Cable risk detection method and device, and storage medium

By receiving production orders, counting bird attack threat coefficients and simulating attacks for stress testing, the problem of low accuracy of existing cable detection is solved, the accuracy of cable detection is improved, the risk of short-circuit fire in cables is reduced, and the power system is guaranteed. Safety.

CN119249205APending Publication Date: 2025-01-03GUANGDONG POWER GRID CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411379677.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2025-01-03

AI Technical Summary

Technical Problem

The existing cable detection methods have low accuracy and are difficult to effectively detect potential defects caused by bird attacks during overhead laying, which increases the risk of cable short circuit and fire and endangers the safety of the power system.

Method used

By receiving production orders, counting bird attack threat coefficients, simulating bird attack manufacturing scratch points, conducting operation stress tests, screening faulty wire segments, determining whether the cable meets the shipment standards, and deciding whether supply or scrapping is allowed.

Benefits of technology

It improves the accuracy of cable defect detection, reduces the risk of cable short circuit and fire, and ensures the normal operation of the power system and the consistency of cable performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119249205A_ABST
    Figure CN119249205A_ABST
Patent Text Reader

Abstract

The invention discloses a cable risk detection method and device, and a storage medium. The method comprises the following steps: determining a to-be-tested wire section in a cable; counting threat coefficients of bird attacks when cables are laid in a regional overhead mode; performing an operation pressure test on the wire section to obtain an operation state of the wire section, and a termination depth and a temperature value of a rubbing point; according to the operation state, the termination depth and the temperature value, screening a faulted wire section as a target section; judging whether the cable meets a preset shipment standard or not according to the target section; if the delivery standard is met, allowing the cable to be provided for the user; if the cable does not meet the shipment standard, the cable is scrapped when the cable does not meet the design requirement, and the cable is provided for a user when the cable meets the design requirement. According to the embodiment, the performance consistency of the cable is guaranteed, the cable can be normally used in a laying area, the problem that the cable is short-circuited and ignited is solved, and normal operation of a power system is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power grids, and in particular to a risk detection method, equipment and storage medium for cables. Background Art

[0002] The power system relies heavily on cables to transmit electricity. The quality of the cables is one of the factors that maintain the safety of the power system. During the operation of the power system, there will be losses, and cable short circuits and fires are prone to occur, which will endanger the normal operation of the power system and even cause serious safety accidents.

[0003] During the cable production process, pulse application, solution immersion, etc. are used to detect whether the cable has defects.

[0004] However, methods such as applying pulses and immersing in solutions mainly detect the strength of the cable itself, which is somewhat one-sided, resulting in low accuracy in detecting cable defects, and causing certain risks when the cables are put into operation in the power system. Summary of the invention

[0005] In view of this, the present invention provides a cable risk detection method, device and storage medium to improve the accuracy of detecting cable defects.

[0006] A first aspect of the present invention provides a risk detection method for a cable, comprising:

[0007] Receiving a production order from a user; the production order records the area and design requirements for laying the cables in an overhead mode;

[0008] When the production of the cable is completed according to the production order, determining the wire segment to be tested in the cable;

[0009] Calculate the threat factor of bird attacks when laying cables in an overhead mode in the area;

[0010] When a scratch point is created by simulating a bird attack on the outer surface of the power line segment according to the number and initial depth of the threat coefficient mapping, an operation pressure test is performed on the power line segment according to the environment of the area to obtain the operation state of the power line segment, the end depth and temperature value of the scratch point;

[0011] selecting the faulty electric wire segment as a target segment according to the operating state, the termination depth and the temperature value;

[0012] Determining whether the cable meets a preset shipping standard according to the target segment;

[0013] If the shipping standard is met, the cable is allowed to be provided to the user;

[0014] If the cable does not meet the shipping standard, then when the cable does not meet the design requirements, the cable is scrapped; when the cable meets the design requirements, the cable is provided to the user.

[0015] A second aspect of the present invention provides a risk detection device for a cable, comprising:

[0016] A production order receiving module, used for receiving a production order from a user; the production order records the area and design requirements for laying cables in an overhead mode;

[0017] A wire segment determination module, used to determine a wire segment to be tested in the cable when the production of the cable is completed according to the production order;

[0018] A threat coefficient statistics module, used to count the threat coefficient of being attacked by birds when laying cables in an overhead mode in the area;

[0019] an operation pressure test execution module, configured to perform an operation pressure test on the electric wire segment according to the environment of the area when simulating a bird attack on the outer surface of the electric wire segment to create a scratch point according to the number and initial depth mapped by the threat coefficient, so as to obtain an operation state of the electric wire segment, a termination depth and a temperature value of the scratch point;

[0020] A fault screening module, used for screening the faulty wire segment as a target segment according to the operating state, the termination depth and the temperature value;

[0021] A shipping standard judgment module, used to judge whether the cable meets the preset shipping standard according to the target segment;

[0022] A supply permission module, used for allowing the cable to be provided to the user if the cable meets the shipping standard;

[0023] The design requirement determination module is used to scrap the cable if it does not meet the shipping standard and to provide the cable to the user if it meets the design requirement.

[0024] A third aspect of the present invention provides an electronic device, the electronic device comprising:

[0025] at least one processor; and

[0026] a memory communicatively connected to the at least one processor; wherein,

[0027] The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the risk detection method for cables as described in the first aspect above.

[0028] A fourth aspect of the present invention provides a computer-readable storage medium storing a computer program, wherein the computer program, when executed by a processor, implements the risk detection method for a cable as described in the first aspect above.

[0029] A fifth aspect of the present invention provides a computer program product, the computer program product comprising a computer program, and when the computer program is executed by a processor, the risk detection method for a cable as described in the first aspect above is implemented.

[0030] In this embodiment, a production order from a user is received; the area and design requirements for laying cables in an overhead mode are recorded in the production order; when the cable production is completed according to the production order, the wire segment to be tested is determined in the cable; the threat coefficient of bird attack when laying the cable in an overhead mode in the area is counted; when the outer surface of the wire segment is simulated to attack the bird to create a scratch point according to the number and initial depth mapped by the threat coefficient, an operation stress test is performed on the wire segment to obtain the operation status of the wire segment, the termination depth and temperature value of the scratch point; the faulty wire segment is selected as the target segment based on the operation status, termination depth and temperature value; based on the target segment, it is determined whether the cable meets the preset shipping standard; if it meets the shipping standard, the cable is allowed to be provided to the user; if it does not meet the shipping standard, the cable is scrapped if it does not meet the design requirements, and is provided to the user if it meets the design requirements. This embodiment focuses on the threat posed by bird activities to cables. It performs a highly simulated operation stress test on the cables according to the environment of the area where the cables are laid, thereby realizing personalized testing, effectively improving the accuracy of detecting cable defects, ensuring the performance consistency of the cables, allowing them to be used normally in the laying area, reducing the problem of cable short circuits and fires, and ensuring the normal operation of the power system.

[0031] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0033] Figure 1 This is a flow chart of a cable risk detection method provided in Embodiment 1 of the present invention.

[0034] Figure 2 It is a structural schematic diagram of a cable risk detection device provided in Embodiment 2 of the present invention.

[0035] Figure 3 It is a structural schematic diagram of an electronic device provided in Embodiment 3 of the present invention. DETAILED DESCRIPTION

[0036] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0037] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable where appropriate, so that the embodiments of the present invention described herein can cover sequential implementations other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0038] Embodiment 1

[0039] See also Figure 1 , shows a flow chart of a cable risk detection method provided by the first embodiment of the present invention, the method can be executed by a cable risk detection device, the cable risk detection device can be implemented in the form of hardware and / or software, and the cable risk detection device can be configured in an electronic device. Figure 1 As shown, the method includes:

[0040] Step 101: Receive a production order from a user.

[0041] In this embodiment, a user's production order for cables may be received in a system such as ERP (Enterprise Resource Planning), wherein the production order records the area and design requirements for laying the cables in an overhead mode.

[0042] Step 102: When the production of the cable is completed according to the production order, a wire segment to be tested is determined in the cable.

[0043] When the production workshop completes the production of cables according to the production order, the wire segments to be tested can be screened from the produced cables.

[0044] In a specific implementation, the distance between utility poles erected in an area is queried in a production order, wherein the utility poles are used to lay cables in an overhead mode.

[0045] An appropriate test length is determined according to the spacing, wherein the test length is positively correlated to the spacing.

[0046] According to the predefined selection strategy, the wire segments that meet the test length are screened out in the cable and wait for testing.

[0047] For example, the predefined selection strategy is to select 10% of the total number of cables produced as test cables. If the test length is 36 meters and the total number of cables produced is 100, 10 cables are selected for the 36-meter pressure test. If the test length is 36 meters, 37 meters, and 40 meters, and the total number of cables produced is 100, 3 cables are selected for the 36-meter, 37-meter, and 40-meter pressure tests respectively. 10% is divided equally. If it is not divisible, it is rounded up.

[0048] Step 103: Count the threat coefficient of bird attacks when laying cables in an overhead mode in the area.

[0049] In actual applications, many birds will stay on overhead cables, causing the overhead cables to be pecked at their outer surfaces by birds with their beaks, resulting in damage to the outer surfaces of the overhead cables, thereby creating weak points, making the overhead cables more susceptible to short circuits in high temperature and high humidity environments, thereby causing fires.

[0050] In one embodiment of the present invention, step 103 may include the following steps:

[0051] Step 1031: Query the number of various types of birds recorded in various areas during multiple historical time periods.

[0052] In this embodiment, the average number of various types of birds recorded in various areas during multiple historical time periods can be queried from the bird data query platform and recorded as the time period number.

[0053] Step 1032: Calculate adjustment parameter values ​​for birds based on the number of time periods.

[0054] In this embodiment, for various birds, adjustment parameter values ​​can be calculated for various birds according to the number of corresponding time periods, and the adjustment parameter values ​​are used to adjust the harm coefficient of birds to cables.

[0055] Exemplarily, the time periods are sorted in chronological order, the difference between the number of time periods in adjacent time periods is calculated to obtain the deviation value, and all the deviation values ​​are summed to obtain the total deviation amount.

[0056] The trend coefficient is calculated as the ratio between the total amount of deviations and the average value of the number of periods.

[0057] Then, in this example, the trend coefficient can be expressed as:

[0058]

[0059] Where x is the number of the region, x = 1, 2, ..., y, y is a positive integer greater than 2, indicating the number of regions, n is the type of bird, n = 1, 2, ..., m, m is a positive integer greater than 2, indicating the number of bird types, b xn is the trend coefficient, a xin is the number of time periods in time period i, a x(i-1)n is the number of time periods in time period (i-1), i=1,2,…,j, j is a positive integer greater than 2, indicating the number of time periods.

[0060] Load a table from the local database; the table records the mapping relationship between the trend range and the parameter value.

[0061] The adjustment parameter values ​​mapped to the trend range of the trend coefficient are extracted from the table as the adjustment parameter values ​​for birds.

[0062] Step 1033: When laying cables in an overhead mode in a region and birds stay on the cables, calculate the hazard coefficient of the birds to the cables.

[0063] In this embodiment, based on the experience of understanding the attributes, living habits and other factors of various birds, the hazard coefficient of the birds to the cables can be calculated when the cables are laid in an overhead mode in the area and the birds stay on the cables.

[0064] For example, the local database is queried for the appropriate number, beak length and wingspan length of various types of birds, and the distance between cables when laying cables in an overhead mode.

[0065] On the one hand, the difference between the average value of the time period quantity and the appropriate quantity is calculated as the proliferation quantity; the first original coefficient is calculated with the natural number as the base and the ratio between the proliferation quantity and the appropriate quantity as the coefficient.

[0066] On the other hand, the second original coefficient is calculated with a natural number as the base and the ratio between the beak length and the average beak length as the coefficient.

[0067] On the other hand, the difference between the wingspan length and the distance is calculated as the contact value; and the third original coefficient is calculated using a natural number as the base and the ratio between the contact value and the distance as the coefficient.

[0068] The first original coefficient, the second original coefficient and the third original coefficient are added together to obtain the coefficient of damage caused by birds to the cables when the cables are laid in an overhead mode in the area and birds stay on the cables.

[0069] Then, in this example, the hazard factor can be expressed as:

[0070]

[0071] Where x is the number of the region, x = 1, 2, ..., y, y is a positive integer greater than 2, indicating the number of regions, n is the type of bird, n = 1, 2, ..., m, m is a positive integer greater than 2, indicating the number of bird types, i = 1, 2, ..., j, j is a positive integer greater than 2, indicating the number of time periods, δ xn is the hazard coefficient, a xin is the number of time periods in time period i, c xn is an appropriate number, d xn is the beak length, f xn is the wingspan length, g x The distance between cables.

[0072] Step 1034: For each area and each type of bird, sum the product of the adjustment parameter value and the hazard coefficient to obtain the threat coefficient.

[0073] In this embodiment, for each area and each type of bird, the product between the adjustment parameter value corresponding to each type of bird and the hazard coefficient is calculated, and all products are summed to obtain the threat coefficient.

[0074] Then, the threat coefficient can be expressed as:

[0075]

[0076] Where x is the number of the region, x = 1, 2, ..., y, y is a positive integer greater than 2, indicating the number of regions, n is the type of bird, n = 1, 2, ..., m, m is a positive integer greater than 2, indicating the number of bird types, ε is the threat coefficient, βxn is the tuning parameter, δ xn is the hazard coefficient.

[0077] Step 104: When simulating a bird attack on the outer surface of the power line segment to create a scratch point according to the number and initial depth mapped by the threat coefficient, perform an operation stress test on the power line segment according to the environment of the area to obtain the operation status of the power line segment, the end depth and temperature value of the scratch point.

[0078] In this embodiment, a production task can be generated according to the threat coefficient, and the threat coefficient is mapped into a quantity and an initial depth, wherein the quantity and the initial depth are both positively correlated with the threat coefficient. The production task instructs the engineer to simulate bird attacks on the outer surface of the wire segment to create scratch points according to the quantity and initial depth mapped by the threat coefficient. That is, scratch points are created on the outer surface of the wire segment using a tool, so that the number of scratch points created is the number mapped according to the threat coefficient, and the depth of the scratch points is the initial depth mapped by the threat coefficient, thereby simulating the damage caused by birds to the cable and facilitating subsequent experimental operations.

[0079] When the production task is completed, a test task is generated to instruct to perform an operation stress test on the wire segment according to the regional environment to achieve a highly simulated operation stress test. During the operation stress test, the operating status of the wire segment and the termination depth and temperature value of the scratch point can be detected.

[0080] In the specific implementation, the historical rainfall and temperature range per unit time recorded for each region can be queried from the weather platform.

[0081] The rainfall in the same area is compared, and the rainfall with the largest value is mapped to the watering volume per unit length when performing an operational stress test on the power line segment.

[0082] Map the upper value of the temperature interval to the ambient temperature when the line segment is stressed.

[0083] At this time, engineers can build a simulation environment based on the watering amount and ambient temperature, that is, the temperature value of the simulation environment is the ambient temperature, and water is sprinkled according to the watering amount. When the power line segment is in the simulation environment containing the watering amount and ambient temperature, the duration of the stress test is queried from the local database. During this duration, the power line segment is energized at the rated voltage to perform the operation stress test.

[0084] During the execution of the running pressure test, the temperature sensor is called to record the running status of the wire segment and measure the temperature value of the scratch point. At the end of the running pressure test, the termination depth of the scratch point is measured.

[0085] Step 105: Filter the faulty wire segment as the target segment according to the operating status, termination depth and temperature value.

[0086] In this embodiment, whether a power line segment is faulty can be evaluated comprehensively based on the operating status, termination depth and temperature value, and the faulty power line segment can be selected and recorded as the target segment.

[0087] In a specific implementation, the operating status of each power line segment may be traversed.

[0088] If the operating state is a short circuit fire state, the electric line segment is determined to be faulty and is taken as the target segment.

[0089] If the operating state is a non-short circuit fire state, the damage coefficient of the wire segment is calculated according to the termination depth and temperature value. The damage coefficient represents the damage caused by the simulation environment to the scratch point of the point line segment.

[0090] For example, the appropriate temperature of the cable is queried, and the initial depth, the end depth, the appropriate temperature and the temperature value are substituted into the following formula to calculate the damage coefficient of the wire segment:

[0091]

[0092] in, is the damage coefficient, h is the temperature value, H is the suitable temperature, l is the termination depth, L is the initial depth, t is the cable number, r is the number of the wire segment at the cable position, r = 1, 2, ..., s, s is a positive integer greater than 2, indicating the number of wire segments in the cable, p is the number of the scratch point, p∈q, p = 1, 2, ..., q, q is a positive integer greater than 2, indicating the number of scratch points, u is the number of the time point for collecting temperature values, u∈w, u = 1, 2, ..., w, w is a positive integer greater than 2, indicating the number of time points for collecting temperature values.

[0093] The damage factor is compared with a preset damage threshold.

[0094] If the damage coefficient is greater than a preset damage threshold, the power line segment is determined to be faulty and is taken as the target segment.

[0095] Step 106: Determine whether the cable meets the preset shipping standard based on the target segment.

[0096] In this embodiment, the condition of the target segment may be evaluated to determine whether the cable meets the preset shipping standard.

[0097] In a specific implementation, on the one hand, the ratio between the total number of target segments and the total number of wire segments is counted to obtain a first proportion. On the other hand, the ratio between the total number of cables with target segments and the total number of cables is counted to obtain a second proportion.

[0098] The first proportion is compared with a preset first proportion threshold, and the second proportion is compared with a preset second proportion threshold.

[0099] If the first proportion is greater than a preset first proportion threshold, and / or the second proportion is greater than a preset second proportion threshold, it is determined that the cable does not meet the preset shipping standard;

[0100] If the first proportion is less than or equal to a preset first proportion threshold, and the second proportion is less than or equal to a preset second proportion threshold, it is determined that the cable meets the preset shipping standard.

[0101] Step 107: If the cable meets the shipping standards, the cable is allowed to be provided to the user.

[0102] If the cable's pressure test results meet the shipping standards, the cable is allowed to be provided to the user, that is, supplied to the user.

[0103] Step 108: If the cable does not meet the shipping standard, the cable is scrapped when it does not meet the design requirements, and is provided to the user when it meets the design requirements.

[0104] If the cable's pressure test results do not meet the shipping standards, it is determined whether the cable meets the design requirements, that is, whether the cable meets the user's order requirements.

[0105] When the cable does not meet the design requirements, the cable is scrapped, and when the cable meets the design requirements, the cable is provided to the user.

[0106] In this embodiment, a production order from a user is received; the area and design requirements for laying cables in an overhead mode are recorded in the production order; when the cable production is completed according to the production order, the wire segment to be tested is determined in the cable; the threat coefficient of bird attack when laying the cable in an overhead mode in the area is counted; when the outer surface of the wire segment is simulated to attack the bird to create a scratch point according to the number and initial depth mapped by the threat coefficient, an operation stress test is performed on the wire segment to obtain the operation status of the wire segment, the termination depth and temperature value of the scratch point; the faulty wire segment is selected as the target segment based on the operation status, termination depth and temperature value; based on the target segment, it is determined whether the cable meets the preset shipping standard; if it meets the shipping standard, the cable is allowed to be provided to the user; if it does not meet the shipping standard, the cable is scrapped if it does not meet the design requirements, and is provided to the user if it meets the design requirements. This embodiment focuses on the threat posed by bird activities to cables. It performs a highly simulated operation stress test on the cables according to the environment of the area where the cables are laid, thereby realizing personalized testing, effectively improving the accuracy of detecting cable defects, ensuring the performance consistency of the cables, allowing them to be used normally in the laying area, reducing the problem of cable short circuits and fires, and ensuring the normal operation of the power system.

[0107] Embodiment 2

[0108] See also Figure 2 , shows a schematic diagram of the structure of a risk detection device for a cable provided in Embodiment 2 of the present invention. Figure 2 As shown, the device comprises:

[0109] The production order receiving module 201 is used to receive a production order from a user; the production order records the area and design requirements for laying cables in an overhead mode;

[0110] A wire segment determination module 202, configured to determine a wire segment to be tested in the cable when the production of the cable is completed according to the production order;

[0111] A threat coefficient statistics module 203, used to count the threat coefficient of being attacked by birds when laying cables in an overhead mode in the area;

[0112] An operation pressure test execution module 204 is used to perform an operation pressure test on the electric wire segment according to the environment of the area when simulating a bird attack on the outer surface of the electric wire segment to create a scratch point according to the number and initial depth of the threat coefficient mapping, so as to obtain an operation state of the electric wire segment, a termination depth and a temperature value of the scratch point;

[0113] A fault screening module 205 is used to screen the faulty wire segment as a target segment according to the operating state, the termination depth and the temperature value;

[0114] A shipping standard determination module 206, configured to determine whether the cable meets a preset shipping standard according to the target segment;

[0115] A supply permitting module 207, configured to permit the cable to be provided to the user if the cable meets the delivery standard;

[0116] The design requirement determination module 208 is used to scrap the cable if it does not meet the shipping standard and to provide the cable to the user if it meets the design requirement.

[0117] In one embodiment of the present invention, the wire segment determination module 202 includes:

[0118] A spacing query module, used to query the spacing between the electric poles erected in the area in the production order; the electric poles are used to lay cables in an overhead mode;

[0119] A test length determination module, used to determine the test length according to the spacing;

[0120] The cable screening module is used to screen out wire segments that meet the test length in the cable to wait for testing.

[0121] In one embodiment of the present invention, the threat coefficient statistics module 203 includes:

[0122] A time period quantity query module is used to query the time period quantity of various types of birds recorded in each of the areas in multiple historical time periods;

[0123] A parameter value calculation module, used for calculating the parameter value of the birds according to the number of the time period;

[0124] A hazard coefficient calculation module, used for calculating the hazard coefficient of the bird to the cable when the cable is laid in an overhead mode in the area and the bird stays on the cable;

[0125] The threat coefficient calculation module is used to sum the products of the adjustment parameter value and the hazard coefficient for each area and each type of bird, so as to obtain the threat coefficient of being attacked by birds when laying cables in an overhead mode in the area.

[0126] In one embodiment of the present invention, the parameter value calculation module is further used for:

[0127] Calculate the difference between the number of time periods in adjacent time periods to obtain a deviation value;

[0128] Sum all the deviation values ​​to obtain a total deviation;

[0129] Calculate the ratio between the total amount of deviations and the average value of the number of time periods as a trend coefficient;

[0130] Loading a table; the table records the mapping relationship between the trend range and the parameter adjustment value;

[0131] The adjustment parameter value mapped to the trend range of the trend coefficient is extracted from the table as the adjustment parameter value of the bird.

[0132] In one embodiment of the present invention, the hazard coefficient calculation module is further used for:

[0133] Query the appropriate number, beak length and wingspan length for each type of bird;

[0134] Query the distance between cables when laying them in an overhead mode;

[0135] Calculate the difference between the average value of the quantity in the time period and the appropriate quantity as the proliferation quantity;

[0136] Taking a natural number as the base and a ratio between the proliferation amount and the appropriate amount as the coefficient, a first original coefficient is calculated;

[0137] The second original coefficient is calculated by taking a natural number as the base and the ratio between the beak length and the average value of the beak length as the coefficient;

[0138] calculating a difference between the wingspan length and the distance as a contact value;

[0139] Calculate a third original coefficient by taking a natural number as a base and a ratio between the contact value and the distance as a coefficient;

[0140] The first original coefficient, the second original coefficient and the third original coefficient are added together to obtain a harm coefficient of the birds to the cables when the cables are laid in an overhead mode in the area and the birds stay on the cables.

[0141] In one embodiment of the present invention, the operation stress test execution module 204 includes:

[0142] An environmental parameter query module is used to query the historical rainfall and temperature range recorded for each of the areas;

[0143] A watering amount mapping module, used for mapping the rainfall amount with the largest value into the watering amount when performing the operation stress test on the power line segment according to the environment of the area;

[0144] An ambient temperature mapping module, used for mapping the upper limit value of the temperature range to the ambient temperature when the operation stress test is performed on the electric wire segment according to the environment of the area;

[0145] a power-on module, configured to power on the electric wire segment at a rated voltage when the electric wire segment is in a simulated environment including the watering amount and the ambient temperature, so as to perform an operation pressure test;

[0146] An information recording module, used to record the operating status of the wire segment and measure the temperature value of the scratch point during the execution of the operating pressure test;

[0147] The termination depth measurement module is used to measure the termination depth of the scratch point when the running pressure test ends.

[0148] In one embodiment of the present invention, the fault screening module 205 includes:

[0149] A first target segment determination module, configured to determine that the electric line segment is faulty as a target segment if the operating state is a short circuit fire state;

[0150] a damage coefficient calculation module, configured to calculate the damage coefficient of the electric wire segment according to the termination depth and the temperature value if the operating state is a non-short circuit fire state;

[0151] The second target segment determination module is used to determine that the power line segment is faulty and use it as a target segment if the damage coefficient is greater than a preset damage threshold.

[0152] In one embodiment of the present invention, the damage coefficient calculation module is further used to:

[0153] Querying the suitable temperature for the cable;

[0154] Substitute the initial depth, the final depth, the suitable temperature and the temperature value into the following formula to calculate the damage coefficient of the wire segment:

[0155]

[0156] in, is the damage coefficient, h is the temperature value, H is the suitable temperature, l is the termination depth, L is the initial depth, t is the number of the cable, r is the number of the wire segment at the position of the cable, p is the number of the scratch point, p∈q, q is the number of the scratch points, u is the number of the time point for collecting the temperature value, u∈w, w is the number of the time point for collecting the temperature value.

[0157] In one embodiment of the present invention, the shipping standard determination module 206 includes:

[0158] A first proportion statistics module, used for counting the ratio between the total number of the target segments and the total number of the wire segments to obtain a first proportion;

[0159] A second proportion statistics module is used to count the ratio between the total number of the cables in the target segment and the total number of the cables to obtain a second proportion;

[0160] a non-compliance determination module, configured to determine that the cable does not comply with a preset shipping standard if the first proportion is greater than a preset first proportion threshold, and / or the second proportion is greater than a preset second proportion threshold;

[0161] The compliance determination module is used to determine that the cable complies with the preset shipping standard if the first proportion is less than or equal to a preset first proportion threshold, and the second proportion is less than or equal to a preset second proportion threshold.

[0162] The risk detection device for cables provided in the embodiment of the present invention can execute the risk detection method for cables provided in any embodiment of the present invention, and has the corresponding functional modules and beneficial effects for executing the risk detection method for cables.

[0163] Embodiment 3

[0164] See also Figure 3, shows a schematic diagram of the structure of an electronic device provided by an embodiment of the present invention. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, blade servers, mainframe computers, and other suitable computers. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or claimed herein.

[0165] like Figure 3 As shown, the electronic device 10 includes at least one processor 11, and a memory connected to the at least one processor 11, such as a read-only memory (ROM) 12, a random access memory (RAM) 13, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 11 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 12 or the computer program loaded from the storage unit 18 to the random access memory (RAM) 13. In the RAM 13, various programs and data required for the operation of the electronic device 10 can also be stored. The processor 11, the ROM 12, and the RAM 13 are connected to each other through a bus 14. An input / output (I / O) interface 15 is also connected to the bus 14.

[0166] A number of components in the electronic device 10 are connected to the I / O interface 15, including: an input unit 16, such as a keyboard, a mouse, etc.; an output unit 17, such as various types of displays, speakers, etc.; a storage unit 18, such as a disk, an optical disk, etc.; and a communication unit 19, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 19 allows the electronic device 10 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.

[0167] The processor 11 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 11 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various dedicated artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The processor 11 executes the various methods and processes described above, such as the risk detection method of the cable.

[0168] In some embodiments, the risk detection method of the cable can be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 18. In some embodiments, part or all of the computer program can be loaded and / or installed on the electronic device 10 via the ROM 12 and / or the communication unit 19. When the computer program is loaded into the RAM 13 and executed by the processor 11, one or more steps of the risk detection method of the cable described above can be performed. Alternatively, in other embodiments, the processor 11 can be configured to execute the risk detection method of the cable in any other appropriate manner (for example, by means of firmware).

[0169] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.

[0170] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.

[0171] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0172] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).

[0173] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.

[0174] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.

[0175] Embodiment 4

[0176] An embodiment of the present invention further provides a computer program product, which includes a computer program. When the computer program is executed by a processor, the risk detection method for a cable provided in any embodiment of the present invention is implemented.

[0177] In the process of implementation, the computer program product can be written in one or more programming languages ​​or a combination thereof to perform the computer program code of the present invention, including object-oriented programming languages, such as Java, Smalltalk, C++, and conventional procedural programming languages, such as "C" language or similar programming languages. The program code can be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer can be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or can be connected to an external computer (for example, using an Internet service provider to connect through the Internet).

[0178] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.

[0179] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A cable risk detection method, characterized in that: include: Receive production orders from users; The production order records the area and design requirements for laying the cables in an overhead mode; When the production of the cable is completed according to the production order, determining the wire segment to be tested in the cable; Calculate the threat factor of bird attacks when laying cables in an overhead mode in the area; When a scratch point is created by simulating a bird attack on the outer surface of the power line segment according to the number and initial depth of the threat coefficient mapping, an operation pressure test is performed on the power line segment according to the environment of the area to obtain the operation state of the power line segment, the end depth and temperature value of the scratch point; selecting the faulty electric wire segment as a target segment according to the operating state, the termination depth and the temperature value; Determining whether the cable meets a preset shipping standard according to the target segment; If the shipping standard is met, the cable is allowed to be provided to the user; If the cable does not meet the shipping standard, then when the cable does not meet the design requirements, the cable is scrapped; when the cable meets the design requirements, the cable is provided to the user.

2. The method according to claim 1, characterized in that The step of determining a wire segment to be tested in the cable comprises: Inquiring in the production order the spacing between utility poles erected in the area; the utility poles are used to lay cables in an overhead mode; Determine the test length according to the spacing; Wire segments meeting the test length are screened out from the cable to wait for testing.

3. The method according to claim 1 or 2, characterized in that: The statistics on the threat factor of bird attacks when laying cables in an overhead mode in the area include: Query the number of various types of birds recorded in each of the areas in multiple historical time periods; Calculating the parameter adjustment value for the birds according to the number of the time period; When the cables are laid in an overhead mode in the area and the birds stay on the cables, calculating the harm coefficient of the birds to the cables; For each of the areas and types of birds, the product of the adjustment parameter value and the hazard coefficient is summed to obtain the threat coefficient of bird attacks when laying cables in an overhead mode in the area.

4. The method according to claim 3, characterized in that The step of calculating the parameter adjustment value for the birds according to the number of the time period includes: Calculate the difference between the number of time periods in adjacent time periods to obtain a deviation value; Sum all the deviation values ​​to obtain a total deviation; Calculate the ratio between the total amount of deviations and the average value of the number of time periods as a trend coefficient; Loading a table; the table records the mapping relationship between the trend range and the parameter adjustment value; The adjustment parameter value mapped to the trend range of the trend coefficient is extracted from the table as the adjustment parameter value of the bird.

5. The method according to claim 3, characterized in that: When the cable is laid in an overhead mode in the area and the birds stay on the cables, the harm coefficient of the birds to the cables includes: Query the appropriate number, beak length and wingspan length for each type of bird; Query the distance between cables when laying them in an overhead mode; Calculate the difference between the average value of the quantity in the time period and the appropriate quantity as the proliferation quantity; Taking a natural number as the base and a ratio between the proliferation amount and the appropriate amount as the coefficient, a first original coefficient is calculated; The second original coefficient is calculated by taking a natural number as the base and the ratio between the beak length and the average value of the beak length as the coefficient; Calculating the difference between the wingspan length and the distance as a contact value; Calculate a third original coefficient by taking a natural number as a base and a ratio between the contact value and the distance as a coefficient; The first original coefficient, the second original coefficient and the third original coefficient are added together to obtain a harm coefficient of the birds to the cables when the cables are laid in an overhead mode in the area and the birds stay on the cables.

6. The method according to any one of claims 1-2, 4-5, characterized in that: The performing of the operating pressure test on the electric wire segment according to the environment of the area to obtain the operating state of the electric wire segment, the termination depth and the temperature value of the scratch point includes: Query the historical rainfall and temperature ranges recorded for each of the areas; Mapping the rainfall with the largest value to the amount of watering when performing an operation stress test on the power line segment according to the environment of the area; Mapping the upper limit value of the temperature range to the ambient temperature when performing an operation stress test on the wire segment according to the environment of the area; When the electric wire segment is in a simulated environment including the watering amount and the ambient temperature, energizing the electric wire segment at a rated voltage to perform an operation pressure test; During the operation pressure test, the operation status of the wire segment is recorded and the temperature value of the scratch point is measured; At the end of the running pressure test, measuring the end depth of the scratch point; The selecting the faulty electric wire segment as the target segment according to the operating state, the termination depth and the temperature value includes: If the operating state is a short circuit fire state, determining that the electric wire segment is faulty is used as a target segment; If the operating state is a non-short circuit fire state, calculating the damage coefficient of the wire segment according to the termination depth and the temperature value; If the damage coefficient is greater than a preset damage threshold, the electric line segment is determined to be faulty and is used as a target segment.

7. The method according to claim 6, characterized in that The calculating the damage coefficient of the electric wire segment according to the termination depth and the temperature value comprises: Querying the suitable temperature for the cable; Substitute the initial depth, the final depth, the suitable temperature and the temperature value into the following formula to calculate the damage coefficient of the wire segment: in, is the damage coefficient, h is the temperature value, H is the suitable temperature, l is the termination depth, L is the initial depth, t is the number of the cable, r is the number of the wire segment at the position of the cable, p is the number of the scratch point, p∈q, q is the number of the scratch points, u is the number of the time point for collecting the temperature value, u∈w, w is the number of the time point for collecting the temperature value.

8. The method according to any one of claims 1-2, 4-5, and 7, characterized in that: The step of judging whether the cable meets a preset shipping standard according to the target segment includes: Counting the ratio between the total number of the target segments and the total number of the wire segments to obtain a first ratio; Counting the ratio between the total number of the cables in the target segment and the total number of the cables to obtain a second ratio; If the first proportion is greater than a preset first proportion threshold, and / or the second proportion is greater than a preset second proportion threshold, it is determined that the cable does not meet the preset shipping standard; If the first proportion is less than or equal to a preset first proportion threshold, and the second proportion is less than or equal to a preset second proportion threshold, it is determined that the cable meets the preset shipping standard.

9. An electronic device, characterized in that: The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can perform the risk detection method for a cable according to any one of claims 1 to 8.