Zinc ingot automatic adjusting and carrying system

By designing an automatic adjustment and handling system for zinc ingots and using automated and mechanized processes to replace manual operations, the problem of high labor costs and safety hazards in the zinc ingot pretreatment process was solved, and accurate zinc ingot placement and production efficiency were improved.

CN119330071APending Publication Date: 2025-01-21NINGBO BEITERUI NEW ENERGY TECH CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411597963.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-11
Publication Date
2025-01-21

AI Technical Summary

Technical Problem

In the prior art, the pretreatment process of zinc ingots is highly dependent on manual operations, and there are problems of high labor costs, safety hazards and low production efficiency.

Method used

An automatic zinc ingot adjustment and handling system is designed, including a zinc ingot cleaning device, a truck, an adjustment component and a delivery device. It replaces manual operations through mechanized and automated processes to achieve precise adjustment and delivery of zinc ingots.

Benefits of technology

The system reduces labor costs, improves production efficiency and safety, and can accurately invest zinc ingot into the boiler, saving production costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119330071A_ABST
    Figure CN119330071A_ABST
Patent Text Reader

Abstract

The invention discloses an automatic adjusting and carrying system for zinc ingots. The automatic adjusting and carrying system is characterized by comprising a zinc ingot cleaning device, a zinc ingot carrying vehicle, a zinc ingot adjusting assembly and a zinc ingot feeding device; the zinc ingot adjusting assembly comprises a material tray, a zinc ingot adjusting device, a zinc ingot placing support, a zinc ingot carrying device and a zinc ingot putting device. The zinc ingot carrying device moves the zinc ingot from the material tray to the zinc ingot adjusting device, and the zinc ingot adjusting device adjusts the zinc ingot to a specific placing position; the zinc ingot carrying device is used for moving the zinc ingots onto the zinc ingot placing bracket; the zinc ingot feeding device has the advantages that by strictly controlling and adjusting the placing position and angle of the zinc ingot, a mechanical arm (zinc ingot carrying device) with common adjusting precision and small angle can be used for operation, a mechanical arm with high operation precision and angle is not needed, and the zinc ingot feeding device is simple in structure and convenient to operate. And the zinc ingot can be accurately put into the boiler, so that the production cost is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of zinc ingots, and in particular to an automatic adjustment and transportation system for zinc ingots. Background Art

[0002] In the modern industrial system, zinc ingots, as an indispensable raw material, are widely used in many key fields such as galvanizing, alloy manufacturing, and battery production. Its unique physical and chemical properties make zinc ingots play an important role in improving product quality and enhancing material corrosion resistance. However, in the process of zinc ingots from procurement to final transformation into various industrial products, a crucial link is the pretreatment and melting process of zinc ingots.

[0003] At present, the industry generally uses traditional manual operation methods for the pretreatment of zinc ingots. This process usually includes multiple steps: first, workers need to clean the zinc ingots one by one to remove oil and other impurities on the surface to ensure the purity of the zinc ingots; then, through natural drying or manual drying, the zinc ingots are made to reach an appropriate moisture content to avoid unnecessary steam or explosion risks during the melting process; then, these pretreated zinc ingots need to be manually transported to the preset position on the production line so that subsequent mechanized equipment such as robotic arms can accurately grab and put them into the melting boiler.

[0004] However, this highly manual pre-processing method has significant limitations. On the one hand, labor costs continue to rise with the fluctuations in the labor market, increasing the operating costs of enterprises; on the other hand, manual operations have major safety hazards, such as falls and burns that may occur during transportation, which seriously threaten the lives of workers. In addition, the efficiency and accuracy of manual operations are also limited by human physical strength, skills and attention, making it difficult to ensure the continuous and stable operation of the production line and the consistency of product quality.

[0005] To this end, the prior art has developed a method of using machines to replace manual operations, but there are still problems. In order to accurately put the zinc ingots into the boiler, a mechanical arm with high operating adjustment accuracy and angle must be used, which greatly increases the production cost. Summary of the invention

[0006] The technical problem to be solved by the present invention is to provide an automatic adjustment and transportation system for zinc ingots, which can replace manual labor and accurately put the zinc ingots into the boiler to prepare for the subsequent production of the zinc ingots.

[0007] The technical solution adopted by the present invention to solve the above technical problems is: a zinc ingot automatic adjustment and transportation system, comprising a zinc ingot cleaning device, a zinc ingot transport vehicle, a zinc ingot adjustment component and a zinc ingot delivery device; the zinc ingot cleaning device is used to clean dust on the surface of the zinc ingot and dry it; the zinc ingot transport vehicle is used to transport the cleaned zinc ingot to a designated location; the zinc ingot adjustment component is used to adjust the placement position of the zinc ingot; the zinc ingot delivery device is used to deliver the zinc ingot into a boiler for melting; the zinc ingot adjustment device comprises a material tray, a zinc ingot adjustment device, a zinc ingot placement bracket, a zinc ingot transport device and a zinc ingot delivery device; the material tray is used to place the zinc ingots transported by the zinc ingot transport vehicle; the zinc ingot adjustment device is used to adjust the zinc ingot to a specific position, the zinc ingot transport device moves the zinc ingot from the material tray to the zinc ingot adjustment device, and the zinc ingot adjustment device adjusts the zinc ingot to a specific placement position; the zinc ingot transport device moves the zinc ingot to the zinc ingot placement bracket; the zinc ingot delivery device moves the zinc ingot from the zinc ingot placement bracket to the boiler.

[0008] A further preselected scheme of the present invention is: the zinc ingot adjustment device comprises an adjustment platform, a first stopper, a second stopper, a first pushing cylinder and a second pushing cylinder, the first stopper and the second stopper are respectively arranged at the lateral position and the longitudinal position of the adjustment platform, the first pushing cylinder and the first stopper are arranged opposite to each other, the second pushing cylinder and the second stopper are arranged opposite to each other, after the zinc ingot is placed on the adjustment platform, the first pushing cylinder pushes the zinc ingot until it is blocked by the first stopper; the second pushing cylinder pushes the zinc ingot until it is blocked by the second stopper.

[0009] A further preselected solution of the present invention is that the space formed by the first stopper, the second stopper, the first pushing cylinder and the second pushing cylinder is larger than the volume of the zinc ingot.

[0010] A further preselected solution of the present invention is: the zinc ingot placement bracket includes a plurality of storage frames, and the zinc ingots are placed into corresponding storage frames by the zinc ingot handling device.

[0011] A further pre-selected scheme of the present invention is: the storage frame has two side baffles, a bottom baffle and a support plate, the support plate is arranged at an angle, the side baffles are arranged on both sides of the support plate, and the bottom baffle is arranged at the bottom of the support plate, the zinc ingot enters the storage frame along the support plate, and the zinc ingot whose position is adjusted by the zinc ingot adjusting device is no longer adjusted after being placed in the zinc ingot placing bracket; a weight sensor is also arranged on the zinc ingot placing bracket, and after the zinc ingot is placed in the storage frame, the value of the weight sensor changes, thereby detecting the placement of the zinc ingot.

[0012] A further alternative of the present invention is as follows: The zinc ingot handling device includes a robotic arm main body and an adsorption device. The adsorption device is arranged at the end of the robotic arm main body. The adsorption device includes a vacuum generator, an adsorption sponge, a support frame, and a turning cylinder. The adsorption sponge is arranged below the vacuum generator. The vacuum generator and the turning cylinder are fixed on the support frame. The turning cylinder pushes the housing of the vacuum generator to rotate. The zinc ingot handling device moves the zinc ingot from the material tray to the zinc ingot adjustment device. The zinc ingot handling device adsorbs and rotates the adjusted zinc ingot to an inclined angle and then places it into the zinc ingot placement bracket.

[0013] A further alternative of the present invention is as follows: The zinc ingot feeding device includes a robotic arm main body and a grasping device. The grasping device includes a clamping pump and two clamping arms. It is characterized in that the two clamping arms are both L-shaped. The inner side of the clamping arm is provided with a guiding surface, a clamping surface, a tip receiving groove, and a abutting surface arranged in sequence from top to bottom. The guiding surface is inclined. The two guiding surfaces are arranged oppositely and are in an open state. The trapezoidal zinc ingot enters the grasping device between the two guiding surfaces. The clamping surface is inclined and is used to directly contact the inclined side surface of the trapezoidal zinc ingot. The tip receiving groove is used to insert the tip of the trapezoidal zinc ingot into the tip receiving groove. The abutting surface is used to contact the bottom surface of the trapezoidal zinc ingot.

[0014] A further alternative of the present invention is as follows: The clamping surface includes a first clamping surface and a second clamping surface. The first clamping surface and the second clamping surface have different inclined angles to achieve clamping of at least two styles of trapezoidal zinc ingots. The inclined amplitude of the inclined side surface of the trapezoidal zinc ingot is the same as that of the guiding surface. When the trapezoidal zinc ingot is inserted into the tip receiving groove, the inner wall of the tip receiving groove does not contact the tip of the trapezoidal zinc ingot. The angle between the first clamping surface and the vertical line is A, and the angle between the second clamping surface and the vertical line is B, and A angle < B angle. The clamping surface includes a first clamping surface, a second clamping surface, and a third clamping surface. The first clamping surface, the second clamping surface, and the third clamping surface have different inclined angles to achieve clamping of at least three styles of trapezoidal zinc ingots. A collision sensor assembly is arranged above the clamping pump. The collision sensor assembly includes a first fixing plate and a second fixing plate. A plurality of springs are arranged between the first fixing plate and the second fixing plate. An induction sheet is arranged on the first fixing plate, and a sensor probe is arranged on the second fixing plate. When the clamping arm collides, the positions of the induction sheet and the sensor probe change, resulting in a change in the induction value. The sensor probe is the probe of an optoelectronic sensor, the induction sheet is an alloy metal sheet, a groove is arranged on the second fixing plate, the probe is arranged around the groove, and the induction sheet is inserted into the groove.

[0015] A further preselected scheme of the present invention is: the zinc ingot cleaning device comprises: a zinc ingot initial area, a water spraying device, a first photographing and identifying device, a zinc ingot grabbing robot arm, a zinc ingot placing area, a zinc ingot placing area and a first blasting device, wherein the zinc ingot initial area is used to place unwashed zinc ingots; the water spraying device is used to spray water on the unwashed zinc ingots; the first photographing and identifying device is used to take pictures of the unwashed zinc ingots, and the position of the zinc ingots is calculated by the analyzing device; the zinc ingot grabbing robot arm is used to grab the unwashed zinc ingots and place the zinc ingots in a regular manner to a specific position and posture; the zinc ingot placing area is used to place the grabbed zinc ingots; the first blasting device is used to blow air to the zinc ingots after placement to blow away dust and water stains until they are dry; the unwashed zinc ingots are first placed in the zinc ingot initial area, and then the position is determined by the first photographing and identifying device and grabbed to the zinc ingot placing position by the zinc ingot grabbing robot arm, and the zinc ingots are cleaned and dried by the first blasting device after being regularly placed.

[0016] A further pre-selected scheme of the present invention is: the zinc ingot grabbing robot arm is provided with a second air blowing device and a second photo-taking and identifying device; the second air blowing device is used for the zinc ingot grabbing robot arm to preliminarily blow away dust and water stains on the surface of the zinc ingot during the grabbing process; the second photo-taking and identifying device is used for the zinc ingot grabbing robot arm to take photos of the surface of the zinc ingot during the grabbing process, and analyze and calculate the quality of the zinc ingot; the zinc ingot placement area includes a qualified zinc ingot placement area and an unqualified zinc ingot placement area; the qualified zinc ingot placement area is used for the area where the ingots are placed after passing the quality inspection by the second photo-taking and identifying device; the unqualified zinc ingot placement area is used for the area where the ingots are placed after failing the quality inspection by the second photo-taking and identifying device; and a support frame is also included, and the water spraying device and the first photo-taking and identifying device are both arranged on the support frame; three trays are arranged in the zinc ingot placement area, and the three trays are arranged in sequence, the middle tray is the unqualified zinc ingot placement area, and the trays on both sides are the qualified zinc ingot placement area. A conveyor belt is arranged in the zinc ingot initial area, and the unwashed zinc ingots are transported to the zinc ingot initial area through the conveyor belt; the tray also includes a deionized water pool, in which a filter is arranged, and the water after washing the zinc ingots is recycled into the deionized water pool and re-enters the water spraying equipment for discharge through the filter; the tray includes a supporting panel and a plurality of supporting members, each supporting member is composed of three supporting feet and a connecting plate, and the connecting plate is arranged between two adjacent supporting feet.

[0017] Compared with the prior art, the ingenuity of the design of the present invention lies in its integrated and automated process, which eliminates manual operation and reduces labor costs. The zinc ingots can be processed automatically and, by strictly controlling the position and angle of the zinc ingots, can be operated using a common robotic arm (zinc ingot handling device) with smaller adjustment accuracy and angle. Without the need for a robotic arm with higher operating accuracy and angle, the zinc ingots can be accurately placed in the boiler, saving production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a three-dimensional diagram of the zinc ingot adjustment assembly of the present invention;

[0019] Figure 2 It is a three-dimensional diagram of the zinc ingot adjustment device of the present invention;

[0020] Figure 3 A three-dimensional diagram of a zinc ingot placement bracket of the present invention;

[0021] Figure 4 It is a side view of the zinc ingot placing support of the present invention;

[0022] Figure 5 A three-dimensional view of the grabbing device for the zinc ingot placing device Figure 1 ;

[0023] Figure 6 is a schematic diagram of the structure of the clamping arm;

[0024] Figure 7 A three-dimensional view of the grabbing device for the zinc ingot placing device Figure 2 ;

[0025] Figure 8 It is a structural schematic diagram of the automatic cleaning assembly of zinc ingot;

[0026] Fig. 9 It is a three-dimensional diagram of the zinc ingot handling device. DETAILED DESCRIPTION

[0027] The present invention is further described in detail below with reference to the accompanying drawings.

[0028] like Figure 1-Figure 9 As shown, a zinc ingot automatic adjustment and handling system includes a zinc ingot cleaning device, a zinc ingot handling vehicle, a zinc ingot adjustment component and a zinc ingot placing device 5; the zinc ingot cleaning device is used to clean the dust on the surface of the zinc ingot and dry it; the zinc ingot handling vehicle is used to transport the cleaned zinc ingot to a designated location; the zinc ingot adjustment component is used to adjust the placement of the zinc ingot; the zinc ingot placing device 5 is used to place the zinc ingot into a boiler for melting; after the zinc ingot is melted, it can be made into various industrial products according to needs.

[0029] like Figure 1As shown, the zinc ingot adjustment assembly includes a material tray 1, a zinc ingot adjustment device 2, a zinc ingot placement bracket 3, a zinc ingot handling device 4 and a zinc ingot delivery device 5; the material tray 1 is used to place the zinc ingots transported by the zinc ingot transporter, and the zinc ingots are installed on the material tray 1, and the zinc ingots are in a horizontal placement state at this time; the zinc ingot adjustment device 2 is used to adjust the zinc ingot to a specific position, and the zinc ingot handling device 4 moves the zinc ingot from the material tray 1 to the zinc ingot adjustment device 2, and the zinc ingot adjustment device 2 adjusts the zinc ingot to a specific placement position; the zinc ingot handling device 4 moves the zinc ingot to the zinc ingot placement bracket 3; the several components in the zinc ingot adjustment assembly cooperate with each other, and their function is to ensure that the zinc ingot is in a specific position to prevent the zinc ingot delivery device 5 from being unable to deliver accurately. The principle of the zinc ingot adjustment device 2 is: the adjustment accuracy and angle of the zinc ingot handling device 4 are not high, and the zinc ingot needs to be transported to the zinc ingot adjustment device 2 for precise adjustment, and then the zinc ingot handling device 4 is moved to the zinc ingot placement bracket 3 to be placed in a specific posture, and then the zinc ingot delivery device 5 delivers the zinc ingot into the boiler. The zinc ingot placing device 5 moves the zinc ingot from the zinc ingot placing support 3 to the boiler.

[0030] like Figure 2 As shown, the zinc ingot adjustment device 2 includes an adjustment platform 6, a first stopper 7, a second stopper 8, a first pushing cylinder 9 and a second pushing cylinder 10. The first stopper 7 and the second stopper 8 are respectively arranged at the lateral position and the longitudinal position of the adjustment platform 6. The first pushing cylinder 9 and the first stopper 7 are arranged relative to each other, and the second pushing cylinder 10 and the second stopper 8 are arranged relative to each other. After the zinc ingot is placed on the adjustment platform 6, the first pushing cylinder 9 pushes the zinc ingot until it is blocked by the first stopper 7; the second pushing cylinder 10 pushes the zinc ingot 40 until it is blocked by the second stopper 8, so as to accurately control the placement position of the zinc ingot and prepare for the subsequent placement of the zinc ingot on the placement bracket.

[0031] The space formed by the first stopper 7, the second stopper 8, the first push cylinder 9 and the second push cylinder 10 is larger than the volume of the zinc ingot. The zinc ingot placement bracket 3 includes a plurality of storage frames 11, and the zinc ingots are placed in the corresponding storage frames 11 by the zinc ingot handling device 4. The storage frame 11 has two side baffles 12, a bottom baffle 13 and a support plate 14, and the support plate 14 is arranged in an inclined manner. The side baffles 12 are arranged on both sides of the support plate 14, and the bottom baffle 13 is arranged at the bottom of the support plate 14. The zinc ingot enters the storage frame 11 along the support plate 14. The zinc ingot adjusted in position by the zinc ingot adjustment device 2 is no longer adjusted in position after being placed in the zinc ingot placement bracket 3; a weight sensor is also arranged on the zinc ingot placement bracket 3. After the zinc ingot is placed in the storage frame 11, the value of the weight sensor changes, thereby detecting the placement of the zinc ingot. The inclined arrangement of the zinc ingot placement is to facilitate the zinc ingot delivery device 5 to pick up the zinc ingot for delivery. The weight sensor is used to detect the values ​​such as the number of zinc ingots placed and the weight of the zinc ingots, so as to facilitate the delivery operation of the zinc ingot delivery device 5.

[0032] like Fig. 9 As shown, the zinc ingot handling device 4 includes a robot arm body and an adsorption device, which is arranged at the end of the robot arm body. The adsorption device includes a vacuum generator 16, an adsorption sponge 17, a support frame 18 and a flip cylinder 19. The adsorption sponge 17 is arranged below the vacuum generator 16, and the vacuum generator 16 and the flip cylinder 19 are fixed on the support frame 18. The flip cylinder 19 pushes the shell of the vacuum generator 16 to rotate; the zinc ingot handling device 4 moves the zinc ingot from the material tray 1 to the zinc ingot adjustment device 2; the zinc ingot handling device 4 adsorbs the adjusted zinc ingot and rotates it to an inclined angle and then places it into the zinc ingot placement bracket 3.

[0033] like Figure 5-Figure 7 As shown, the zinc ingot delivery device 5 includes a mechanical arm body and a grasping device, the grasping device includes a clamping pump 20 and two clamping arms 21, the two clamps and arms are L-shaped, the inner side of the clamping arm 21 is provided with a guide surface 22, a clamping surface 23, a tip accommodating groove 24 and abutting surface 25 arranged in sequence from top to bottom, the guide surface 22 is inclined, the two guide surfaces 22 are relatively arranged and in an open state, the trapezoidal zinc ingot enters the grasping device from between the two guide surfaces 22; the clamping surface 23 is in an inclined state, the clamping surface 23 is used to directly contact the inclined side surface of the trapezoidal zinc ingot, and the inclined surface can better fit the surface of the zinc ingot; the tip accommodating groove 24 is used to insert the tip of the trapezoidal zinc ingot into the tip accommodating groove 24, so as to avoid the tip of the zinc ingot directly contacting the clamping arm 21, resulting in damage to the tip surface of the zinc ingot; the abutting surface 25 is used to contact the bottom surface of the trapezoidal zinc ingot, and help the two clamping arms 21 to clamp the zinc ingot.

[0034] The clamping surface 23 includes a first clamping surface 231 and a second clamping surface 232. The first clamping surface 231 and the second clamping surface 232 present different inclination angles to achieve the clamping of at least two styles of trapezoidal zinc ingots. The surface of the zinc ingot is in contact with the two clamping surfaces 23, which belongs to the best match of the zinc ingot. Even if they cannot be completely in contact, they can still be used normally. The inclination of the inclined side of the trapezoidal zinc ingot is the same as that of the guiding surface 22 to achieve the best clamping effect. The trapezoidal zinc ingot is inserted into the tip receiving groove 24, and the inner wall of the tip receiving groove 24 does not contact the tip of the trapezoidal zinc ingot to avoid damage to the tip of the zinc ingot. The angle between the first clamping surface 231 and the vertical line is A, and the angle between the second clamping surface 232 and the vertical line is B, and angle A < angle B. Cooperating with the guiding surface 22, the transition between the first guiding surface 22 and the second guiding surface 22 is smooth. The clamping surface 23 includes a first clamping surface 231, a second clamping surface 232 and a third clamping surface 233. The first clamping surface 231, the second clamping surface 232 and the third clamping surface 233 present different inclination angles to achieve the clamping of at least three styles of trapezoidal zinc ingots. A collision sensor assembly is provided above the clamping pump 20, which can immediately detect when the clamping pump 20 collides with the two clamping arms 21, and immediately take measures such as sending an alarm or immediately stopping the movement. The collision sensor assembly includes a first fixing plate 26 and a second fixing plate 27. A plurality of springs 28 are arranged between the first fixing plate 26 and the second fixing plate 27. An induction sheet 15 is arranged on the first fixing plate 26, and a sensor probe 29 is arranged on the second fixing plate 27. When the clamping arm 21 collides, the positions of the induction sheet and the sensor probe 29 change, resulting in a change in the induction value. When it is detected that the value changes, a collision occurs. The sensor probe 29 is the probe of an optoelectronic sensor, the induction sheet is an alloy metal sheet, a groove 40 is arranged on the second fixing plate 27, the probe is arranged around the groove 40, and the induction sheet is inserted into the groove, effectively utilizing the positions of the fixing plates above and below the spring 28 without the need to provide additional space for the collision sensor assembly.

[0035] Such as Figure 8As shown, the automatic cleaning assembly of the zinc ingot includes: the zinc ingot initial area 30, the water spraying device 31, the first photographing and identifying device 32, the zinc ingot grabbing mechanical arm 33, the zinc ingot placing area 34 and the first blasting device 35. The zinc ingot initial area 30 is used to place the unwashed zinc ingot; the water spraying device 31 is used to spray water on the unwashed zinc ingot, which can spray water on the unwashed zinc ingot evenly and forcefully, effectively remove the dirt and initial wetting on the surface, and prepare for subsequent cleaning. The first photographing and identifying device 32 is used to take a photo of the unwashed zinc ingot, and the position and posture of the zinc ingot are calculated by the analysis device; the accuracy of this step is directly related to the operating efficiency and success rate of the subsequent grabbing mechanical arm, and is a key link in the automated cleaning process. The zinc ingot grabbing mechanical arm 33 is used to grab the unwashed zinc ingot and place the zinc ingot in a specific position in an orderly manner; in this process, the flexibility and stability of the mechanical arm are fully demonstrated, ensuring the accuracy and efficiency of the grabbing action. The zinc ingot placement area 34 is used to place the grabbed zinc ingots; the first air blast device 35 is used to blow air to the zinc ingots after they are placed, to blow away dust and water stains until they are dry; the unwashed zinc ingots are first placed in the zinc ingot initial area 30, and then the position is determined by the first photo recognition device 32 and the zinc ingot grabbing mechanical arm 33 grabs the zinc ingot placement position. The existing technology can easily identify the position and posture through photos, and then the mechanical arm determines the grabbing method according to the position and posture to avoid grabbing failure. After the zinc ingots are neatly placed, they are cleaned and dried by the first air blast device 35. This automatic cleaning assembly of zinc ingots achieves efficient cleaning and accurate classification of zinc ingots through integrated and automated design ideas, bringing significant economic and social benefits to the zinc ingot processing industry.

[0036] The zinc ingot grabbing mechanical arm 33 is provided with a second air blowing device and a second photo identification device; the second air blowing device is used for the zinc ingot grabbing mechanical arm 33 to preliminarily blow away the dust and water stains on the surface of the zinc ingot during the grabbing process; the second photo identification device is used for the zinc ingot grabbing mechanical arm 33 to take photos of the surface of the zinc ingot during the grabbing process, and analyze and calculate the quality of the zinc ingot. The zinc ingot placement area 34 includes a qualified zinc ingot placement area 34 and an unqualified zinc ingot placement area 34; the qualified zinc ingot placement area 34 is used for the area where the ingots are placed after the second photo identification device passes the quality inspection; the unqualified zinc ingot placement area 34 is used for the area where the ingots are placed after the second photo identification device fails the quality inspection. During the cleaning process, the zinc ingots are screened simultaneously to increase the function of the equipment and omit the subsequent steps of screening the zinc ingots. It also includes a support frame 35, and the water spraying device 31 and the first photo identification device 32 are both arranged on the support frame 36. Three trays are arranged in the zinc ingot placement area 34, and the three trays are arranged in sequence. The middle tray is the unqualified zinc ingot placement area 34, and the trays on both sides are the qualified zinc ingot placement area 34. A conveyor belt is arranged in the zinc ingot initial area, and the unwashed zinc ingots are transported to the zinc ingot initial area through the conveyor belt; the tray also includes a deionized water pool, in which a filter is arranged, and the water after washing the zinc ingots is recycled into the deionized water pool and re-enters the water spraying equipment for discharge through the filter; the tray includes a supporting panel and a plurality of supporting members, each supporting member is composed of three supporting feet and a connecting plate, and the connecting plate is arranged between two adjacent supporting feet.

[0037] The above is a detailed introduction to the automatic adjustment and handling system for zinc ingots provided by the present invention. The principles and implementation methods of the present invention are described in detail using specific examples. The description of the above embodiments is only used to help understand the present invention and its core ideas. It should be pointed out that for ordinary technicians in this technical field, the present invention can also be improved and modified without departing from the principles of the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

Claims

1. A zinc ingot automatic adjustment and handling system, characterized in that It includes a zinc ingot cleaning device, a zinc ingot transporter, a zinc ingot adjustment component and a zinc ingot placing device; the zinc ingot cleaning device is used to clean the dust on the surface of the zinc ingot and dry it; the zinc ingot transporter is used to transport the cleaned zinc ingot to a designated location; the zinc ingot adjustment component is used to adjust the placement of the zinc ingot; the zinc ingot placing device is used to place the zinc ingot into the boiler for melting; The zinc ingot adjustment component includes a material tray, a zinc ingot adjustment device, a zinc ingot placement bracket, a zinc ingot handling device and a zinc ingot placing device; The material tray is used to place the zinc ingots transported by the zinc ingot transporter; The zinc ingot adjusting device is used to adjust the zinc ingot to a specific position. The zinc ingot handling device moves the zinc ingot from the material tray to the zinc ingot adjusting device, and the zinc ingot adjusting device adjusts the zinc ingot to a specific placement position. The zinc ingot transporting device moves the zinc ingot to the zinc ingot placing support; The zinc ingot placing device moves the zinc ingot from the zinc ingot placing support to the boiler.

2. The zinc ingot automatic adjustment and handling system according to claim 1 is characterized in that The zinc ingot adjustment device comprises an adjustment platform, a first stopper, a second stopper, a first pushing cylinder and a second pushing cylinder. The first stopper and the second stopper are respectively arranged at the lateral position and the longitudinal position of the adjustment platform. The first pushing cylinder and the first stopper are arranged opposite to each other, and the second pushing cylinder and the second stopper are arranged opposite to each other. After the zinc ingot is placed on the adjustment platform, the first pushing cylinder pushes the zinc ingot until it is blocked by the first stopper; the second pushing cylinder pushes the zinc ingot until it is blocked by the second stopper.

3. The zinc ingot automatic adjustment and handling system according to claim 1 is characterized in that The space formed by the first stopper, the second stopper, the first pushing cylinder and the second pushing cylinder is larger than the volume of the zinc ingot.

4. The zinc ingot automatic adjustment and handling system according to claim 1 is characterized in that The zinc ingot placement support comprises a plurality of storage frames, and each zinc ingot is placed into a corresponding storage frame by a zinc ingot handling device.

5. The zinc ingot automatic adjustment and handling system according to claim 4 is characterized in that The storage frame has two side baffles, a bottom baffle and a support plate, the support plate is arranged in an inclined manner, the side baffles are arranged on both sides of the support plate, and the bottom baffle is arranged at the bottom of the support plate. The zinc ingots enter the storage frame along the support plate. After the zinc ingots whose positions are adjusted by the zinc ingot adjusting device are placed in the zinc ingot placing bracket, their positions are no longer adjusted; a weight sensor is also arranged on the zinc ingot placing bracket. After the zinc ingot is placed in the storage frame, the value of the weight sensor changes, thereby detecting the placement of the zinc ingot.

6. The zinc ingot automatic adjustment and handling system according to claim 1, characterized in that The zinc ingot handling device includes a mechanical arm main body and an adsorption device, which is arranged at the end of the mechanical arm main body. The adsorption device includes a vacuum generator, an adsorption sponge, a support frame and a flip cylinder. The adsorption sponge is arranged below the vacuum generator, and the vacuum generator and the flip cylinder are fixed on the support frame. The flip cylinder pushes the shell of the vacuum generator to rotate; the zinc ingot handling device moves the zinc ingot from the material tray to the zinc ingot adjustment device; the zinc ingot handling device adsorbs the adjusted zinc ingot and rotates it to an inclined angle and then places it into the zinc ingot placement bracket.

7. The automatic adjustment and handling system for zinc ingots according to claim 1 is characterized in that The described zinc ingot feeding device includes a robotic arm main body and a grasping device. The grasping device includes a clamping pump and two clamping arms. It is characterized in that the two clamping arms are both L-shaped. On the inner side of the clamping arms, there are successively arranged a guiding surface, a clamping surface, a tip accommodating groove, and a abutting surface from top to bottom. The guiding surface is inclined. The two guiding surfaces are oppositely arranged and in an open state. The trapezoidal zinc ingot enters the grasping device between the two guiding surfaces. The clamping surface is inclined and is used to directly contact the inclined side surface of the trapezoidal zinc ingot. The tip accommodating groove is used to insert the tip of the trapezoidal zinc ingot into the tip accommodating groove. The abutting surface is used to contact the bottom surface of the trapezoidal zinc ingot.

8. The zinc ingot automatic adjustment and handling system according to claim 7, characterized in that The clamping surface includes a first clamping surface and a second clamping surface. The first clamping surface and the second clamping surface have different inclination angles to achieve clamping of at least two styles of trapezoidal zinc ingots. The inclination amplitude of the inclined side surface of the trapezoidal zinc ingot is the same as that of the guiding surface. When the trapezoidal zinc ingot is inserted into the tip accommodating groove, the inner wall of the tip accommodating groove does not contact the tip of the trapezoidal zinc ingot. The angle between the first clamping surface and the vertical line is A, and the angle between the second clamping surface and the vertical line is B, and angle A < angle B. The clamping surface includes a first clamping surface, a second clamping surface, and a third clamping surface. The first clamping surface, the second clamping surface, and the third clamping surface have different inclination angles to achieve clamping of at least three styles of trapezoidal zinc ingots. A collision sensor assembly is arranged above the clamping pump. The collision sensor assembly includes a first fixing plate and a second fixing plate. A plurality of springs are arranged between the first fixing plate and the second fixing plate. An induction sheet is arranged on the first fixing plate, and a sensor probe is arranged on the second fixing plate. When the clamping arm collides, the positions of the induction sheet and the sensor probe change, resulting in a change in the induction value. The sensor probe is the probe of an optoelectronic sensor, the induction sheet is an alloy metal sheet, a groove is arranged on the second fixing plate, the probe is arranged around the groove, and the induction sheet is inserted into the groove.

9. The zinc ingot automatic adjustment and handling system according to claim 1, characterized in that The described zinc ingot cleaning device includes: a zinc ingot initial area, a water spraying device, a first photo recognition device, a zinc ingot grasping robotic arm, a zinc ingot placement area, and a first air blowing device. The zinc ingot initial area is used to place the uncleaned zinc ingots. The water spraying device is used to spray water on the uncleaned zinc ingots. The first photo recognition device is used to take pictures of the uncleaned zinc ingots and calculate the positions of the zinc ingots by an analysis device. The zinc ingot grasping robotic arm is used to grasp the uncleaned zinc ingots and regularly place the zinc ingots in a specific position and posture. The zinc ingot placement area is used to place the grasped zinc ingots. The first air blowing device is used to blow air on the placed zinc ingots to blow away dust and water stains until they are dry. The uncleaned zinc ingots are first placed in the zinc ingot initial area, then the position is determined by the first photo recognition device and the zinc ingots are grasped by the zinc ingot grasping robotic arm to the zinc ingot placement position. After the zinc ingots are regularly placed, they are cleaned and dried by the first air blowing device.

10. The zinc ingot automatic adjustment and handling system according to claim 1, characterized in that The zinc ingot grabbing mechanical arm is provided with a second air blowing device and a second photo-taking and identifying device; the second air blowing device is used for the zinc ingot grabbing mechanical arm to preliminarily blow away dust and water stains on the surface of the zinc ingot during the grabbing process; the second photo-taking and identifying device is used for the zinc ingot grabbing mechanical arm to take photos of the surface of the zinc ingot during the grabbing process, and analyze and calculate the quality of the zinc ingot; the zinc ingot placement area includes a qualified zinc ingot placement area and an unqualified zinc ingot placement area; the qualified zinc ingot placement area is used as an area for placing the ingots after passing the quality inspection by the second photo-taking and identifying device; An unqualified zinc ingot placement area is an area for placing zinc ingots that fail to pass quality inspection by a second camera identification device; it also includes a support frame, on which the water spray device and the first camera identification device are both arranged; three trays are arranged in the zinc ingot placement area, the three trays are arranged in sequence, the middle tray is the unqualified zinc ingot placement area, and the trays on both sides are the qualified zinc ingot placement area; a conveyor belt is arranged in the zinc ingot initial area, and the unwashed zinc ingots are transported to the zinc ingot initial area through the conveyor belt; it also includes a deionized water pool, in which a filter is arranged, and water after washing the zinc ingots is recycled into the ionized water pool and re-enters the water spray device through the filter for discharge; the tray includes a supporting panel and a plurality of support members, each of which is composed of three support legs and a connecting plate, and the connecting plate is arranged between two adjacent support legs.

Citation Information

Patent Citations

  • Grasping device for transporting zinc ingots and zinc ingots grasping method

    CN107803488A

  • Automatic placing equipment suitable for zinc ingots

    CN110723529A

  • Full-automatic intelligent rack inserting device

    CN114476605A

  • Automatic cleaning, drying and feeding machine for aluminum ingots

    CN219688267U

  • Automatic plastic plate feeding device

    CN221836241U