roller. The inner ring of the bearing is sleeved on the roller connecting device. The roller connecting device is connected to the buffering energy absorbing device at the right end of the main load-bearing truss through a latch.
[0012] The buffer energy absorption device is composed of a nut, a buffer spring, a spring sleeve and a buffer strut, and the buffer strut is hinged to the roller connecting device through a pin; the middle part of the buffer strut is sleeved in the round tube in the middle part of the main load-bearing truss, the lower part of the buffer strut is sleeved with a buffer spring, the upper end of the buffer spring is pressed against the shoulder in the middle part of the buffer strut, the buffer spring is sleeved with a spring sleeve, the lower end of the inner cavity of the spring sleeve is connected to the lower end of the buffer spring, the spring sleeve is connected to the thread on the round tube in the middle part of the main load-bearing truss through a thread, and the lower end of the buffer strut is fixed as a whole by the nut, the buffer spring and the spring sleeve.
[0013] The RTK high-precision measurement system consists of a satellite positioning system, an RTK reference station, an RTK mobile station for the umbrella-shaped spanning frame body, an RTK mobile station for the rotation center of the crane boom, an RTK mobile station for the crossing point of the spanned wire, and an RTK mobile station for the direction of the spanned wire. The RTK reference station is installed and fixed at a safe position at the work site; the RTK mobile station for the umbrella-shaped spanning frame body is installed on the lower umbrella base of the spanning frame; the RTK mobile station for the crane boom is installed at the rotation center of the turntable of the crane; the RTK mobile station for the crossing point of the spanned wire and the RTK mobile station for the direction of the spanned wire are installed directly below the spanned wire; the satellite positioning system is connected to the RTK reference station, the RTK mobile station for the umbrella-shaped spanning frame body, the RTK mobile station for the crane boom, the RTK mobile station for the crossing point of the spanned wire, the RTK mobile station for the direction of the spanned wire, the RTK mobile station for the adjacent line, and the RTK mobile station for the direction of the adjacent wire through wireless signal communication.
[0014] The RTK base station and the umbrella-shaped spanning frame body RTK mobile station, the crane boom RTK mobile station, the spanning point RTK mobile station and the spanning direction RTK mobile station all have the same structure. All base stations contain a base station circuit board, an RTK satellite positioning chip, a signal conversion chip, a base station wireless communication module and a satellite signal transceiver antenna; the RTK satellite positioning chip, the signal conversion chip, the base station wireless communication module and the satellite signal transceiver antenna are installed on their respective base station circuit boards.
[0015] The laser radar ranging system is composed of a front laser radar ranging device and a rear laser radar ranging device. The front laser radar ranging device is installed on the umbrella-shaped lower base of the umbrella-shaped spanning frame body, and the rear laser radar ranging device is installed on the umbrella-shaped upper base of the umbrella-shaped spanning frame body. The front laser radar ranging device and the rear laser radar ranging device have the same structure, and are composed of a gimbal base plate, a horizontal motor, a vertical motor, a horizontal angle detection sensor, a vertical angle detection sensor and a laser ranging radar. The gimbal base plate, the horizontal motor and the vertical motor form a two-axis gimbal, and the laser ranging radar is installed on the output shaft of the two-axis gimbal.
[0016] The beneficial effects of the present invention compared with the prior art are: The mobile crossing frame with buffering and energy absorption, lifting horns and trajectory monitoring has added a lifting horn device on the basis of the existing functions of the mobile umbrella-shaped crossing frame. The height adjustment function of the horns can ensure that the mobile umbrella-shaped crossing frame can be smoothly evacuated from the layout position, reducing the requirements for the design distance of the intersection of power lines; a main load-bearing roller buffering and energy absorption device is added, which reduces the force on the main load-bearing roller by increasing the load force duration, so that the impact resistance of the entire mobile umbrella-shaped crossing frame is significantly improved; a safety monitoring system for the moving trajectory during the layout and evacuation process, an umbrella-shaped crossing frame body switch umbrella state detection, a rotation angle detection and a pitch angle detection device are added, and through the application of real-time dynamic carrier phase difference technology and laser radar measurement technology, the layout and evacuation trajectory of the mobile umbrella-shaped crossing frame during operation are accurately controlled, and an alarm prompt can be issued when an operation error occurs to avoid misoperation. The invention solves the problems that the horn device of the existing mobile umbrella-shaped crossing frame is a fixed structure, the main bearing roller is a rigid structure, and there is no accurate detection means during the on-site arrangement and evacuation of the mobile crossing frame, resulting in inaccurate detection of the safety distance value between the crossing frame and the crossed line, causing the boom of the automobile crane and the crossing frame to be too close to or contact the live line, causing significant economic losses and casualties of construction personnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 A schematic diagram of a mobile crossing frame with buffer energy absorption, lifting horns and track monitoring during operation without power outage; Figure 2 A top view of a mobile crossing frame with buffer energy absorption, lifting horns and track monitoring during operation without power outage; Figure 3 This is a schematic diagram of the installation of the control system of the crossing frame body on the base of the crossing frame; Figure 4 This is the circuit block diagram of the control system of the spanning rack body; Figure 5 This is a schematic diagram of the structure of the remote control operating system of the spanning frame; Figure 6 A diagram of a remote control system across a rack; Figure 7 It is a structural schematic diagram of the lifting horn device and the buffer energy absorption device of the main bearing roller; Figure 8 is a cross-sectional view of the lifting drive module; Fig. 9 It is a structural schematic diagram of the umbrella-shaped lower base of the spanning frame; Fig.10 It is a structural schematic diagram of the umbrella-shaped upper base of the spanning frame; Fig.11 This is a schematic diagram of the structure of the RTK base station; Fig.12 This is the circuit block diagram of the RTK base station; Fig.13 It is a structural diagram of a dual-axis pan-tilt laser ranging radar with feedback signal.
[0018] In the figure: 1. Mobile umbrella-shaped spanning frame, 101. Crane, 102. Umbrella-shaped spanning frame body, 10201. Spanning frame base, 10202. Umbrella-shaped lower base, 10203. Umbrella-shaped upper base, 10204. Main bearing truss, 10205. Ordinary umbrella-shaped truss, 10206. Pull rod, 10207. Switch umbrella drive motor, 10208. Switch umbrella drive screw rod, 10209. Switch umbrella state sensor, 10210. Rotation drive motor, 10211. Rotation drive device, 10212. Rotation angle sensor, 10213. Pitch drive motor, 10214. Pitch drive device, 10215. Pitch angle sensor, 103. Network sealing device, 104. Wireless cellular communication base Station, 105, user receiving terminal, 2, new conductor, 3, crossed line, 4, crossing frame body control system, 401, body control system circuit board, 402, data integration processing unit, 403, body wired communication module, 404, body wireless communication module, 405, wireless cellular communication module, 406, MIS card, 5, crossing frame remote control operating system, 501, remote control circuit board, 502, remote data processing module, 503, remote control operation button, 504, display screen, 505, USB interface, 506, buzzer alarm, 507, remote control wireless communication module, 6, liftable horn device, 601, lifting drive module, 60101, module drive motor, 60102, planet Reducer, 60103, screw bearing seat, 60104, T-shaped screw, 60105, double-row tapered roller bearing, 60106, screw nut, 60107, screw, 60108, screw nut guide, 60109, deep groove ball bearing, 602, pin, 603, clevis rod, 604, clevis support rod, 7, buffer energy absorption device of main bearing roller, 701, buffer energy absorption device, 70101, nut, 70102, buffer spring, 70103, spring sleeve, 70104, buffer support rod, 702, roller connection device, 703, latch, 704, rubber-coated roller, 705, bearing, 8, safety monitoring system for moving trajectory during layout and evacuation, 801, RTK high-precision measurement system system, 80101, satellite positioning system, 80102, RTK base station, 8010201, base station circuit board, 8010202, RTK satellite positioning chip, 8010203, signal conversion chip, 8010204, base station wireless communication module, 8010205, satellite signal receiving antenna, 80103, umbrella-shaped spanning frame body RTK mobile station, 80104, crane boom rotation center RTK mobile station, 80105, spanning point RTK mobile station, 80106, spanning direction RTK mobile station, 802, laser radar ranging system, 80201, front laser radar ranging device, 8020101, pan-tilt base plate, 8020102, horizontal motor,8020103, vertical motor, 8020104, laser ranging radar, 8020105, horizontal angle sensor, 8020106, vertical angle sensor, 80202, rear laser radar ranging device, 9, mounting bolts. DETAILED DESCRIPTION
[0019] The following is combined with Figure 1-13 The technical solution of the present invention is further described as follows.
[0020] The mobile crossing frame with buffering energy absorption, lifting cleats and track monitoring is composed of a mobile umbrella-shaped crossing frame 1, an umbrella-shaped crossing frame body integrated control system 4, a crossing frame remote operation remote control system 5, a lifting cleat device 6, a buffering energy absorption device of a main bearing roller 7, a safety monitoring system 8 for the moving track during the arrangement and evacuation process, and mounting bolts 9. Furthermore, the mobile umbrella-shaped spanning frame 1 is composed of a crane 101, an umbrella-shaped spanning frame body 102, a network sealing device 103, a mobile cellular communication system 104 and a user receiving terminal 105. The crane 101 can be a truck crane or a crawler crane of different tonnages, which is combined with the umbrella-shaped spanning frame body 102 to form a mobile umbrella-shaped spanning frame 1. The crane 101 serves as a lifting, swinging and bearing support device for the umbrella-shaped spanning frame body 102, and arranges the umbrella-shaped spanning frame body 102 to a location where construction is required; the umbrella-shaped spanning frame body 102 includes a spanning frame base 10201, an umbrella lower base 10202, an umbrella upper base 10203, a main bearing truss 10204, and a common umbrella Truss 10205, pull rod 10206, switch umbrella drive motor 10207, switch umbrella drive screw 10208, switch umbrella state detection sensor 10209, rotation drive motor 10210, rotation drive device 10211, rotation angle detection sensor 12012, pitch drive motor 10213, pitch drive device 10214 and pitch angle detection sensor 10215; the bottom of the crossing frame base 10201 has four adjustable supports, which can be connected to cranes 101 of different brands and tonnages. The pitch drive motor 10213 is installed on the pitch drive device 10214 in the middle of the crossing frame base 10201. A pitch angle detection sensor 10215 is installed at the other end, a rotation drive motor 10210 is installed on the rotation drive device 10211 at the top of the crossing frame base 10201, and a rotation angle detection sensor 10212 is installed at the other end of the rotation drive device 10211; an umbrella-shaped lower base 10202 is installed on the top of the crossing frame base 10201 through a mounting bolt 9, a switch umbrella drive motor 10207 is installed in the middle of the umbrella-shaped lower base 10202, the lower end of the switch umbrella drive motor 10207 is connected to the switch umbrella state detection sensor 10209, the upper end of the switch umbrella drive motor 10207 is connected to the switch umbrella drive screw rod 10208, and the switch umbrella drive screw rod 10208 The upper end is connected to the square tube of the umbrella-shaped upper base 10203, and the square tube of the umbrella-shaped upper base 10203 is fitted with the square tube of the umbrella-shaped lower base 10202. 8 groups of ordinary umbrella-shaped trusses 10205 are distributed around the umbrella-shaped lower base 10202. The ends of the ordinary umbrella-shaped trusses 10205 are respectively hinged to the umbrella-shaped lower base 10202, and the middle part of the ordinary umbrella-shaped trusses 10205 are respectively hinged to the umbrella-shaped upper base 10203 through 8 tie rods 10206 to form a rectangular sealing platform; the two main bearing trusses 10204 are respectively hinged to the umbrella-shaped upper base 10203, and the middle part of the main bearing trusses 10204 is supported by three tie rods 10206 on the ordinary umbrella-shaped trusses 10205 on both sides;The described net sealing device 103 is installed at the front and rear positions of the short side of the rectangular net sealing platform after the umbrella-shaped spanning frame body 102 is arranged in place during the spanning construction, and is combined with the rectangular net sealing platform to realize the front and rear net sealing functions of the mobile umbrella-shaped spanning frame, increase the net sealing coverage area of the mobile umbrella-shaped spanning frame, and prevent the wires from falling due to the breakage of the main wire during construction, causing the wires to be thrown back and contact the high-voltage live wires below and hit vehicles and pedestrians; the described switch umbrella drive motor 10207 and the switch umbrella drive screw 10208 can realize the expansion and folding functions of the umbrella-shaped spanning frame body 102; the described rotary The rotation drive motor 10210 and the rotation drive device 10211 can realize the rotation function of the umbrella-shaped spanning frame body 102; the pitch drive motor 10213 and the pitch drive device 10214 can realize the pitch function of the umbrella-shaped spanning frame body 102; the switch umbrella drive motor 10207, the switch umbrella state detection sensor 10209, the rotation drive motor 10210, the rotation angle detection sensor 10212, the pitch drive motor 10213 and the pitch angle detection sensor 10214 all communicate with the spanning frame body control system 4 through wired signals.
[0021] The umbrella-shaped crossing frame body integrated control system 4 is installed in the control box of the crossing frame base 10201 of the mobile umbrella-shaped crossing frame 1.
[0022] Furthermore, the control system 4 of the crossing frame body is composed of a body control system circuit board 401, a data integration processing unit 402, a body wired communication module 403, a body wireless communication module 404, a wireless cellular communication module 405 and a SIM card 406. The data integration processing unit 402, the body wired communication module 403, the body wireless communication module 404, the wireless cellular communication module 405 and the SIM card 406 are installed on the body control system circuit board 401; the data integration processing unit 402 is responsible for data transmission, danger signal identification and providing danger warning signals, and the body wired communication module 403 is responsible for communicating with the switch umbrella drive motor 10207, the switch umbrella state detection sensor 10209, the rotation drive motor 10210, and the rotation angle detection sensor 10211. 212, data exchange is performed between the pitch drive motor 10213 and the pitch angle detection sensor 10214, the lifting drive module 601, the front laser ranging device 80201 and the rear laser ranging device 80202; the main body wireless communication module 404 is responsible for data exchange with the RTK base station 80102, the umbrella-shaped crossing frame body RTK mobile station 80103, the crane boom rotation center RTK mobile station 80104, the crossed wire crossing point RTK mobile station 80105, the crossed wire direction RTK mobile station 80106 and the crossing frame remote operation remote control device 5; the wireless cellular communication module 405 and the SIM card 406 work together to send the danger warning signal of the data integration processing unit to the user receiving terminal 105 through the wireless cellular communication base station 104.
[0023] Furthermore, the control system 4 of the crossing frame body collects the various parameter values of the switch umbrella state detection sensor 10209, the rotation angle detection sensor 10212, the pitch angle detection sensor 10215, the RTK high-precision measurement system and the special plan for crossing operations that require input into the system. When it is detected that the minimum actual distance between the mobile umbrella-shaped crossing frame 1 and the crossed wire 3 or the mobile umbrella-shaped crossing frame 1 and the newly built line 2 is close to or less than the distance value required by the system, the control system 4 of the crossing frame body will send an alarm prompt signal to the remote operation remote control system 5 of the crossing frame, and the alarm signal will be displayed on the display 504. At the same time, the buzzer alarm 506 will also send an alarm sound to prompt the operator to make adjustments. At this time, the control system 4 of the crossing frame body will also issue an instruction to stop the action of the mobile umbrella-shaped crossing frame 1 to prevent the operator from making an operation accident due to misoperation, until the operator adjusts the mobile umbrella-shaped crossing frame 1 to a safe area before continuing normal operation.
[0024] Furthermore, the remote control system 5 of the crossing frame is operated by the operating personnel in a place with good communication; the remote control system 5 of the crossing frame is composed of a remote control circuit board 501, a remote data processing module 502, a remote control operation button 503, a display screen 504, a USB data interface 505, a buzzer alarm 506 and a remote control wireless communication module 507; the remote data processing module 502, the remote control operation button 503, the display screen 504, the USB data interface 505, the buzzer alarm 506 and the remote control wireless communication module 507 are installed on the remote control circuit board 501; through the USB The data interface 505 can input the operation data of the mobile umbrella-shaped spanning frame 1 required by the current special spanning construction plan and the minimum allowable distance value between the mobile umbrella-shaped spanning frame 1 and the spanned line 3 or the newly built conductor 2 and other parameters, which are processed by the remote data processing module 502 and transmitted to the spanning frame body control system 4 through the remote control wireless communication module 507, and stored in the data integration processing unit 402 of the spanning frame body control system 4. When the umbrella-shaped spanning frame body 102 is operated by the remote control operation button 503 during operation, if the operator's operation instruction does not match the operation instruction currently stored in the data integration processing unit 402, the spanning frame body 102 is not in compliance with the operation instruction currently stored in the data integration processing unit 402. The over-frame body control system 4 will issue an operation error warning signal, which is transmitted to the controller wireless communication module 507 through the body wireless communication module 404. After being processed by the remote data processing module 502, the operation error warning signal is displayed on the display screen 504. At the same time, the remote data processing module 502 sends an alarm prompt sound to the buzzer alarm 506. The USB data interface 505 can also transmit data through an external line to integrate the control instructions of the crane 101 issued by the data integration processing unit 402 in the over-frame body control system 4, so as to achieve the purpose of controlling the action of the truck crane 101; at the same time, the remote control operation button 503 The communication number of the user receiving terminal 104 that needs early warning notification is preset on the display screen 504, and the remote control circuit board 501 transmits it to the remote data processing module 502 for processing to produce user identity data D, and then the remote control-free wireless communication module 507 sends the user identity data D to the cross-rack body control system 4; after the main body wireless communication module 404 of the cross-rack body control system 4 receives the user identity data D, it is transmitted to the data integration processing unit 402 for processing through the internal circuit of the main body control system circuit board 401, and then stored in the wireless cellular communication module 405 for use when a dangerous situation early warning signal needs to be issued.
[0025] Furthermore, the liftable ram horn device 6 is divided into two groups, which are symmetrically distributed and installed on the main load-bearing trusses 10204 on both sides of the umbrella-shaped crossing frame body 102 of the mobile umbrella-shaped crossing frame 1; the liftable ram horn device 6 is composed of a lifting drive module 601, a pin shaft 602, a ram horn rod 603 and a ram horn support rod 604, the lifting drive module 601 is installed on the main load-bearing truss 10204 by installing bolts 10, the screw nut 60106 in the lifting drive module 601 is hinged to one end of the ram horn support rod 604, and the other end of the ram horn support rod 604 is hinged to one end of the ram horn rod 603 through the pin shaft 602, and the other end of the ram horn rod 603 is hinged to the middle part of the main load-bearing truss 10204 through the pin shaft 602; the screw nut 60106, the ram horn rod 603 and the ram horn support rod 604 are hinged head to tail to form a liftable triangular structure.
[0026] Furthermore, the lifting drive module 601 is composed of a module drive motor 60101, a planetary reducer 60102, a screw bearing seat 60103, a T-shaped screw 60104, a double-row tapered roller bearing 60105, a screw nut 60106, a screw 60107, a screw nut guide plate 60108 and a deep groove ball bearing 60109. The module drive motor 60101 is connected to one end of the planetary reducer 60102, and the other end of the planetary reducer 60102 is installed on the screw bearing seat 60103. 103, the screw bearing seat 60103 is installed on the main bearing truss 10204 by means of mounting bolts 10, a double-row tapered roller bearing 60105 is installed in the screw bearing seat 60103, and the double-row tapered roller bearing 60105 is mounted on the bearing position at the right end of the T-shaped screw 60104, the end of the T-shaped screw 60104 is connected to the planetary reducer 60102, and the outer surface of the screw bearing seat 60103 is connected to one end of the screw nut guide plate 60108 by means of screws 60107, and the screw nut guide plate 60108 is connected to the outer surface of the screw bearing seat 60103 by means of screws 60107. The other end of 108 is connected to the end support plate of the main load-bearing truss 10204 through a screw 60107. The end support plate of the main load-bearing truss 10204 is installed with a deep groove ball bearing 60109. The deep groove ball bearing 60109 is mounted on the left end of the T-shaped screw rod 60104. The T-shaped screw rod 60104 is mounted with a screw nut 60106. The screw nut 60106 is machined with a guide shaft. The guide shaft cooperates with the guide groove of the screw nut guide plate 60108. When the T-shaped screw rod 60104 rotates, the guide shaft can It can slide freely in the guide groove; the guide shaft is hingedly installed with one end of the ram's horn support rod 604, and the module driving motor 60101 drives the T-shaped screw rod 60104 to rotate forward and reverse through the planetary reducer 60102, so that the screw nut 60106 moves forward and backward, thereby realizing the swing of the ram's horn support rod 604 to adjust the height of the ram's horn rod 603, and finally to lay the ram's horn rod 603 down flat, so that the liftable ram's horn device 6 will not be scratched with the newly built line 2 above, thereby ensuring the smooth arrangement and evacuation of the mobile umbrella-shaped crossing frame 1.
[0027] Furthermore, the buffering energy absorbing device 7 of the main bearing roller is composed of four groups, two of which are installed on the umbrella-shaped upper base 10203 of the mobile umbrella-shaped spanning frame 1, and the other two groups are respectively installed on the main bearing trusses 10204 of the mobile umbrella-shaped spanning frame 1; The buffering energy absorbing device 7 of the main bearing roller is composed of a buffering energy absorbing device 701, a roller connecting device 702, a latch 703, a rubber-coated roller 704 and a bearing 705; the buffering energy absorbing device 701 is composed of a nut 70101, a buffer spring 70102, a spring sleeve 70103 and a buffering support rod 70104, and the buffering support rod 70104 is hinged to the roller connecting device 702 through the latch 703; the middle part of the buffering support rod 70104 is sleeved in the round tube in the middle part of the main bearing truss 10204, and the buffering support rod 70104 is sleeved in the middle part of the main bearing truss 10204. 4 is sleeved with a buffer spring 70102, the upper end of the buffer spring 70102 is pressed against the shoulder of the middle part of the buffer support rod 70104, the outer part of the buffer spring 70102 is sleeved with a spring sleeve 70103, the lower end of the inner cavity of the spring sleeve 70103 is connected with the lower end of the buffer spring 70102, the spring sleeve 70103 is connected with the thread on the middle part of the round tube of the main bearing truss 10204 through a thread, and the lower end of the buffer support rod 70104 is fixed as a whole by a nut 70101, a buffer spring 70102 and a spring sleeve 70103. The buffer support rod 70104 can freely move up and down in the circular tube in the middle of the main load-bearing truss 10204. Under the action of the elastic force of the buffer spring 70102, the buffer support rod 70104 is pushed to the top, and the upper end surface of the circular axis in the middle section of the buffer support rod 70104 and the upper end surface of the circular tube in the middle of the main load-bearing truss 10204 form a space in which one end can move freely; when an accident occurs, the newly built conductor 2 suddenly breaks and contacts the buffer energy-absorbing device 7 of the main load-bearing roller, and an impact force is generated between the newly built conductor 2 and the buffer energy-absorbing device 7 of the main load-bearing roller. After a period of displacement and deceleration, the newly built conductor 2 and the buffer energy-absorbing device 7 of the main load-bearing roller are relatively stationary, and the impact process ends. Due to the existence of the free space, the change S of the motion displacement can be increased, so that the action time t of the impact process force is lengthened (the principle is derived from the displacement-speed-time formula of classical mechanics). , S is the displacement change, V is the velocity change, and t is the movement time. When the velocity change V is constant, the larger the displacement change S is, the longer the movement time t is.
[0028] The free movement space can increase the time t for the buffer energy-absorbing device 7 to act from contact to static force after the newly built conductor 2 suddenly breaks and impacts the main bearing roller during an accident.
[0029] Furthermore, bearings 705 are installed at the two inner ends of the rubber-coated drum 704, and the inner ring of the bearing 705 is sleeved on the drum connection device 702. The drum connection device 702 is connected to the buffer energy absorption device 701 at the right end of the main bearing truss 10204 through the latch 703. The buffer energy absorption device 701 is installed at both ends of the rubber-coated drum 704, so that the rubber-coated drum 704 moves up and down along the axis direction of the buffer energy absorption device 701. Because the buffer energy absorption devices 701 at both ends have free movement space, in the state of a crossing construction accident, the impact force between the newly built conductor 2 and the buffer energy absorption device 7 of the main bearing drum is reduced (according to the impulse theorem of classical mechanics, , where P is the change in impulse of the newly built conductor 2 contacting the buffer energy absorbing device 7 of the main load-bearing roller during the accident, F is the force of the newly built conductor 2 contacting the buffer energy absorbing device 7 of the main load-bearing roller, and t is the time for the newly built conductor 2 to contact the buffer energy absorbing device 7 of the main load-bearing roller to exert its static force during the accident. Since P is a fixed value, the larger t is, the smaller F is).
[0030] Furthermore, the safety monitoring system 8 of the moving trajectory during the arrangement and evacuation process, together with the mobile umbrella-shaped crossing frame 1, the crossing frame body control system 4, and the crossing frame remote operation and remote control system 5, completes the safety monitoring function of the moving trajectory of the mobile umbrella-shaped crossing frame 1 during the arrangement and evacuation process during the operation. The safety monitoring system 8 of the moving trajectory during the arrangement and evacuation process includes an RTK high-precision measurement system 801 and a laser radar measurement system 802; the RTK high-precision measurement system 801 is composed of a satellite positioning system 80101, an RTK reference station 80102, an umbrella-shaped crossing frame body RTK mobile station 80310, a crane boom rotation center RTK mobile station 80104, a crossover point RTK mobile station 80105, and a crossover direction RTK mobile station 80106. The RTK reference station 80102 is installed and fixed at a safe position at the operation site; the umbrella-shaped crossing frame body RTK mobile station 80103 Installed on the umbrella-shaped lower base 10202 of the crossing frame; the crane arm RTK mobile station 80104 is installed at the rotation center of the turntable of the crane 101; the RTK mobile station 80105 at the crossing point of the crossed wire and the RTK mobile station 80106 in the direction of the crossed wire are installed directly below the crossed wire 3; the satellite positioning system 80101 and the RTK base station 80102, the umbrella-shaped crossing frame body RTK mobile station 80103, the crane arm RTK mobile station 80104, the RTK mobile station 80105 at the crossing point of the crossed wire and the RTK mobile station 80106 in the direction of the crossed wire are all connected through wireless signal communication.
[0031] Furthermore, the RTK base station 80102 and the umbrella-shaped spanning frame body RTK mobile station 80103, the crane arm RTK mobile station 80104, the cross-wire crossing point RTK mobile station 80105 and the cross-wire direction RTK mobile station 80106 are all of the same structure, and all the base stations include a base station circuit board 8010201, an RTK satellite positioning chip 8010202, a signal conversion chip 8010203, a base station wireless communication module 8010204 and a satellite signal transceiver antenna 8010205; the RTK satellite positioning chip 8010202, the signal conversion chip 8010203, the base station wireless communication module 8010204 and the satellite signal transceiver antenna 8010205 are installed on their respective base station circuit boards 8010201.
[0032] Furthermore, the RTK high-precision measurement system 801 realizes the motion trajectory control function of the deployment and evacuation of the mobile umbrella-shaped spanning frame 1 during operation through real-time dynamic carrier phase differential technology, and can issue an alarm prompt function when the actual operation trajectory deviates from the system preset trajectory; through the absolute position relationship between the RTK reference station 80102 and the umbrella-shaped spanning frame body RTK mobile station 80103 and the crane boom rotation center RTK mobile station 80104, the correctness of the absolute position where the crane 101 needs to be parked during operation can be verified, and the correctness of the parking direction of the crane 101 during operation can also be verified, and the spatial position coordinate value of the umbrella-shaped spanning frame body 102 during the entire operation process can also be determined; through the absolute position relationship between the RTK reference station 80102 and the RTK mobile station 80105 of the crossing point of the crossed wire and the RTK mobile station 80106 of the direction of the crossed wire, the direction of the crossed wire 3 can be determined, and the spatial position relationship between the crossed wire 3 and the mobile umbrella-shaped spanning frame 1 can also be determined.
[0033] Furthermore, the laser radar ranging system 802, the overpass body control system 4 and the overpass remote operation remote control system 5 jointly implement the laser radar ranging technology. The laser radar ranging system 802 is composed of a front laser radar ranging device 80201 and a rear laser radar ranging device 80202, wherein the front laser radar ranging device 80201 is installed on the umbrella-shaped lower base 10202 of the umbrella-shaped overpass body, and the rear laser radar ranging device 80202 is installed on the umbrella-shaped upper base 10203 of the umbrella-shaped overpass body. The function of the front laser radar ranging device 80201 is to measure in real time the minimum distance between the front laser radar ranging device 80201 and the obstacle in front of the crane 101 boom, and the minimum distance value and angle value between the front laser radar ranging device 80201 and the crossed wire 3; the function of the rear laser radar ranging device 80202 is to measure in real time the minimum distance between the rear laser radar ranging device 80202 and the obstacle behind the crane 101 boom, and the minimum distance value and angle value between the rear laser radar ranging device 80202 and the newly built wire 2.
[0034] Furthermore, the front laser radar ranging device 80201 and the rear laser radar ranging device 80202 have the same structure, and are composed of a pan-tilt base plate 8020101, a horizontal motor 8020102, a vertical motor 8020103, a horizontal angle detection sensor 8020105, a vertical angle detection sensor 8020106 and a laser ranging radar 8020104. 20103 forms a two-axis gimbal, and the laser ranging radar 8020104 is installed on the output shaft of the two-axis gimbal. When the crane 101 boom rotates and retracts and the umbrella-shaped spanning frame body 102 opens and closes the umbrella and rotates and pitches, it is ensured that the laser beam of the laser ranging radar 8020104 can always vertically scan the crossed wire 3 and the current construction wire 2. The horizontal angle detection sensor 8020105 and the vertical angle detection sensor 8020106 respectively detect the horizontal motor 802 0102 and the angle value of the rotation of the vertical motor 8020103 are transmitted to the control system of the crossing frame body 4 by wired transmission. The data integration processing unit 402 in the control system of the crossing frame body 4 calculates the required rotation angle of the two-axis gimbal of the front laser radar ranging device 80201 and the rear laser radar ranging device 80202 through the obtained spatial data value of the mobile umbrella-shaped crossing frame, so that the laser beam of the laser ranging radar 8020104 is always perpendicular to the direction of the object to be measured. At the same time, the laser ranging radar 8020104 will also measure the distance value and angle value between the obstacle and the obstacle, and transmit them to the control system of the crossing frame body 4. After calculation and comparison by the data integration processing unit 402, if the distance value is close to or lower than the minimum distance value required in the system, the data integration processing unit 402 will send a warning signal to the remote operation and remote control system 5 of the crossing frame, and the warning signal will be displayed on the display screen 504. At the same time, the buzzer alarm 506 will also send an alarm sound.
[0035] Furthermore, the crossing frame body control system 4, the crossing frame remote operation and remote control system 5, the satellite positioning system 80101, the RTK base station 80102, the umbrella crossing frame body RTK mobile station 80103, the mobile cellular communication system 104 and the user receiving terminal 105 can also simultaneously realize the intelligent duty function of the mobile umbrella crossing frame 1 during operation.
Claims
1. A mobile crossing frame with buffering energy absorption, lifting cleats and trajectory monitoring, comprising a mobile umbrella-shaped crossing frame (1), an umbrella-shaped crossing frame body integrated control system (4), a crossing frame remote operation remote control system (5), a lifting cleat device (6), a buffering energy absorption device for a main bearing roller (7), and a safety monitoring system (8) for the moving trajectory during deployment and evacuation; characterized in that: The umbrella-shaped spanning frame body integrated control system (4) is installed in a control box of the spanning frame base (10201) of the mobile umbrella-shaped spanning frame (1); the spanning frame remote operation remote control system (5) is operated by an operator at a place with good communication; the liftable horn device (6) is composed of two groups, which are symmetrically installed on the main bearing trusses (10204) on both sides of the umbrella-shaped spanning frame body (102) of the mobile umbrella-shaped spanning frame (1); the main bearing roller buffer energy absorption device (7) is composed of four groups, two of which are installed on the mobile umbrella-shaped spanning frame (1), and the other two groups are respectively installed on the main bearing trusses (10204) of the movable umbrella-shaped spanning frame (1); the safety monitoring system (8) for the moving trajectory during the deployment and evacuation process comprises an RTK high-precision measurement system (801) and a laser radar ranging system (802); the RTK high-precision measurement system (801) comprises a satellite positioning system (80101), an RTK base station (80102), an umbrella-shaped spanning frame body RTK mobile station (80103), a crane boom rotation center The RTK mobile station (80104), the RTK mobile station (80105) of the crossing point of the cross-wire and the RTK mobile station (80106) of the cross-wire direction, the RTK base station (80102) is installed and fixed at a safe position on the work site, the RTK mobile station (80103) of the umbrella-shaped cross-frame body is installed on the umbrella-shaped lower base (10202) of the cross-frame, the RTK mobile station (80104) of the crane boom is installed at the rotation center position of the turntable of the crane (101), the RTK mobile station (80105) of the crossing point of the cross-wire and the RTK mobile station (80106) of the cross-wire direction The station (80105) and the RTK mobile station (80106) in the direction of the crossed wire are installed directly below the crossed wire (3); the laser radar ranging system (802) includes a front laser radar ranging device (80201) and a rear laser radar ranging device (80202), the front laser radar ranging device (80201) is installed on the umbrella-shaped lower base (10202) of the umbrella-shaped crossing frame body, and the rear laser radar ranging device (80202) is installed on the umbrella-shaped upper base (10203) of the umbrella-shaped crossing frame body.
2. A mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 1, characterized in that: The main control system (4) of the crossing frame is composed of a main control system circuit board (401), a data integration processing unit (402), a main wired communication module (403), a main wireless communication module (404), a wireless cellular communication module (405) and a SIM card (406), wherein the data integration processing unit (402), the main wired communication module (403), the main wireless communication module (404), the wireless cellular communication module (405) and the SIM card (406) are mounted on the main control system circuit board (401); the main control system (4) of the crossing frame collects the switch umbrella state detection sensor (10209), the rotation angle detection sensor (10212), the pitch angle detection sensor (10215), the safety monitoring system (8) of the movement trajectory during the deployment and evacuation process, and various parameter values required to be input into the system by the special plan for the crossing operation.
3. The mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 1 is characterized in that: The remote control system (5) for remote operation of the crossing frame is composed of a remote control circuit board (501), a remote data processing module (502), a remote control operation button (503), a display screen (504), a USB data interface (505), a buzzer alarm (506) and a remote control wireless communication module (507); the remote data processing module (502), the remote control operation button (503), the display screen (504), the USB data interface (505), the buzzer alarm (506) and the remote control wireless communication module (507) are installed on the remote control circuit board (501); the operation data of the mobile umbrella-shaped crossing frame (1) required by the special crossing construction plan and the minimum allowable distance value between the mobile umbrella-shaped crossing frame (1) and the crossed line (3) or the newly built wire (2) are input through the USB data interface (505), and after being processed by the remote data processing module (502), they are transmitted to the crossing frame body control system (4) through the remote control wireless communication module (507).
4. The mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 1 is characterized in that: The liftable horn device (6) is composed of a lift drive module (601), a pin shaft (602), a horn rod (603) and a horn support rod (604); the lift drive module (601) is mounted on the main load-bearing truss (10204) by means of mounting bolts (10); the screw nut (60106) in the lift drive module (601) is hinged to one end of the horn support rod (604); the other end of the horn support rod (604) is hinged to one end of the horn rod (603) by means of a pin shaft (602); the other end of the horn rod (603) is hinged to the middle of the main load-bearing truss (10204) by means of a pin shaft (602); the screw nut (60106), the horn rod (603) and the horn support rod (604) are hinged end to end to form a liftable triangular structure.
5. The mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 4 is characterized in that: The lifting drive module (601) is composed of a module drive motor (60101), a planetary reducer (60102), a screw bearing seat (60103), a T-shaped screw (60104), a double-row tapered roller bearing (60105), a screw nut (60106), a screw (60107), a screw nut guide plate (60108) and a deep groove ball bearing (60109). The module drive motor (60101) is connected to one end of the planetary reducer (60102). The planetary reducer (6010 2) is mounted on the screw bearing seat (60103), the screw bearing seat (60103) is mounted on the main bearing truss (10204) by means of mounting bolts (9), a double-row tapered roller bearing (60105) is mounted in the screw bearing seat (60103), the double-row tapered roller bearing (60105) is mounted on the bearing position at the right end of the T-shaped screw (60104), the end of the T-shaped screw (60104) is connected to the planetary reducer (60102), and a screw bearing seat (60103) is provided on the outer surface thereof. The screw (60107) is connected to one end of the screw nut guide plate (60108), and the other end of the screw nut guide plate (60108) is connected to the end support plate of the main load-bearing truss (10204) through the screw (60107). The end support plate of the main load-bearing truss (10204) is installed with a deep groove ball bearing (60109), and the deep groove ball bearing (60109) is mounted on the left end of the T-shaped screw rod (60104). The T-shaped screw rod (60104) is mounted with a screw nut (60106), and the screw nut (60109) is mounted on the left end of the T-shaped screw rod (60104). 6) is processed with a guide shaft, which cooperates with the guide groove of the screw nut guide plate (60108). When the T-shaped screw (60104) rotates, the guide shaft can slide freely in the guide groove; the guide shaft is hingedly installed with one end of the horn support rod (604), and the module drive motor (60101) drives the T-shaped screw (60104) to rotate forward and reverse through the planetary reducer (60102), so that the screw nut (60106) moves forward and backward, thereby realizing the swing of the horn support rod (604) to adjust the height of the horn rod (603).
6. The mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 1 is characterized in that: The buffering energy absorbing device (7) of the main bearing roller is composed of a buffering energy absorbing device (701), a roller connecting device (702), a latch (703), a rubber-coated roller (704) and a bearing (705). The two inner ends of the rubber-coated roller (704) are provided with bearings (705). The inner ring of the bearing (705) is sleeved on the roller connecting device (702). The roller connecting device (702) is connected to the buffering energy absorbing device (701) at the right end of the main bearing truss (10204) via the latch (703).
7. The mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 6 is characterized in that: The buffer energy absorption device (701) is composed of a nut (70101), a buffer spring (70102), a spring sleeve (70103) and a buffer support rod (70104); the buffer support rod (70104) is hinged to the roller connection device (702) via a latch (703); the middle part of the buffer support rod (70104) is sleeved in a round tube in the middle part of the main bearing truss (10204); the lower part of the buffer support rod (70104) is sleeved with a buffer spring (70102); the buffer spring (70102) is sleeved on the lower part of the buffer support rod (70104); The upper end is pressed against the shoulder of the middle part of the buffer strut (70104); a spring sleeve (70103) is sleeved on the outside of the buffer spring (70102); the lower end of the inner cavity of the spring sleeve (70103) is connected to the lower end of the buffer spring (70102); the spring sleeve (70103) is connected to the thread on the middle round tube of the main load-bearing truss (10204) through a thread; the lower end of the buffer strut (70104) is fixed as a whole through a nut (70101), the buffer spring (70102) and the spring sleeve (70103).
8. The mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 1 is characterized in that: The safety monitoring system (8) for the movement trajectory during the deployment and evacuation process comprises an RTK high-precision measurement system (801) and a laser radar ranging system (802); the RTK high-precision measurement system (801) is composed of a satellite positioning system (80101), an RTK reference station (80102), an umbrella-shaped spanning frame body RTK mobile station (80103), a crane boom rotation center RTK mobile station (80104), a spanning wire crossing point RTK mobile station (80105) and a spanning wire direction RTK mobile station (80106), the RTK reference station (80102) is installed and fixed at a safe position on the work site; the umbrella-shaped spanning frame body RTK mobile station (80103) The RTK mobile station (80104) is installed on the umbrella-shaped lower base (10202) of the crossing frame; the crane arm RTK mobile station (80104) is installed at the rotation center of the turntable of the crane (101); the RTK mobile station (80105) for the crossing point of the crossed wire and the RTK mobile station (80106) for the direction of the crossed wire are installed directly below the crossed wire (3); the satellite positioning system (80101) is connected to the RTK base station (80102), the umbrella-shaped crossing frame body RTK mobile station (80310), the crane arm RTK mobile station (80104), the RTK mobile station (80105) for the crossing point of the crossed wire and the RTK mobile station (80106) for the direction of the crossed wire through wireless signal communication.
9. The mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 8 is characterized in that: The RTK base station (80102) has the same structure as the umbrella-shaped spanning frame body RTK mobile station (80103), the crane arm RTK mobile station (80104), the spanning point RTK mobile station (80105) and the spanning direction RTK mobile station (80106). All base stations contain a base station circuit board (8010201), an RTK satellite positioning chip (8010202), a signal conversion chip (8010203), a base station wireless communication module (8010204) and a satellite signal transceiver antenna (8010205); the RTK satellite positioning chip (8010202), the signal conversion chip (8010203), the base station wireless communication module (8010204) and the satellite signal transceiver antenna (8010205) are installed on their respective base station circuit boards (8010201).
10. The mobile crossing frame with buffering energy absorption, lifting horns and trajectory monitoring according to claim 1 is characterized in that: The laser radar ranging system (802) is composed of a front laser radar ranging device (80201) and a rear laser radar ranging device (80202), wherein the front laser radar ranging device (80201) is mounted on an umbrella-shaped lower base (10202) of the umbrella-shaped spanning frame body, and the rear laser radar ranging device (80202) is mounted on an umbrella-shaped upper base (10203) of the umbrella-shaped spanning frame body; the structure of the front laser radar ranging device (80201) and the rear laser radar ranging device (80202) is as follows: The structure is the same, consisting of a gimbal base plate (8020101), a horizontal motor (8020102), a vertical motor (8020103), a horizontal angle detection sensor (8020105), a vertical angle detection sensor (8020106) and a laser ranging radar (8020104). The gimbal base plate (8020101), the horizontal motor (8020102) and the vertical motor (8020103) form a two-axis gimbal, and the laser ranging radar (8020104) is installed on the output shaft of the two-axis gimbal.
Citation Information
Patent Citations
Portable automatic crossing structure that expandes fast
CN205452971U
Movable umbrella-shaped crossing frame with rotating and pitching functions
CN216598743U
Self-lifting rotatable cantilever crossing structure
CN108718058A
Method for measuring distance between power transmission line and crossing object and related device
CN115900622A
Movable umbrella-shaped spanning frame capable of safely carrying out spanning construction without power failure