Reinforcement cage of long spiral cast-in-situ bored pile with integrated structure and manufacturing method of reinforcement cage

By adopting steel casing and steel pipe reinforcement structures in long auger drilling piles and combining position sensors, the problems of conical ports of the steel cage and verticality control are solved, and efficient and safe reinforcement cage insertion and construction quality are achieved. promote.

CN119287886APending Publication Date: 2025-01-10CHINA AEROSPACE CONSTR GROUP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411537666.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-31
Publication Date
2025-01-10

AI Technical Summary

Technical Problem

In the construction of long auger drilling and press-filled piles, the welding point of the conical port of the steel cage is prone to fall off, resulting in the steel cage not reaching the designed depth and the pile top is not equipped with a steel casing protection device, making it difficult to control the verticality and pile positioning of the steel cage , increasing labor demand and construction costs.

Method used

Adopt integrated structure long spiral drilling pile cast-injected pile cage, including steel casing protection device and steel pipe reinforcement conical port protection device, use position sensor to obtain the position and verticality information of the steel cage, and reinforce the cone through ship-type pile diameter card and steel pipe reinforcement The shaped opening protection device fixes the steel cage to ensure that it is inserted vertically and reaches the designed depth.

Benefits of technology

Effectively prevent the welding of the conical port of the steel cage from falling off, ensure that the steel cage reaches the design depth, improve construction quality and safety, reduce construction costs, and simplify the operation process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119287886A_ABST
    Figure CN119287886A_ABST
Patent Text Reader

Abstract

The invention discloses a long auger bored pile reinforcement cage with an integrated structure and a manufacturing method thereof, relates to the technical field of building construction, and is used for solving the technical problem that the perpendicularity and pile positioning of an existing long auger bored press-grouting pile (namely a post-insertion reinforcement cage process) reinforcement cage are difficult to control. The long spiral cast-in-situ bored pile reinforcement cage of the integrated structure comprises a steel casing protection device and a steel pipe reinforcing conical opening protection device connected with the steel casing protection device. The steel casing protection device comprises a steel casing body and a ship-shaped pile diameter clamp connected with the steel casing body. The steel pipe reinforcing conical opening protection device is made of a steel pipe and welded to a steel bar conical body in a sleeving mode. A position sensor is installed at the top of the steel casing protection device and used for obtaining the pile forming position, the steel reinforcement cage position and perpendicularity information.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction engineering, and in particular to an integrated structure long spiral bored cast-in-place pile reinforcement cage and a manufacturing method thereof. Background Art

[0002] At present, when most construction sites are constructing long spiral bored and grouted piles (also known as the post-insertion steel cage process), the tapered mouth of the steel cage is usually formed by single-sided welding of the main reinforcement. When the steel cage is implanted in the concrete and the vibrating hammer is started, the welding part of the tapered mouth of the steel cage is easily detached, causing the steel cage inlet pipe to pass through the tapered mouth, and then causing the steel cage to fail to reach the design depth. In addition, in the prior art, no steel casing protection device is set at the top of the pile, and the verticality of the steel cage and the quality of pile positioning are difficult to control. Moreover, this traditional method requires a lot of manpower under tight construction schedules, which leads to increased costs, correspondingly increased risks, and difficult to guarantee construction quality.

[0003] Therefore, how to provide an integrated structure long spiral bored pile reinforcement cage and its manufacturing method, and how to ensure the construction quality by changing the reinforcement cage manufacturing method and applying it, has become a technical problem that technical personnel in this field urgently need to solve. Summary of the invention

[0004] The purpose of the present invention is to provide an integrated structure long spiral bored pile reinforcement cage and a manufacturing method thereof, so as to solve the technical problem that the verticality of the reinforcement cage and the pile positioning of the existing long spiral bored pile (that is, the post-insertion reinforcement cage process) are difficult to control; at the same time, it also solves the technical defect that the welding place of the tapered mouth of the reinforcement cage falls off, causing the reinforcement cage introduction pipe to pass through the tapered mouth, resulting in the reinforcement cage failing to reach the design required depth.

[0005] In order to achieve the above object, the present invention adopts the following technical scheme: An integrated structure long spiral bored pile reinforcement cage, comprising: a steel casing protection device, and a steel pipe reinforced conical mouth protection device connected to the steel casing protection device; The steel casing protection device comprises: a steel casing body, and a ship-shaped pile diameter clamp connected to the steel casing body; The steel pipe reinforced conical mouth protection device is made of steel pipe and is welded on the conical body of the steel bar; A position sensor is installed on the top of the steel casing protection device, and the position sensor is used to obtain the pile position and the steel cage position and verticality information.

[0006] In actual application, the steel casing body is welded from 3mm steel plates and is cylindrical in shape, and the steel casing body is arranged at the designed pile top elevation.

[0007] The ship-shaped pile diameter clamps are made of Ф8 threaded steel bars and are arranged at intervals along the vertical direction of the pile.

[0008] Specifically, the steel pipe reinforced cone mouth protection device is made of a DN100 steel pipe and has a length of 150 mm; the welding point between the steel pipe and the steel bar cone body is connected by spot welding.

[0009] A method for manufacturing an integrated structure long spiral bored pile reinforcement cage comprises the following steps: Step S1: before construction, using BIM technology according to the design drawings, extract the size and layout of the steel casing protection device and the steel pipe reinforcement cone mouth protection device; Step S2: The steel casing body of the steel casing protection device is welded with 3mm steel plates to a height of 1000m and arranged at the designed pile top position; Step S3, the position sensor extracts the pile position and the position and verticality information of the reinforcement cage, and the output interface outputs the processed information to the pile driver or crane operator; Step S4: The ship-shaped pile diameter card is made of Ф8 threaded steel bars, 50 mm high and 410 mm long, and is welded to the main reinforcement of the steel cage of the steel casing body; Step S5: The steel pipe reinforcement tapered mouth protection device is processed with a DN100 steel pipe with a length of 150 mm. The steel pipe is sleeved on the welded steel bar cone and spot welded on the bottom.

[0010] Compared with the prior art, the integrated structure long spiral bored pile reinforcement cage and the manufacturing method thereof of the present invention have the following advantages: The integrated structure long spiral bored pile steel cage and the manufacturing method thereof provided by the present invention are that when in use, the ship-shaped pile diameter clamp is welded and fixed to the main reinforcement of the steel cage of the steel casing body, and the steel casing body is arranged at the designed pile position, and the pile foundation point position is ensured, and the verticality of the steel cage insertion is received and processed by the position sensor and the information is transmitted to the pile driver or crane operator at the same time; the tapered mouth of the steel cage is welded and reinforced with a steel pipe, and when the steel cage is implanted in the concrete and the vibrating hammer is started, the welding part of the tapered mouth of the steel cage can be effectively prevented from falling off, thereby avoiding the steel cage introduction pipe from passing through the tapered mouth, and the steel cage reaches the designed depth; in addition, the integrated structure long spiral bored pile steel cage and the manufacturing method thereof provided by the present invention are simple and practical in overall operation, and have high installation and disassembly efficiency during construction, can be reused, and effectively reduce construction costs, thereby achieving the purposes of safety, economy and efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 A schematic structural diagram of a steel casing protection device in a steel cage of a long spiral bored pile provided by an embodiment of the present invention; Figure 2A schematic structural diagram of a tapered mouth protection device for reinforcing steel pipes in a reinforcement cage of a long spiral bored pile provided in an embodiment of the present invention.

[0012] Reference numerals: 1- steel casing protection device; 11- steel casing body; 12- ship-shaped pile diameter card; 2- steel pipe reinforced cone mouth protection device; 3- position sensor. DETAILED DESCRIPTION

[0013] For ease of understanding, the integrated structure long spiral bored pile reinforcement cage and the manufacturing method thereof provided by the embodiments of the present invention are described in detail below in conjunction with the accompanying drawings of the specification.

[0014] The embodiment of the present invention provides an integrated structure long spiral bored pile reinforcement cage, such as Figure 1 and Figure 2 As shown, it includes: a steel casing protection device 1, and a steel pipe reinforced conical mouth protection device 2 connected to the steel casing protection device 1; The steel casing protection device comprises 1: a steel casing body 11, and a ship-shaped pile diameter clamp 12 connected to the steel casing body 11; The steel pipe reinforced conical mouth protection device 2 is made of a steel pipe and is welded on the steel bar conical body; A position sensor 3 is installed on the top of the steel casing protection device 1, and the position sensor 3 is used to obtain the pile position and the steel cage position and verticality information.

[0015] The embodiment of the present invention further provides a method for manufacturing a steel cage of an integrated long spiral bored pile, comprising the following steps: Step S1: before construction, using BIM technology according to the design drawings, extract the size and layout of the steel casing protection device 1 and the steel pipe reinforcement tapered mouth protection device 2; Step S2, the steel casing body 11 of the steel casing protection device 1 is made of 3mm steel plate welding and 1000m high, and arranged at the designed pile top position; Step S3, the position sensor 3 extracts the pile position and the position and verticality information of the reinforcement cage, and the output interface outputs the processed information to the pile driver or crane operator; Step S4, the ship-shaped pile diameter card 12 is made of Ф8 threaded steel bars, 50mm high and 410mm long, and is welded to the main reinforcement of the steel cage of the steel casing body 11; Step S5, steel pipe reinforcement tapered mouth protection device 2 is processed with DN100 steel pipe, length 150mm, the steel pipe is sleeved on the welded steel bar cone, and the bottom is spot welded again.

[0016] Compared with the prior art, the integrated structure long spiral bored pile reinforcement cage and the manufacturing method thereof described in the embodiment of the present invention have the following advantages: The embodiment of the present invention provides an integrated structure long spiral bored pile steel cage and a manufacturing method thereof. When in use, the ship-shaped pile diameter clamp 12 is welded and fixed to the main steel cage reinforcement of the steel casing body 11, and the steel casing body 11 is arranged at the designed pile position to ensure the pile foundation point position. The verticality of the steel cage insertion is received and processed by the position sensor 3 and the information is transmitted to the pile driver or crane operator at the same time. The conical mouth of the steel cage is welded and reinforced with a steel pipe. When the steel cage is implanted in the concrete and the vibrating hammer is started, the conical mouth of the steel cage can be effectively prevented from falling off at the welding point, thereby avoiding the steel cage introduction pipe from passing through the conical mouth and allowing the steel cage to reach the designed depth. In addition, the embodiment of the present invention provides an integrated structure long spiral bored pile steel cage and a manufacturing method thereof. The overall operation is simple and practical, and the installation and disassembly efficiency is high during construction. It can be reused and the construction cost is effectively reduced, achieving the purpose of safety, economy and efficiency.

[0017] In practical application, such as Figure 1 and Figure 2 As shown, the steel casing body 11 can be welded from 3mm steel plates and present a cylindrical shape, and the steel casing body 11 can be set at the designed pile top elevation.

[0018] Among them, Figure 1 and Figure 2 As shown, the ship-shaped pile diameter clamps 12 can be made of Ø8 threaded steel bars and arranged at intervals along the vertical direction of the pile.

[0019] Specifically, Figure 1 and Figure 2 As shown, the steel pipe reinforced cone mouth protection device 2 can be made of a DN100 steel pipe with a length of 150 mm; the welding point between the steel pipe and the steel bar cone is connected by spot welding.

[0020] During construction, you can first measure and lay out the lines and verify the pile position, then use a drill to drill holes, then pump concrete to form piles, then make (integrated structure long spiral bored piles) steel cages, then hoist the steel cages for construction, and finally clean the pile heads.

[0021] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. An integrated structure long spiral bored pile reinforcement cage, characterized in that: include: A steel casing protection device, and a steel pipe reinforced conical mouth protection device connected to the steel casing protection device; The steel casing protection device comprises: a steel casing body, and a ship-shaped pile diameter clamp connected to the steel casing body; The steel pipe reinforced conical mouth protection device is made of steel pipe and is welded on the conical body of the steel bar; A position sensor is installed on the top of the steel casing protection device, and the position sensor is used to obtain the pile position and the steel cage position and verticality information.

2. The integrated structure long spiral bored pile reinforcement cage according to claim 1 is characterized in that: The steel casing body is welded from 3mm steel plates and is cylindrical in shape, and the steel casing body is arranged at the designed pile top elevation.

3. The integrated structure long spiral bored pile reinforcement cage according to claim 1 or 2, characterized in that: The ship-shaped pile diameter clamps are made of Ф8 threaded steel bars and are arranged at intervals along the vertical direction of the pile.

4. The integrated structure long spiral bored pile reinforcement cage according to claim 3 is characterized in that: The steel pipe reinforced conical mouth protection device is made of a DN100 steel pipe and has a length of 150 mm; the welding point between the steel pipe and the steel bar cone is connected by spot welding.

5. A method for manufacturing an integrated structure long spiral bored pile reinforcement cage, characterized in that: The following steps are involved: Before construction, the size and layout of the steel casing protection device and the steel pipe reinforcement cone protection device were extracted using BIM technology according to the design drawings; The steel casing body of the steel casing protection device is made of 3mm steel plate welding, 1000m high, and arranged at the designed pile top position; The position sensor extracts the pile position and the position and verticality information of the reinforcement cage, and the output interface outputs the processed information to the pile driver or crane operator; The ship-shaped pile diameter card is made of Ф8 threaded steel bars, 50mm high and 410mm long, and is welded to the main reinforcement of the steel cage of the steel casing body; The steel pipe reinforced cone mouth protection device is made of DN100 steel pipe with a length of 150mm. The steel pipe is put on the welded steel bar cone and spot welded at the bottom.