Heavy load inquiry control method and system for ship load pressing and discharging device
By designing a heavy-load inquiry control system in the ship's load-load device, the problems of extended ups and downs and reduced response speeds of large ships or special ships when using high-power load-load-load device are solved, and more efficient ups and downs are achieved and attitude adjustment improves the operating efficiency of the ship and the safety of the power grid.
Patent Information
- Application Number
- CN202411276127.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2025-01-10
- Estimated Expiration
- 2044-09-12
AI Technical Summary
When large ships or special ships use high-power pressure-loading equipment, they need to conduct heavy-load inquiry processes, resulting in an extended ups and downsizing operation time and a reduced response speed of the attitude balance system, affecting the rapid ups and downs of the ship and the attitude adjustment efficiency.
A heavy-load inquiry control system for ship pressure-discharging device is designed, including system comprehensive control device, signal sub-control box, pressure-discharging device control box and power station monitoring system. It is connected through communication cables to realize remote control and on-site control. , improve the automation and intelligence of reload inquiries, simplify the operation process and speed up the startup response speed.
It improves the starting response speed of the pressure-and-load load device and the efficiency of the ship's sinking and floating operation, reduces the operation steps of crew members, enhances the vitality of the control system, and ensures the safe and reliable operation of the ship's power grid.
Smart Images

Figure CN119284097A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a monitoring and control technology for a ship's sinking and buoyancy and attitude balance system, which is applicable to the design of a ship's sinking and buoyancy and attitude balance system or a pressure displacement loading system, and in particular to a heavy load inquiry control method and system for a ship's pressure displacement loading device. Background Art
[0002] According to the requirements of relevant specifications and standards, before a large-power load device is put into use on a ship, a heavy load inquiry should be carried out first, and it can only be put into use after obtaining permission from the power station monitoring system to ensure that the operating power of the ship's power grid meets the use requirements and avoid power outages, short circuits and other faults in the ship's power grid when directly turning on large-power load equipment.
[0003] For large ships or special ships with high demands for ship attitude adjustment, they have high requirements for operation time and efficiency. Ballast load devices are key equipment in the sinking and floating and attitude balance system, and generally include large-displacement ballast pumps, large-displacement ballast load air compressors and other high-power equipment. However, the high-power ballast load device needs to go through a heavy-load inquiry process before starting, which will extend the sinking and floating operation time and reduce the response speed of the sinking and floating and attitude balance system. In order to ensure that the ballast load device can be put into use quickly when the ship's sinking and floating tasks are required, the automation and intelligence of its heavy-load inquiry control method and system are of great significance to ensuring the realization of the sinking and floating operation time indicators and improving the efficiency of ship sinking and floating operations. Summary of the invention
[0004] For large ships or special ships with high demands for ship attitude adjustment, in order to ensure that the pressure-displacement load device can be quickly put into use when the ship's sinking and floating tasks require it, to ensure the realization of the sinking and floating operation time index, and to improve the efficiency of the ship's sinking and floating operations, the present invention proposes a ship pressure-displacement load device heavy load inquiry control method and system. The system mainly includes a system integrated control device, a signal sub-control box, a pressure-displacement load device control box, and a power station monitoring system, which are connected through communication cables. There may be one or more pressure-displacement load device control boxes to achieve remote control and local control of the pressure-displacement load device and improve the vitality of the control system. The control method includes a remote control method and a local control method. Through this method and system, the degree of automatic control of the heavy load inquiry before the pressure-displacement load device is improved, the starting response speed of the pressure-displacement load device is accelerated, and the convenience of operation and the efficiency of ship sinking and floating operations are improved.
[0005] The technical solution of the present invention is:
[0006] A heavy load inquiry control system for a ship pressure relief load device, comprising a system integrated control device, a signal sub-control box, a pressure relief load device control box, and a power station monitoring system; the system integrated control device is a remote control terminal of the pressure relief load device, and is provided with <remote control>, <heavy load inquiry>, <heavy load permission>, <start>, <stop / cancel> soft / hard operation buttons and status indications, and is directly connected to the signal sub-control box through a communication cable; the signal sub-control box is directly connected to the system integrated control device and the pressure relief load device control box through communication cables respectively; the pressure relief load device control box is an on-site control terminal of the pressure relief load device, and is provided with <local / remote control>, <heavy load inquiry>, <heavy load permission>, <start>, <stop / cancel> soft / hard operation buttons and status indications, and is directly connected to the signal sub-control box and the power station monitoring system through communication cables respectively; the power station monitoring system is a ship power grid management terminal, and is provided with <heavy load inquiry>, <heavy load permission> soft / hard operation buttons and status indications for the pressure relief load device, and is directly connected to the pressure relief load device control box through a communication cable;
[0007] The pressure-displacement load device control box continuously sends a "remote control status indication" hold signal to the system integrated control device; when in the remote control state, the pressure-displacement load device control box and the system integrated control device <remote control> indication are always on; when in the local control state, the system integrated control device <remote control> has no indication;
[0008] The control box of the pressure-displacement load device continuously sends the "operation status" hold signal to the system integrated control device and the power station monitoring system; when the pressure-displacement load device is in the operation status, the <start> indication of the system integrated control device and the pressure-displacement load device control box is always on; when the pressure-displacement load device is in the stop status, there is no <start> indication of the system integrated control device and the pressure-displacement load device control box;
[0009] <Stop / Cancel> button and status indicator: when the pressure-displacement load device is in operation, the system's integrated control device or the pressure-displacement load device control box's <Stop / Cancel> button and status indicator enable the pressure-displacement load device to stop; when the pressure-displacement load device is in stop status, the system's integrated control device or the pressure-displacement load device control box's <Stop / Cancel> button and status indicator enable the system's integrated control device or the pressure-displacement load device control box to stop sending the "heavy load inquiry" hold signal, and the signal is reset.
[0010] Furthermore, the communication cables can generally adopt serial, parallel, Ethernet, switch quantity / analog quantity communication modes.
[0011] Furthermore, the <Heavy Load Inquiry>, <Start>, and <Stop / Cancel> buttons on the system integrated control device also have status indication functions, and <Remote Control> and <Heavy Load Allow> only have status indication functions; the <Local / Remote Control>, <Heavy Load Inquiry>, <Start>, and <Stop / Cancel> buttons on the pressure relief load device control box should have status indication functions at the same time, and <Heavy Load Allow> only has a status indication function; the <Heavy Load Inquiry> on the power station monitoring system only has a status indication function, and the <Heavy Load Allow> button should have a status indication function at the same time.
[0012] Furthermore, the system integrated control device, signal sub-control box and power station monitoring system are one, and there can be multiple control boxes for the pressure-displacement load device; when there are multiple control boxes for the pressure-displacement load device, there should be multiple corresponding groups of <local / remote control>, <heavy load inquiry>, <start>, <stop / cancel> buttons and status indicators in the system integrated control device, and there should be multiple corresponding groups of <heavy load allow> buttons in the power station monitoring system.
[0013] A method for controlling a heavy load inquiry of a ship's pressure-displacement loading device, which is used for the heavy load inquiry control system of the ship's pressure-displacement loading device, is a remote control method, comprising the following steps:
[0014] S1.1. The crew member presses the <Heavy Load Inquiry> button on the system integrated control device; at this time, the system integrated control device sends a "Heavy Load Inquiry" hold signal to the signal sub-control box; the signal sub-control box sends the hold signal to the pressure-displacement load device control box, so that the <Heavy Load Inquiry> indicator on the pressure-displacement load device control box is always on; the pressure-displacement load device control box feeds back the "received" hold signal, which is finally transmitted to the system integrated control device via the signal sub-control box, so that the <Heavy Load Inquiry> indicator on the system integrated control device is always on, and at the same time, the pressure-displacement load device control box sends a "Heavy Load Inquiry" hold signal to the power station monitoring system;
[0015] S1.2. After the power station monitoring system receives the "heavy load inquiry" hold signal, it analyzes whether the pressure relief load device can be allowed to start according to the power consumption of the ship's power grid at this time; if the starting conditions are not met, the crew operates the <Stop / Cancel> button on the system integrated control device to stop the system integrated control device from sending the "heavy load inquiry" hold signal and reset the "heavy load inquiry" hold signal, that is, the <heavy load inquiry> indication of the system integrated control device and the pressure relief load device control box is cancelled, and the process ends; if the starting conditions are met, the crew operates the power station monitoring system to send a "heavy load allowed" hold signal to the pressure relief load device control box, so that the <heavy load allowed> indication on the pressure relief load device control box is always on, and at the same time, the pressure relief load device control box sends a "heavy load allowed" hold signal to the signal sub-control box, and then the signal sub-control box sends a "heavy load allowed" hold signal to the system integrated control device, so that the <heavy load allowed> indication on the system integrated control device is always on;
[0016] S1.3. When the <heavy load allowed> indicator on the system integrated control device is always on, the crew member presses the <start> button on the system integrated control device, and the system integrated control device sends a "start" instantaneous signal to the signal sub-control box and stops sending the "heavy load inquiry" holding signal at the same time. At this time, the "heavy load inquiry" holding signal is reset; the signal sub-control box sends a "start" instantaneous signal to the pressure-displacement load device control box, so that the pressure-displacement load device control box executes the command to start the pressure-displacement load device. After the start is successful, the <start> indicator of the pressure-displacement load device control box is always on; because the system integrated control device and the power station monitoring system continue to receive the "operating status" holding signal from the pressure-displacement load device control box through the signal sub-control box, the <start> indicator of the system integrated control device is always on at this time, and the power station monitoring system stops sending the "heavy load allowed" holding signal, and the "heavy load allowed" holding signal is reset;
[0017] S1.4. After the ship's sinking and floating operation is completed, the crew operates the <Stop / Cancel> button on the system's integrated control device, and the system's integrated control device sends a "Stop" instantaneous signal to the signal sub-control box, which sends a "Stop" instantaneous signal to the pressure-displacement load device control box. The pressure-displacement load device control box executes the command to stop the pressure-displacement load device. After the stop is successful, the <Start> indication of the pressure-displacement load device control box is cancelled; since the system's integrated control device and the power station monitoring system continue to receive the "Operation Status" hold signal from the pressure-displacement load device control box through the signal sub-control box, the <Start> indication of the system's integrated control device is cancelled at this time.
[0018] A method for controlling a heavy load inquiry of a ship pressure displacement loading device, which is used for the heavy load inquiry control system of the ship pressure displacement loading device, is an on-site control method, and the specific steps of the on-site control method are as follows:
[0019] S2.1. The crew member operates the <heavy load inquiry> button on the pressure relief device control box to make the <heavy load inquiry> indicator always on, and at the same time sends the "heavy load inquiry" hold signal to the signal sub-control box and the power station monitoring system; the signal sub-control box sends the "heavy load inquiry" hold signal to the system integrated control device, making the <heavy load inquiry> indicator of the system integrated control device always on;
[0020] S2.2. After the power station monitoring system receives the "heavy load inquiry" hold signal, it analyzes whether the pressure relief load device can be allowed to start according to the power consumption of the ship's power grid at this time; if the starting conditions are not met, the crew presses the <Stop / Cancel> button on the pressure relief load device control box to stop the pressure relief load device control box from sending the "heavy load inquiry" hold signal, and the signal is reset, that is, the <heavy load inquiry> indication of the system integrated control device and the pressure relief load device control box is cancelled, and the process ends; if the starting conditions are met, the crew operates the power station monitoring system to send a "heavy load allowed" hold signal to the pressure relief load device control box, so that the <heavy load allowed> indication on the pressure relief load device control box is always on, and at the same time, the pressure relief load device control box sends a "heavy load allowed" hold signal to the signal sub-control box, and the signal sub-control box sends a "heavy load allowed" hold signal to the system integrated control device, so that the <heavy load allowed> indication on the system integrated control device is always on;
[0021] S2.3. When the <heavy load allowed> indicator on the pressure relief load device control box is always on, the crew member operates the <start> button on the pressure relief load device control box, and the pressure relief load device control box stops sending the "heavy load inquiry" hold signal. At this time, the "heavy load inquiry" hold signal is reset, and the command to start the pressure relief load device is executed. After the start is successful, the <start> indicator on the pressure relief load device control box is always on; because the system integrated control device and the power station monitoring system continue to receive the "operating status" hold signal from the pressure relief load device control box through the signal sub-control box, the <start> indicator on the system integrated control device is always on, and the power station monitoring system stops sending the "heavy load allowed" hold signal, and the "heavy load allowed" hold signal is reset;
[0022] S2.4. After the ship's sinking and floating operation is completed, the crew operates the <Stop / Cancel> button on the pressure-displacement load device control box, and the pressure-displacement load device control box executes the command to stop the pressure-displacement load device. After the stop is successful, the <Start> indication of the pressure-displacement load device control box is cancelled; because the system integrated control device and the power station monitoring system continue to receive the "operating status" holding signal from the pressure-displacement load device control box through the signal sub-control box, the <Start> indication of the system integrated control device is cancelled at this time.
[0023] Furthermore, in the remote control method, except for the control of <heavy load inquiry>, <stop / cancel>, <start> of the system integrated control device and <heavy load permission> of the power station monitoring system, which require crew operation, other operations are automatic control processes.
[0024] Furthermore, in the local control method, except for the <heavy load inquiry>, <stop / cancel>, <start> of the pressure discharge loading device control box and the <heavy load permission> of the power station monitoring system, which require crew operation, other operations are automatic control processes.
[0025] Furthermore, the "heavy load inquiry", "heavy load permission" and "operating status" signals are holding signals; the "start" and "stop / cancel" signals are instantaneous signals; the "heavy load inquiry" or "heavy load permission" holding signal reset means that when the "heavy load inquiry" or "heavy load permission" holding signal stops sending, the indication of the corresponding permanently lit indication part is automatically canceled.
[0026] Furthermore, the buttons and status indicators of the system integrated control device, the pressure-displacement load device control box, and the power station monitoring system are aimed at a certain pressure-displacement load device; the control methods of different pressure-displacement load devices are the same.
[0027] The beneficial effects of the present invention are:
[0028] A multi-level ship pressure relief load device heavy load inquiry control system is proposed. The system integrated control device and the pressure relief load device control box are the remote control terminal and the local control terminal of the pressure relief load device respectively, which improves the vitality of the pressure relief load device control system. The pressure relief load device control box exchanges information with the power station monitoring system to ensure the safe and reliable operation of the ship's power grid, and provide ideas for the control design of the ship's sinking and attitude balance system.
[0029] A heavy load inquiry control method for a ship's pressure displacer loading device is proposed. According to this method, the control process and control strategy can be designed to reduce the crew's operating steps, improve the degree of automatic control of the pressure displacer loading device's heavy load inquiry control process, and improve the operating convenience and efficiency of the ship's sinking and floating operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 This is a diagram of a heavy load inquiry control system for a ship pressure discharge loading device of the present invention;
[0031] Figure 2 It is a layout diagram of buttons and status indicators of the integrated alarm device of the system of the present invention;
[0032] Figure 3-1 This is a schematic diagram of the heavy load inquiry remote control method of the ship pressure discharge loading device of the present invention;
[0033] Figure 3-2 This is a flow chart of the heavy load inquiry remote control method of the ship pressure discharge loading device of the present invention;
[0034] Figure 4-1 This is a schematic diagram of the on-site control method for heavy load inquiry of a ship pressure discharge loading device of the present invention;
[0035] Figure 4-2 The present invention is a flow chart of the on-site control method for heavy load inquiry of a ship pressure discharge loading device. DETAILED DESCRIPTION
[0036] The present invention is described in detail below in conjunction with the accompanying drawings and specific embodiments. This embodiment is implemented based on the technical solution of the present invention, and provides a detailed implementation method and specific operation process, but the protection scope of the present invention is not limited to the following embodiments.
[0037] The present invention provides a heavy load inquiry control system for ship pressure discharge loading device, see Figure 1 , Figure 2 , mainly including system integrated control device, signal sub-control box, pressure-displacement load device control box, and power station monitoring system. Among them, there are one system integrated control device, signal sub-control box, and power station monitoring system, and there are one or more pressure-displacement load device control boxes. In this embodiment, the pressure-displacement load device control boxes include No. 1 pressure-displacement load device control box and No. 2 pressure-displacement load device control box.
[0038] More specifically, the system integrated control device is the remote control terminal of the No. 1 pressure-displacement load device and the No. 2 pressure-displacement load device, and the No. 1 pressure-displacement load device and the No. 2 pressure-displacement load device are respectively provided with <remote control>, <heavy load inquiry>, <heavy load permission>, <start>, <stop / cancel> and other soft / hard operation buttons and status indicators, which are directly connected to the signal sub-control box through communication cables; the signal sub-control box is directly connected to the system integrated control device, the No. 1 pressure-displacement load device control box, and the No. 2 pressure-displacement load device control box through communication cables; the No. 1 pressure-displacement load device control box and the No. 2 pressure-displacement load device control box are respectively connected to the system integrated control device, the No. 1 pressure-displacement load device control box, and the No. 2 pressure-displacement load device control box. The box is the local control terminal of the pressure-displacement load device, which is equipped with soft / hard operation buttons and status indicators such as <local / remote control>, <heavy load inquiry>, <heavy load permission>, <start>, and <stop / cancel>, and is directly connected to the signal sub-control box and the power station monitoring system through communication cables; the power station monitoring system is the ship power grid management terminal, which is equipped with soft / hard operation buttons and status indicators such as <heavy load inquiry> and <heavy load permission> corresponding to the No. 1 pressure-displacement load device and the No. 2 pressure-displacement load device, and is directly connected to the control box of the No. 1 pressure-displacement load device and the control box of the No. 2 pressure-displacement load device through communication cables.
[0039] More specifically, the communication cable can generally adopt, but is not limited to, serial, parallel, Ethernet, switch quantity / analog quantity and other communication methods.
[0040] More specifically, the buttons <Heavy Load Inquiry>, <Start>, and <Stop / Cancel> on the system integrated control device should also have the status indication function, while <Remote Control> and <Heavy Load Permission> only have the status indication function. The buttons <Local / Remote Control>, <Heavy Load Inquiry>, <Start>, and <Stop / Cancel> on the No. 1 pressure-displacement load device control box and the No. 2 pressure-displacement load device control box should also have the status indication function, while <Heavy Load Permission> only has the status indication function. The <Heavy Load Inquiry> on the power station monitoring system only has the status indication function, while the button <Heavy Load Permission> should also have the status indication function.
[0041] More specifically, the No. 1 pressure-displacement load device control box and the No. 2 pressure-displacement load device control box continuously send the "remote control state indication" hold signal to the system integrated control device through the signal sub-control box. When in the remote control state, the pressure-displacement load device control box and the system integrated control device <remote control> indication are always on; when in the local control state, the system integrated control device <remote control> has no indication.
[0042] The present invention also proposes a method for remotely controlling a heavy load inquiry of a ship pressure discharge loading device, see Figure 3-1 to Figure 3-2 , using the ship's pressure relief loading device heavy load inquiry control system, this embodiment uses pressure relief loading device No. 1 as the control object, and the control methods of different pressure relief loading devices are the same. The steps of remote control include:
[0043] S101: The crew member presses the <heavy load inquiry> button of No. 1 pressure discharge loading device on the system integrated control device;
[0044] S102: The system integrated control device sends a "heavy load inquiry" holding signal of the No. 1 pressure discharge load device to the signal sub-control box;
[0045] S103: The signal sub-control box sends a "heavy load inquiry" holding signal of the No. 1 pressure discharging load device to the No. 1 pressure discharging load device control box, so that the <heavy load inquiry> indicator of the No. 1 pressure discharging load device control box is always on;
[0046] S104: The No. 1 pressure discharge loading device control box sends a "received" holding signal to the signal sub-control box;
[0047] S105: The signal sub-control box sends a "received" holding signal of the No. 1 pressure-displacement load device to the system integrated control device, so that the No. 1 pressure-displacement load device <heavy load inquiry> indicator on the system integrated control device is always on;
[0048] S106: The control box of the No. 1 pressure discharge load device sends a "heavy load inquiry" holding signal to the power station monitoring system;
[0049] According to the current power consumption of the ship's power grid, analyze whether the No. 1 pressure discharge load device can be allowed to start. If the starting conditions are not met, execute:
[0050] S117: Press the <Stop / Cancel> button on the No. 1 pressure discharging load device on the crew operating system integrated control device to stop the system integrated control device from sending the "heavy load inquiry" holding signal for the No. 1 pressure discharging load device, and the "heavy load inquiry" holding signal is reset.
[0051] The process ends.
[0052] If the starting conditions are met, execute:
[0053] S107: The crew performs the <heavy load allowed> operation on the No. 1 pressure discharge loading device in the power station monitoring system;
[0054] S108: The power station monitoring system sends a "heavy load allowed" holding signal of the No. 1 pressure discharging load device to the control box of the No. 1 pressure discharging load device, so that the <heavy load allowed> indicator on the control box of the No. 1 pressure discharging load device is always on;
[0055] S109: The No. 1 pressure discharge load device control box sends a "heavy load allowed" holding signal to the signal sub-control box;
[0056] S110: The signal sub-control box sends a "heavy load allowed" hold signal to the system integrated control device, so that the No. 1 pressure discharge load device <heavy load allowed> indicator on the system integrated control device is always on;
[0057] S111: Press the <Start> button for the No. 1 pressure relief device on the integrated control device of the crew operating system;
[0058] S112: The system integrated control device sends the "start" instantaneous signal of the No. 1 pressure discharging load device to the signal sub-control box, and at the same time stops sending the "heavy load inquiry" holding signal of the No. 1 pressure discharging load device. At this time, the "heavy load inquiry" holding signal is reset;
[0059] S113: The signal sub-control box sends a "start" instantaneous signal of the No. 1 pressure-displacement load device to the No. 1 pressure-displacement load device control box, so that the No. 1 pressure-displacement load device control box executes the command to start the No. 1 pressure-displacement load device. After success, the <start> indicator of the No. 1 pressure-displacement load device control box is always on;
[0060] S114: The control box of the No. 1 pressure discharge loading device sends a "running status" hold signal to the signal sub-control box;
[0061] S115: The control box of the No. 1 pressure-displacement load device sends a "running status" holding signal to the power station monitoring system, causing the power station monitoring system to stop sending the "heavy load allowed" holding signal of the No. 1 pressure-displacement load device, and the "heavy load allowed" holding signal is reset.
[0062] S116: The signal sub-control box sends the "operation status" holding signal of the No. 1 pressure discharging load device to the system integrated control device, so that the No. 1 pressure discharging load device <start> indicator of the system integrated control device is always on;
[0063] When the ship sinking and floating operation task is completed, continue to execute:
[0064] S117: No. 1 pressure relief device <Stop / Cancel> button on the integrated control device of the crew operating system;
[0065] S118: The system integrated control device sends a "stop" instantaneous signal of the No. 1 pressure discharge loading device to the signal sub-control box;
[0066] S119: The signal sub-control box sends a "stop" instantaneous signal of the No. 1 pressure-displacement load device to the No. 1 pressure-displacement load device control box, and the No. 1 pressure-displacement load device control box executes the command to stop the No. 1 pressure-displacement load device, and the <start> instruction of the No. 1 pressure-displacement load device control box is cancelled;
[0067] S114: The control box of the No. 1 pressure discharge loading device sends a "running status" hold signal to the signal sub-control box;
[0068] S116: The signal sub-control box sends a "running state" holding signal of the No. 1 pressure discharging load device to the system integrated control device, so that the <start> instruction of the No. 1 pressure discharging load device of the system integrated control device is cancelled;
[0069] The process ends.
[0070] More specifically, steps S101, S107, S111, and S117 require crew operation, and other steps are automatic control processes.
[0071] The present invention also proposes a method for on-site control of heavy load inquiry of ship pressure discharge loading device, see Figure 4-1 to Figure 4-2 , using the ship's pressure relief loading device heavy load inquiry control system, with pressure relief loading device No. 1 as the control object, the control methods of different pressure relief loading devices are the same. The steps of local control include:
[0072] S201: The crew member presses the <Heavy Load Inquiry> button on the No. 1 pressure discharge device control box, and the <Heavy Load Inquiry> indicator is always on;
[0073] S202: The control box of the No. 1 pressure discharge load device sends a "heavy load inquiry" holding signal to the signal sub-control box;
[0074] S203: The signal sub-control box sends a "heavy load inquiry" holding signal of the No. 1 pressure discharging load device to the system integrated control device, so that the No. 1 pressure discharging load device <heavy load inquiry> indicator of the system integrated control device is always on;
[0075] S204: The control box of the No. 1 pressure discharge load device sends a "heavy load inquiry" holding signal to the power station monitoring system;
[0076] According to the current power consumption of the ship's power grid, analyze whether the No. 1 pressure discharge load device can be allowed to start. If the starting conditions are not met, execute:
[0077] S210: The crew member operates the <Stop / Cancel> button on the No. 1 pressure relief loading device control box, and at the same time, the No. 1 pressure relief loading device control box stops sending the "heavy load inquiry" holding signal, and the signal is reset.
[0078] The process ends.
[0079] If the starting conditions are met, execute:
[0080] S205: The crew performs the <heavy load allowed> operation on the No. 1 pressure discharge loading device in the power station monitoring system;
[0081] S206: The power station monitoring system sends a "heavy load allowed" holding signal of the No. 1 pressure discharging load device to the control box of the No. 1 pressure discharging load device, and the <heavy load allowed> indicator on the control box of the No. 1 pressure discharging load device is always on;
[0082] S207: The No. 1 pressure discharge load device control box sends a "heavy load allowed" holding signal to the signal sub-control box;
[0083] S208: The signal sub-control box sends the "heavy load allowed" holding signal of the No. 1 pressure discharging load device to the system integrated control device, so that the No. 1 pressure discharging load device <heavy load allowed> indicator on the system integrated control device is always on;
[0084] S209: The crew member presses the <Start> button on the No. 1 pressure relief load device control box, and the No. 1 pressure relief load device control box stops sending the "heavy load inquiry" holding signal. At this time, the "heavy load inquiry" holding signal is reset, and the command to start the No. 1 pressure relief load device is executed at the same time. After success, the <Start> indicator of the No. 1 pressure relief load device control box is always on;
[0085] S114: The control box of the No. 1 pressure discharge loading device sends a "running status" hold signal to the signal sub-control box;
[0086] S115: The control box of the No. 1 pressure-displacement load device sends a "running status" holding signal to the power station monitoring system, causing the power station monitoring system to stop sending the "heavy load allowed" holding signal of the No. 1 pressure-displacement load device, and the "heavy load allowed" holding signal is reset.
[0087] S116: The signal sub-control box sends the "operation status" holding signal of the No. 1 pressure discharging load device to the system integrated control device, so that the No. 1 pressure discharging load device <start> indicator of the system integrated control device is always on;
[0088] When the ship sinking and floating operation task is completed, continue to execute:
[0089] S210: The crew member operates the <Stop / Cancel> button on the No. 1 pressure discharging device control box, and the No. 1 pressure discharging device control box executes the command to stop the No. 1 pressure discharging device, and the <Start> instruction of the No. 1 pressure discharging device control box is cancelled;
[0090] S114: The control box of the No. 1 pressure discharge loading device sends a "running status" hold signal to the signal sub-control box;
[0091] S116: The signal sub-control box sends a "running state" holding signal of the No. 1 pressure discharging load device to the system integrated control device, so that the <start> instruction of the No. 1 pressure discharging load device of the system integrated control device is cancelled;
[0092] The process ends.
[0093] More specifically, steps S201, S205, S209, and S210 require crew operation, and other steps are automatic control processes.
[0094] More specifically, the control box of the No. 1 pressure-displacement load device continuously sends a "running state" hold signal (S116) to the system integrated control device through the signal sub-control box (S114); the control box of the No. 1 pressure-displacement load device continuously sends a "running state" hold signal (S115) to the power station monitoring system. Therefore, when the No. 1 pressure-displacement load device is in the running state, the No. 1 pressure-displacement load device <start> indication of the system integrated control device is always on; when the No. 1 pressure-displacement load device is in the stopped state, the No. 1 pressure-displacement load device <start> indication of the system integrated control device is cancelled and there is no indication.
[0095] The above-mentioned embodiment only expresses one implementation mode of the present invention, and its description is relatively specific and detailed, but it cannot be understood as limiting the scope of the invention patent. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be based on the attached claims.
Claims
1. A heavy load inquiry control system for a ship pressure discharge device, characterized in that: It includes a system integrated control device, a signal sub-control box, a pressure-displacement load device control box, and a power station monitoring system; the system integrated control device is a remote control terminal of the pressure-displacement load device, which is provided with <remote control>, <heavy load inquiry>, <heavy load permission>, <start>, <stop / cancel> soft / hard operation buttons and status indications, and is directly connected to the signal sub-control box through a communication cable; the signal sub-control box is directly connected to the system integrated control device and the pressure-displacement load device control box through communication cables respectively; the pressure-displacement load device control box is an on-site control terminal of the pressure-displacement load device, which is provided with <local / remote control>, <heavy load inquiry>, <heavy load permission>, <start>, <stop / cancel> soft / hard operation buttons and status indications, and is directly connected to the signal sub-control box and the power station monitoring system through communication cables respectively; the power station monitoring system is a ship power grid management terminal, which is provided with <heavy load inquiry>, <heavy load permission> soft / hard operation buttons and status indications of the pressure-displacement load device, and is directly connected to the pressure-displacement load device control box through a communication cable; The pressure-displacement load device control box continuously sends the "remote control status indication" hold signal to the system integrated control device; when in the remote control state, the pressure-displacement load device control box and the system integrated control device <remote control> indication are always on; when in the local control state, the system integrated control device <remote control> has no indication; The pressure-displacement load device control box continuously sends the "operation status" hold signal to the system integrated control device and the power station monitoring system; when the pressure-displacement load device is in the operation status, the <start> indication of the system integrated control device and the pressure-displacement load device control box is always on; when the pressure-displacement load device is in the stop status, there is no <start> indication of the system integrated control device and the pressure-displacement load device control box; <Stop / Cancel> button and status indicator: when the pressure-displacement load device is in operation, the <Stop / Cancel> button and status indicator on the operating system integrated control device or the pressure-displacement load device control box are pressed to stop the pressure-displacement load device; when the pressure-displacement load device is in stop state, the <Stop / Cancel> button and status indicator on the operating system integrated control device or the pressure-displacement load device control box are pressed to stop the system integrated control device or the pressure-displacement load device control box from sending the "heavy load inquiry" hold signal, and the signal is reset.
2. The heavy load inquiry control system for ship pressure discharge loading device according to claim 1 is characterized in that: Communication cables can generally use serial, parallel, Ethernet, and switch / analog communication methods.
3. The heavy load inquiry control system for ship pressure discharge loading device according to claim 1 is characterized in that: The <Heavy Load Inquiry>, <Start>, and <Stop / Cancel> buttons on the system integrated control device also have status indication functions, while <Remote Control> and <Heavy Load Permission> only have status indication functions; the <Local / Remote Control>, <Heavy Load Inquiry>, <Start>, and <Stop / Cancel> buttons on the pressure relief load device control box should also have status indication functions, while <Heavy Load Permission> only has status indication functions; the <Heavy Load Inquiry> on the power station monitoring system only has status indication functions, while <Heavy Load Permission> should also have status indication functions.
4. The heavy load inquiry control system for ship pressure discharge loading device according to claim 1, characterized in that: There is one system integrated control device, signal sub-control box and power station monitoring system, and there can be multiple control boxes for the pressure-displacement load device; when there are multiple control boxes for the pressure-displacement load device, there should be multiple groups of corresponding <local / remote control>, <heavy load inquiry>, <start>, <stop / cancel> buttons and status indicators in the system integrated control device, and there should be multiple groups of corresponding <heavy load allow> buttons in the power station monitoring system.
5. A method for controlling overload inquiry of a ship pressure discharge device, characterized in that: The heavy load inquiry control system for the ship pressure discharge loading device according to claim 1 is a remote control method, comprising the following steps: S1.
1. The crew member presses the <Heavy Load Inquiry> button on the system integrated control device; at this time, the system integrated control device sends a "Heavy Load Inquiry" hold signal to the signal sub-control box; the signal sub-control box sends the hold signal to the pressure-displacement load device control box, so that the <Heavy Load Inquiry> indicator on the pressure-displacement load device control box is always on; the pressure-displacement load device control box feeds back the "received" hold signal, which is finally transmitted to the system integrated control device via the signal sub-control box, so that the <Heavy Load Inquiry> indicator on the system integrated control device is always on, and at the same time, the pressure-displacement load device control box sends a "Heavy Load Inquiry" hold signal to the power station monitoring system; S1.
2. After the power station monitoring system receives the "heavy load inquiry" hold signal, it analyzes whether the pressure relief load device can be allowed to start according to the power consumption of the ship's power grid at this time; if the starting conditions are not met, the crew operates the <Stop / Cancel> button on the system integrated control device to stop the system integrated control device from sending the "heavy load inquiry" hold signal and reset the "heavy load inquiry" hold signal, that is, the <heavy load inquiry> indication of the system integrated control device and the pressure relief load device control box is cancelled, and the process ends; if the starting conditions are met, the crew operates the power station monitoring system to send a "heavy load allowed" hold signal to the pressure relief load device control box, so that the <heavy load allowed> indication on the pressure relief load device control box is always on, and at the same time, the pressure relief load device control box sends a "heavy load allowed" hold signal to the signal sub-control box, and then the signal sub-control box sends a "heavy load allowed" hold signal to the system integrated control device, so that the <heavy load allowed> indication on the system integrated control device is always on; S1.
3. When the <heavy load allowed> indicator on the system integrated control device is always on, the crew member operates the <start> button on the system integrated control device, and the system integrated control device sends a "start" instantaneous signal to the signal sub-control box and stops sending the "heavy load inquiry" holding signal at the same time. At this time, the "heavy load inquiry" holding signal is reset; the signal sub-control box sends a "start" instantaneous signal to the pressure-displacement load device control box, so that the pressure-displacement load device control box executes the command to start the pressure-displacement load device. After the start is successful, the <start> indicator on the pressure-displacement load device control box is always on; because the system integrated control device and the power station monitoring system continue to receive the "operating status" holding signal from the pressure-displacement load device control box through the signal sub-control box, the <start> indicator on the system integrated control device is always on at this time, and the power station monitoring system stops sending the "heavy load allowed" holding signal, and the "heavy load allowed" holding signal is reset; S1.
4. After the ship's sinking and floating operation is completed, the crew member operates the <Stop / Cancel> button on the system's integrated control device, and the system's integrated control device sends a "Stop" instantaneous signal to the signal sub-control box, which sends a "Stop" instantaneous signal to the pressure-displacement load device control box. The pressure-displacement load device control box executes the command to stop the pressure-displacement load device. After the stop is successful, the <Start> indication of the pressure-displacement load device control box is cancelled; since the system's integrated control device and the power station monitoring system continue to receive the "Operation Status" hold signal from the pressure-displacement load device control box through the signal sub-control box, the <Start> indication of the system's integrated control device is cancelled at this time.
6. A method for controlling overload inquiry of a ship pressure discharge device, characterized in that: The heavy load inquiry control system for the ship pressure discharge loading device according to claim 1 is a local control method, and the specific steps of the local control method are as follows: S2.
1. The crew member operates the <heavy load inquiry> button on the pressure relief device control box to make the <heavy load inquiry> indicator always on, and at the same time sends the "heavy load inquiry" hold signal to the signal sub-control box and the power station monitoring system; the signal sub-control box sends the "heavy load inquiry" hold signal to the system integrated control device, making the <heavy load inquiry> indicator of the system integrated control device always on; S2.
2. After the power station monitoring system receives the "heavy load inquiry" hold signal, it analyzes whether the pressure relief load device can be allowed to start according to the power consumption of the ship's power grid at this time; if the starting conditions are not met, the crew presses the <Stop / Cancel> button on the pressure relief load device control box to stop the pressure relief load device control box from sending the "heavy load inquiry" hold signal, and the signal is reset, that is, the <heavy load inquiry> indication of the system integrated control device and the pressure relief load device control box is cancelled, and the process ends; if the starting conditions are met, the crew operates the power station monitoring system to send a "heavy load allowed" hold signal to the pressure relief load device control box, so that the <heavy load allowed> indication on the pressure relief load device control box is always on, and at the same time, the pressure relief load device control box sends a "heavy load allowed" hold signal to the signal sub-control box, and the signal sub-control box sends a "heavy load allowed" hold signal to the system integrated control device, so that the <heavy load allowed> indication on the system integrated control device is always on; S2.
3. When the <heavy load allowed> indicator on the pressure relief load device control box is always on, the crew member operates the <start> button on the pressure relief load device control box, and the pressure relief load device control box stops sending the "heavy load inquiry" holding signal. At this time, the "heavy load inquiry" holding signal is reset, and the command to start the pressure relief load device is executed at the same time. After the start is successful, the <start> indicator on the pressure relief load device control box is always on; because the system integrated control device and the power station monitoring system continue to receive the "operating status" holding signal from the pressure relief load device control box through the signal sub-control box, the <start> indicator on the system integrated control device is always on at this time, and the power station monitoring system stops sending the "heavy load allowed" holding signal, and the "heavy load allowed" holding signal is reset; S2.
4. After the ship's sinking and floating operation is completed, the crew operates the <Stop / Cancel> button on the pressure-displacement device control box, and the pressure-displacement device control box executes the command to stop the pressure-displacement device. After the stop is successful, the <Start> instruction of the pressure-displacement device control box is cancelled; because the system integrated control device and the power station monitoring system continue to receive the "operating status" holding signal from the pressure-displacement device control box through the signal sub-control box, the <Start> instruction of the system integrated control device is cancelled at this time.
7. The heavy load inquiry control method for ship pressure discharge loading device according to claim 5 is characterized in that: In the remote control method, except for the control of <heavy load inquiry>, <stop / cancel>, <start> of the system integrated control device and <heavy load permission> of the power station monitoring system, which require crew operation, other operations are automatic control processes.
8. The heavy load inquiry control method for ship pressure discharge loading device according to claim 6, characterized in that: In the local control method, except for the <heavy load inquiry>, <stop / cancel>, <start> of the pressure discharge loading device control box and the <heavy load permission> of the power station monitoring system, which require crew operation, other operations are automatic control processes.
9. The heavy load inquiry control method for ship pressure discharge loading device according to any one of claims 5 and 6, characterized in that: "Heavy load inquiry", "Heavy load permission" and "Operation status" signals are holding signals; "Start" and "Stop / Cancel" signals are instantaneous signals; "Heavy load inquiry" or "Heavy load permission" holding signal reset means that when the "Heavy load inquiry" or "Heavy load permission" holding signal stops sending, the corresponding permanently lit indication part indication is automatically cancelled.
10. The heavy load inquiry control method for a ship pressure discharge device according to any one of claims 5 and 6, characterized in that: The buttons and status indicators of the system integrated control device, the pressure-displacement load device control box, and the power station monitoring system are aimed at a certain pressure-displacement load device; the control methods of different pressure-displacement load devices are the same.
Citation Information
Patent Citations
Method for inquiring heavy load of ship power station power management
CN101577433A
Ship electric power intelligent monitoring system
CN107479515A
Pure battery ship full-revolving steering oar system and suspension type electric propulsion and control system
CN110920848A
Navigation task working condition indicating equipment
CN115743449A
System and method for controlling job multiplicity overloading and recording medium
JP1999237994A