A kind of lifting equipment for installing power tower

By designing lifting equipment for power tower installation, the mobile rack, climbing unit and guide mechanism are used to solve the problems of low docking accuracy and low lifting efficiency of tower sections, and an efficient and safe tower section installation process is achieved.

CN119143004BActive Publication Date: 2025-02-11SHANDONG ZHIXING INTELLIGENT EQUIP CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411658173.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-11-20
Publication Date
2025-02-11
Estimated Expiration
2044-11-20

AI Technical Summary

Technical Problem

When installing a single pipe tower, the docking accuracy of the manual guide tower section is low, the lifting efficiency is low, and high-altitude operations increase safety hazards.

Method used

A lifting equipment including an up and down mobile rack is designed, and a climbing unit and a guide mechanism are provided on the mobile rack. Through the cooperation of the climbing wheel and the guide column, the precise docking and stable fixation of the tower section is achieved.

Benefits of technology

It improves the accuracy and convenience of tower section docking, forms a stable framework, reduces the participation of manual guidance, improves lifting efficiency, and reduces the time and risks of manual aerial operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119143004B_ABST
    Figure CN119143004B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of electric iron towers, and specifically to a hoisting device for installing electric iron towers, including a mobile frame, a climbing unit and a guide mechanism. The present invention makes the axis of the tower segment and the axis of the mobile frame collinear through three processes: a climbing wheel presses against a tower segment, a bonding plate presses against the stairs of the corresponding tower segment, and a pressing plate presses against the circumferential surface of the tower segment, and makes the docking reference of the tower segment the corresponding mobile frame. After that, the docking process of the two mobile frames is used as a transition, and the guide column is gradually inserted into the guide cylinder for a first guide limit, and the docking column moves downward and is inserted into the docking groove of the pressing plate on the lower mobile frame for a second guide limit. Through the two guide limit processes, the accuracy and convenience of the tower segment docking process are improved, and a stable frame is formed at the same time to ensure the stability of the tower segment docking process, which is convenient for manual subsequent operations, improves the efficiency of the hoisting process, and reduces the time of manual high-altitude operations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of power iron towers, in particular to a hoisting device for installing a power iron tower. Background Art

[0002] Power towers, also known as transmission towers or high-voltage towers, are structures used to support high-voltage transmission lines. They play a vital role in the power system, ensuring the transmission of electricity from power stations to power-consuming areas. They are divided into many types according to different usage scenarios and usage requirements, such as self-supporting towers, guyed towers and single-tube towers. Among them, single-tube towers are widely used in urban distribution networks and landscape-sensitive areas due to their beauty, space saving, easy installation and maintenance.

[0003] A single-tube tower is usually formed by splicing multiple tower sections and is installed after being transported to the installation site. Currently, when installing a single-tube tower, the required base is first cast at the designated installation location, and then the lowest tower section is hoisted to the top of the designated location through external lifting equipment. The tower section is manually guided to dock with the base and fixed and locked. After that, the external lifting equipment hoists each tower section from bottom to top in turn. During the connection of two adjacent tower sections, the stairs on the tower section are manually climbed to the fixed tower section on the lower side to guide the two tower sections to dock. After docking, the two tower sections are manually fixed and locked, and the installation process of the single-tube tower is finally completed.

[0004] The above-mentioned installation process has the following problems: during the docking installation of two adjacent tower sections, after the upper tower section is lifted by external lifting equipment to the top of the fixed lower tower section, the two tower sections are mainly guided to dock by the staff located on the stairs of the lower tower section. The manual guidance accuracy is low. Secondly, the stairs on the tower section can only accommodate one staff member to climb up or stand, so the overall lifting efficiency is low, and the overall height of the single-tube tower is relatively high, so personnel are required to climb continuously for guidance and installation. The staff need to stay on the tower section for a long time, which increases the safety hazards during the installation process. Summary of the invention

[0005] Based on this, it is necessary to provide a hoisting device for installing a power tower, aiming to solve the problems of the above-mentioned prior art.

[0006] The present application provides a lifting device for installing an electric power tower, comprising: two upper and lower moving frames, the two moving frames are respectively arranged on two upper and lower adjacent tower sections, the moving frame is a ring-shaped frame with an opening on the rear side, and a climbing unit for climbing the frame along the length direction of the tower section is arranged on the moving frame, the climbing unit comprises a horizontal column, two groups of column groups symmetrically distributed on the left and right are slidably penetrated on the moving frame, the column group comprises a plurality of horizontal columns distributed in the circumferential direction and having horizontal axes and pointing to the axes of the moving frames, the end faces of the horizontal columns located on the inner sides of the moving frames are fixedly provided with U-shaped blocks with openings facing the tower sections, climbing wheels are arranged in the U-shaped blocks through the rotation of the rotating columns, and the climbing unit also comprises a locking group for locking the climbing wheels.

[0007] A guiding mechanism is commonly provided on the upper and lower movable frames, and the guiding mechanism comprises a plate frame. Four plate frames distributed in a matrix are fixedly provided on the opposite back surfaces of the two movable frames. Guide columns with vertical axes are fixedly provided on the upper and lower end surfaces of the upper plate frame, and guide cylinders with vertical axes are fixedly provided on the upper and lower end surfaces of the lower plate frame, and the openings of the guide cylinders are chamfered.

[0008] The guiding mechanism also includes an auxiliary unit, and the two moving frames are commonly provided with an auxiliary unit for assisting the guiding process, and the auxiliary unit includes a clamping plate. The moving frame is provided with two groups of left-right symmetrical plate groups, and the plate group includes two arc-shaped clamping plates distributed up and down, and the inner arc surface of the clamping plate faces the tower section.

[0009] According to a preferred embodiment, the locking group includes a spring 1, a spring 1 mounted on the corresponding horizontal column is fixedly arranged between the U-shaped block and the corresponding movable frame, an arc-shaped bar is symmetrically slidably arranged on the outer arc surface of the movable frame, and an L-shaped locking block corresponding to the horizontal column is fixedly arranged on the end surface of the arc-shaped bar facing the adjacent horizontal column, and the horizontal section of the locking block is chamfered near the end surface of the horizontal column, and a locking groove is opened on the horizontal column, and the direction of the locking groove from the U-shaped block to the arc-shaped bar is a triangular section and a rectangular section respectively, and the inclined surface of the triangular section of the locking groove faces the corresponding locking block.

[0010] According to a favorable embodiment, the auxiliary unit also includes a hinge bar, and the upper and lower end surfaces of the movable frame are hingedly provided with two hinge bars that are symmetrical on the left and right and hinged to the corresponding clamping plates. The movable frame is rotated and penetrated by two threaded rods with horizontal axes and pointing to the axes of the movable frame. The threaded rod is located between the two corresponding upper and lower hinge bars, and a rectangular block is threadedly sleeved on the threaded rod, and a driving bar is hingedly installed between the rectangular block and the corresponding hinge bar.

[0011] According to a preferred embodiment, the auxiliary unit also includes a gear, and the end face of the threaded rod away from the rectangular block is fixed with a gear, and the outer arc surface of the movable frame is slidably provided with two left-right symmetrical and arc-shaped tooth plates through the connecting block, and the tooth plates are meshed with adjacent gears.

[0012] According to a favorable embodiment, the auxiliary unit also includes a spiral spring, and a spiral spring located between the corresponding gear and the moving frame is commonly provided between the moving frame and the threaded rod, and two left-right symmetrical rope-supporting members are fixedly provided on opposite back surfaces of the two moving frames through connecting blocks, and a rope is commonly fixedly provided between the two tooth plates on the same moving frame, and the rope passes through the two rope-supporting members on the same moving frame, and arc-shaped rope-pushing plates are fixedly provided on the upper and lower end surfaces of the moving frame through connecting frames, and the two rope-pushing plates on the same moving frame are symmetrical up and down and the inner arc surfaces are opposite to each other, and the connecting frames on the two moving frames are staggered left and right.

[0013] According to a favorable embodiment, a guide block is fixedly provided on the front end surface of the connecting frame on the upper movable frame through a fixing block 1, and a guide plate is fixedly provided on the front end surface of the connecting frame on the lower movable frame through a fixing block 2, and a guide groove is opened on the guide plate, and the guide groove passes through the upper and lower end surfaces of the corresponding guide plate, and the guide groove is, from left to right, an isosceles trapezoid with a small diameter section facing right and a rectangular section cooperating with the guide plate, and the upper and lower ends of the guide groove are chamfered.

[0014] According to a favorable embodiment, the guiding mechanism further comprises a docking column, the end surface of the clamping plate on the upper movable frame away from the movable frame is fixedly provided with a docking column, and the clamping plate on the lower movable frame is provided with a docking groove cooperating with the docking column.

[0015] According to a favorable embodiment, the guiding mechanism also includes side plates, and two left-right symmetrical side plates are fixedly provided on the opposite back surfaces of the two movable frames, and sliding columns with axes extending from left to right are penetrated through the side plates for left-right sliding, and fitting plates are fixedly provided on the opposite surfaces of the two adjacent sliding columns on the left and right.

[0016] According to a favorable embodiment, guide plates are fixedly provided on both end surfaces of the bonding plate, and the two guide plates on the same bonding plate are symmetrical to each other, and the two guide plates opposite to each other on the left and right are symmetrical to each other. Taking the guide plate on the left front side as an example, the guide plate is composed of a rectangular section and an inclined section from left to right, and the inclined section is inclined forward from left to right.

[0017] According to a favorable embodiment, the guiding mechanism also includes a pushing frame, the rectangular block is fixedly provided with a pushing frame, the pushing frame is fixedly provided with a pushing plate, the pushing plate is slidably sleeved on an adjacent sliding column, the sliding column is fixedly provided with a mounting plate located between the fitting plate and the pushing plate, and a spring 2 sleeved on the sliding column is fixedly provided between the mounting plate and the pushing plate.

[0018] In summary, the present invention includes at least one of the following beneficial effects: First, the present invention makes the axis of the tower section and the axis of the moving frame collinear through three processes of the climbing wheel pressing against the tower section, the bonding plate pressing against the stairs of the corresponding tower section, and the pressing plate pressing against the circumferential surface of the tower section, and makes the docking reference of the tower section the corresponding moving frame. Afterwards, the docking process of the two moving frames is used as a transition, and a guide limit is performed by gradually inserting the guide column into the guide cylinder, and the docking column is moved down and inserted into the docking groove on the lower moving frame for a second guide limit. Through the two guide limit processes, the accuracy and convenience of the tower section docking process are improved, and at the same time a stable frame is formed to ensure the stability of the tower section docking process, facilitate subsequent manual operations, reduce the participation of manual guidance, improve the efficiency of hoisting, and reduce the time of manual high-altitude operations.

[0019] 2. In the present invention, after all the climbing wheels on the same mobile frame are locked, the axis of the mobile frame is made to be in line with the axis of the tower section, which is convenient for the subsequent guided docking process of the two tower sections based on the mobile frame. After completing one tower section docking operation, the mobile frame on the lower tower section moves down through the climbing unit thereon, is manually removed and reinstalled on the tower section to be hoisted, and the mobile frame on the upper tower section moves up to the upper area of ​​the tower section through the climbing unit thereon, and the above operation process is repeated to perform the docking operation of multiple tower sections, which improves the docking accuracy of the two tower sections while simplifying the operation method and facilitates operation.

[0020] 3. During the hoisting process of the present invention, the guide block is inserted into the guide groove when the upper tower section moves downward, which is convenient for the hoisting of the upper tower section and at the same time makes the push rope plate on the connecting frame and the relative rope face up and down. Then, the guide column and the guide cylinder are coordinated, and the docking column and the docking groove are coordinated. The guiding process is carried out in turn to continuously improve the accuracy of the docking process. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0022] Figure 1 A schematic diagram of the three-dimensional structure of a lifting device for installing a power tower provided according to an embodiment of the present invention is shown.

[0023] Figure 2 A schematic diagram of the three-dimensional structure among the guide cylinder, the movable frame and the docking column provided according to an embodiment of the present invention is shown.

[0024] Figure 3A schematic diagram of a partial three-dimensional structure between a docking column, a moving frame and a driving bar provided according to an embodiment of the present invention is shown.

[0025] Figure 4 The embodiment provided according to the present invention shows Figure 3 Enlarged view of point A in the middle.

[0026] Figure 5 A schematic diagram of a partial cross-sectional three-dimensional structure between a horizontal column, a climbing wheel and a clamping slot is shown according to an embodiment of the present invention.

[0027] Figure 6 A schematic diagram of the three-dimensional structure among the moving frame, the docking column and the pressing plate provided according to an embodiment of the present invention is shown.

[0028] Figure 7 A schematic diagram of a partial three-dimensional structure among a rope pushing plate, a guide block and a guide plate provided according to an embodiment of the present invention is shown.

[0029] The above drawings include the following reference numerals: 1, mobile frame; 2, climbing unit; 20, horizontal column; 21, U-shaped block; 22, climbing wheel; 23, locking group; 230, spring 1; 231, arc strip; 232, positioning block; 233, slot; 3, guide mechanism; 30, plate frame; 300, guide column; 301, guide cylinder; 31, docking column; 310, docking slot; 32, side plate; 320, sliding column; 322, bonding plate ; 33. Guide plate; 34. Push frame; 340. Push plate; 341. Mounting plate; 342. Spring 2; 4. Auxiliary unit; 40. Pressing plate; 41. Hinge strip; 410. Threaded rod; 411. Rectangular block; 412. Driving strip; 413. Gear; 414. Tooth plate; 415. Volute spring; 416. Rope support member; 417. Rope; 418. Rope push plate; 42. Guide block; 420. Guide plate; 421. Guide groove. DETAILED DESCRIPTION

[0030] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present invention, so the present invention is not limited by the specific embodiments disclosed below.

[0031] like Figure 1 and Figure 2As shown, a hoisting device for installing an electric tower comprises: two upper and lower moving frames 1, the two moving frames 1 are respectively arranged on two upper and lower adjacent tower sections, the moving frame 1 is a ring with an opening on the rear side, and a climbing unit 2 for climbing along the length direction of the tower section is arranged on the moving frame 1, the climbing unit 2 comprises a horizontal column 20, two groups of column groups symmetrically distributed on the left and right are slidably penetrated on the moving frame 1, the column group comprises a plurality of horizontal columns 20 distributed in the circumferential direction and with horizontal axes and pointing to the axes of the moving frame 1, the end faces of the horizontal columns 20 located on the inner side of the moving frame 1 are fixedly provided with U-shaped blocks 21 with openings facing the tower section, a climbing wheel 22 is arranged in the U-shaped block 21 through rotation of a rotating column, the rotating column is connected to an external motor, and the climbing unit 2 also comprises a locking group 23 for locking the climbing wheel 22.

[0032] like Figure 1 and Figure 2 As shown, a guiding mechanism 3 is commonly provided on the upper and lower moving frames 1, and the guiding mechanism 3 includes a plate frame 30. Four plate frames 30 distributed in a matrix are fixedly provided on the opposite back surfaces of the two moving frames 1, and guiding columns 300 with vertical axes are fixedly provided on the upper and lower end surfaces of the upper plate frame 30, and guiding cylinders 301 with vertical axes are fixedly provided on the upper and lower end surfaces of the lower plate frame 30, and the openings of the guiding cylinders 301 are chamfered.

[0033] like Figure 1 As shown, the guiding mechanism 3 also includes an auxiliary unit 4. The two mobile frames 1 are commonly provided with an auxiliary unit 4 for assisting the guiding process. The auxiliary unit 4 includes a clamping plate 40. The mobile frame 1 is provided with two groups of left-right symmetrical plate groups. The plate group includes two upper and lower distributed and arc-shaped clamping plates 40, and the inner arc surface of the clamping plate 40 faces the tower section.

[0034] When the upper tower section is hoisted to dock with the lower tower section, the guide column 300 is inserted into the corresponding guide tube 301 to limit and guide the docking process of the two.

[0035] During the installation of a power tower, the lowest tower section is first hoisted and moved to the installation base by external lifting equipment such as a crane, and the installation process of the tower section is manually guided. After the tower section is fixed on the installation base, the remaining tower sections are hoisted. That is, after the lowest tower section is in a fixed state, the remaining tower sections are hoisted.

[0036] During operation, the staff places the lower mobile frame 1 on the lower tower section. The opening area of ​​the mobile frame 1 is convenient for the staff to place the mobile frame 1 on the tower section, and the opening area of ​​the mobile frame 1 faces the stairs on the tower section. The external hoisting equipment works to lift the upper tower section and repeats the above operation, placing the upper mobile frame 1 on the upper tower section, and all the climbing wheels 22 on the same mobile frame 1 are locked through the locking group 23, and kept in close contact with the tower section, which is convenient for subsequent climbing operations. At the same time, through the above operation, the axis of the mobile frame 1 is made to be in line with the axis of the tower section, and the external motor works to rotate the climbing wheel 22, so that The mobile frame 1 moves synchronously, the mobile frame 1 of the upper tower section moves to its lower end, and the mobile frame 1 of the lower tower section moves to its upper end. Then, the external lifting equipment works to drive the upper tower section to move to the top of the lower tower section and then gradually moves downward. During the downward movement, the clamping plate 40 on the mobile frame 1 presses the tower section so that the axis of the tower section is colinear with the axis of the mobile frame 1. At the same time, the guide column 300 is gradually inserted into the guide cylinder 301, so that the upper and lower mobile frames 1 are opposite to each other, which indirectly aligns the two tower sections up and down, thereby realizing guided docking. After docking, the staff fixes the upper tower section by tightening the bolts.

[0037] Afterwards, the mobile frame 1 on the lower tower section is moved downward by the climbing unit 2 thereon, removed manually and installed again on the tower section to be hoisted, and the mobile frame 1 on the upper tower section is moved upward to the upper area of ​​the tower section by the climbing unit 2 thereon, and the above operations are repeated to complete the hoisting and guiding process of the subsequent tower sections.

[0038] like Figure 1 , Figure 2 , Figure 4 and Figure 5 As shown, the locking group 23 includes a spring 230, and a spring 230 mounted on the corresponding horizontal column 20 is fixedly arranged between the U-shaped block 21 and the corresponding moving frame 1. The outer arc surface of the moving frame 1 is symmetrically slidably arranged with an arc strip 231, and the end surface of the arc strip 231 facing the adjacent horizontal column 20 is fixedly provided with an L-shaped positioning block 232 corresponding to the horizontal column 20. The horizontal section of the positioning block 232 is chamfered near the end surface of the horizontal column 20, and a slot 233 is opened on the horizontal column 20. The direction of the slot 233 from the U-shaped block 21 to the arc strip 231 is a triangular section and a rectangular section, and the inclined surface of the triangular section of the slot 233 faces the corresponding positioning block 232.

[0039] During operation, in the process of moving the mobile frame 1 to surround the corresponding tower section, the tower section squeezes the climbing wheel 22 on the mobile frame 1, so that the climbing wheel 22 drives the U-shaped block 21 and the horizontal column 20 to move in the direction away from the axis of the mobile frame 1, and the spring 1 230 is compressed. At the same time, the elastic force generated by the compression deformation of the spring 1 230 makes the corresponding climbing wheel 22 close to the outer wall of the tower section. All the climbing wheels 22 on the same mobile frame 1 are close to the outer wall of the tower section at the same time, so that the axis of the mobile frame 1 is initially collinear with the axis of the tower section. Then, the arc bar 231 is manually rotated, and the arc bar 231 drives the positioning block 232 thereon to move synchronously, and the positioning The block 232 is gradually inserted into the slot 233. The blocking block 232 first contacts the inclined surface of the triangular section of the slot 233 and gradually squeezes the inner wall of the slot 233, so that the horizontal column 20 drives the corresponding climbing wheel 22 to press against the outer wall of the tower section. Then the blocking block 232 moves into the rectangular section of the corresponding slot 233, completing the fixed locking of the horizontal column 20 and the climbing wheel 22, and then locking the moving frame 1 in the circumferential direction, which is convenient for the subsequent guiding process and the climbing process of the moving frame 1 in the axial direction of the tower section. The chamfered area of ​​the blocking block 232 makes it easy for the blocking block 232 to be inserted into the slot 233 and contact and cooperate with the inclined surface of the triangular section of the slot 233.

[0040] like Figure 1 , Figure 2 and Figure 3 As shown, the auxiliary unit 4 also includes a hinge bar 41, and the upper and lower end surfaces of the mobile frame 1 are hingedly provided with two left-right symmetrical hinge bars 41 hinged to the corresponding clamping plates 40. The mobile frame 1 is rotatably penetrated by a threaded rod 410 with two horizontal axes and pointing to the axis of the mobile frame 1. The threaded rod 410 is located between the two corresponding upper and lower hinge bars 41, and a rectangular block 411 is threadedly sleeved on the threaded rod 410. A driving bar 412 is hingedly installed between the rectangular block 411 and the corresponding hinge bar 41.

[0041] like Figure 1 and Figure 3 As shown, the auxiliary unit 4 also includes a gear 413, and the end face of the threaded rod 410 away from the rectangular block 411 is fixedly provided with a gear 413, and the outer arc surface of the mobile frame 1 is slidably provided with two left-right symmetrical and arc-shaped tooth plates 414 through the connecting block, and the tooth plates 414 are meshed with adjacent gears 413.

[0042] like Figure 1 , Figure 3 and Figure 6As shown, the auxiliary unit 4 also includes a vortex spring 415, and a vortex spring 415 located between the corresponding gear 413 and the mobile frame 1 is commonly provided between the mobile frame 1 and the threaded rod 410, and two left-right symmetrical support rope members 416 are fixedly provided on the opposite back surfaces of the two mobile frames 1 through a connecting block, and a rope 417 is commonly fixedly provided between the two tooth plates 414 on the same mobile frame 1, and the rope 417 passes through the two support rope members 416 on the same mobile frame 1, and arc-shaped push rope plates 418 are fixedly provided on the upper and lower end surfaces of the mobile frame 1 through a connecting frame, and the two push rope plates 418 on the same mobile frame 1 are symmetrical up and down and the inner arc surfaces are opposite to each other, and the connecting frames on the two mobile frames 1 are staggered left and right.

[0043] like Figure 6 and Figure 7 As shown, the front end surface of the connecting frame on the upper movable frame 1 is fixedly provided with a guide block 42 through a fixing block 1, and the front end surface of the connecting frame on the lower movable frame 1 is fixedly provided with a guide plate 420 through a fixing block 2. A guide groove 421 is opened on the guide plate 420, and the guide groove 421 passes through the upper and lower end surfaces of the corresponding guide plate 420. The guide groove 421 is, from left to right, an isosceles trapezoid with a small diameter section facing right and a rectangular section cooperating with the guide plate 420, and the upper and lower ends of the guide groove 421 are chamfered.

[0044] During operation, after the mobile frame 1 is locked on the corresponding tower section and moved to the specified position of the tower section, the external lifting equipment lifts the upper tower section to the top of the lower tower section and gradually moves it downward. During the downward movement, the position of the upper tower section is adjusted, and the guide block 42 is made to be opposite to the guide groove 421 up and down. As the upper tower section gradually moves downward, the guide block 42 is inserted into the guide groove 421 to complete the initial guidance, which is convenient for the lifting of the upper tower section and at the same time makes the push rope plate 418 on the connecting frame opposite to the relative rope 417 up and down. Secondly, the isosceles trapezoidal section on the guide groove 421 and the upper and lower chamfers of the guide groove 421 make it convenient for the guide block 42 to move into the guide groove 421 and cooperate with the rectangular section of the guide groove 421 to perform the guiding operation.

[0045] As the upper tower section gradually moves downward, the rope-pushing plate 418 on the mobile frame 1 approaches the rope 417 on the other mobile frame 1, and finally the rope-pushing plate 418 pushes the rope 417 on the other mobile frame 1. The rope 417 pulls the tooth plates 414 at both ends thereof and makes the corresponding two tooth plates 414 approach each other. During the movement of the tooth plates 414, the tooth plates 414 mesh with the corresponding gears 413, so that the gears 413 drive the threaded rod 410 to rotate. Through the threaded cooperation between the threaded rod 410 and the corresponding rectangular block 411, The rectangular block 411 is close to the tower section, and the rectangular block 411 drives the driving bar 412 thereon to move synchronously. The transmission of the driving bar 412 enables the hinged bar 41 to drive the clamping plate 40 thereon to move synchronously until the two clamping plates 40 corresponding to the same rectangular block 411 both clamp the corresponding tower section. The inner arc surfaces of the four clamping plates 40 on the mobile frame 1 simultaneously clamp the tower section, so that the axis of the mobile frame 1 is collinear with the axis of the corresponding tower section, completing the second limiting process of the tower section, and at the same time improving the stability of the mobile frame 1 during the docking process.

[0046] During the rotation of the above-mentioned gear 413, the vortex spring 415 is deformed. After the lifting process is completed, the rope pushing plate 418 stops pushing the corresponding rope 417. The elastic force generated by the deformation of the vortex spring 415 causes the gear 413 and the threaded rod 410 to reverse, so that the rectangular block 411 is reset and the tooth plate 414 is reset to the initial state, which is convenient for subsequent operations.

[0047] like Figure 1 and Figure 6 As shown, the guiding mechanism 3 also includes a docking column 31, and the end surface of the clamping plate 40 on the upper side of the mobile frame 1 away from the mobile frame 1 is fixedly provided with a docking column 31, and the clamping plate 40 on the lower side of the mobile frame 1 is provided with a docking groove 310 that cooperates with the docking column 31.

[0048] When the clamping plate 40 clamps the tower section and completes the locking of the moving frame 1, the axes of the upper and lower moving frames 1 are both in line with the corresponding tower sections, and preliminary guidance is performed through the cooperation of the guide block 42 and the guide groove 421, so that the clamping plates 40 on the two moving frames 1 are opposite to each other up and down. As the external lifting equipment continues to place the upper tower section from top to bottom, the upper tower section and the moving frame 1 thereon continue to move downward, and the docking column 31 on the moving frame 1 continues to move downward and is inserted into the docking groove 310 of the lower clamping plate 40 for secondary guidance and limiting, guiding the precise docking of the upper and lower tower sections. At the same time, through the above method, the upper and lower moving frames 1 are connected to each other through the clamping plate 40, and at the same time, the plug-in between the guide column 300 and the guide cylinder 301 is cooperated to form a stable frame to ensure the stability during the docking process of the tower sections.

[0049] like Figure 1 and Figure 2As shown, the guide mechanism 3 also includes a side plate 32. Two left-right symmetrical side plates 32 are fixedly provided on the opposite back surfaces of the two movable frames 1. A sliding column 320 with an axis extending from left to right is passed through the side plate 32 for left-right sliding. A fitting plate 322 is fixedly provided on the opposite surfaces of the two adjacent sliding columns 320 on the left and right.

[0050] like Figure 1 and Figure 2 As shown, guide plates 33 are fixedly provided on both end surfaces of the bonding plate 322, and the two guide plates 33 on the same bonding plate 322 are symmetrical to each other, and the two guide plates 33 opposite to each other on the left and right are symmetrical to each other. Taking the guide plate 33 on the left front side as an example, the guide plate 33 is composed of a rectangular section and an inclined section from left to right, and the inclined section is inclined forward from left to right.

[0051] like Figure 1 and Figure 2 As shown, the guiding mechanism 3 also includes a pushing frame 34, the pushing frame 34 is fixedly arranged on the rectangular block 411, the pushing frame 34 is fixedly arranged on the pushing frame 34, the pushing plate 340 is slidably sleeved on the adjacent sliding column 320, the sliding column 320 is fixedly sleeved with a mounting plate 341 located between the fitting plate 322 and the pushing plate 340, and a spring 2 342 sleeved on the sliding column 320 is fixedly arranged between the mounting plate 341 and the pushing plate 340.

[0052] During operation, in the process of installing the mobile frame 1 on the tower section, the mounting plate 341 is manually moved so that the mounting plate 341 drives the sliding column 320 and the bonding plate 322 away from the stairs of the tower section, and the spring 2 342 is compressed. Then the mobile frame 1 is moved and the climbing wheel 22 on the mobile frame 1 presses the tower section under the action of the spring 1 230, and the mounting plate 341 is released. The elastic force generated by the compression of the spring 2 342 causes the mounting plate 341 to drive the sliding column 320 and the bonding plate 322 close to the stairs. During the movement of the bonding plate 322, the bonding plate 322 drives the guide plate 33 thereon to move synchronously. The inclined section of the guide plate 33 first contacts the stairs, so that the rectangular sections of the corresponding two guide plates 33 can cooperate with each other in the subsequent process.

[0053] Then, in the process of driving the pressing plate 40 to press the tower section, the rectangular block 411 approaches the tower section, and the rectangular block 411 drives the pushing plate 340 to move synchronously through the pushing frame 34, and the pushing plate 340 compresses the corresponding spring 2 342. The elastic force generated by the deformation of the spring 2 342 makes the mounting plate 341 drive the fitting plate 322 to approach the stairs through the sliding column 320, and the guide plate 33 continues to move with the fitting plate 322, and the rectangular section of the guide plate 33 gradually contacts the stairs, and finally the fitting plate 322 is close to the stairs, and the two rectangular sections of the guide plates 33 are They cooperate with each other and press against the stairs. Taking the stair position of the corresponding tower section as a reference, the axis of the mobile frame 1 is made to be collinear with the axis of the corresponding tower section through the fitting of the two fitting plates 322, and the circumferential angle of the tower section is locked with the mobile frame 1. Therefore, in the subsequent process of guiding the two mobile frames 1 to dock up and down, the docking process of the two mobile frames 1 can be used as a transition, so that the axes of the two tower sections are not only collinear but also aligned up and down, which ensures the accuracy of the connection and installation process of the two tower sections and avoids the problem of the upper and lower tower sections not being aligned and affecting the subsequent installation.

[0054] In the description of the present invention, it is necessary to understand that the directions or positional relationships indicated by directional words such as "front, back, up, down, left, right", "lateral, vertical, perpendicular, horizontal" and "top, bottom" are usually based on the directions or positional relationships shown in the drawings. They are only for the convenience of describing the present invention and simplifying the description. Unless otherwise specified, these directional words do not indicate or imply that the devices or elements referred to must have a specific direction or be constructed and operated in a specific direction. Therefore, they cannot be understood as limiting the scope of protection of the present invention. The directional words "inside and outside" refer to the inside and outside relative to the contours of each component itself.

[0055] In addition, the terms "first", "second", "number one", "number two" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first", "second", "number one", "number two" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "multiple" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0056] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "connect", "install", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0057] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, all equivalent changes made according to the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A hoisting device for installing a power tower, characterized in that: include: Two upper and lower moving frames (1), the two moving frames (1) are respectively arranged on two upper and lower adjacent tower sections, the moving frame (1) is annular with an opening at the rear side, the moving frame (1) is provided with a climbing unit (2) for climbing along the length direction of the tower section, the climbing unit (2) comprises a horizontal column (20), two groups of column groups symmetrically distributed on the left and right are slidably penetrated on the moving frame (1), the column group comprises a plurality of horizontal columns (20) distributed in the circumferential direction and with horizontal axes pointing to the axis of the moving frame (1), the end surfaces of the horizontal columns (20) located on the inner side of the moving frame (1) are fixedly provided with U-shaped blocks (21) with openings facing the tower section, the U-shaped blocks (21) are provided with climbing wheels (22) which are rotatably arranged by a rotating column, and the climbing unit (2) further comprises a locking group (23) for locking the climbing wheels (22); A guiding mechanism (3) is commonly provided on the upper and lower moving frames (1), and the guiding mechanism (3) comprises a plate frame (30), and four plate frames (30) distributed in a matrix are fixedly provided on opposite back surfaces of the two moving frames (1), and guiding columns (300) with vertical axes are fixedly provided on the upper and lower end surfaces of the upper plate frame (30), and guiding cylinders (301) with vertical axes are fixedly provided on the upper and lower end surfaces of the lower plate frame (30), and the opening of the guiding cylinder (301) is chamfered; The guiding mechanism (3) further comprises an auxiliary unit (4), the two moving frames (1) are jointly provided with an auxiliary unit (4) for assisting the guiding process, the auxiliary unit (4) comprises a clamping plate (40), the moving frame (1) is provided with two groups of plate groups which are symmetrical left and right, the plate groups comprising two vertically distributed and arc-shaped clamping plates (40), the inner arc surface of the clamping plate (40) facing the tower section; It also includes a bonding plate (322), and guide plates (33) are fixedly arranged on both front and rear end surfaces of the bonding plate (322); The fitting plate (322) is closely attached to the stairs, and is pressed against the stairs by the mutual cooperation of the rectangular sections of the two guide plates (33).

2. The hoisting equipment for installing a power tower according to claim 1, characterized in that: The locking group (23) comprises a spring (230), a spring (230) sleeved on the corresponding horizontal column (20) is fixedly arranged between the U-shaped block (21) and the corresponding moving frame (1), an arc strip (231) is symmetrically slidably arranged on the outer arc surface of the moving frame (1), an L-shaped locking block (232) corresponding to the horizontal column (20) is fixedly arranged on the end surface of the arc strip (231) facing the adjacent horizontal column (20), a horizontal section of the locking block (232) is chamfered at the end surface close to the horizontal column (20), a locking groove (233) is provided on the horizontal column (20), and the direction of the locking groove (233) from the U-shaped block (21) to the arc strip (231) is a triangular section and a rectangular section, and the inclined surface of the triangular section of the locking groove (233) faces the corresponding locking block (232).

3. The hoisting equipment for installing a power tower according to claim 1, characterized in that: The auxiliary unit (4) further comprises a hinge bar (41), and the upper and lower end surfaces of the movable frame (1) are both hingedly provided with two hinge bars (41) which are symmetrical on both sides and hinged to the corresponding clamping plates (40). The movable frame (1) is rotatably penetrated by a threaded rod (410) with two horizontal axes pointing to the axis of the movable frame (1). The threaded rod (410) is located between the two corresponding upper and lower hinge bars (41). A rectangular block (411) is threadedly sleeved on the threaded rod (410), and a driving bar (412) is hingedly installed between the rectangular block (411) and the corresponding hinge bar (41).

4. The hoisting equipment for installing a power tower according to claim 3, characterized in that: The auxiliary unit (4) further comprises a gear (413), the end surface of the threaded rod (410) away from the rectangular block (411) is fixedly provided with the gear (413), and the outer arc surface of the mobile frame (1) is slidably provided with two left-right symmetrical and arc-shaped tooth plates (414) through the connecting block, and the tooth plates (414) are meshed with adjacent gears (413).

5. The hoisting equipment for installing a power tower according to claim 4, characterized in that: The auxiliary unit (4) further comprises a spiral spring (415), a spiral spring (415) located between the corresponding gear (413) and the mobile frame (1) is commonly provided between the mobile frame (1) and the threaded rod (410), two left-right symmetrical supporting rope members (416) are fixedly provided on opposite sides of the two mobile frames (1) through a connecting block, a rope (417) is commonly fixedly provided between two tooth plates (414) on the same mobile frame (1), and the rope (417) passes through the two supporting rope members (416) on the same mobile frame (1), arc-shaped pushing rope plates (418) are fixedly provided on the upper and lower end surfaces of the mobile frame (1) through a connecting frame, and the two pushing rope plates (418) on the same mobile frame (1) are symmetrical in the upper and lower directions and their inner arc surfaces are opposite to each other, and the connecting frames on the two mobile frames (1) are staggered left and right.

6. The hoisting equipment for installing a power tower according to claim 1, characterized in that: A guide block (42) is fixedly arranged on the front end surface of the upper connecting frame of the upper moving frame (1) through a fixing block 1, and a guide plate (420) is fixedly arranged on the front end surface of the upper connecting frame of the lower moving frame (1) through a fixing block 2. A guide groove (421) is provided on the guide plate (420), and the guide groove (421) penetrates the upper and lower end surfaces of the corresponding guide plate (420). From left to right, the guide groove (421) is sequentially an isosceles trapezoid with a small diameter section facing right and a rectangular section cooperating with the guide plate (420), and the upper and lower ends of the guide groove (421) are both chamfered.

7. The hoisting equipment for installing a power tower according to claim 1, characterized in that: The guiding mechanism (3) further comprises a docking column (31), and the end surface of the clamping plate (40) on the upper side of the movable frame (1) away from the movable frame (1) is fixedly provided with a docking column (31), and the clamping plate (40) on the lower side of the movable frame (1) is provided with a docking groove (310) which cooperates with the docking column (31).

8. The hoisting equipment for installing a power tower according to claim 3, characterized in that: The guide mechanism (3) further comprises a side plate (32), and two symmetrical side plates (32) are fixedly arranged on opposite sides of the two movable frames (1), a sliding column (320) with an axis extending from left to right is slidably penetrated on the side plate (32), and a fitting plate (322) is fixedly arranged on opposite sides of two adjacent sliding columns (320) on the left and right.

9. The hoisting equipment for installing a power tower according to claim 8, characterized in that: The two guide plates (33) on the same laminating plate (322) are symmetrical to each other, and the two guide plates (33) opposite to each other are symmetrical to each other. The guide plate (33) on the left front side is composed of a rectangular section and an inclined section from left to right, and the inclined section is inclined forward from left to right.

10. The hoisting equipment for installing a power tower according to claim 8, characterized in that: The guiding mechanism (3) further comprises a pushing frame (34), the pushing frame (34) being fixedly arranged on the rectangular block (411), a pushing plate (340) being fixedly arranged on the pushing frame (34), the pushing plate (340) being slidably sleeved on an adjacent sliding column (320), a mounting plate (341) being fixedly sleeved on the sliding column (320) and being located between the fitting plate (322) and the pushing plate (340), and a second spring (342) sleeved on the sliding column (320) being fixedly arranged between the mounting plate (341) and the pushing plate (340).