Floating control type cross-sea bridge
Through the design of the floating-controlled cross-sea bridge, the floating-controlled weight body and floating box structure settled on the seabed, and the tower columns supported the pavement flat beams, solving the problems of complex geology and sea surface wind and waves in the seabed, achieving the shortening of construction costs and construction periods, and improving the construction cost and construction period. The wind resistance and design reliability of the bridge body are achieved.
Patent Information
- Application Number
- CN202411278354.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-12-31
AI Technical Summary
The existing cross-sea bridges have problems such as complex geological conditions under the seabed and strong winds and waves on the sea surface.
Designed with a floating-controlled cross-sea bridge, the floating-controlled weight body and floating box structure settle at the seabed. The floating-controlled box position is controlled by a floating-controlled tie rod, the tower column supports the pavement flat beams, and additional support is provided through the clamped tie rod, using hot-rolled seamless Steel pipe material to improve wind resistance and reduce wind resistance coefficient.
It effectively solves the complex geology and sea surface wind and wave problems, shortens the construction period and cost, and improves the wind resistance of the bridge, design reliability and corrosion resistance, and has a running time of more than a hundred years.
Smart Images

Figure CN119221364A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of bridges, and in particular to a controlled floating sea-crossing bridge. Background Art
[0002] Existing cross-sea bridges are mostly built with reinforced concrete, which are large in size, heavy in weight, and have a large wind resistance coefficient. They can neither adapt to the complex geological conditions of the seabed nor to the natural environment such as strong winds and waves on the sea surface. They require a large amount of work, high construction costs, and a long construction period. Summary of the invention
[0003] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a bridge foundation that avoids complex geological conditions such as deep seabed, trenches, earthquakes, etc., and improves the ability of the bridge body on the sea surface to resist strong winds and waves, and is not affected by the sea depth within a certain range. The bridge body does not require concrete. The main materials used are steel pipes, towers, pillars, and flat beams. It is a controlled floating cross-sea bridge with the advantages of high strength, small volume, and low wind resistance coefficient.
[0004] The device includes a buoyancy control weight, which has a counterweight and is set at the seabed level when in use; The buoyancy control weight is connected with a buoyancy box via a buoyancy control pull rod; A tower column is arranged on the pontoon, a road surface flat beam is arranged on the tower column, and a plurality of inclined tie rods are arranged in an array between the road surface flat beam and the tower column.
[0005] The effect achieved in this way is that the buoyant weight sinks to the seabed level, and the pontoon is controlled to be below the sea surface by the buoyant control rod. The tower column on its upper part serves as a supporting member to support the pavement flat beam, and a plurality of inclined rods are arranged between the pavement flat beam and the tower column to pull the pavement flat beam, so that the pavement flat beam can be used as a direct support for the means of passage for the passage of vehicles.
[0006] The beneficial effects of the present invention are as follows: the present invention solves the problems of deep sea, complex seabed geological conditions, strong winds and waves on the sea surface, etc. of cross-sea bridges, and reduces and shortens the cost and construction period of bridge construction. It can greatly shorten the construction period and construction cost; and because the present invention has advanced design and reliable anti-corrosion technology, the operation time is not less than 100 years. It is applicable to many coastal straits, bays, and offshore islands, and has huge economic and social benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0007] Figure 1 It is a schematic diagram of the cross-sectional structure of a controlled floating sea-crossing bridge according to the present invention; Figure 2 It is a structural schematic diagram of an implementation method of a controlled floating cross-sea bridge according to the present invention; Figure 3 This is a schematic diagram of the structure of the power supply organization Figure 4 It is a structural diagram of the anchorage tie rod joint; Figure 5 It is a schematic diagram of the structure of the power line protection device configuration; Figure 6 It is a partial structural schematic diagram of a preferred embodiment; Figure 7 It is a schematic diagram of the local position relationship structure from a bird's-eye view; Reference numerals: 1-tower column 2-isolation platform 3-anchorage tie rod adjustable joint 4-cross tie rod 5-floating box 6-tension sleeve 7-floating control tie rod 8-tie rod joint 9-floating control weight 10-anchorage gear ring 11-seabed level 12-lightning rod 13-tower top interconnection 14-power line rack 15-rail 16-I-beam 17-anchor tie rod 18-drain pipe 19-anchor weight 20-pavement flat beam 21-diagonal tie rod 22-connecting flange 23-screw Cap 24-exhaust plate 25-brush 26-pantograph 27-torsion spring 28-pantograph support 29-power line 30-passing vehicle 31-upper end plate of inclined tie rod 32-tap thread at the end of tie rod 33-upper inclined tie rod joint 34-lower inclined tie rod joint 35-adjusting nut 36-lower end plate of inclined tie rod 37-support insulator 38-connecting plate 39-right power line 40-bolt 41-left power line 42-anti-collision device 43-buoy rod The realization of the purpose, functional features and advantages of the present invention will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0008] Reference Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 and Figure 7 The floating cross-sea bridge of the present invention comprises a floating weight body 9, wherein the floating weight body 9 has a counterweight and has sufficient weight. When in use, the floating weight body 9 is arranged on the seabed level 11; The buoyancy control weight 9 is connected with a buoyancy box 5 via a buoyancy control pull rod 7; The pontoon 5 is provided with a tower column 1, and a road surface beam 20 is provided on the tower column 1. A plurality of inclined rods 21 are arranged in an array between the road surface beam 20 and the tower column 1, so as to ensure the stability of the bridge body.
[0009] The effect achieved in this way is that the buoyancy-controlled weight 9 sinks to the seabed level 11, and the pontoon 5 is controlled below the sea level by the buoyancy-controlled pull rod 7. The tower column 1 on the top serves as a support member to support the pavement beam 20, and a plurality of inclined pull rods 21 are arranged between the pavement beam 20 and the tower column 1 for pulling the pavement beam 20, so that the pavement beam 20 can be used as a direct support for the means of transportation for the passage of the means of transportation.
[0010] Furthermore, each buoyancy box 5 is equipped with at least three buoyancy control weights 9 , which are arranged at intervals and connected to the buoyancy box 5 via a buoyancy control rod 7 .
[0011] Preferably, the buoyancy tank 5 is arranged at a position 6-7 meters below the sea level.
[0012] The effect achieved in this way is that the location is less affected by the waves and is not constrained by the complex geological conditions of the seabed. The structure is simplified, there are no changes in bridges, islands, and tunnels, and there are no unforeseen projects. Relevant components can use standard parts to facilitate quantitative production. Construction is only an "assembly" process, which greatly shortens the construction period and significantly reduces the cost.
[0013] In this way, the weight support structure of the bridge is not located at a great depth or under complex geological conditions, but on a pontoon 6-7 meters below the sea surface that is not affected by wind and waves. The pontoon is connected to the buoyancy control weight that is sunk to the seabed through a tie rod; Preferably, each buoyancy control weight 9 is connected to the buoyancy box 5 via at least four buoyancy control rods 7 .
[0014] The effect achieved by this is to ensure the stability of the buoyancy box 5.
[0015] Furthermore, the bottom surface of the control buoyancy weight 9 is provided with an anchorage gear ring 10, and the anchorage gear ring 10 is in the form of a fence provided around the bottom surface of the control buoyancy weight 9; A drainage pipe 18 is provided on the buoyancy-controlling weight 9 . The drainage pipe 18 is connected to the inner cavity of the anchor gear ring 10 , and a one-way valve is provided in the drainage pipe 18 .
[0016] The effect achieved by this is that after the water in the gear ring is extracted, the negative pressure generated helps press the gear ring into the seabed formation, making the anchor body more stable. That is, the anchor ground gear ring 10 is clamped into the seabed formation to ensure the stability of the buoyancy control weight 9.
[0017] Furthermore, the tower columns 1 are arranged in a tic-tac-toe pattern, with a plurality of them being arranged in a uniform array, and cross tie bars 4 are arranged between the tower columns 1 to ensure the service strength of the tower columns 1 .
[0018] Furthermore, an isolation platform 2 is provided on the side of the pavement flat beam 20 .
[0019] Preferably, the isolation platform 2 is a safety facility for up and down vehicles, and an anti-glare plate can be set on it; there is an isolation platform 2 on each side of the bridge body, which can be used as a sidewalk; there is also a safety handrail on the outside.
[0020] In order to improve the wind and wave resistance of the bridge deck, the main material of the bridge body is a hot-rolled seamless steel pipe with high strength, small volume, smooth exterior and low wind resistance coefficient.
[0021] Furthermore, a tension sleeve 6 is provided at the lower side of the buoyancy box 5, one end of the floating control rod 7 is fixedly provided on the tension sleeve 6, and the other end is provided on the floating control weight 9; The floating control rod 7 is formed by connecting multiple rod sections in sequence through a rod joint 8. The rod joint 8 includes the end of the rod. The rod joint 8 is threadedly connected to the tension sleeve 6 through a nut 23.
[0022] Furthermore, the inclined tie rod 21 includes an anchor tie rod 17, and an anchor tie rod adjustable joint 3 is provided at both ends thereof; The adjustable joint 3 of the anchor tie rod includes an upper joint and a lower joint, the upper joint includes an upper end plate 31 of the inclined tie rod, a tie rod end taper thread 32 is provided on the upper end plate of the lower tie rod, and an upper inclined tie rod joint 33 is threadedly connected in the taper thread of the tie rod end; the lower joint includes a lower end plate 36 of the inclined tie rod, an adjustment nut 35 is provided on the lower end plate 36 of the inclined tie rod, and the lower inclined tie rod joint 34 is threadedly connected in the adjustment nut 35.
[0023] Furthermore, a lightning rod 12 is provided on the tower column 1 , and a tower top interconnector 13 is provided between the tower columns 1 .
[0024] Preferably, a power line rack 14 , a steel rail 15 and an I-beam 16 are also provided on the road surface flat beam 20 .
[0025] The effect achieved by this is that more vehicles such as trains, trams, etc. can pass on the road surface beam 20.
[0026] Preferably, a power supply mechanism is also provided on the vehicle 30 passing through the pavement flat beam 20 , and the power supply mechanism includes a brush 25 , a pantograph 26 , a torsion spring 27 , a pantograph support 28 , a foreign object removal plate 24 , and a power line 29 .
[0027] Preferably, in order to improve the wind resistance of the bridge and save materials, the height of the transmission line rack is lowered to less than 1 meter, and the up and down vehicles use the same rack, with a corresponding power receiving device at the lower left bottom of the vehicle.
[0028] Preferably, the power cord is configured through a power cord protection device, and the power cord protection device includes a supporting insulator 37, on which two opposite connecting plates 38 are arranged, and a left power cord 41 and a right power cord 39 are respectively arranged in the connecting plates 38; and the supporting insulator 37 and the connecting plates 38 are encapsulated by bolts 40.
[0029] Furthermore, the pavement flat beams 20 are connected in sequence via connecting flanges 22 .
[0030] Furthermore, the road surface flat beam 20 is provided with an array of anti-collision devices 42 and anti-collision enclosures, and a buoy rod 43 is inserted in the anti-collision rod, and the buoy rod 43 is provided with a light source.
[0031] Preferably, regarding the anti-corrosion technology of this equipment, the material used is tung oil, which is a natural preservative with stable performance and durable anti-corrosion power. All metal parts of the bridge are coated with this oil. The outside is wrapped with double-sided glass cloth coated with tung oil, no less than two layers, one layer on the left and one layer on the right. In addition to coating the inside and outside of the pontoon 5, the metal parts need to be filled with inert gas before closing. The tie rod joint 8, dead corners and cracks are filled with water-resistant grease (such as sodium-based grease), and the outside is wrapped with glass cloth. The terminal is tied with stainless steel wire and coated with tung oil again.
[0032] Preferably, monitoring rooms are provided at both ends of the bridge to display changes in the air pressure in the pontoon 5 and abnormal phenomena in other parts of the bridge body in a timely manner so as to facilitate response.
[0033] The bridge deck height should meet the needs of large ships. The bridge deck should be straight, without ups and downs or bends. The length from the top dead point of the approach bridge to the bridge end should not be less than the length of the train set.
[0034] If there are reefs or shoals along the bridge route, the underwater part can be steel-concrete piers. The bridge deck should be kept straight and the anchor stabilization technology of the tower top or bridge body should remain unchanged.
[0035] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It is obvious to those skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and the present invention can be implemented in other specific forms without departing from the spirit or basic features of the present invention. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the present invention is defined by the attached claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention. Any figure mark in the claims should not be regarded as limiting the claims.
[0036] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A controlled floating cross-sea bridge, comprising a controlled floating weight, the controlled floating weight having its own counterweight, and the controlled floating weight being arranged at the seabed level when in use, characterized in that: The buoyancy control weight is connected with a buoyancy box via a buoyancy control pull rod; A tower column is arranged on the pontoon, a road surface flat beam is arranged on the tower column, and a plurality of inclined tie rods are arranged in an array between the road surface flat beam and the tower column.
2. A controlled floating sea-crossing bridge according to claim 1, characterized in that: Each buoyancy box is equipped with at least three buoyancy control weights, which are arranged at intervals and connected to the buoyancy box via a buoyancy control pull rod.
3. The controlled floating sea-crossing bridge according to claim 1, characterized in that: The bottom surface of the controlled buoyancy weight is provided with an anchorage gear ring, and the anchorage gear ring is in the form of a fence provided around the bottom surface of the controlled buoyancy weight; A drainage pipe is arranged on the buoyancy-controlling weight, the drainage pipe is connected to the inner cavity of the anchor ground gear ring, and a one-way valve is arranged in the drainage pipe.
4. The controlled floating sea-crossing bridge according to claim 1, characterized in that: The tower columns are arranged in a tic-tac-toe pattern, with a plurality of them arranged in a uniform array, and cross-tensioning bars are arranged between the tower columns.
5. The controlled floating sea-crossing bridge according to claim 1, characterized in that: An isolation platform is arranged on the side of the pavement flat beam.
6. The controlled floating cross-sea bridge according to claim 1, characterized in that: A tension sleeve is arranged on the lower side of the buoyancy box, one end of the floating control rod is fixedly arranged in the tension sleeve, and the other end is arranged in the floating control weight body; The floating control rod is formed by connecting multiple rod sections in sequence through a rod joint. The rod joint includes the end of the rod, and the rod joint is threadedly connected to the tension sleeve through a nut.
7. The controlled floating sea-crossing bridge according to claim 1, characterized in that: The inclined tie rod comprises an anchor tie rod, and an anchor tie rod adjustable joint is provided at both ends thereof; The anchor tie rod joint includes an upper joint and a lower joint, the upper joint includes an upper end plate of the inclined tie rod, a tie rod end taper thread is arranged on the upper end plate of the lower tie rod, and an inclined tie rod joint is threadedly connected in the taper thread of the tie rod end; the lower joint includes a lower end plate of the inclined tie rod, an adjustment nut is arranged on the lower end plate of the inclined tie rod, and the lower inclined tie rod joint is threadedly connected in the adjustment nut.
8. The controlled floating sea-crossing bridge according to claim 1, characterized in that: The tower columns are provided with lightning rods, and tower top interconnectors are provided between the tower columns.
9. The controlled floating cross-sea bridge according to claim 1, characterized in that: The pavement flat beams are connected in sequence via connecting flanges.
10. The controlled floating cross-sea bridge according to claim 1, characterized in that: The road surface flat beam is arrayed with anti-collision devices and anti-collision enclosures, and a buoy rod is inserted in the anti-collision rod, and a light source is arranged on the buoy rod.