Construction technology for pulling PE pipe in engineering pipeline

By utilizing liquid buoyancy and sealing pull head, combined with the limiting mechanism, the suspension traction of PE pipes in the engineering pipeline is realized, solving the problems of installation complexity and offset in the prior art, and improving construction convenience and efficiency.

CN119146272APending Publication Date: 2024-12-17HONG KONG CHINA CONSTR DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411159876.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-12-17

AI Technical Summary

Technical Problem

In the prior art, when laying engineering pipelines underground, there are problems such as inconvenient disassembly of track installation, difficult to fix the guide wheels, and easy to deviate during the installation process of PE pipes.

Method used

The PE pipe is suspended or floated in the engineering pipeline by using the buoyancy of liquid, and used to pull the traction head and traction rope to reduce the track installation and guide wheel fixing process, and prevent deviation through the limiting mechanism.

Benefits of technology

The construction process of PE pipes is simplified, the convenience is improved, the installation complexity and error are reduced, and the construction efficiency is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119146272A_ABST
    Figure CN119146272A_ABST
Patent Text Reader

Abstract

The invention provides a construction technology for pulling a PE pipe in an engineering pipeline, and relates to the technical field of pipeline construction engineering. Comprising the steps that the front end of a to-be-dragged PE pipe is sealed through a sealing traction head and then placed in an engineering pipeline, and the rear end of the to-be-dragged PE pipe is clamped to the inner side wall of the engineering pipeline through a limiting mechanism; a traction rope transversely penetrates through the engineering pipeline, one end of the traction rope is located outside the engineering pipeline and connected with a power mechanism, and the other end of the traction rope is located inside the engineering pipeline and connected with a sealing traction head; liquid is injected into the engineering pipeline, so that the to-be-dragged PE pipe floats in the liquid; and the power mechanism is started, the traction rope is pulled through the power mechanism, the PE pipe floating in the liquid is pulled by the traction rope to move forwards, and traction is completed. By the adoption of the device, the front end of the PE pipe can suspend or float in liquid of an engineering pipeline through buoyancy of the liquid, the PE pipe is pulled to move forwards through the pulling rope, the working procedures of rail installation, guide wheel fixing and the like are omitted, and construction is more convenient and faster.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pipeline construction engineering, and in particular to a construction process for pulling a PE pipe in an engineering pipeline. Background Art

[0002] In the prior art, after the engineering pipeline is laid underground, the PE pipe needs to be passed through the engineering pipeline for installation. In the prior art, most of the PE pipes are fixed and pulled forward using guide rails / guide wheels. This technology has the steps of track installation and guide wheel fixing. The track is inconvenient to disassemble after installation, and the guide wheel is not easy to fix and is prone to deviation. Summary of the invention

[0003] The purpose of the present invention is to provide a construction process for towing a PE pipe in an engineering pipeline, which can utilize the buoyancy of the liquid to make the front end of the PE pipe suspend or float in the liquid of the engineering pipeline. The front end of the PE pipe is sealed with a sealed traction head and is towed forward by a traction rope, thereby reducing the processes of track installation, guide wheel fixing, etc., and the construction is more convenient.

[0004] The technical solution adopted by the present invention is:

[0005] The present application embodiment provides a construction process for pulling a PE pipe in an engineering pipeline, comprising:

[0006] The front end of the PE pipe to be pulled is sealed with a sealing pulling head and then placed in the engineering pipeline. The rear end of the PE pipe to be pulled is clamped to the inner wall of the engineering pipeline through a limiting mechanism to prevent the PE pipe from deviating relative to the engineering pipeline when pulling the PE pipe;

[0007] A traction rope is passed through the engineering pipeline, one end of the traction rope is located outside the engineering pipeline and connected to the power mechanism, and the other end of the traction rope is located inside the engineering pipeline and connected to the sealing traction head;

[0008] Inject liquid into the engineering pipeline so that the PE pipe to be pulled floats in the liquid;

[0009] The power mechanism is started, and the traction rope is pulled by the power mechanism, so that the PE pipe floating on the liquid is pulled forward by the traction rope to complete the traction.

[0010] Furthermore, in some embodiments of the present invention, the front end of the PE pipe to be pulled is sealed with a sealing pulling head and then placed in the engineering pipeline. Specifically, the front end 10-20 meters of the PE pipe to be pulled is placed in the engineering pipeline.

[0011] Furthermore, in some embodiments of the present invention, the sealing traction head is partially embedded in the front end of the PE pipe to be pulled to achieve sealing, and the sealing traction head is fixed by passing through the PE pipe through fixing bolts and being threadedly connected with the sealing traction head.

[0012] Furthermore, in some embodiments of the present invention, the liquid includes water or mud.

[0013] Furthermore, in some embodiments of the present invention, the power mechanism includes a power locomotive.

[0014] Furthermore, in some embodiments of the present invention, the limiting mechanism includes a limiting clamp and a plurality of telescopic components circumferentially spaced along the outer wall of the limiting clamp, the limiting clamp is located inside the engineering pipeline, the telescopic components abut against the inner wall of the engineering pipeline, and the PE pipe slides through the limiting clamp.

[0015] Furthermore, in some embodiments of the present invention, the telescopic assembly includes a base fixed to the outer wall of the limiting clamp and a fixed sleeve fixed to the base, and the fixed sleeve is threadedly connected with a screw; one end of the screw is located in the fixed sleeve, and the other end of the screw is located outside the fixed sleeve and is provided with a pad, which abuts against the inner wall of the engineering pipeline.

[0016] Compared with the prior art, the embodiments of the present invention have at least the following advantages or beneficial effects:

[0017] The embodiment of the present invention provides a construction process for pulling a PE pipe in an engineering pipeline, comprising:

[0018] The front end of the PE pipe to be pulled is sealed with a sealing pulling head and then placed in the engineering pipeline. The rear end of the PE pipe to be pulled is clamped to the inner wall of the engineering pipeline through a limiting mechanism to prevent the PE pipe from deviating relative to the engineering pipeline when pulling the PE pipe;

[0019] A traction rope is passed through the engineering pipeline, one end of the traction rope is located outside the engineering pipeline and connected to the power mechanism, and the other end of the traction rope is located inside the engineering pipeline and connected to the sealing traction head;

[0020] Inject liquid into the engineering pipeline so that the PE pipe to be pulled floats in the liquid;

[0021] The power mechanism is started, and the traction rope is pulled by the power mechanism, so that the PE pipe floating on the liquid is pulled forward by the traction rope to complete the traction.

[0022] It can use the buoyancy of the liquid to make the front end of the PE pipe suspend or float in the liquid of the engineering pipeline. The front end of the PE pipe is sealed with a sealed traction head and pulled forward by a traction rope, which reduces the processes of track installation, guide wheel fixing, etc., and makes construction more convenient. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0024] Figure 1 A partial cross-sectional view of the installation structure provided by an embodiment of the present invention;

[0025] Figure 2 A side view of a limiting mechanism provided in an embodiment of the present invention;

[0026] Figure 3 A cross-sectional view of a telescopic assembly provided in an embodiment of the present invention.

[0027] Icons: 1-engineering pipeline; 2-PE pipe; 3-sealed traction head; 4-traction rope; 5-liquid; 6-fixing bolt; 7-limiting clamp; 8-base; 9-fixing sleeve; 10-screw; 11-pad. DETAILED DESCRIPTION

[0028] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0029] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0030] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0031] In the description of the embodiments of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, or are the orientation or position relationship in which the product of the invention is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", etc., if used, are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0032] In addition, the use of terms such as "horizontal" and "vertical" does not mean that the components must be absolutely horizontal or vertical, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0033] In the description of the embodiments of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "setting" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0034] Example

[0035] Please refer to Figure 1-Figure 3 This embodiment provides a construction process for pulling a PE pipe in an engineering pipeline, including:

[0036] The front end of the PE pipe 2 to be pulled is sealed with the sealing pulling head 3 and then placed in the engineering pipeline 1. Specifically, the front end 10-20 meters of the PE pipe 2 to be pulled is placed in the engineering pipeline 1. The rear end of the PE pipe 2 to be pulled is clamped to the inner wall of the engineering pipeline 1 through a limiting mechanism to prevent the PE pipe 2 from deviating relative to the engineering pipeline 1 when pulling the PE pipe 2;

[0037] A traction rope 4 is passed through the engineering pipeline 1, one end of which is located outside the engineering pipeline 1 and connected to a power mechanism, which includes a power locomotive. The other end of the traction rope 4 is located inside the engineering pipeline 1 and connected to a sealed traction head 3;

[0038] Inject liquid 5 into the engineering pipeline 1. The liquid 5 in this embodiment includes water, mud, etc., so that the PE pipe 2 to be pulled floats in the liquid 5.

[0039] The power mechanism is started, and the traction rope 4 is pulled by the power mechanism, so that the PE pipe 2 floating on the liquid 5 is pulled forward by the traction rope 4 to complete the traction.

[0040] The sealing traction head 3 of this embodiment is partially embedded in the front end of the PE pipe 2 to be pulled to achieve sealing. The sealing traction head 3 passes through the PE pipe 2 and is threadedly connected with the sealing traction head 3 to achieve fixation.

[0041] When the PE pipe 2 is actually pulled, the buoyancy of the liquid is used to suspend or float the front end of the PE pipe in the liquid of the engineering pipeline. The front end of the PE pipe is sealed with a sealing traction head and pulled forward by a traction rope, which reduces the processes of track installation and guide wheel fixing, making the construction more convenient. The rear section of the PE pipe is fixed outside and fixed in position by a limiting mechanism to prevent deviation, so as to facilitate the connection of a new PE pipe at the rear end of the PE pipe.

[0042] like Figure 1-Figure 3 As shown, in some embodiments of the present invention, the limiting mechanism includes a limiting clamp ring 7 and a plurality of telescopic components arranged at intervals along the outer wall of the limiting clamp ring 7 in the circumferential direction. The limiting clamp ring 7 is located inside the engineering pipeline 1, and the telescopic components abut against the inner wall of the engineering pipeline 1, and the PE pipe 2 slides through the limiting clamp ring 7. The telescopic component includes a base 8 fixed to the outer wall of the limiting clamp ring 7 and a fixed sleeve 9 fixed to the base 8, and the fixed sleeve 9 is threadedly connected with a screw 10; one end of the screw 10 is located in the fixed sleeve 9, and the other end of the screw 10 is located outside the fixed sleeve 9 and is provided with a pad 11, and the pad 11 abuts against the inner wall of the engineering pipeline 1.

[0043] The present invention provides a limiting clamp ring 7 and a telescopic assembly, and the inner diameter of the limiting clamp ring 7 is slightly larger than the outer diameter of the PE pipe 2, so that the PE pipe 2 can pass through the limiting clamp ring 7 and slide, and the limiting clamp ring 7 can limit the PE pipe 2 to prevent the PE pipe 2 from deviating relative to the engineering pipeline 1 when the PE pipe 2 is pulled. When installing the limiting mechanism, each screw rod 10 can be rotated according to the actual interval, and the position of the pad 11 at the end of the screw rod 10 can be adjusted by sliding the screw rod 10 relative to the fixed sleeve 9, so that the pad 11 is tightly against the inner wall of the engineering pipeline 1, so that the limiting mechanism is conveniently fixed to the inner wall of the engineering pipeline 1.

[0044] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. It is obvious to those skilled in the art that the present application is not limited to the details of the above exemplary embodiments, and the present application can be implemented in other specific forms without departing from the spirit or basic features of the present application.

[0045] Therefore, no matter from which point of view, the embodiments should be regarded as illustrative and non-restrictive, and the scope of the present application is limited by the appended claims rather than the above description, and it is intended that all changes that fall within the meaning and scope of the equivalent elements of the claims are included in the present application. Any figure mark in the claims should not be regarded as limiting the claims involved. For those skilled in the art, the present invention can have various changes and variations. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A construction process for pulling a PE pipe in an engineering pipeline, characterized in that: include The front end of the PE pipe to be pulled is sealed with a sealing pulling head and then placed in the engineering pipeline. The rear end of the PE pipe to be pulled is clamped to the inner wall of the engineering pipeline through a limiting mechanism to prevent the PE pipe from deviating relative to the engineering pipeline when pulling the PE pipe; A traction rope is passed through the engineering pipeline, one end of the traction rope is located outside the engineering pipeline and connected to the power mechanism, and the other end of the traction rope is located inside the engineering pipeline and connected to the sealing traction head; Inject liquid into the engineering pipeline so that the PE pipe to be pulled floats in the liquid; The power mechanism is started, and the traction rope is pulled by the power mechanism, so that the PE pipe floating on the liquid is pulled forward by the traction rope to complete the traction.

2. A construction process for pulling a PE pipe in an engineering pipeline according to claim 1, characterized in that: The front end of the PE pipe to be pulled is sealed with a sealing pulling head and then placed in the engineering pipeline. Specifically, the front end 10-20 meters of the PE pipe to be pulled is placed in the engineering pipeline.

3. A construction process for pulling a PE pipe in an engineering pipeline according to claim 1, characterized in that: The sealing traction head is partially embedded in the front end of the PE pipe to be pulled to achieve sealing, and the sealing traction head passes through the PE pipe through a fixing bolt and is threadedly connected with the sealing traction head to achieve fixing.

4. A construction process for pulling a PE pipe in an engineering pipeline according to claim 1, characterized in that: The liquid includes water and mud.

5. The construction process for pulling a PE pipe in an engineering pipeline according to claim 1 is characterized in that: The power mechanism includes a power locomotive.

6. A construction process for pulling a PE pipe in an engineering pipeline according to claim 1, characterized in that: The limiting mechanism includes a limiting clamp and a plurality of telescopic components arranged at circumferential intervals along the outer wall of the limiting clamp. The limiting clamp is located inside the engineering pipeline, the telescopic component abuts against the inner wall of the engineering pipeline, and the PE pipe slides through the limiting clamp.

7. A construction process for pulling a PE pipe in an engineering pipeline according to claim 6, characterized in that: The telescopic assembly includes a base fixed to the outer wall of the limiting clamp and a fixed sleeve fixed to the base, and the fixed sleeve is threadedly connected with a screw; one end of the screw is located in the fixed sleeve, and the other end of the screw is located outside the fixed sleeve and is provided with a pad, and the pad abuts against the inner wall of the engineering pipeline.