Installation method for combined structure of theme park laminated slab and cast-in-place frame beam

By setting up support frames and installing support templates in the theme park project, binding and penetrating frame beam reinforcement bars, the problem of repeated bending of the laminated plate ribs is solved, the construction steps are simplified, labor costs are saved and structural safety performance is improved.

CN119221718APending Publication Date: 2024-12-31SHANGHAI BAOYE GRP CORP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411691730.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-25
Publication Date
2024-12-31

AI Technical Summary

Technical Problem

In the theme park project, in the combined structure of the overlapping plate and cast-in-place frame beam, the overlapping plate ribs are repeatedly bent and cannot be fully restored, which affects the safety function of the structure and is limited in operating space, resulting in complex construction and increased labor costs.

Method used

By setting up roof or interlayer support frames, install cast-in-place beams and stacked plate support formwork, tie the steel bars at the bottom of the frame beam, hoist the laminated plates, and penetrate the waist and longitudinal bars, and finally pour concrete to ensure the correct construction operation space and steel bars. Position, avoid conflict and bends.

Benefits of technology

The lifting steps of laminated plates are simplified, labor costs are saved, the bending problem of laminated plate ribs is solved, and the safety performance of the structure is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119221718A_ABST
    Figure CN119221718A_ABST
Patent Text Reader

Abstract

The invention relates to an installation method for a combined structure of a laminated slab and a cast-in-place frame beam of a theme park. The installation method comprises the steps that firstly, a roof or interlayer supporting frame is erected, and a cast-in-place beam and a laminated slab supporting formwork are installed; 2, mounting and binding steel bars and stirrups at the bottoms of all frame beams on the roof or the interlayer top; thirdly, the laminated slab is hoisted; fourthly, frame column stirrups at beam-column joint positions are bound; 5, penetrating frame beam waist bars and upper longitudinal bars, and mounting, connecting and fixing the frame beam waist bars and the upper longitudinal bars; and 6, binding and overlapping plate surface reinforcing steel bars, and finally pouring frame beams and plate surface concrete. According to the invention, the problem that the laminated plate rib in the combined structure of the laminated plate and the cast-in-place frame beam in the theme park is repeatedly bent or cannot be recovered after being bent is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of civil engineering prefabricated component installation, and in particular to an installation method for a combined structure of a theme park composite slab and a cast-in-place frame beam. Background Art

[0002] In theme park projects, although most buildings have only one floor, there are many special-shaped structures and they are very complex. There are great limitations in the actual construction process of prefabricated components, especially in the combination of composite slabs and cast-in-place beams. The traditional practice is to tie the frame beam reinforcement first, and then hoist the composite slabs. Due to the structural limitations of the park, most composite slabs have cast-in-place frame beam reinforcements all around. The composite slabs can only be tilted to put in reinforcements in one direction, and the composite slab reinforcements in the other directions must be bent. After the composite slab is hoisted, the slab reinforcements are restored again, resulting in repeated bending of the composite slab reinforcements. In addition, due to the complex structure, the operating space is limited, and some composite slab reinforcements cannot be restored to their original state, seriously affecting the structural safety function. Summary of the invention

[0003] The present invention aims to overcome the defects of the prior art and provide an installation method for a combination structure of a theme park composite slab and a cast-in-place frame beam, so as to solve the problem of repeated bending of composite slab reinforcement in the combination structure of the theme park composite slab and the cast-in-place frame beam.

[0004] In order to solve the above-mentioned technical problems, the present invention is achieved as follows: A method for installing a theme park composite slab and a cast-in-place frame beam combined structure, characterized in that it comprises the following steps: Step 1: Set up the roof or interlayer support frame and install the cast-in-place beam and composite slab support formwork; Step 2: Install and tie all the bottom steel bars and stirrups of the frame beams at the top of the roof or interlayer; Step 3: Hoisting the composite board; Step 4: Tie the frame column stirrups at the beam-column joints; Step 5: Insert the waist reinforcement and upper longitudinal reinforcement of the frame beam, and install and connect them; Step 6: Tie up the composite slab reinforcement and finally pour the frame beams and slab concrete.

[0005] The installation method of the combined structure of the theme park composite slab and the cast-in-place frame beam is characterized in that: in step 2, 12 cm high horse stool reinforcement is prepared, and the rear drop beam is supported on the bottom template of each beam to ensure that there is sufficient construction operation space when installing the upper reinforcement of the beam.

[0006] The installation method of the combination structure of the composite slab and cast-in-place frame beam of a theme park is characterized by: in step three, according to the order of the drawing, ensure that the position of each composite slab is consistent with the support formwork. In the process, if the composite slab reinforcement and the frame beam stirrups overlap, the stirrup position needs to be fine-tuned.

[0007] The method for installing a theme park composite slab and cast-in-place frame beam combination structure is characterized in that: in step five, during installation, if there is a conflict between the frame beam steel bars and the frame column steel bars, fine-tuning is performed.

[0008] The installation method of the combined structure of the theme park composite slab and the cast-in-place frame beam is characterized in that after the waist reinforcement and the upper longitudinal reinforcement of the frame beam are installed, the horse stool reinforcement is removed to make the overall steel bar skeleton of the frame beam fall to the bottom.

[0009] The installation method of the combined structure of the theme park composite slab and the cast-in-place frame beam is characterized in that a 3*3*2.5 cm pad is supported at the bottom of the frame beam to ensure the thickness of the steel bar protective layer of the frame beam.

[0010] The beneficial effects of the present invention are as follows: It can be seen from the above technical scheme that the present application provides a method for installing a composite slab of a theme park and a cast-in-place frame beam combination structure. Compared with the traditional method for installing a composite slab of a frame beam combination structure, the composite slab hoisting steps are simplified, part of the labor cost is saved, and the problem of repeated bending or inability to restore the composite slab reinforcement after bending in the composite slab of a theme park and a cast-in-place frame beam combination structure is solved, thereby improving the safety performance of the main structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments: Figure 1 This is a schematic diagram of the structure of this application.

[0012] Figure 2 It is a local schematic diagram.

[0013] Figure 3 for Figure 1 A is an enlarged schematic diagram. DETAILED DESCRIPTION

[0014] The technical solutions of the embodiments of the present application will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field without creative work based on the embodiments in the embodiments of the present application are within the scope of protection requested by the present application. like Figure 1-3 As shown: A method for installing a structure combining a composite slab and a cast-in-place frame beam in a theme park, specifically comprising: Step 1: erecting a roof or interlayer support frame 1 and installing cast-in-place beams and composite slab support formwork; Step 2: Install and tie the bottom reinforcement 3 and stirrups 4 of all frame beams on the roof or interlayer top. Prepare 12cm high horse stool reinforcement, and support the rear drop beam on the bottom formwork of each beam to ensure that there is enough construction space when installing the upper reinforcement of the beam; Step 3: Hoist the composite board 6 according to the order of the drawings, and ensure that each composite board is in line with the position of the supporting formwork. In the process, if the composite board reinforcement and the frame beam stirrups overlap, the stirrups need to be fine-tuned; Step 4: Tie the frame column stirrups at the beam-column joints; Step 5: Insert the frame beam waist reinforcement 7 and the upper longitudinal reinforcement 8, and install and connect them. When there is a conflict between the frame beam reinforcement and the frame column reinforcement, make fine adjustments; Step 6: Remove the horse stool reinforcement to make the overall reinforcement skeleton of the frame beam fall to the bottom, and support the 3*3*2.5cm pad 9 according to the specification requirements to ensure the thickness of the reinforcement protection layer of the frame beam; Step 7: Tie up the composite slab reinforcement and finally pour the frame beams and slab concrete.

[0015] Compared with the traditional frame beam composite plate combination structure installation method, the present invention simplifies the composite plate hoisting steps, saves part of the labor cost, solves the problem that the composite plate reinforcement is repeatedly bent or cannot be restored after bending in the composite plate and cast-in-place frame beam combination structure of the theme park, and improves the safety performance of the main structure.

[0016] The above are only embodiments provided for the present application and are not intended to limit the present application. Although the present application is described in detail with reference to the embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. However, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A method for installing a theme park composite slab and cast-in-place frame beam combined structure, characterized in that It includes the following steps: Step 1: Set up the roof or interlayer support frame and install the cast-in-place beam and composite slab support formwork; Step 2: Install and tie all the bottom steel bars and stirrups of the frame beams at the top of the roof or interlayer; Step 3: Hoisting the composite board; Step 4: Tie the frame column stirrups at the beam-column joints; Step 5: Insert the waist reinforcement and upper longitudinal reinforcement of the frame beam, and install and connect them; Step 6: Tie up the composite slab reinforcement and finally pour the frame beams and slab concrete.

2. The method for installing a theme park composite slab and cast-in-place frame beam combination structure according to claim 1, characterized in that: In step 2, prepare 12cm high horse stool reinforcement and support the rear drop beam on the bottom formwork of each beam to ensure that there is enough construction operation space when installing the upper reinforcement of the beam.

3. The method for installing a theme park composite slab and cast-in-place frame beam combination structure according to claim 1, characterized in that: In step three, follow the order of the drawings to ensure that each composite slab matches the position of the supporting formwork. If there is a part where the composite slab reinforcement overlaps with the frame beam stirrups, the stirrup position needs to be fine-tuned.

4. The method for installing a theme park composite slab and cast-in-place frame beam combination structure according to claim 1, characterized in that: In step five, during installation, if there is a conflict between the frame beam reinforcement and the frame column reinforcement, make fine adjustments.

5. The method for installing a combined structure of a theme park composite slab and a cast-in-place frame beam according to claim 2, characterized in that: After installing the waist reinforcement and upper longitudinal reinforcement of the frame beam, remove the horse stool reinforcement to allow the overall steel frame of the frame beam to fall to the bottom.

6. The method for installing a theme park composite slab and cast-in-place frame beam combination structure according to claim 5, characterized in that: A 3*3*2.5cm pad is supported at the bottom of the frame beam to ensure the thickness of the frame beam steel bar protective layer.

Citation Information

Patent Citations

  • Assembly type laminated slab installing and locating method

    CN106284787A

  • Novel manufacturing and installing method for prefabricated laminated beam board

    CN107386512A

  • Method for interpenetration construction of cast-in-situ frame structure and prefabricated floor slab

    CN109930840A

  • Cast-in-place beam and laminated slab installation construction method

    CN116657806A

  • Construction method for crossed construction of cast-in-place beam and fabricated laminated slab

    CN117489040A