Large-span steel structure diagonal bracing construction operation platform and construction method thereof

Through the hinged block drive and hydraulic cylinder system, the standing plate of the large-span steel structure obliquely supported construction operation platform can be folded or telescopic, solving the problems of large volume and poor lifting safety of the existing operating platform, and achieving convenient installation and safe construction.

CN119221682APending Publication Date: 2024-12-31甘肃省安装建设集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411506681.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-28
Publication Date
2024-12-31

AI Technical Summary

Technical Problem

The existing large-span steel structure oblique bracing construction operation platform is large in size, inconvenient installation, and there is a risk of slippage during lifting, and staff are prone to step on air, which lead to safety hazards.

Method used

The standing plate is folded or telescopic through the hinged block drive, and the lifting lugs and load-bearing block design is used, combined with hydraulic cylinders and threaded sleeve systems, the tightening and safe reinforcement of the operating platform is achieved, the use of bolts is reduced, and the convenience of installation and lifting is improved.

Benefits of technology

The size of the operating platform is reduced, which is easy to install and hoist, which improves the safety of staff and operation convenience, reduces installation time, and enhances construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119221682A_ABST
    Figure CN119221682A_ABST
Patent Text Reader

Abstract

The invention discloses a large-span steel structure diagonal bracing construction operation platform and a construction method thereof, and relates to the technical field of diagonal bracing construction operation platforms. The inclined strut part comprises an inclined strut body, lifting lugs fixed to the two sides of the inclined strut body, and bearing blocks evenly fixed to the two sides of the top of the inclined strut body; the operation platform component comprises a frame assembly arranged at the top of the inclined strut body, a rotating assembly arranged in the frame assembly, a driving assembly arranged at the bottom of the rotating assembly and a step assembly arranged at the bottom of the rotating assembly; the reinforcing component comprises a connecting rod assembly arranged on the top of the bearing block. The standing plate is indirectly driven by the hinge block to move, the standing plate is folded or stretched out and drawn back, when the standing plate is in a folded state, the size is small, installation is convenient, when the standing plate is in the folded state, workers are borne, normal operation is achieved, and the problem that an existing operation platform is large in size and not suitable for hoisting is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of diagonal brace construction operation platforms, and in particular relates to a large-span steel structure diagonal brace construction operation platform and a construction method thereof. Background Art

[0002] For steel structure equipment frames, the inter-column supports are generally set in an eight-shaped shape, located between the upper and lower beams, with a box-shaped structure or H-shaped steel in cross section, and connected by welding or high-strength bolts. When installing the inter-column supports, the on-site workers have no working surface for welding and other work, so an operating platform for workers is made according to demand.

[0003] The existing construction operation platform is relatively large in size, which is not only inconvenient to install, but also has the risk of accidental slipping during the hoisting process, which may cause harm to people on the ground. In addition, the existing construction operation platform is just a simple frame, and workers can easily step on empty space, which can cause danger.

[0004] To this end, we provide a large-span steel structure diagonal bracing construction operation platform and a construction method thereof to solve the above-mentioned problems. Summary of the invention

[0005] The purpose of the present invention is to provide a large-span steel structure diagonal brace construction operation platform and a construction method thereof. The standing board is indirectly moved by driving a hinge block so that the standing board can be folded or retracted. When the standing board is in a folded state, it is small in size and convenient for installation. When the standing board is in a folded state, it can carry workers and perform normal operations, thereby solving the problem that the existing operation platform is large in size and difficult to hoist.

[0006] In order to solve the above technical problems, the present invention is achieved through the following technical solutions:

[0007] The present invention is a large-span steel structure diagonal brace construction operation platform and a construction method thereof, comprising a diagonal brace component, including a diagonal brace body, hanging ears fixed on both sides of the diagonal brace body, and bearing blocks evenly fixed on both sides of the top of the diagonal brace body;

[0008] The operating platform component includes a frame assembly arranged at the top of the diagonal support body, a rotating assembly arranged inside the frame assembly, a driving assembly arranged at the bottom of the rotating assembly, and a ladder assembly arranged at the bottom of the rotating assembly;

[0009] The reinforcing component includes a connecting rod assembly arranged on the top of the bearing block, a receiving assembly arranged inside the connecting rod assembly, a fixing assembly arranged inside the receiving assembly, and a receiving assembly arranged on the top of the step assembly.

[0010] The present invention is further configured such that the frame assembly includes a mounting frame arranged on the inner side of the upper lifting ear, a reinforcing rod for reinforcing the mounting frame, and a fixing frame arranged at the bottom of the mounting frame.

[0011] The present invention is further configured such that the rotating assembly includes a fixed plate arranged inside the fixed frame, a base plate arranged at the bottom of the fixed plate, a connecting shaft arranged at the top of the base plate corresponding to both sides of the fixed plate, and a supporting spring arranged between the fixed plate and the base plate.

[0012] The present invention is further configured such that the driving assembly includes an articulated block arranged on one side of the fixed frame, a hydraulic cylinder arranged inside the articulated block, a connecting cross rod arranged at the driving end of the hydraulic cylinder, a connecting rod sleeved on the outside of the connecting cross rod, a connecting rod arranged at the other end of the connecting rod, and a fixed rod arranged at the other end of the connecting rod.

[0013] The present invention is further configured such that the step assembly includes a connecting plate arranged inside the fixed frame, a first rotating rod arranged on the opposite side of the connecting plate, a standing plate arranged at the end of the first rotating rod, and a second rotating rod arranged at the midline of both sides of the standing plate.

[0014] The present invention is further configured such that the connecting rod assembly includes a lap cross bar arranged on the top of the bearing block, a threaded sleeve arranged at the bottom of both sides of the lap cross bar, a connecting sleeve arranged at the bottom end of the threaded sleeve, and a screw arranged at the top end of the connecting sleeve.

[0015] The present invention is further configured such that the accommodating assembly comprises an accommodating hole opened inside the connecting sleeve, a through hole penetrating inside the accommodating hole, and the through hole penetrates the side wall of the connecting sleeve;

[0016] The fixing assembly includes a connecting wedge block arranged inside the through hole, a moving rod arranged at the opposite end of the connecting wedge block, and the other end of the moving rod extends to the outside of the connecting sleeve, a return spring sleeved on the outer wall of the moving rod, and a baffle arranged at the end of the moving rod.

[0017] The present invention is further configured such that the receiving assembly includes a base arranged on the top of the standing board, a guide rod arranged on the top of the base, a moving block sleeved on the outer wall of the guide rod, and an end head arranged on the top of the guide rod, and a receiving groove opened inside the end head.

[0018] In addition, the present invention also provides the following technical solutions: a construction method of a large-span steel structure diagonal brace construction operation platform, wherein the large-span steel structure diagonal brace construction operation platform is implemented according to the following specific steps;

[0019] S1. First, the frame assembly is set up in the gap between the lifting ears, so that the frame assembly is set on the diagonal support body as a whole. Compared with the traditional platform, this design is more compact and convenient to use;

[0020] S2. Then start the hydraulic cylinder to drive the connecting vertical rod, and drive the first rotating rod to move through the connecting rod, so that the standing board is unfolded to facilitate the operation of the staff;

[0021] S3. The connecting rod assembly is then set at the top of the lifting lug, and then the distance between the connecting sleeve and the standing plate is adjusted by rotating the threaded sleeve;

[0022] S4. When the adjustment distance is appropriate, the connecting wedge block will be stuck at the bottom of the end to fix the standing board, making the standing board more stable to ensure the safety of the staff.

[0023] The present invention has the following beneficial effects:

[0024] 1. The present invention fixes the operating platform components as a whole through the lifting ears, so that the fixing of the operating platform components as a whole is more convenient, and does not need to use a large number of bolts for fixing, thus saving the time of the staff and improving the work efficiency.

[0025] 2. The present invention controls whether the standing board is unfolded by controlling the movement of the hinge block. When the standing board is in the unfolded state, the overall volume of the operating platform component is small, which is convenient for lifting. When the standing board is unfolded, multiple standing boards form a ladder, which is convenient for staff to operate.

[0026] 3. The present invention rotates the threaded sleeve to make the connecting sleeve sleeve on the outer wall of the base. Under the action of the end head, the connecting wedge block will be squeezed outward, and then the connecting sleeve continues to move downward. The connecting wedge block is stuck under the end head under the action of the return spring, thereby completing the reinforcement of the standing board and making the working environment of the staff safer.

[0027] Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for describing the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0029] Figure 1 It is a schematic diagram of the overall structure of the large-span steel structure diagonal bracing construction operation platform.

[0030] Figure 2This is a schematic diagram of the overall structure of the large-span steel structure diagonal bracing construction operation platform from another angle.

[0031] Figure 3 This is a schematic diagram of the overall structure of the operating platform components used in the large-span steel structure diagonal bracing construction operating platform.

[0032] Figure 4 It is a schematic diagram of the overall structure of the frame assembly for the operating platform parts.

[0033] Figure 5 It is a schematic diagram of the overall structure of the drive assembly for the operating platform components.

[0034] Figure 6 This is a schematic diagram of the partial structure of the standing board unfolded.

[0035] Figure 7 This is a schematic diagram of the overall structure of the reinforcement components used for the large-span steel structure diagonal bracing construction operation platform.

[0036] Figure 8 This is a schematic diagram of the cross-sectional structure of the receiving assembly for the reinforcement component.

[0037] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0038] 100, diagonal brace component; 101, diagonal brace body; 102, lifting ear; 103, bearing block; 200, operating platform component; 201, frame assembly; 201a, mounting frame; 201b, reinforcing rod; 201c, fixed frame; 202, rotating assembly; 202a, fixed plate; 202b, bottom plate; 202c, connecting shaft; 202d, supporting spring; 203, driving assembly; 203a, hinge block; 203b, hydraulic cylinder; 203c, connecting vertical rod; 203d, connecting rod; 203e, connecting cross rod; 203f, fixing rod; 204, ladder assembly; 204a, connecting plate; 204b, first rotating rod; 204c, second rotating rod; 204d, standing plate; 300, reinforcing component; 301, connecting rod assembly; 301a, overlapping cross bar; 301b, threaded sleeve; 301c, connecting sleeve; 301d, screw; 302, accommodating assembly; 302a, accommodating hole; 302b, through hole; 303, fixing assembly; 303a, connecting wedge block; 303b, moving rod; 303c, return spring; 303d, baffle; 304, receiving assembly; 304a, base; 304b, guide rod; 304c, moving block; 304d, end; 304e, accommodating groove. DETAILED DESCRIPTION

[0039] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0040] Example 1

[0041] See also Figure 1-6 The present invention is a large-span steel structure diagonal brace construction operation platform and a construction method thereof, comprising a large-span steel structure diagonal brace construction operation platform, characterized in that it comprises:

[0042] The diagonal brace component 100 includes a diagonal brace body 101, lifting ears 102 fixed on both sides of the diagonal brace body 101, and supporting blocks 103 evenly fixed on both sides of the top of the diagonal brace body 101; wherein, the lifting ears 102 are fixed on both sides of the top of the diagonal brace body 101, and the number is multiple to meet more lifting requirements. In addition, at the top of the diagonal brace body 101, multiple supporting blocks 103 are arranged between the lifting ears 102 on both sides for subsequent installation work.

[0043] The operating platform component 200 includes a frame assembly 201 arranged on the top of the diagonal support body 101, a rotating assembly 202 arranged inside the frame assembly 201, a driving assembly 203 arranged at the bottom of the rotating assembly 202, and a step assembly 204 arranged at the bottom of the rotating assembly 202; wherein, the frame assembly 201 is used to fix the rotating assembly 202, the driving assembly 203 and the step assembly 204, and the rotating assembly 202 can rotate to ensure that the angle of the step assembly 204 can be suitable for the inclination angle of the diagonal support body 101. In addition, the driving assembly 203 serves as a driving member of the step assembly 204, which can enable the step assembly 204 to unfold and assist the staff to complete the work.

[0044] Furthermore, the frame assembly 201 includes an installation frame 201a arranged on the inner side of the upper lifting ear 102, a reinforcing rod 201b for reinforcing the installation frame 201a, and a fixed frame 201c arranged at the bottom of the installation frame 201a, wherein the diameter of the installation frame 201a is the same as the gap between the bearing blocks 103, and can be well inserted and is not prone to shaking. In addition, by adding the reinforcing rod 201b, the rigidity of the installation frame 201a is increased to prevent the installation frame 201a from being deformed. Finally, the fixed frame 201c is fixed to the bottom of the reinforcing rod 201b.

[0045] Specifically, the rotating assembly 202 includes a fixed plate 202a arranged inside the fixed frame 201c, a bottom plate 202b arranged at the bottom of the fixed plate 202a, a connecting shaft 202c arranged at the top of the bottom plate 202b corresponding to the two sides of the fixed plate 202a, and a supporting spring 202d arranged between the fixed plate 202a and the bottom plate 202b, wherein the fixed plate 202a is fixed inside the fixed frame 201c, and the bottom plate 202b is arranged at the bottom of the fixed plate 202a, and the two are connected by the connecting shaft 202c, and the bottom plate 202b can rotate freely. In addition, the bottom plate 202b is designed in a T-shape, and the end face of the fixed plate 202a is arranged in an arc shape, so that the bottom plate 202b can rotate freely. In addition, by arranging a supporting spring 202d between the connecting shaft 202c and the bottom plate 202b, a large rotation range between the two is prevented to prevent shaking.

[0046] Furthermore, the driving assembly 203 includes an articulated block 203a disposed on one side of the interior of the fixed frame 201c, a hydraulic cylinder 203b disposed inside the articulated block 203a, a connecting cross bar 203e disposed at the driving end of the hydraulic cylinder 203b, a connecting rod 203d sleeved on the outside of the connecting cross bar 203e, a connecting rod 203d disposed at the other end of the connecting rod 203d, and a fixed rod 203f disposed at the other end of the connecting rod 203d, wherein the articulated block 203a is fixed to one side of the interior of the fixed frame 201c, and the hydraulic cylinder 203b is disposed inside the articulated block 203a, and the hydraulic cylinder 203e is disposed at the driving end of the hydraulic cylinder 203b. The hydraulic cylinder 203b is arranged at the other end of the hinge block 203a, and the two are hinged so that the hydraulic cylinder 203b can rotate freely. In addition, a connecting vertical rod 203c is connected to the driving end of the hinge block 203a, and a connecting cross rod 203e is connected to the center of the connecting vertical rod 203c. When the hydraulic cylinder 203b is driven, one end of the connecting vertical rod 203c will move, and a connecting rod 203d is connected to the other end of the connecting vertical rod 203c. Therefore, after the connecting rod 203d moves, it will drive the connecting rod 203d to move.

[0047] Furthermore, the ladder assembly 204 includes a connecting plate 204a arranged inside the fixed frame 201c, a first rotating rod 204b arranged on the opposite side of the connecting plate 204a, a standing plate 204d arranged at the end of the first rotating rod 204b, and a second rotating rod 204c arranged at the midline of both sides of the standing plate 204d, wherein the connecting plate 204a is fixed inside the fixed frame 201c, and the first rotating rod 204b and the first rotating rod 204b are rotatably connected to the opposite side of the connecting plate 204a, and the standing plate 204d at the other end of the first rotating rod 204b is rotatably connected, and the other end of the second rotating rod 204c is rotatably connected to the next standing plate 204d, and the center of the connecting vertical rod 203c is rotatably connected to the standing plate 204d.

[0048] The operation process of this embodiment is: first, use the installation frame 201a to set up the operating platform component 200 as a whole on the top of the diagonal support body 101 to complete the fixation of the operating platform component 200, and then start the hydraulic cylinder 203b to drive the connecting vertical rod 203c to move. Since the other end of the connecting vertical rod 203c is connected to the connecting rod 203d, the connecting rod 203d is driven to move under the action of the connecting vertical rod 203c. In the process of moving the connecting rod 203d, the first rotating rod 204b will be driven to move, and the standing board 204d will push the second rotating rod 204c to move. The first rotating rod 204b, the second rotating rod 204c and the standing board 204d cooperate with each other, so that multiple standing boards 204d can be fully unfolded to facilitate workers to operate and construct.

[0049] Example 2

[0050] See also Figure 1 , Figure 2 , Figure 7 and Figure 8 On the basis of Example 1, the reinforcement component 300 includes a connecting rod assembly 301 arranged on the top of the bearing block 103, a containing assembly 302 arranged inside the connecting rod assembly 301, a fixing assembly 303 arranged inside the containing assembly 302, and a receiving assembly 304 arranged on the top of the step assembly 204, wherein the connecting rod assembly 301 is mounted on the bearing block 103, and then the height of the containing assembly 302 is adjusted to make it sleeved on the outer wall of the receiving assembly 304, and then the fixing assembly 303 is used to clamp the receiving assembly 304, thereby completing the reinforcement of the standing board 204d.

[0051] Specifically, the connecting rod assembly 301 includes a lap cross bar 301a arranged on the top of the supporting block 103, a threaded sleeve 301b arranged at the bottom of both sides of the lap cross bar 301a, a connecting sleeve 301c arranged at the bottom of the threaded sleeve 301b, and a screw 301d arranged at the top of the connecting sleeve 301c, wherein the threaded sleeve 301b is fixed at both ends of the lap cross bar 301a, and the lap cross bar 301a and the threaded sleeve 301b are perpendicular to each other, and the lap cross bar 301a and the threaded sleeve 301b are threadedly connected, and the other end of the threaded sleeve 301b is threadedly connected to the connecting sleeve 301c through the screw 301d.

[0052] Furthermore, the accommodating assembly 302 includes an accommodating hole 302a opened inside the connecting sleeve 301c, a through hole 302b penetrating inside the accommodating hole 302a, and the through hole 302b penetrates the side wall of the connecting sleeve 301c;

[0053] The fixing assembly 303 includes a connecting wedge 303a disposed inside the through hole 302b, a moving rod 303b disposed at the opposite end of the connecting wedge 303a, and the other end of the moving rod 303b extends to the outside of the connecting sleeve 301c, a return spring 303c sleeved on the outer wall of the moving rod 303b, and a baffle 303d disposed at the end of the moving rod 303b, wherein the receiving hole 302a is opened at the bottom end of the connecting sleeve 301c, and the receiving hole 302a is penetrated by the through hole 302b. In addition, the other end of the threaded sleeve 301b passes through the connecting sleeve 301c, and a connecting wedge block 303a is arranged inside the accommodating hole 302a, and a moving rod 303b is fixed to the outward end of the connecting wedge block 303a, and a return spring 303c is sleeved on the outer wall of the moving rod 303b, which helps the connecting wedge block 303a to return to its original position. In addition, a moving rod 303b is fixed to the outward end of the moving rod 303b to prevent the moving rod 303b from sinking into the interior of the connecting sleeve 301c.

[0054] Furthermore, the receiving assembly 304 includes a base 304a disposed on the top of the standing plate 204d, a guide rod 304b disposed on the top of the base 304a, a moving block 304c sleeved on the outer wall of the guide rod 304b, and an end 304d disposed on the top of the guide rod 304b, and a receiving groove 304e opened inside the end 304d, wherein the base 304a is disposed directly below the connecting sleeve 301c, and the base 304a is fixedly connected to the standing plate 204d. A guide rod 304b is fixed at the top of the base 304a, and a moving block 304c is slidably connected to the outside of the guide rod 304b, an end head 304d is fixed at the top of the guide rod 304b, and a receiving groove 304e capable of receiving the guide rod 304b is provided at the bottom of the end head 304d, wherein the diameter of the end head 304d is the same as the diameter of the receiving hole 302a, and the diameter of the moving block 304c is slightly smaller than the diameter of the end head 304d and is the same as the diameter of the receiving groove 304e.

[0055] The operation process of this embodiment is as follows: when the standing plate 204d is fully unfolded, the connecting sleeve 301c is moved down by rotating the threaded sleeve 301b and is sleeved on the outside of the base 304a. During the descending process of the connecting sleeve 301c, the connecting wedge block 303a will expand outward due to the pressure of the end head 304d, and at the same time, the return spring 303c is deformed to generate elastic force. When the connecting wedge block 303a moves below the end head 304d, the connecting wedge block 303a will no longer be hindered. Therefore, under the action of the return spring 303c, the connecting wedge block 303a will return to its original position and be at the lower end surface of the end head 304d. At this time, the reinforcement of the standing plate 204d is completed, and then continue When the connecting sleeve 301c moves downward, the connecting wedge block 303a will first expand to both sides under the force of the moving block 304c. When the connecting wedge block 303a moves to the lower half of the moving block 304c, the connecting sleeve 301c is controlled to move upward, and the moving block 304c will be driven to move upward, and then the moving block 304c will enter the interior of the accommodating groove 304e. The connecting sleeve 301c continues to move upward, and under the action of the moving block 304c, the connecting wedge block 303a will move to the outside. Continuing to move upward, the connecting wedge block 303a will detach from the moving block 304c and contact the end 304d, thereby contacting the fixation of the standing plate 204d, completing the disassembly of the device, so that the device can be used repeatedly.

[0056] Example 3

[0057] See also Figure 1-8 , based on Example 1 and Example 2, S1. First, the frame assembly 201 is set in the gap between the lifting ears 102, so that the frame assembly 201 is set on the diagonal support body 101 as a whole. Compared with the traditional platform, this design is more compact and convenient to use;

[0058] S2. Then start the hydraulic cylinder 203b to drive the connecting vertical rod 203c, and drive the first rotating rod 204b to move through the connecting rod 203d, so that the standing board 204d is unfolded to facilitate the staff to work

[0059] S3. The connecting rod assembly 301 is then set at the top of the lifting lug 102, and then the distance between the connecting sleeve 301c and the standing plate 204d is adjusted by rotating the threaded sleeve 301b;

[0060] S4. When the adjustment distance is appropriate, the connecting wedge 303a will be stuck at the bottom of the end 304d, completing the fixation of the standing board 204d, making the standing board 204d more stable to ensure the safety of the staff.

[0061] The operation process of this embodiment is: first, use the installation frame 201a to set up the operating platform component 200 as a whole on the diagonal support body 101, and then start the hydraulic cylinder 203b to unfold the standing board 204d for the staff to stand and facilitate operation, and then rotate the threaded sleeve 301b to move the connecting sleeve 301c downward, so that the connecting wedge block 303a is stuck at the lower end surface of the end head 304d, thereby completing the reinforcement of the standing board 204d to prevent shaking. In addition, by controlling the connecting sleeve 301c to move downward first and then upward, the connecting wedge block 303a is no longer stuck at the lower end surface of the end head 304d, and the device is disassembled for reuse.

[0062] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0063] The preferred embodiments of the present invention disclosed above are only used to help illustrate the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. Large-span steel structure diagonal bracing construction operation platform, characterized by: include, The diagonal support component (100) comprises a diagonal support body (101), hanging ears (102) fixed on both sides of the diagonal support body (101), and bearing blocks (103) evenly fixed on both sides of the top of the diagonal support body (101); The operating platform component (200) comprises a frame assembly (201) arranged at the top of the diagonal support body (101), a rotating assembly (202) arranged inside the frame assembly (201), a driving assembly (203) arranged at the bottom of the rotating assembly (202), and a step assembly (204) arranged at the bottom of the rotating assembly (202); The reinforcing component (300) comprises a connecting rod assembly (301) arranged on the top of the bearing block (103), a receiving assembly (302) arranged inside the connecting rod assembly (301), a fixing assembly (303) arranged inside the receiving assembly (302), and a receiving assembly (304) arranged on the top of the step assembly (204).

2. The large-span steel structure diagonal bracing construction operation platform according to claim 1 is characterized in that: The frame assembly (201) comprises a mounting frame (201a) arranged on the inner side of the upper lifting ear (102), a reinforcing rod (201b) for reinforcing the mounting frame (201a), and a fixing frame (201c) arranged at the bottom of the mounting frame (201a).

3. The large-span steel structure diagonal bracing construction operation platform according to claim 2 is characterized in that: The rotating assembly (202) includes a fixed plate (202a) arranged inside the fixed frame (201c), a base plate (202b) arranged at the bottom of the fixed plate (202a), a connecting shaft (202c) arranged at the top of the base plate (202b) corresponding to both sides of the fixed plate (202a), and a supporting spring (202d) arranged between the fixed plate (202a) and the base plate (202b).

4. The large-span steel structure diagonal bracing construction operation platform according to claim 3 is characterized in that: The driving assembly (203) comprises an articulated block (203a) arranged on one side inside the fixed frame (201c), a hydraulic cylinder (203b) arranged inside the articulated block (203a), a connecting cross bar (203e) arranged at the driving end of the hydraulic cylinder (203b), a connecting rod (203d) sleeved on the outside of the connecting cross bar (203e), a connecting rod (203d) arranged at the other end of the connecting rod (203d), and a fixed rod (203f) arranged at the other end of the connecting rod (203d).

5. The large-span steel structure diagonal bracing construction operation platform according to claim 4 is characterized in that: The ladder assembly (204) comprises a connecting plate (204a) arranged inside the fixed frame (201c), a first rotating rod (204b) arranged on a side opposite to the connecting plate (204a), a standing plate (204d) arranged at the end of the first rotating rod (204b), and a second rotating rod (204c) arranged at the midline of both sides of the standing plate (204d).

6. The large-span steel structure diagonal bracing construction operation platform according to claim 5 is characterized in that: The connecting rod assembly (301) comprises a lap cross bar (301a) arranged on the top of the bearing block (103), a threaded sleeve (301b) arranged at the bottom of both sides of the lap cross bar (301a), a connecting sleeve (301c) arranged at the bottom end of the threaded sleeve (301b), and a screw (301d) arranged at the top end of the connecting sleeve (301c).

7. The large-span steel structure diagonal bracing construction operation platform according to claim 6 is characterized in that: The accommodating component (302) comprises an accommodating hole (302a) opened inside the connecting sleeve (301c), a through hole (302b) penetrating the inside of the accommodating hole (302a), and the through hole (302b) penetrates the side wall of the connecting sleeve (301c); The fixing assembly (303) includes a connecting wedge (303a) arranged inside the through hole (302b), a moving rod (303b) arranged at the opposite end of the connecting wedge (303a), and the other end of the moving rod (303b) extends to the outside of the connecting sleeve (301c), a return spring (303c) sleeved on the outer wall of the moving rod (303b), and a baffle (303d) arranged at the end of the moving rod (303b).

8. The large-span steel structure diagonal bracing construction operation platform according to claim 7 is characterized in that: The receiving assembly (304) includes a base (304a) arranged on the top of the standing board (204d), a guide rod (304b) arranged on the top of the base (304a), a moving block (304c) sleeved on the outer wall of the guide rod (304b), and an end (304d) arranged on the top of the guide rod (304b), and a receiving groove (304e) opened inside the end (304d).

9. The construction method of the large-span steel structure diagonal bracing construction operation platform is characterized in that: The large-span steel structure diagonal bracing construction operation platform described in any one of claims 1 to 8 is constructed according to the following steps; S1. First, the frame assembly (201) is set in the gap between the lifting ears (102), so that the frame assembly (201) is set on the diagonal support body (101) as a whole. Compared with the traditional platform, this design is more compact and easy to use; S2. Then start the hydraulic cylinder (203b) to drive the connecting vertical rod (203c), and drive the first rotating rod (204b) to move through the connecting rod (203d), so that the standing board (204d) is unfolded to facilitate the staff to work S3. The connecting rod assembly (301) is then set on the top of the lifting ear (102), and then the distance between the connecting sleeve (301c) and the standing plate (204d) is adjusted by rotating the threaded sleeve (301b); S4. When the adjustment distance is appropriate, the connecting wedge block (303a) will be stuck at the bottom of the end (304d), completing the fixation of the standing board (204d), making the standing board (204d) more stable to ensure the safety of the staff.