Relay protection mirror image simulation training system

Through the relay protection mirror simulation training system, the mirror synchronization technology is used to simulate power system failures and abnormalities, and interactive training between teachers and operation and maintenance students is achieved, solving the problem that existing training methods are difficult to improve operation and maintenance personnel skills, significantly improving operation and maintenance The students' skills and emergency response capabilities.

CN119323911APending Publication Date: 2025-01-17CHINA SOUTHERN POWER GRID COMPANY
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411454151.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-17
Publication Date
2025-01-17

AI Technical Summary

Technical Problem

The existing relay protection training methods are difficult to systematically reflect the phenomena in power system failures and abnormal processes, resulting in poor improvement of skills for operation and maintenance personnel.

Method used

A relay protection mirror simulation training system was designed, including mirror simulation module, login registration center module, training business management control module and database module. Through mirror synchronization technology, the basic model of the actual factory station is simulated, and the simulation training scenario is generated to realize Interactive training between teachers and operation and maintenance students improves the training effect.

Benefits of technology

The system can systematically reflect power system failures and abnormal processes, improve the skill level and emergency response capabilities of operation and maintenance trainees, and provide a more practical and effective training experience.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119323911A_ABST
    Figure CN119323911A_ABST
Patent Text Reader

Abstract

The invention discloses a relay protection mirror image simulation training system, and relates to the technical field of relay protection training, the relay protection mirror image simulation training system comprises a mirror image simulation module, a login registration center module, a training business management control module and a database module, the mirror image simulation module simulates a basic model and a section state of an actual production plant station by using a mirror image synchronization technology; a production plant station simulation basic model is generated and used for forming a relay protection simulation training scene model for teachers and operation and maintenance students to carry out relay protection simulation training services, phenomena in the power system fault and abnormal process can be systematically reflected, high simulation is carried out on a relay protection scene, interaction of the teachers, the operation and maintenance students and the relay protection scene is achieved, and the training efficiency is improved. The training effect is improved, and the skill level of operation and maintenance students is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of relay protection training, and more specifically, to a relay protection mirror simulation training system. Background Art

[0002] Relay protection can ensure the safety and normal operation of the power system, and is one of the most practical and effective technical means for the maintenance and protection of the power system. The smooth implementation of relay protection operations, while eliminating power failures, not only ensures the normal operation of social life and economy, but also guarantees social stability and the safety of people's lives and property to a certain extent.

[0003] At present, a new power system with new energy as the main body is gradually taking shape, and the power system regulation and fault mechanism will become more complex. Therefore, the new power system has put forward higher requirements for the secondary professional operation and maintenance management level of the power grid. At the same time, the increasingly complex environment has put forward higher standards for the emergency response and fault abnormality handling capabilities of the operation and maintenance personnel, requiring the operation and maintenance personnel to be on duty on a regular basis and be familiar with the relevant skills required for duty, including the steps, process methods of business operations such as access substation debugging, remote control, and daily operation and maintenance, as well as emergency handling skills in the event of power grid failure, protection alarm, system operation abnormality, network abnormality, etc.

[0004] In order to improve the operation and maintenance level of operation and maintenance personnel, it is necessary to train them. At present, the training of relay protection at the dispatching end mainly adopts the method of learning the prescribed materials in the regulations and is carried out in an offline form. This method is difficult to systematically reflect the problems and phenomena in the process of power system failure and abnormality. Trainees lack practical operation and disposal, and it is difficult to improve their experience and skills. Summary of the invention

[0005] In order to solve the problem that the current relay protection training method is difficult to systematically reflect the phenomena in the power system fault and abnormal process, and the training effect is poor, the present invention proposes a relay protection mirror simulation training system, which highly simulates the relay protection scene, realizes the interaction between instructors, operation and maintenance trainees and relay protection scenes, improves the training effect, and improves the skill level of operation and maintenance trainees.

[0006] In order to solve the above technical problems, the technical solution of the present invention is as follows:

[0007] This application proposes a relay protection mirror simulation training system, including:

[0008] The mirror simulation module is used to obtain the basic model, section information, operation information and operation files of the actual production plant, and use the mirror synchronization technology to simulate the basic model and section status of the actual production plant to generate the basic model of the production plant simulation;

[0009] The login and registration center module is used for the login and registration of instructors and operation and maintenance trainees, so that instructors and operation and maintenance trainees can obtain login, query, and application operation permissions related to relay protection training, and record the unique identity ID of instructors and operation and maintenance trainees;

[0010] The training business management and control module is used to receive the basic simulation model of the production plant and station, and form a relay protection simulation training scenario model based on the basic simulation model of the production plant and station for instructors and operation and maintenance trainees to conduct relay protection simulation training business;

[0011] The database module is used to store the basic models, section information, operation information and operation files of the actual production plant obtained by the mirror simulation module, and to store the relay protection simulation training scenario models and relay protection simulation training scenario model section information files required for instructors and operation and maintenance trainees to conduct relay protection simulation training business.

[0012] Preferably, the training business management control module includes an operation and maintenance trainee management control submodule and an instructor management control submodule, and the operation and maintenance trainee management control submodule includes: a simulation scene management unit, a simulation operation application unit, an alarm monitoring unit, an instructor interaction unit, and a training process playback unit.

[0013] The simulation scenario management unit is used to instantiate the relay protection simulation training scenario model according to the identity ID of the operation and maintenance trainee when the operation and maintenance trainee loads the relay protection simulation training scenario;

[0014] The simulation operation application unit is used to simulate relay protection simulation training services and provide relay protection simulation training service operation applications;

[0015] The alarm monitoring unit is used to monitor the abnormalities and errors that occur during the training operation of the operation and maintenance trainees, and issue alarms;

[0016] The instructor interaction unit is used for the operation and maintenance trainee to receive emergency response events and commands sent temporarily by the instructor, and send the operation and operation results of the operation and maintenance trainee to the instructor, and send the operation and maintenance trainee's simulated actual fault handling process, typical abnormality analysis and handling results, and personal simulation training notification to the on-duty instructor;

[0017] The training process playback unit is used for operation and maintenance trainees to review the entire process of their training operations through playback.

[0018] Preferably, the teacher management control submodule includes a setting management unit, a teaching plan management unit, a training management unit, a preset plan management unit, a student monitoring management unit and an evaluation management unit;

[0019] Among them, the setting management unit is used to set the limit of the number of production plants and stations included in the relay protection simulation training scenario when the operation and maintenance trainees undergo relay protection simulation training, and browse, compile and edit the specified operation process of application operations related to relay protection training;

[0020] The lesson plan management unit is used by teachers to compile training plans, set up training plans, and manage historical lesson plans;

[0021] The training management unit is used to manage training matters, including starting training, pausing training, resuming training, replaying training, and inserting temporary training events;

[0022] A preset plan management unit is used to preset training plans;

[0023] The trainee monitoring management unit is used to monitor the abnormalities that occur during the training process of the operation and maintenance trainees, the results of fault handling, the notification information during the interactive training with the instructor, the notification of the completion of the training, and the notification of personal simulation training;

[0024] The evaluation management unit includes an objective evaluation subunit and a subjective evaluation subunit. The objective evaluation subunit is used to provide quantitative evaluation results of operation and maintenance trainees, and the subjective evaluation subunit is used to provide subjective non-quantitative evaluation results of operation and maintenance trainees. The evaluation management unit outputs a comprehensive evaluation result based on the quantitative evaluation result and the subjective non-quantitative evaluation result.

[0025] According to the above-mentioned technical means, the objective evaluation sub-unit provides standards, and combined with the instructor's monitoring of the operation and maintenance trainees' operations, subjective qualitative non-quantitative evaluation guidance suggestions are given, and finally a comprehensive evaluation result is formed. It is of great significance to accurately reflect the skill mastery of operation and maintenance trainees and guide the rapid improvement of trainees' technical level.

[0026] Preferably, when the teaching plan management unit is used for instructors to prepare training plans, it receives the production plant simulation basic model generated by the mirror simulation module. The instructor creates a relay protection simulation training scenario for the operation and maintenance trainees based on the production plant simulation basic model, determines the number of production plants included in each relay protection simulation training scenario, forms a simulation basic model, and backs up the section information of the production plants;

[0027] The instructor frames the production plant based on the production plant simulation basic model, forms a new relay protection simulation training scenario, or calls the historical relay protection simulation scenario in the historical training lesson plan for modification. When modifying the historical training lesson plan, the production plant simulation basic model in the historical training lesson plan is compared with the real-time production plant simulation basic model. When there is a difference between the production plant simulation basic model and the real-time production plant simulation basic model, the lesson plan management unit gives a prompt, and the instructor chooses whether to replace the production plant simulation basic model;

[0028] Receive and edit existing fault reports in the operation information in the database module to form typical fault handling training cases for the device and typical abnormal handling training cases for system operation; the instructor sets the simulation parameters, sets the training start time, duration, and lesson plan name, and after the training plan is compiled, save it to the database module.

[0029] Preferably, in the simulation scenario management unit, the relay protection simulation training scenario loaded by the operation and maintenance trainee includes a real-time teaching plan scenario and a historical teaching plan scenario. The real-time teaching plan scenario is a relay protection simulation training scenario in the training plan issued by the instructor, which is created based on the production plant simulation basic model. After the operation and maintenance trainee logs in to the login registration center module, he completes the simulation training according to the relay protection simulation training scenario model corresponding to the real-time teaching plan scenario;

[0030] The historical teaching scenario is used for daily skill training of operation and maintenance trainees. The simulation scenario management unit detects whether the historical teaching scenario is compatible with the production plant simulation basic model, and gives a prompt when it is not compatible. The operation and maintenance trainee decides whether to continue. When the operation and maintenance trainee chooses to continue, the simulation scenario management unit sends a simulation exercise notification to the instructor, and then starts the training;

[0031] After the operation and maintenance trainees finish the training operation, they save the relay protection simulation training scenario model data as a section information file and store it in the database module.

[0032] Preferably, after the operation and maintenance trainees load the relay protection simulation training scenario, they enter the training state. In the training state, the production plant and equipment names simulated by each operation and maintenance trainee are consistent with the real-time state, but the equipment ID is different. They are numbered according to "original production plant / equipment ID_user ID_production plant state" to form a unique identifier.

[0033] According to the above-mentioned technical means, for the teaching simulation scene of the same section, the self-recovery technology of differential instantiation is adopted to create the same simulation scene for each operation and maintenance trainee, which effectively solves the scene model conflict problem when multiple operation and maintenance trainees simulate the same production plant, and ensures that the device name displayed on the simulation interface of each operation and maintenance trainee is consistent.

[0034] Preferably, the relay protection simulation training service includes an operation and maintenance simulation training service, a power grid fault handling simulation training service and a remote control operation simulation training service.

[0035] Preferably, the operation and maintenance simulation training business includes: data blocking handling simulation training, IP blocking handling simulation training, device operation abnormality handling simulation training, power system operation abnormality handling simulation training, device maintenance listing handling simulation training, production plant substation access simulation training;

[0036] Among them, data blocking handling simulation training is used to simulate the high-frequency alarm transmission of a small number of non-important signals in actual production plants and stations, and train operation and maintenance trainees to handle the abnormal high-frequency alarm transmission of a small number of non-important signals;

[0037] IP blocking handling simulation training is used to simulate the traffic storm caused by network anomalies in production plants and train operation and maintenance trainees to handle such anomalies;

[0038] Device operation abnormality handling simulation training is used to load typical fault handling training case scenarios pre-set by the instructor, simulating the occurrence of important alarms in the device to train operation and maintenance trainees to detect and handle alarms;

[0039] Power system operation abnormality handling simulation training is used to load the typical system operation abnormality handling training case scenarios pre-set by the instructor, simulating the abnormal operation of the power system to train the operation and maintenance trainees to detect abnormalities;

[0040] Equipment maintenance tag-out simulation training is used to train operation and maintenance trainees to master the operation methods of equipment tag-out and tag-out;

[0041] Production plant substation access simulation training is used to train operation and maintenance trainees on the process and methods of accessing production plant substations.

[0042] Preferably, the power grid fault handling simulation training service is used to simulate the emergency response capabilities of operation and maintenance trainees in responding to abnormal reports and analyzing faults after a power system fault occurs; in the training plan formed by the teaching plan management unit, it supports relay protection simulation scenarios in which preset protection action events are missing or erroneous, recording files are missing or erroneous, and analysis results are incorrect.

[0043] Preferably, the remote control operation simulation training service is used to train operation and maintenance trainees to master the process and methods of remote operation and the ability to handle abnormal situations during operation; in the training plan formed by the teaching plan management unit, it supports relay protection simulation scenarios in which the preset device name does not correspond to the interval and the modification of the set value exceeds the limit.

[0044] The above-mentioned technical means provide great convenience for trainees to quickly locate relay protection business problems, improve operation and maintenance and abnormal handling capabilities during training.

[0045] Compared with the prior art, the technical solution of the present invention has the following beneficial effects:

[0046] The present invention proposes a relay protection mirror simulation training system, comprising: a mirror simulation module, a login registration center module, a training business management control module and a database module. The mirror simulation module utilizes mirror synchronization technology to simulate the basic model and section state of an actual production plant and generates a basic simulation model of the production plant, which is used to form a relay protection simulation training scenario model for instructors and operation and maintenance trainees to conduct relay protection simulation training business. It can systematically reflect the phenomena in the process of power system failure and abnormality, highly simulate the relay protection scenario, realize the interaction between instructors, operation and maintenance trainees and relay protection scenarios, improve the training effect, and improve the skill level of the operation and maintenance trainees. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] Figure 1 This is an overall structural diagram of the relay protection mirror simulation training system proposed in an embodiment of the present invention;

[0048] Figure 2 A specific structural composition diagram of the relay protection mirror simulation training system proposed in an embodiment of the present invention is shown;

[0049] Figure 3 The flowchart of the training plan preparation proposed in the embodiment of the present invention is shown. DETAILED DESCRIPTION

[0050] The drawings are for illustrative purposes only and should not be construed as limiting the present patent;

[0051] In order to better illustrate the present embodiment, some parts in the drawings may be omitted, enlarged or reduced, and do not represent the size of the actual product;

[0052] It is understandable to those skilled in the art that some well-known structures and their descriptions may be omitted in the drawings.

[0053] The technical solution of the present invention is further described below in conjunction with the accompanying drawings and embodiments.

[0054] Example 1

[0055] This embodiment proposes a relay protection mirror simulation training system, which can provide a complete mirror simulation environment for operation and maintenance personnel to complete operation training of various simulation applications and improve the daily operation and maintenance and emergency response capabilities of operation and maintenance personnel. The overall structure diagram of the system can be found in Figure 1 ,include:

[0056] The mirror simulation module is used to obtain the basic model, section information, operation information and operation files of the actual production plant, and use the mirror synchronization technology to simulate the basic model and section status of the actual production plant to generate the basic model of the production plant simulation;

[0057] The login and registration center module is used for the login and registration of instructors and operation and maintenance trainees, so that instructors and operation and maintenance trainees can obtain login, query, and application operation permissions related to relay protection training, and record the unique identity ID of instructors and operation and maintenance trainees;

[0058] The training business management and control module is used to receive the basic simulation model of the production plant and station, and form a relay protection simulation training scenario model based on the basic simulation model of the production plant and station for instructors and operation and maintenance trainees to conduct relay protection simulation training business;

[0059] The database module is used to store the basic models, section information, operation information and operation files of the actual production plant obtained by the mirror simulation module, and to store the relay protection simulation training scenario models and relay protection simulation training scenario model section information files required for instructors and operation and maintenance trainees to conduct relay protection simulation training business.

[0060] Among them, the mirror synchronization technology can be implemented based on digital twins. The login registration center module registers the logon user as a unique ID for teachers and operation and maintenance trainees to register, log in, and obtain permissions. After teachers and operation and maintenance trainees log in to the system, they automatically complete the registration in the login registration center module and record the unique ID. According to the actual division of labor, the user and user group names and their permissions are customized. All login, query, application operations and other functions of the system require corresponding permissions to be performed. The mirror simulation module has data synchronization functions, including: supporting teachers to control the actual production plant through soft switches to transmit information data to the mirror simulation module, including the basic model, cross-section information, operation information and operation files of the actual production plant.

[0061] Example 2

[0062] This embodiment proposes a specific structure of the relay protection mirror simulation training system, which includes a mirror simulation module, a login registration center module, a training business management control module and a database module as a whole, and has some specific components, see Figure 2 The training business management and control module includes an operation and maintenance trainee management and control submodule and an instructor management and control submodule. The operation and maintenance trainee management and control submodule includes: a simulation scene management unit, a simulation operation application unit, an alarm monitoring unit, an instructor interaction unit, and a training process playback unit.

[0063] The simulation scenario management unit is used to instantiate the relay protection simulation training scenario model according to the identity ID of the operation and maintenance trainee when the operation and maintenance trainee loads the relay protection simulation training scenario;

[0064] The simulation operation application unit is used to simulate relay protection simulation training services and provide relay protection simulation training service operation applications;

[0065] The alarm monitoring unit is used to monitor the abnormalities and errors that occur during the training operation of the operation and maintenance trainees, and issue alarms;

[0066] The instructor interaction unit is used for the operation and maintenance trainee to receive emergency response events and commands sent temporarily by the instructor, and send the operation and operation results of the operation and maintenance trainee to the instructor, and send the operation and maintenance trainee's simulated actual fault handling process, typical abnormality analysis and handling results, and personal simulation training notification to the on-duty instructor;

[0067] The training process playback unit is used for operation and maintenance trainees to review the entire process of their training operations through playback.

[0068] See also Figure 2 ,The teacher management and control submodule includes a setting management unit, a teaching plan management unit, a training management unit, a preset plan management unit, a trainee monitoring management unit, and an evaluation management unit;

[0069] Among them, the management unit is set to set the limit on the number of production plants and stations included in the relay protection simulation training scenario when the operation and maintenance trainees undergo relay protection simulation training, and to browse, compile and edit the operating procedures of specified application operations related to relay protection training.

[0070] The lesson plan management unit is used for teachers to prepare training plans, set up training plans and manage historical lesson plans.

[0071] The relay protection mirror simulation training system proposed in this embodiment supports the open setting of simulation application functions and the editing of simulation processes of various functions, and supports teachers to browse and compile detailed operation processes of designated simulation applications. The teaching plan management unit also includes teacher preparation and sending of teaching plans and historical teaching plan management.

[0072] like Figure 3 The lesson plan preparation process shown is carried out by the following steps:

[0073] (1) The instructor creates relay protection simulation training scenarios for operation and maintenance trainees based on the production plant simulation basic model, determines the number of plants and stations included in each simulation scenario, and forms a simulation basic model;

[0074] (2) Back up the model section data of the plant;

[0075] (3) The teacher frames the relevant plants based on the simulation basic model, forms a new simulation scenario, or calls the historical simulation scenario in the historical teaching plan for modification. When the teacher chooses to modify the historical teaching plan, the system compares the plant model in the historical teaching plan with the real-time plant model. If there is a difference, a prompt is given, and the teacher can choose whether to replace the new plant model;

[0076] (4) The instructor selects the simulation application supported by the system, compiles the training content, and sets the training standards, including normal, error, and corresponding correct operation standards; the events of the simulation application can be set to occur regularly or at a specified time;

[0077] (5) Edit the existing fault reports in the database module to form typical fault handling training cases and system operation typical abnormal handling training cases. The cases support the setting of abnormal scenarios such as incomplete report information, missing / wrong action events, missing / wrong recordings, and incorrect analysis results;

[0078] (6) The instructor sets simulation-related parameters, including plant-station communication parameters, line parameters, device maintenance signboard, and device setting sheet;

[0079] (7) Set the training start time, duration, and lesson plan name;

[0080] (8) After the lesson plan is completed, the lesson plan name, creation time, training content, trainees, scores, and plant model sections backed up during this training will be saved in the database module.

[0081] The instructor frames the production plant based on the production plant simulation basic model, forms a new relay protection simulation training scenario, or calls the historical relay protection simulation scenario in the historical training lesson plan for modification. When modifying the historical training lesson plan, the production plant simulation basic model in the historical training lesson plan is compared with the real-time production plant simulation basic model. When there is a difference between the production plant simulation basic model and the real-time production plant simulation basic model, the lesson plan management unit gives a prompt, and the instructor chooses whether to replace the production plant simulation basic model;

[0082] Receive and edit existing fault reports in the operation information in the database module to form typical fault handling training cases for the device and typical abnormal handling training cases for system operation; the instructor sets the simulation parameters, sets the training start time, duration, and lesson plan name, and after the training plan is compiled, save it to the database module.

[0083] The training management unit is used to manage training matters, including starting training, pausing training, resuming training, replaying training and inserting temporary training events; starting training: after the instructor confirms the lesson plan, he / she presses the start button, the training starts and the timing starts, and the timing of related scheduled services set in the lesson plan also starts at the same time; pausing training: during the training process, it supports pausing the specified training service, the timing stops, and the timing of related scheduled services set in the lesson plan is also paused at the same time; resuming training: after the training is paused, it supports resuming the specified training service, the training can continue, and the timing of related scheduled services set in the lesson plan resumes; replaying training: after the training is completed, it supports replaying the training process records; inserting training events: during the training process, the instructor can temporarily insert events and send them immediately to relevant operation and maintenance trainees.

[0084] The preset plan management unit is used to preset training plans; it supports instructors to preset training plans and send them to operation and maintenance trainees at regular intervals, or allows operation and maintenance trainees to call them during personal simulation exercises.

[0085] The trainee monitoring management unit is used to monitor the abnormalities that occur during the training process of the operation and maintenance trainees, the results of fault handling, the notification information during the interactive training with the instructor, the notification of the completion of the training, and the notification of personal simulation training;

[0086] The evaluation management unit includes an objective evaluation subunit and a subjective evaluation subunit. The objective evaluation subunit is used to provide quantitative evaluation results of operation and maintenance trainees, and the subjective evaluation subunit is used to provide subjective non-quantitative evaluation results of operation and maintenance trainees. The evaluation management unit outputs a comprehensive evaluation result based on the quantitative evaluation result and the subjective non-quantitative evaluation result.

[0087] Specifically, the objective evaluation subunit provides the quantitative evaluation results of the operation and maintenance trainees in the following steps:

[0088] (1) The instructor browses and edits the process steps of typical simulation application business;

[0089] (2) The instructor first sets the total score for the simulation application, and then sets a quantitative score for each step based on the importance of each operation step;

[0090] (3) During the student's operation, the system records the correct and incorrect results of each step;

[0091] (4) After the student completes the operation, the system automatically calculates the total score based on the scoring criteria set by the instructor and the student's operation results.

[0092] The steps for the subjective evaluation subunit to provide the subjective non-quantitative evaluation results of the operation and maintenance trainees are as follows:

[0093] (1) The instructor records the overall evaluation and guidance suggestions of the trainee's operation;

[0094] (2) Record the trainee’s satisfaction with the operation, including excellent, good, average, and poor.

[0095] (3) Support teachers to set standard scores for excellent, good, fair, and poor;

[0096] The evaluation management unit outputs the comprehensive evaluation results according to the quantitative evaluation results and the subjective non-quantitative evaluation results as follows:

[0097] (1) Support teachers to set the proportion of objective and subjective evaluation in the final score;

[0098] (2) Automatically calculate the comprehensive score based on the set proportion. Comprehensive score = objective score × proportion + subjective score × proportion;

[0099] (3) Keep records of the details of each training session, including: name of the trainee, operation time, name of the lesson plan, overall score, objective score and scores of each step, subjective score and instructor's suggestions, etc.;

[0100] (4) Supports statistical analysis of students' historical training scores in the form of line charts, bar charts, etc., visually displaying the students' growth trajectory.

[0101] (5) Support ranking of trainees’ training results by training content.

[0102] In this embodiment, in the simulation scenario management unit, the relay protection simulation training scenario loaded by the operation and maintenance trainee includes a real-time teaching plan scenario and a historical teaching plan scenario. The real-time teaching plan scenario is a relay protection simulation training scenario in the training plan issued by the instructor, which is created based on the production plant simulation basic model. After the operation and maintenance trainee logs in to the login registration center module, he completes the simulation training according to the relay protection simulation training scenario model corresponding to the real-time teaching plan scenario;

[0103] The historical teaching scenario is used for daily skill training of operation and maintenance trainees. The simulation scenario management unit detects whether the historical teaching scenario is compatible with the production plant simulation basic model, and gives a prompt when it is not compatible. The operation and maintenance trainee decides whether to continue. When the operation and maintenance trainee chooses to continue, the simulation scenario management unit sends a simulation exercise notification to the instructor, and then starts the training;

[0104] After the operation and maintenance trainees finish the training operation, they save the relay protection simulation training scenario model data as a section information file and store it in the database module.

[0105] After the operation and maintenance trainees load the relay protection simulation training scenario, they enter the training state. In the training state, the production plant and equipment names simulated by each operation and maintenance trainee are consistent with the real-time state, but the equipment ID is different. They are numbered according to "original production plant / equipment ID_user ID_production plant state" to form a unique identification.

[0106] For the teaching simulation scenario of the same section, the self-recovery technology of differential instantiation is used to create the same simulation scenario for each operation and maintenance trainee, which effectively solves the scene model conflict problem when multiple operation and maintenance trainees simulate the same production plant, and ensures that the device names displayed on the simulation interface of each operation and maintenance trainee are consistent.

[0107] Example 3

[0108] This embodiment illustrates the relay protection simulation training service. In this embodiment, the relay protection simulation training service includes an operation and maintenance simulation training service, a power grid fault handling simulation training service, and a remote control operation simulation training service.

[0109] During specific simulation training, a wizard-style method is used to guide operation and maintenance trainees to complete simulation operations. Operation and maintenance trainees are supported to complete operation result confirmation in different ways such as single selection, multiple selection, and text input, and record and save them. The system promptly gives prompts on whether the operation results are correct or not according to the standards preset by the instructor. Operation and maintenance trainees conduct simulation training according to the prompts, and can repeatedly practice the current step content and proceed to the next step after becoming proficient in it. The system interface proposed in this embodiment supports visual display of each operation step in the form of a flowchart, and presents the operation results of each step in different colors (green: correct, red: wrong, blue: not performed). When an abnormality or error occurs during the trainee's operation, it supports prompting in the form of an alarm window.

[0110] The operation and maintenance simulation training business includes: data blocking treatment simulation training, IP blocking treatment simulation training, device operation abnormality treatment simulation training, power system operation abnormality treatment simulation training, device maintenance hanging treatment simulation training, production plant substation access simulation training;

[0111] Among them, data blocking handling simulation training is used to simulate the high-frequency alarm transmission of a small number of non-important signals in actual production plants and stations, and train operation and maintenance trainees to handle the abnormal high-frequency alarm transmission of a small number of non-important signals;

[0112] The specific steps are:

[0113] (1) When an abnormality is found, the training lesson plan presets the normal transmission signal and includes several high-frequency transmission signal points. By publishing the lesson plan, the corresponding students are selected and the simulation substation is notified to send the signal content preset in the lesson plan. The corresponding data model is generated according to different students. Students need to find the frequent data signal in the simulation operation and enter the plant name, equipment name, signal point name and judgment conclusion of the frequent signal in the operation conclusion through options and subjective conclusion filling;

[0114] (2) Data suppression: After the trainee completes the suppression operation of the corresponding signal point through the interface, he / she can input the operation conclusion through the options in the operation conclusion;

[0115] (3) Check the results. After checking whether there are still a large number of frequent data, the students can enter the check conclusions through the options in the operation conclusion;

[0116] (4) Release the suppression. After receiving the abnormal signal sending completion notification preset in the teaching plan and sending it to the simulation substation, the students complete the release of the suppression of the corresponding signal point through the interface, and enter the operation conclusion through the option method in the operation conclusion. The system prompts whether the release is successful.

[0117] (5) Report results: Students input reasons and treatment results through the interface and send a notification to the instructor.

[0118] IP blocking handling simulation training is used to simulate the traffic storm caused by network anomalies in production plants and train operation and maintenance trainees to handle such anomalies. The specific steps are as follows:

[0119] (1) When an abnormality is found, the training lesson plan presets a normal signal transmission and includes a large number of high-frequency transmission signals. The simulation substation is notified to send the signal content preset in the lesson plan to simulate a network storm. The trainees need to find the relevant substations that frequently send data signals and enter the plant station name and IP address of the frequent signal through options in the operation conclusion;

[0120] (2) Block the IP. The trainee disconnects from the substation through the interface and modifies the firewall configuration to prohibit the corresponding plant station IP address from communicating with the main station. Then, the trainee enters the operation conclusion through the option mode in the operation conclusion.

[0121] (3) Check results: After checking that the network storm has been eliminated, the trainee can enter the check results through the options in the operation conclusion;

[0122] (4) Unblocking. After receiving the abnormal end notification preset in the teaching plan and sending it to the simulation substation, the student modifies the firewall configuration through the interface, removes the restrictions on the corresponding IP, reconnects to the substation, and enters the operation conclusion through the options in the operation conclusion. The system prompts whether the unblocking is successful.

[0123] (5) Report results: Students input reasons and treatment results through the interface and send a notification to the instructor.

[0124] The simulation training for handling abnormal operation of the device is used to load the typical fault handling training case scenarios pre-set by the instructor, and simulate the occurrence of important alarms in the device to train the operation and maintenance trainees to detect and handle alarms; the specific steps are:

[0125] (1) When an abnormality is found, the training lesson plan presets the sending of device alarm signals, such as PT disconnection, channel interruption, etc. Trainees need to find the device alarm and enter the plant station name, equipment name, and signal point name of the alarm device through options in the operation conclusion;

[0126] (2) Alarm handling: students send alarms to the instructor through the interface, and notify on-site personnel to eliminate the faults after simulating abnormalities;

[0127] (3) Confirmation of treatment: After receiving the alarm recovery notification preset in the teaching plan, the trainees check whether the device alarm has been eliminated and enter the treatment completion through the option method in the operation conclusion.

[0128] (4) Report the results. Students enter the cause and the result through the interface and send a notification to the instructor.

[0129] Power system operation abnormality handling simulation training is used to load the typical system operation abnormality handling training case scenarios pre-set by the instructor, simulating the abnormal operation of the power system to train the operation and maintenance trainees to detect abnormalities;

[0130] (1) Detecting anomalies: The training lesson plan presets a command to stop a certain process in the system, such as stopping front-end communication. Trainees need to discover the system anomalies through system operation phenomena. After the problem is confirmed, they can enter the system anomalies through options in the operation conclusion;

[0131] (2) Abnormal analysis: After the abnormality is confirmed, students need to check the help document to understand the common phenomena and treatment methods of system operation and maintenance, and then enter the cause of the system abnormality and the treatment method through the options in the operation conclusion;

[0132] (3) Exception handling: Restart or resume the relevant processes through interface operations, check whether all functions are running normally, and then enter the handling completion through options in the operation conclusion.

[0133] (4) Report results: Students input reasons and treatment results through the interface and send a notification to the instructor.

[0134] The simulation training of equipment maintenance and tag-out disposal is used to train operation and maintenance trainees to master the operation methods of equipment tag-out and tag-out. The specific steps are:

[0135] (1) Status confirmation: After checking the current operating status of the device specified in the teaching plan through the interface, the students can enter the operation conclusion through the options in the operation conclusion;

[0136] (2) Equipment listing: Trainees complete the equipment listing through interface operations, check the changes in the equipment operation status, and then enter the operation conclusion through options in the operation conclusion;

[0137] (3) Quality confirmation: the training lesson plan presupposes that the simulation substation periodically sends part of the device signal. After checking the quality of the sent information through the interface, the operation conclusion is entered through the options in the operation conclusion;

[0138] (4) Cancel the listing. The trainees complete the device delisting through the interface operation, check the changes in the device operation status, and then enter the operation conclusion through the options in the operation conclusion;

[0139] (5) Quality confirmation: The training lesson plan sets the device to send some signals regularly. After checking the quality of the uploaded information through the interface, the operation conclusion can be entered through the options in the operation conclusion.

[0140] (6) Report results: Students input training status through the interface and send notifications to the instructor.

[0141] The production plant substation access simulation training is used to train operation and maintenance trainees on the process and method of accessing the production plant substation. The prefabricated production plant substation model is pre-configured by the instructor through the tool software, including all model files of the simulation substation and simulation device. After one production, it supports multiple reuse. The specific steps are as follows:

[0142] (1) Notification of station pick-up. The teaching plan presets the sending of station pick-up notification, which includes the station name, region, IP address, port number, and communication protocol. After receiving the notification, the trainees send it to the instructor through the interface for confirmation.

[0143] (2) Adding a plant station: students add a plant station and communication channel model through the interface operation, including: plant station name, region, channel IP, port, communication protocol, and then enter the operation conclusion through the options in the operation conclusion;

[0144] () Connect to the substation. Students complete the connection between the front-end and the simulation substation through interface operation, observe the communication status with the substation, and then enter the operation conclusion through options in the operation conclusion;

[0145] (4) Primary equipment modeling: students import the preset CIME model file through the tool, build a primary equipment model, and then input the operation conclusion through the options in the operation conclusion;

[0146] (5) Secondary equipment modeling: trainees are guided by the tool to complete the operation of initializing the secondary equipment model from the simulation substation, initializing the 103 protocol through the message method, and modeling the 61850 protocol by calling the model file and importing it. They can also complete the protection signal point table level classification and semantic setting with one click, and then enter the operation conclusion through the option method in the operation conclusion;

[0147] (6) Model association: trainees use the tool to complete the association and inspection of the secondary equipment model and the primary equipment model, and then enter the operation conclusion through the options in the operation conclusion;

[0148] (7) Verification of calling function: trainees conduct batch calling function test on access substations through interface operation. After the test is completed, the interface displays the test results. Trainees confirm whether the functions of the access device are normal. If there are any abnormalities, they troubleshoot the problem according to the help document until all functions are normal. Then, they enter the operation conclusion through options in the operation conclusion.

[0149] (8) Event uploading verification: The student sends a point-to-point notification to the instructor. After receiving the notification, the instructor sends the preset point-to-point signal content to the student and the simulation substation, triggering the simulation substation to simulate the uploading of various corresponding event signals. The student performs signal point-to-point in the simulation system interface. After the point-to-point is completed, the student enters the operation conclusion through the options in the operation conclusion.

[0150] (9) After the station pick-up is completed, the trainee enters the station pick-up completion result through the interface operation options and sends a notification to the instructor, simulating the actual station pick-up to inform the substation manufacturer that the station pick-up is completed and the trainee can leave.

[0151] The power grid fault handling simulation training service is used to simulate the emergency response capabilities of operation and maintenance trainees in dealing with abnormal reports and analyzing faults after a power system fault occurs; in the training plan formed by the teaching plan management unit, it supports relay protection simulation scenarios in which preset protection action events are missing or wrong, recording files are missing or wrong, and analysis results are incorrect. The specific steps are:

[0152] (1) Open the fault report, receive the new fault notification sent by the instructor, and then open the fault report through the interface;

[0153] (2) Check the equipment status, check the operating status and listing status of the equipment related to the fault. After the check is completed, select the status of each equipment through the interface operation and confirm;

[0154] (3) View action details, fault briefings, and details of each protection action and recording. It supports selecting and confirming the collection and analysis results of each protection action event, recording, and briefing through interface operations;

[0155] (4) Data supplementary recruitment analysis: when the analysis results are affected by incomplete data, data supplementary recruitment and re-analysis are required. The interface supports the selection and confirmation of whether to supplement recruitment and supplementary recruitment information;

[0156] (5) Fault analysis and disposal. Fault analysis results, events, and waveforms are further analyzed and confirmed. The interface supports the input of analysis conclusions and disposal suggestions. The input information is presented in the form of options and text. Key conclusions, such as fault type, instantaneous / permanent, and reclosing success / failure, support quick selection and completion. Other information, such as distance measurement, reclosing time, tripping information, and disposal suggestions, support entry.

[0157] (6) Fault situation reporting: reporting the fault situation and handling suggestions to the instructor via message.

[0158] The remote control operation simulation training service is used to train operation and maintenance trainees to master the remote operation process, methods and the ability to handle abnormal situations during operation; in the training plan formed by the teaching plan management unit, it supports relay protection simulation scenarios in which the preset device name does not correspond to the interval and the modification of the set value exceeds the limit.

[0159] The specific steps are:

[0160] (1) Receive notifications. The teaching plan presets the notification of modifying the setting value, which includes the plant name, interval name, device name, and setting value list content. After receiving the notification, the trainees first confirm the correctness of the relevant information, and then send it to the instructor through the interface to confirm the notification;

[0161] (2) Calling the operation setting value: the trainee calls the current operation zone setting value through the interface and enters the operation conclusion through the option mode in the operation conclusion;

[0162] (3) Synchronize the editing area settings. Before modifying, the trainee first sends a notification to the instructor to simulate the supervisor verification. After receiving the confirmation, the trainee performs the operator verification. Then, the trainee switches the editing area to the preparation area (area 31) through the interface. Then, the current operation area settings are copied to the editing area write cache in batches. The trainee then enters the operation conclusion through the option mode in the operation conclusion.

[0163] (4) Modify the set value in the editing area. The trainee selects and enters the set value item to be modified according to the content of the set value list, and then sends a notification to the instructor to simulate the verification of the supervisor. After receiving the confirmation, the trainee performs the operator verification, and then completes the operation of updating the set value of the specified item in the write cache and downloading the set value item in the write cache to the device editing area through the interface. After the modification of the set value in the editing area is completed, the operation conclusion is entered through the option method in the operation conclusion;

[0164] (5) Calling the editing area setting, the trainee calls the editing area setting through the interface, confirms that the specified modification item takes effect, and enters the operation conclusion through the option mode in the operation conclusion;

[0165] (6) Switching the setting of the operating area. Before switching the area, the trainee first sends a notification to the instructor, simulates the verification of the supervisor, and after receiving the confirmation, performs the operator verification. Then, the trainee completes the switch of the setting of the preparation area (area 31) to the current operating area through the interface, and enters the operation conclusion through the option mode in the operation conclusion;

[0166] (7) Calling the operation setting value. The trainee calls the setting value of the current operation area through the interface, confirms the calling result with the setting value list, and then enters the operation conclusion through the option method in the operation conclusion;

[0167] (8) Calling the setting file. The trainee calls the device setting file through the interface, confirms the calling result with the setting sheet again, and then enters the operation conclusion through the option method in the operation conclusion.

[0168] (9) After the modification is completed, the trainee enters the result of the fixed value modification through the interface options and sends a notification to the instructor, simulating the reporting of the fixed value modification results in actual work.

[0169] It provides great convenience for trainees to quickly locate relay protection business problems and improve operation and maintenance and abnormal handling capabilities during training.

[0170] The following is an explanation with some training cases.

[0171] The teaching case of power grid fault handling is carried out by the following steps;

[0172] (1) The trainee receives the new fault notification preset by the instructor and then opens the fault report through the interface;

[0173] (2) Trainees check the operating status and listing status of the equipment related to the fault. After the inspection, they select and confirm the status of each equipment through the interface operation;

[0174] (3) Trainees view fault briefings and details of each protection action and recording. They are supported to select and confirm the inclusion and analysis results of each protection action event, recording, and briefing through interface operations;

[0175] (4) When the data is incomplete, students select supplementary recruitment information to supplement the data;

[0176] (5) Trainees further analyze and confirm the fault analysis results, events, and waveforms, input the analysis conclusions and disposal suggestions through the interface in a combination of options and text, and report to the instructor.

[0177] The remote control operation simulation case is carried out by the following steps:

[0178] (1) Before the simulation operation begins, the instructor first starts the operation of the relevant virtual substations and virtual devices through the pre-made image files of the simulation substations and simulation devices, and ensures that the virtual substations and virtual devices can communicate normally;

[0179] (2) The instructor sends a notification of setting modification through the teaching plan preset, which includes the plant name, interval name, device name, and setting list content, and the trainees receive and confirm it;

[0180] (3) The trainee calls the current operating area setting through the interface and enters the operation conclusion through the options in the operation conclusion;

[0181] (4) The student sends a notification to the instructor, simulating guardian verification;

[0182] (5) After receiving the instructor's confirmation, the trainee performs operator verification, then switches the editing area to the preparation area (area 31) through the interface, and enters the operation conclusion through the option mode in the operation conclusion;

[0183] (6) Students select and enter the specified value items to be modified according to the value list content;

[0184] (7) The trainee sends a notification to the instructor, simulating the verification of the supervisor, with the same effect as step (4);

[0185] (8) After receiving the confirmation, the trainee will perform operator verification, and then complete the operation of downloading the fixed value items in the cache to the device editing area through the interface, and enter the operation conclusion through the option method in the operation conclusion;

[0186] (9) The trainee calls up the editing area setting through the interface and enters the operation conclusion through the options in the operation conclusion;

[0187] (10) The trainee sends a notification to the instructor, simulating the verification of the guardian, with the same effect as step (4);

[0188] (11) After the monitoring verification, the operator verification is carried out, and then the trainee completes the switch from the setting of the preparation area (area 31) to the current operation area through the interface, and enters the operation conclusion through the option mode in the operation conclusion;

[0189] (12) The trainee calls the current operating area setting through the interface, confirms the calling result with the setting list, and then enters the operation conclusion through the option method in the operation conclusion;

[0190] (13) The trainee calls the device setting file through the interface, confirms the call result with the setting sheet again, and then enters the operation conclusion through the option method in the operation conclusion;

[0191] (14) Students input the fixed value modification results through interface options and report to the instructor.

[0192] Operation and maintenance simulation cases include data blocking processing simulation, IP blocking processing simulation, device operation abnormality processing simulation, system operation abnormality processing simulation, device maintenance and listing processing simulation and substation access simulation.

[0193] The simulation steps of blocking disposal are as follows:

[0194] (1) Before the simulation operation begins, the instructor first starts the virtual substation using the pre-made image file of the simulation substation, and then ensures that the simulation master station and the virtual substation can communicate normally;

[0195] (2) The instructor presets the normal transmission signal in the training lesson plan and includes several high-frequency transmission signal points, and then notifies the simulation substation. The simulation master station notifies the simulation substation of the relevant transmission signal and transmission frequency in the form of a file;

[0196] (3) The simulation substation sends corresponding signals to the simulation main station according to the preset method of the teaching plan;

[0197] (4) The simulation master station receives information and displays it on the monitoring interface, from which students can find frequent data signals;

[0198] (5) The trainee completes the suppression operation of the corresponding signal point through the interface and checks whether the suppression is successful;

[0199] (6) The simulation master station sends a notification of the end of abnormal signal transmission to the simulation substation and releases the inhibition;

[0200] (7) After receiving the notification, the simulation substation actively stops the periodic automatic sending function of the corresponding signal;

[0201] (8) The trainees input the treatment results through the simulation interface and send a notification report to the instructor. The whole process simulation operation related to data blocking treatment simulation is completed, including finding anomalies, suppressing data, checking results, releasing suppression, and reporting results.

[0202] The steps of IP blocking simulation are as follows:

[0203] (1) Before the simulation operation begins, the instructor first starts multiple virtual substations using the pre-made image file of the simulation substation, and then ensures that the simulation master station and each virtual substation can communicate normally;

[0204] (2) The instructor presets a normal transmission signal in the training lesson plan and includes more high-frequency transmission signal points, and then notifies one of the simulation substations. The simulation master station notifies the simulation substation of the relevant transmission signal and transmission frequency in a file format;

[0205] (3) The simulation substation that receives the notification sends a corresponding signal to the simulation main station according to the preset method of the teaching plan to simulate a network storm;

[0206] (4) The trainees find the relevant substations that frequently send data signals in the simulation master station, and enter the plant station name and IP address of the frequent signal through the options in the operation conclusion;

[0207] (5) The trainee disconnects from the substation through the interface and modifies the firewall configuration to prohibit the corresponding plant station IP address from communicating with the main station, and then enters the operation conclusion through the option method in the operation conclusion;

[0208] (6) After the trainee has checked that the network storm has been eliminated, he / she can enter the inspection conclusion through the options in the operation conclusion;

[0209] (7) According to the teaching plan preset, the simulation master station sends an abnormal signal to the simulation substation to notify the end of sending;

[0210] (8) After receiving the notification, the simulation substation actively stops the periodic automatic sending function of the corresponding signal. The trainee modifies the firewall configuration through the interface, removes the restriction on the corresponding IP, reconnects to the substation, and enters the operation conclusion through the option method in the operation conclusion;

[0211] (9) The trainees input the treatment results through the simulation interface and send a notification report to the instructor. The whole process simulation operation of [IP blocking treatment] including finding abnormalities, blocking IP, checking results, unblocking, and reporting results is completed.

[0212] The simulation steps for handling abnormal operation of the device are as follows:

[0213] (1) The instructor presets the device alarm signal in the training lesson plan. For example, if the PT is disconnected, the trainees need to detect the device alarm.

[0214] (2) The trainee enters the plant name, equipment name, and signal point name of the alarm device through options in the operation conclusion, and reports the alarm situation to the instructor, simulating the discovery of abnormalities and notifying on-site disposal;

[0215] (3) The instructor sends an alarm reset signal, and the trainee checks whether the device alarm has been eliminated;

[0216] (4) The trainee completes the operation by entering the options in the operation conclusion and reports the results to the instructor.

[0217] The simulation steps for handling system operation exceptions are as follows:

[0218] (1) The instructor presets in the training lesson plan a command to stop a certain process in the system;

[0219] (2) Students need to discover system anomalies through system process monitoring;

[0220] (3) After the trainee confirms the problem, he / she enters the system abnormality through options in the operation conclusion;

[0221] (4) Students read the help documents to understand the common problems and solutions of system operation and maintenance, and then enter the causes and solutions of system abnormalities through options in the operation conclusion;

[0222] (5) Students restart or resume relevant processes through interface operations and check whether various functions are running normally;

[0223] (6) The trainee enters the completion of the treatment through the options in the operation conclusion and reports the treatment results to the instructor.

[0224] The simulation steps for device maintenance and tag disposal are as follows:

[0225] (1) The instructor specifies a signboard simulation device in the lesson plan. The trainee first checks the current operating status of the device specified in the lesson plan through the interface, and then enters the current status through the options in the operation conclusion;

[0226] (2) The trainee completes the device registration through the interface operation, and then enters the operation conclusion through the options in the operation conclusion;

[0227] (3) The training lesson plan pre-sets that some signals of the device are sent periodically. After checking the quality of the sent information through the interface, the operation conclusion is entered through the options in the operation conclusion;

[0228] (4) The trainee completes the device delisting through the interface operation and enters the operation conclusion through the options in the operation conclusion;

[0229] (5) The trainee checks whether the quality of the newly received device signal has become normal, and enters the operation conclusion through the options in the operation conclusion, and reports to the instructor that the training is completed.

[0230] The operation steps of substation access simulation are as follows:

[0231] (1) Before the simulation operation begins, the instructor first starts the operation of the relevant virtual substations and virtual devices through the pre-made image files of the simulation substations and simulation devices, and ensures that the virtual substations and virtual devices can communicate normally;

[0232] (2) The instructor sends a station pick-up notification to the trainee through the teaching plan preset, which includes the station name, region, IP address, port number, and communication protocol. The trainee receives and confirms the notification;

[0233] (3) Trainees add plant and communication channel models through interface operation, including: plant name, region, channel IP, port, communication protocol, and then input operation conclusions through options in the operation conclusion;

[0234] (4) The trainees complete the connection between the front-end and the simulation substation through interface operation, observe the communication status with the substation, and then enter the operation conclusion through options in the operation conclusion;

[0235] (5) The trainees import the preset CIME model file through the tool, build a device model, and then input the operation conclusion through the options in the operation conclusion;

[0236] (6) Trainees complete the operation of initializing the secondary equipment model from the simulation substation through tool guidance, and complete the level classification and semantic setting of the protection signal point table, and then enter the operation conclusion through options in the operation conclusion;

[0237] (7) Trainees use the tool to complete the association and inspection of the secondary equipment model and the primary equipment model, and then enter the operation conclusion through options in the operation conclusion;

[0238] (8) Trainees select the device to be tested and its calling function items through the simulation interface. The function items mainly include calling setting value, calling setting value area, calling soft pressure plate, calling switch quantity, calling simulation quantity, calling recording list, calling recording file, and then generate batch calling commands and send them to the simulation substation according to the device;

[0239] (9) After receiving the call command from the simulation master station, the simulation substation forwards the command to the corresponding simulation device; the call command issued between stations needs to be converted into a command corresponding to the communication protocol of the simulation device;

[0240] (10) After receiving the command from the simulation substation, the simulation device processes and responds to the command, and then generates a corresponding result and sends it to the simulation substation;

[0241] (11) After receiving the call result sent by the simulation device, the simulation substation converts it into a format corresponding to the inter-station protocol and sends it to the simulation master station;

[0242] (12) The simulation master station will display the received results. Trainees can directly view the test results of each calling function of each device through the simulation operation interface, thereby achieving the goal of verifying the simulation calling function of the access device until all calling functions of the access device are normal;

[0243] (13) The student sends a point-to-point notification to the instructor. After receiving the notification, the instructor sends a preset point-to-point signal content to the student and the simulation substation, triggering the simulation substation to simulate and send the corresponding corresponding event signal;

[0244] (14) Students perform signal matching in the simulation system interface. After matching is completed, they enter the operation conclusion through options in the operation conclusion;

[0245] (15) The trainee enters the completion result of the station connection through the interface operation options and sends a notification to the instructor, simulating the actual station connection to inform the substation manufacturer that the station connection is completed.

[0246] This embodiment analyzes various types of simulation application services, realizes process-based and granular operation step modeling, provides standards for objective quantitative evaluation, and then combines the instructor's monitoring of the trainee's operation to give subjective qualitative evaluation guidance suggestions, and finally forms a comprehensive evaluation conclusion, which is of great significance for accurately reflecting the trainee's skill mastery and guiding the rapid improvement of the trainee's technical level. Each typical business completes the training operation based on an interactive and visual way, which greatly facilitates the trainee to quickly locate business problems and improve operation and maintenance and abnormal handling capabilities during the training process.

[0247] The terms used to describe the positional relationship in the accompanying drawings are only used for illustrative purposes and should not be construed as limiting this patent; it is clear that the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not limitations on the implementation methods of the present invention. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made on the basis of the above description. It is not necessary and impossible to list all implementation methods here. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the claims of the present invention.

Claims

1. A relay protection mirror simulation training system, characterized in that: include: The mirror simulation module is used to obtain the basic model, section information, operation information and operation files of the actual production plant, and use the mirror synchronization technology to simulate the basic model and section status of the actual production plant to generate the basic model of the production plant simulation; The login and registration center module is used for the login and registration of instructors and operation and maintenance trainees, so that instructors and operation and maintenance trainees can obtain login, query, and application operation permissions related to relay protection training, and record the unique identity ID of instructors and operation and maintenance trainees; The training business management and control module is used to receive the basic simulation model of the production plant and station, and form a relay protection simulation training scenario model based on the basic simulation model of the production plant and station for instructors and operation and maintenance trainees to conduct relay protection simulation training business; The database module is used to store the basic model, section information, operation information and operation files of the actual production plant obtained by the mirror simulation module, and to store the relay protection simulation training scenario model and relay protection simulation training scenario model section information files required for instructors and operation and maintenance trainees to conduct relay protection simulation training business.

2. The relay protection mirror simulation training system according to claim 1 is characterized in that: The training business management control module includes an operation and maintenance trainee management control submodule and an instructor management control submodule. The operation and maintenance trainee management control submodule includes: a simulation scene management unit, a simulation operation application unit, an alarm monitoring unit, an instructor interaction unit, and a training process playback unit. The simulation scenario management unit is used to instantiate the relay protection simulation training scenario model according to the identity ID of the operation and maintenance trainee when the operation and maintenance trainee loads the relay protection simulation training scenario; The simulation operation application unit is used to simulate relay protection simulation training services and provide relay protection simulation training service operation applications; The alarm monitoring unit is used to monitor the abnormalities and errors that occur during the training operation of the operation and maintenance trainees, and issue alarms; The instructor interaction unit is used for the operation and maintenance trainee to receive emergency handling events and commands sent temporarily by the instructor, and send the operation and operation results of the operation and maintenance trainee to the instructor, and send the operation and maintenance trainee's simulated actual fault handling process, typical abnormality analysis and handling results, and personal simulation training notification to the on-duty instructor; The training process playback unit is used for operation and maintenance trainees to review the entire process of their training operations through playback.

3. The relay protection mirror simulation training system according to claim 2 is characterized in that: The teacher management control submodule includes a setting management unit, a teaching plan management unit, a training management unit, a preset plan management unit, a student monitoring management unit and an evaluation management unit; Among them, the setting management unit is used to set the limit of the number of production plants and stations included in the relay protection simulation training scenario when the operation and maintenance trainees undergo relay protection simulation training, and browse, compile and edit the specified operation process of application operations related to relay protection training; The lesson plan management unit is used by teachers to compile training plans, set up training plans, and manage historical lesson plans; The training management unit is used to manage training matters, including starting training, pausing training, resuming training, replaying training, and inserting temporary training events; A preset plan management unit is used to preset training plans; The trainee monitoring management unit is used to monitor the abnormalities that occur during the training process of the operation and maintenance trainees, the results of fault handling, the notification information during the interactive training with the instructor, the notification of the completion of the training, and the notification of personal simulation training; The evaluation management unit includes an objective evaluation subunit and a subjective evaluation subunit. The objective evaluation subunit is used to provide quantitative evaluation results of operation and maintenance trainees, and the subjective evaluation subunit is used to provide subjective non-quantitative evaluation results of operation and maintenance trainees. The evaluation management unit outputs a comprehensive evaluation result based on the quantitative evaluation result and the subjective non-quantitative evaluation result.

4. The relay protection mirror simulation training system according to claim 3 is characterized in that: When the teaching plan management unit is used by the instructor to prepare the training plan, it receives the production plant simulation basic model generated by the mirror simulation module. The instructor creates a relay protection simulation training scenario for the operation and maintenance trainees based on the production plant simulation basic model, determines the number of production plants included in each relay protection simulation training scenario, forms a simulation basic model, and backs up the section information of the production plants; The instructor frames the production plant based on the production plant simulation basic model, forms a new relay protection simulation training scenario, or calls the historical relay protection simulation scenario in the historical training lesson plan for modification. When modifying the historical training lesson plan, the production plant simulation basic model in the historical training lesson plan is compared with the real-time production plant simulation basic model. When there is a difference between the production plant simulation basic model and the real-time production plant simulation basic model, the lesson plan management unit gives a prompt, and the instructor chooses whether to replace the production plant simulation basic model; Receive and edit existing fault reports in the operation information in the database module to form typical fault handling training cases for the device and typical abnormal handling training cases for system operation; the instructor sets the simulation parameters, sets the training start time, duration, and lesson plan name, and after the training plan is compiled, save it to the database module.

5. The relay protection mirror simulation training system according to claim 4 is characterized in that: In the simulation scenario management unit, the relay protection simulation training scenarios loaded by the operation and maintenance trainees include real-time teaching plan scenarios and historical teaching plan scenarios. The real-time teaching plan scenarios are relay protection simulation training scenarios in the training plan issued by the instructor, which are created based on the production plant simulation basic model. After logging in to the registration center module, the operation and maintenance trainees complete the simulation training according to the relay protection simulation training scenario model corresponding to the real-time teaching plan scenario; The historical teaching scenario is used for daily skill training of operation and maintenance trainees. The simulation scenario management unit detects whether the historical teaching scenario is compatible with the production plant simulation basic model, and gives a prompt when it is not compatible. The operation and maintenance trainee decides whether to continue. When the operation and maintenance trainee chooses to continue, the simulation scenario management unit sends a simulation exercise notification to the instructor, and then starts the training; After the operation and maintenance trainees finish the training operation, they save the relay protection simulation training scenario model data as a section information file and store it in the database module.

6. The relay protection mirror simulation training system according to claim 5 is characterized in that: After the operation and maintenance trainees load the relay protection simulation training scenario, they enter the training state. In the training state, the production plant and equipment names simulated by each operation and maintenance trainee are consistent with the real-time state, but the equipment IDs are different. They are numbered according to "original production plant / equipment ID_user ID_production plant state" to form a unique identification.

7. The relay protection mirror simulation training system according to claim 5, characterized in that: The relay protection simulation training business includes operation and maintenance simulation training business, power grid fault handling simulation training business and remote control operation simulation training business.

8. The relay protection mirror simulation training system according to claim 7 is characterized in that: The operation and maintenance simulation training business includes: data blocking treatment simulation training, IP blocking treatment simulation training, device operation abnormality treatment simulation training, power system operation abnormality treatment simulation training, device maintenance hanging treatment simulation training, production plant substation access simulation training; Among them, data blocking handling simulation training is used to simulate the high-frequency alarm transmission of a small number of non-important signals in actual production plants and stations, and train operation and maintenance trainees to handle the abnormal high-frequency alarm transmission of a small number of non-important signals; IP blocking handling simulation training is used to simulate the traffic storm caused by network anomalies in production plants and train operation and maintenance trainees to handle such anomalies; Device operation abnormality handling simulation training is used to load typical fault handling training case scenarios pre-set by the instructor, simulating the occurrence of important alarms in the device to train operation and maintenance trainees to detect and handle alarms; Power system operation abnormality handling simulation training is used to load the typical system operation abnormality handling training case scenarios pre-set by the instructor, simulating the abnormal operation of the power system to train the operation and maintenance trainees to detect abnormalities; Equipment maintenance tag-out simulation training is used to train operation and maintenance trainees to master the operation methods of equipment tag-out and tag-out; Production plant substation access simulation training is used to train operation and maintenance trainees on the process and methods of accessing production plant substations.

9. The relay protection mirror simulation training system according to claim 7, characterized in that: The power grid fault handling simulation training service is used to simulate the emergency response capabilities of operation and maintenance trainees in responding to abnormal reports and analyzing faults after a power system fault occurs; in the training plan formed by the teaching plan management unit, it supports relay protection simulation scenarios in which preset protection action events are missing or erroneous, recording files are missing or erroneous, and analysis results are incorrect.

10. The relay protection mirror simulation training system according to claim 7, characterized in that: The remote control operation simulation training service is used to train operation and maintenance trainees to master the process and methods of remote operation and the ability to handle abnormal situations during operation; in the training plan formed by the teaching plan management unit, it supports relay protection simulation scenarios in which the preset device name does not correspond to the interval and the modification of the set value exceeds the limit.

Citation Information

Patent Citations

  • Simulation data forwarding-based maintenance-free power grid dispatching center simulation training method

    CN105989545A

  • A power grid simulation training method based on multi-scene application

    CN108877368A

  • Power grid simulation training system based on monitoring signal simulation

    CN109785702A

  • Distribution network dispatcher training simulation system and method

    CN113380102A

  • Intelligent simulation training system based on waste incineration power plant

    CN117612431A