Power grid operation mode online configuration method and device, equipment and storage medium
By establishing an online configuration system in the power grid system, data coordination is achieved between the total adjustment point and the middle adjustment point, the problem of insufficient coordination and real-time in the configuration of the power grid operation mode is solved, and the effects of data sharing and historical data backtracking are achieved.
Patent Information
- Application Number
- CN202411592807.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-08
- Publication Date
- 2025-02-07
Smart Images

Figure CN119401439A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of power system operation mode, and in particular to an online configuration method, device, equipment and storage medium for power grid operation mode. Background Art
[0002] During the daily operation of the power grid, the dispatching department needs to configure the corresponding operation mode, and determine the operation mode within a certain period according to the grid structure data to ensure the normal operation of the power grid. However, the current grid system dispatching agency uses the sending notification file when organizing the editing of the operation mode, so as to complete the configuration of the operation mode through offline calculation. At the same time, since the text editing structure used by each node when editing the grid operation mode may be different, this offline notification mode leads to data not being shared, data editing errors are difficult to check, and there is a lack of coordination after the task is issued. At the same time, it is difficult to realize the backtracking of historical data.
[0003] Therefore, a method for online configuration of power grid operation mode is needed to solve the problem of insufficient coordination and real-time performance between nodes during the configuration process of power grid operation mode. Summary of the invention
[0004] The purpose of this application is to solve at least one of the above-mentioned technical defects, especially the technical defects of insufficient coordination and real-time performance between the general dispatching and the central dispatching in the process of configuring the power grid operation mode in the prior art.
[0005] In a first aspect, the present application provides a method for online configuration of a power grid operation mode, the method being applied to a target configuration system, the target configuration system comprising a total regulation point and a plurality of intermediate regulation points, the method comprising:
[0006] Determine a first operating mode through the master regulating point, and send the first operating mode to each of the intermediate regulating points;
[0007] Processing the first operation mode through each of the intermediate adjustment points to generate a second operation mode;
[0008] Reporting the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points;
[0009] A target operating mode is determined through the overall adjustment point according to the second operating mode of each of the intermediate adjustment points.
[0010] As an optional implementation manner, determining the first operating mode through the total adjustment point includes:
[0011] By means of the total adjustment point, the operation mode data of the previous cycle is used as the initial data;
[0012] According to the operation status of the electrical equipment in this cycle, the initial data is adjusted to determine the first operation mode.
[0013] As an optional implementation, the method further includes:
[0014] After determining the first operation mode, performing power flow calculation on the first operation mode;
[0015] The validity of the first operation mode is determined according to the result of the power flow calculation, and if the first operation mode is valid, the first operation mode is sent to each of the intermediate regulation points.
[0016] As an optional implementation manner, the processing of the first operation mode by each of the intermediate adjustment points to generate a second operation mode includes:
[0017] Determining first target data in the first operation mode according to corresponding areas of each of the intermediate adjustment points;
[0018] The first target data is processed according to the target operation status of each electrical device in the corresponding area in this cycle to obtain a second operation mode.
[0019] As an optional implementation manner, before reporting the determined second operating mode to the overall adjustment point through each of the intermediate adjustment points, the method further includes:
[0020] performing power flow calculation for the second operation mode;
[0021] Determining the validity of the second operation mode according to the result of the power flow calculation;
[0022] The step of reporting the determined second operation mode to the overall adjustment point includes:
[0023] If the second operating mode is valid, the second operating mode is uploaded to the master adjustment point.
[0024] As an optional implementation manner, the overall adjustment point determines the target operation mode according to the second operation mode of each of the intermediate adjustment points, including:
[0025] The overall adjustment point is spliced according to each of the second operating modes to determine a third operating mode;
[0026] The validity of the third operating mode is determined through power flow calculation. If the third operating mode is valid, the third operating mode is used as the target operating mode. If the third operating mode is invalid, the third operating mode is corrected and the corrected third operating mode is used as the target operating mode.
[0027] As an optional implementation manner, after the overall adjustment point determines the target operation mode according to the second operation mode of each of the intermediate adjustment points, the method further includes:
[0028] The general regulating point determines the second target data in the target operation mode according to the corresponding areas of each of the intermediate regulating points, and sends the second target data to each of the intermediate regulating points;
[0029] Each of the intermediate adjustment points adjusts the operating parameters of the electrical equipment in the corresponding area according to the second target data.
[0030] In a second aspect, the present application provides an online configuration device for a power grid operation mode, the device being applied to a target configuration system, the target configuration system comprising a total regulation point and a plurality of intermediate regulation points, the device comprising:
[0031] A determination module, configured to determine a first operation mode through the overall adjustment point;
[0032] A processing module, used for sending the first operation mode to each of the intermediate adjustment points;
[0033] The processing module is further used to process the first operation mode through each of the intermediate adjustment points to generate a second operation mode;
[0034] The processing module is further used to report the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points;
[0035] The processing module is further configured to determine a target operating mode according to the second operating mode of each of the intermediate regulating points through the overall regulating point.
[0036] As an optional implementation manner, the processing module determines a specific manner of the first operation mode through the total adjustment point, including:
[0037] By means of the total adjustment point, the operation mode data of the previous cycle is used as the initial data;
[0038] According to the operation status of the electrical equipment in this cycle, the initial data is adjusted to determine the first operation mode.
[0039] As an optional implementation manner, the processing module is further used for:
[0040] After determining the first operation mode, performing power flow calculation on the first operation mode;
[0041] The validity of the first operation mode is determined according to the result of the power flow calculation, and if the first operation mode is valid, the first operation mode is sent to each of the intermediate regulation points.
[0042] As an optional implementation manner, the processing module processes the first operation mode through each of the intermediate adjustment points to generate a specific mode of the second operation mode, including:
[0043] Determining first target data in the first operation mode according to corresponding areas of each of the intermediate adjustment points;
[0044] The first target data is processed according to the target operation status of each electrical device in the corresponding area in this cycle to obtain a second operation mode.
[0045] As an optional implementation manner, the processing module is further configured to, before reporting the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points,
[0046] performing power flow calculation for the second operation mode;
[0047] Determining the validity of the second operation mode according to the result of the power flow calculation;
[0048] The step of reporting the determined second operation mode to the overall adjustment point includes:
[0049] If the second operating mode is valid, the second operating mode is uploaded to the master adjustment point.
[0050] As an optional implementation manner, the processing module is used for the overall adjustment point to determine a specific method of the target operation mode according to the second operation mode of each of the intermediate adjustment points, including:
[0051] The overall adjustment point is spliced according to each of the second operating modes to determine a third operating mode;
[0052] The validity of the third operating mode is determined through power flow calculation. If the third operating mode is valid, the third operating mode is used as the target operating mode. If the third operating mode is invalid, the third operating mode is corrected and the corrected third operating mode is used as the target operating mode.
[0053] As an optional implementation manner, the processing module is further configured to, after the overall adjustment point determines the target operation mode according to the second operation mode of each of the intermediate adjustment points,
[0054] Triggering the master adjustment point to determine the second target data in the target operation mode according to the corresponding area of each of the intermediate adjustment points, and sending the second target data to each of the intermediate adjustment points;
[0055] And trigger each of the intermediate adjustment points to adjust the operating parameters of the electrical equipment in the corresponding area according to the second target data.
[0056] In a third aspect, the present application provides a computer device comprising one or more processors and a memory, wherein the memory stores computer-readable instructions, and when the computer-readable instructions are executed by the one or more processors, the steps of the method described in the first aspect are performed.
[0057] In a fourth aspect, the present application provides a storage medium storing computer-readable instructions, which, when executed by one or more processors, causes the one or more processors to perform the steps of the method described in the first aspect.
[0058] It can be seen from the above technical solutions that the embodiments of the present application have the following advantages:
[0059] Based on any of the above embodiments, the method provided by the present application is applied to a target configuration system including a general regulation point and multiple intermediate regulation points to achieve data coordination between the general regulation point and each intermediate regulation point, and improve the data coordination and real-time performance between the general regulation point and the intermediate regulation point during the configuration process of the power grid operation mode. Specifically, based on the same working platform, the general regulation point first determines an overall first operation mode and distributes it to each intermediate regulation point. Each intermediate regulation point processes the first operation mode and then generates a corresponding second operation mode. After the second operation mode is generated, it is reported to the general regulation point, so that the general regulation point can complete the splicing of the operation mode according to the second operation mode corresponding to each intermediate regulation point, thereby completing the online configuration of the operation mode. Through the implementation scheme of the working platform, the interaction process of the operation mode data is carried out online, realizing online data interaction and data sharing in the whole process of mode configuration, and improving the coordination and real-time performance between each node during the configuration process of the power grid operation mode. BRIEF DESCRIPTION OF THE DRAWINGS
[0060] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0061] Figure 1 A schematic diagram of a flow chart of an online configuration method for a power grid operation mode provided by an embodiment of the present application;
[0062] Figure 2 A schematic diagram of a flow chart of an online configuration method for a power grid operation mode provided by an embodiment of the present application;
[0063] Figure 3 A schematic diagram showing the effect of an online configuration method for a power grid operation mode provided by an embodiment of the present application;
[0064] Figure 4 A schematic diagram showing the effect of an online configuration method for a power grid operation mode provided by an embodiment of the present application;
[0065] Figure 5 This is a diagram of the internal structure of a computer device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0066] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0067] With the continuous development and expansion of new energy power systems, the construction of new energy power grid models has become increasingly complex, requiring the integration of data and information from multiple sources to ensure the safe and stable operation of the power grid. As an effective means, splicing technology can improve the structural accuracy and integrity of power grid models by integrating and splicing power grid models from different sources, thereby improving the accuracy of calculation results for static safety analysis, dispatcher flow, and other applications, and ensuring the safe and stable operation of the power grid.
[0068] The units carry out the work offline independently, and each unit adopts a text editing structure when editing the grid operation mode. This operation mode leads to problems such as non-sharing of data, difficulty in verifying data editing errors, lack of collaborative office capabilities after the task is issued, and inability to trace back historical data.
[0069] This application implements the task distribution based on the unified grid structure data provided by the general dispatcher, and edits the grid operation mode in an online mode. In practical applications, the following effects can be achieved:
[0070] Quickly and conveniently implement data editing, and realize data sharing, historical data backtracking, collaborative office, and batch editing capabilities by editing power grid operation mode data online.
[0071] Flexible task allocation and delivery, quickly generate a complete set of method data according to the research area and give it to the lower-level dispatching units.
[0072] The subordinate dispatching unit can edit the data of the dispatching method and submit it after completing the processing.
[0073] After all the issued task mode data are submitted, the general dispatcher can splice them together with one click to form a new compiled mode data.
[0074] Specifically, the technical concept of the present application is that the method provided by the present application is applied to a target configuration system including a general regulation point and multiple intermediate regulation points, so as to realize data coordination between the general regulation point and each intermediate regulation point, and improve the data coordination and real-time performance between the general regulation point and the intermediate regulation point in the process of configuring the power grid operation mode. Specifically, based on the same working platform, the general regulation point first determines an overall first operation mode and distributes it to each intermediate regulation point. Each intermediate regulation point processes the first operation mode and then generates a corresponding second operation mode. After generating the second operation mode, it is reported to the general regulation point, so that the general regulation point can complete the splicing of the operation mode according to the second operation mode corresponding to each intermediate regulation point, thereby completing the online configuration of the operation mode. Through the implementation scheme of the working platform, the interactive process of the operation mode data is carried out online, realizing the online data interaction and data sharing of the whole process of mode configuration, and improving the coordination and real-time performance between each node in the process of configuring the power grid operation mode.
[0075] See also Figure 1 , Figure 1 A schematic diagram of a flow chart of a method for online configuration of a power grid operation mode provided by an embodiment of the present application, wherein the method is applied to a target configuration system, wherein the target configuration system includes a total regulation point and multiple intermediate regulation points, such as Figure 1 As shown, the method includes:
[0076] S101, determining a first operating mode through the master regulating point, and sending the first operating mode to each of the intermediate regulating points;
[0077] In the power system, the operation mode of the power system includes the working status and operation strategy of the power system under different conditions, which ensures that the power system can operate safely, reliably and economically. In the scenario where the general dispatching and the central dispatching work together to configure the operation mode, the mode of the general dispatching side can be issued and the mode can be spliced, and the general regulation point and the central regulation point can complete data collaboration and data sharing through the same work platform.
[0078] Specifically, the general regulation point first generates a first operating mode of the overall scope to indicate the overall operating effect of each electrical equipment in the corresponding area of all the intermediate regulation points under the general regulation point within a specific period, such as a monthly period. The specific scenario in which the general regulation point generates the first operating mode may include: copying the data of the previous month to create the monthly mode data of the entire network as the initial data, and modifying and editing the entire network data of the corresponding area of the general regulation of the current month based on the initial data. The editing content includes: maintaining the model parameters of the general regulation equipment, determining the operating status of the inter-provincial AC interconnection lines and DC transmission, and the inter-provincial exchange power.
[0079] When determining the first operation mode, the master adjustment point can also verify the user identity at the current master adjustment point, thereby further ensuring the effectiveness and security of data processing. For example, a certain data is restricted to expert users in Group A for editing, and users in Group B and non-expert users in Group A cannot edit it, thereby ensuring the accuracy of the operation mode configuration, and only specific users have access to confidential data, which improves data security.
[0080] Similarly, corresponding user identity authentication mechanisms can also be introduced at the intermediate adjustment points.
[0081] S102, processing the first operation mode through each of the intermediate adjustment points to generate a second operation mode;
[0082] After completing the configuration of the first operating mode, the mode can be issued and the first operating mode can be sent to each central controller, and each central controller determines the corresponding second operating mode according to the corresponding area.
[0083] Among them, the method distribution includes: a complete set of method data, which generates multiple method data based on the research area, that is, the area associated with the central adjustment point, and gives them to the subordinate units.
[0084] Each intermediate adjustment point can actively select part of the data in the first operation mode to configure the second operation mode according to its own area, such as the electrical equipment in the province corresponding to each intermediate adjustment. In addition, in the first operation mode, the data respectively belonging to the configuration of each intermediate adjustment point can also be allocated through the master adjustment point, that is, after the master adjustment point determines the first operation mode, it is directly allocated according to the area corresponding to each intermediate adjustment point, thereby realizing flexible configuration of data and improving the efficiency of determining the operation mode.
[0085] S103, reporting the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points;
[0086] After completing the corresponding configuration task, each intermediate regulation point will uniformly report the determined second operating mode to the general regulation point. Later, after completing the configuration of the target operating mode, the general regulation point can also allocate it to each intermediate regulation point, so that each intermediate regulation point can complete the adjustment of the electrical equipment parameters in its area according to the allocation data of the general regulation point.
[0087] S104: Determine a target operating mode through the total adjustment point and according to the second operating mode of each of the intermediate adjustment points.
[0088] The overall adjustment point may summarize and process the second operating modes generated by the intermediate adjustment points to generate a target operating mode in a splicing or integration manner.
[0089] The method splicing includes: merging the selected method data set according to the proposed rules.
[0090] The method provided in this application is mainly to improve the coordination between the total regulation point and the central regulation point in the process of configuring the power grid operation mode. Therefore, the total regulation and the central regulation can process, upload and distribute data on the same work platform, and the work platform can also realize the recording, backtracking and visualization of the processing process to improve the efficiency and effectiveness of data interaction and data processing. At the same time, front-end buttons can also be set on the work platform for users to execute corresponding functions with one click, which improves the interaction efficiency. For example, the specific splicing during the mode splicing process, the verification of the effectiveness of the operation mode, the flow calculation and other functions can be encapsulated and integrated, and the user can further execute the corresponding function by triggering instructions on the front-end interface.
[0091] Correspondingly, part or all of the concepts of the working platform used to implement the corresponding method of the present application should also be included in the corresponding protection scope of the present application.
[0092] This implementation is applied to a target configuration system including a general regulation point and multiple intermediate regulation points to achieve data coordination between the general regulation point and each intermediate regulation point, and improve the data coordination and real-time performance between the general regulation point and the intermediate regulation point during the configuration process of the power grid operation mode. Specifically, based on the same working platform, the general regulation point first determines an overall first operation mode and distributes it to each intermediate regulation point. Each intermediate regulation point processes the first operation mode and then generates a corresponding second operation mode. After the second operation mode is generated, it is reported to the general regulation point, so that the general regulation point can complete the splicing of the operation mode according to the second operation mode corresponding to each intermediate regulation point, thereby completing the online configuration of the operation mode. Through the implementation scheme of the working platform, the interactive process of the operation mode data is carried out online, realizing online data interaction and data sharing in the whole process of mode configuration, and improving the coordination and real-time performance between each node during the configuration process of the power grid operation mode.
[0093] As an optional implementation manner, determining the first operating mode through the total adjustment point includes:
[0094] By means of the total adjustment point, the operation mode data of the previous cycle is used as the initial data;
[0095] According to the operation status of the electrical equipment in this cycle, the initial data is adjusted to determine the first operation mode.
[0096] This implementation method calls the operating mode data of the previous cycle as the initial data of this cycle through the total adjustment point. If the operating conditions have not changed significantly, the operating mode data of the previous cycle can be directly used as the first operating mode of this cycle. If the expected operating conditions of the electrical equipment change during this cycle, the initial data is compiled accordingly to obtain the first operating mode, thereby improving the efficiency and effectiveness of the compilation of the first operating mode, and the compilation process is completed online, which is conducive to data modification and backtracking.
[0097] As an optional implementation, the method further includes:
[0098] After determining the first operation mode, performing power flow calculation on the first operation mode;
[0099] The validity of the first operation mode is determined according to the result of the power flow calculation, and if the first operation mode is valid, the first operation mode is sent to each of the intermediate regulation points.
[0100] After determining the first operating mode, this embodiment performs power flow calculation, judges the effectiveness of the first operating mode based on the convergence of the power flow calculation, and sends it to each intermediate regulation point after determining that the first operating mode is effective. The power flow calculation can be implemented through the calculation module in the target configuration system, which is convenient for operation through the interface, thereby improving the effectiveness and efficiency of the first operating mode determination process.
[0101] As an optional implementation manner, the processing of the first operation mode by each of the intermediate adjustment points to generate a second operation mode includes:
[0102] Determining first target data in the first operation mode according to corresponding areas of each of the intermediate adjustment points;
[0103] The first target data is processed according to the target operation status of each electrical device in the corresponding area in this cycle to obtain a second operation mode.
[0104] In this embodiment, according to the area corresponding to each intermediate adjustment point, the first target data related to the corresponding area is obtained in the first operating mode through the total adjustment point or each intermediate adjustment point itself, and each intermediate adjustment point can only process the first target data, and compile the second operating mode according to the expected operating conditions of the electrical equipment in the corresponding area within this cycle, thereby improving the effectiveness of the second operating mode, reducing the amount of data in the processing process, and improving the compilation efficiency of the second operating mode.
[0105] As an optional implementation manner, before reporting the determined second operating mode to the overall adjustment point through each of the intermediate adjustment points, the method further includes:
[0106] performing power flow calculation for the second operation mode;
[0107] Determining the validity of the second operation mode according to the result of the power flow calculation;
[0108] The step of reporting the determined second operation mode to the overall adjustment point includes:
[0109] If the second operating mode is valid, the second operating mode is uploaded to the master adjustment point.
[0110] After determining the second operating mode, this embodiment performs power flow calculation, judges the effectiveness of the second operating mode based on the convergence of the power flow calculation, and sends it to the general regulation point through the intermediate regulation point for aggregation after determining that the second operating mode is effective. The power flow calculation can be implemented through the calculation module in the target configuration system, which is convenient for operation through the interface, thereby improving the effectiveness and efficiency of the second operating mode determination process.
[0111] As an optional implementation manner, the overall adjustment point determines the target operation mode according to the second operation mode of each of the intermediate adjustment points, including:
[0112] The overall adjustment point is spliced according to each of the second operating modes to determine a third operating mode;
[0113] The validity of the third operating mode is determined through power flow calculation. If the third operating mode is valid, the third operating mode is used as the target operating mode. If the third operating mode is invalid, the third operating mode is corrected and the corrected third operating mode is used as the target operating mode.
[0114] In this embodiment, after the general regulation point receives the second operating mode of each intermediate regulation point, it performs splicing to obtain the third operating mode and executes the power flow calculation. The validity of the third operating mode is judged according to the convergence of the power flow calculation, and after determining that the third operating mode is valid, it is used as the target operating mode of this cycle. The power flow calculation can be implemented through the calculation module in the target configuration system, which is convenient for operation through the interface, thereby improving the effectiveness and efficiency of the target operating mode determination process.
[0115] As an optional implementation manner, after the overall adjustment point determines the target operation mode according to the second operation mode of each of the intermediate adjustment points, the method further includes:
[0116] The general regulating point determines the second target data in the target operation mode according to the corresponding areas of each of the intermediate regulating points, and sends the second target data to each of the intermediate regulating points;
[0117] Each of the intermediate adjustment points adjusts the operating parameters of the electrical equipment in the corresponding area according to the second target data.
[0118] After determining the target operating mode, this embodiment splits the data in the target operating mode and sends it to the corresponding intermediate adjustment point. The intermediate adjustment point can adjust the operating parameters of each electrical equipment in this cycle according to the corresponding data, thereby improving the practicality of the target operating mode.
[0119] See also Figure 2 , Figure 2 A flowchart of an online configuration method for a power grid operation mode provided by an embodiment of the present application is shown in FIG. Figure 2 A scheme for combining the various implementation methods of the present application is shown, including the coordination process and data verification process of the general dispatching and each intermediate dispatching. Specifically, its principle can refer to the introduction in Table 1 and the description in the relevant implementation methods. In the power system, the area corresponding to the intermediate dispatching can be based on provinces, and the user group includes a group leader and group members. In some implementation methods, during the process of configuring the operating mode, the identity of the current user can also be verified to ensure the security and validity of the data. Figure 2 In the corresponding implementation manner, the mode configuration takes a month as an example cycle.
[0120] Table 1
[0121]
[0122] From Table 1 and the descriptions of the various implementation methods, it can be seen that the overall process mainly includes:
[0123] Monthly method for preparing the general survey:
[0124] The general adjustment copies the method data of last month and compiles the latest initial data.
[0125] Issued:
[0126] After the initial mode data is successfully calculated, the general dispatching sends multiple modes to the central dispatching according to the central dispatching unit.
[0127] In the specific implementation method, when issuing, only the central dispatching unit with the regional responsible user can be selected. The regional responsible user is set in the regional department management. The responsible user can be changed when issuing. The power flow calculation will be performed when issuing, but it cannot be reflected on the page. There is also a page for performing calculations in the method details. Please refer to Figure 3 , Figure 3 A schematic diagram of the effect of an online configuration method for a power grid operation mode provided in an embodiment of the present application is used to illustrate the result of successful convergence when calculating a certain mode after clicking the power flow calculation option.
[0128] The tasks of each central adjustment are:
[0129] See also Figure 4 , Figure 4 This is a schematic diagram of the effect of the online configuration method of the power grid operation mode provided by an embodiment of the present application, specifically, a page for compiling a certain generator, and the user can modify the data in the white background box, and after the modification, the user can also Figure 3 The power flow calculation shown tests for convergence.
[0130] submit:
[0131] After each central dispatching department has prepared the mode data and successfully completed the flow calculation, it will submit the mode data.
[0132] Stitching:
[0133] The general adjustment splices the data submitted by the intermediate adjustment to form the final mode data for the month, that is, the target operating mode.
[0134] Each process can be implemented through the aforementioned work platform. When the status of all issued data has become submitted, the user of the general coordination office can click the splicing button. After splicing, a new mode data will be generated, which will be the target operation mode after verification.
[0135] The embodiment of the present application further provides a corresponding device, which is applied to a target configuration system, wherein the target configuration system includes a total adjustment point and multiple intermediate adjustment points, and the device includes:
[0136] A determination module, configured to determine a first operation mode through the overall adjustment point;
[0137] A processing module, used for sending the first operation mode to each of the intermediate adjustment points;
[0138] The processing module is further used to process the first operation mode through each of the intermediate adjustment points to generate a second operation mode;
[0139] The processing module is further used to report the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points;
[0140] The processing module is further configured to determine a target operating mode according to the second operating mode of each of the intermediate regulating points through the overall regulating point.
[0141] This implementation is applied to a target configuration system including a general regulation point and multiple intermediate regulation points to achieve data coordination between the general regulation point and each intermediate regulation point, and improve the data coordination and real-time performance between the general regulation point and the intermediate regulation point during the configuration process of the power grid operation mode. Specifically, based on the same working platform, the general regulation point first determines an overall first operation mode and distributes it to each intermediate regulation point. Each intermediate regulation point processes the first operation mode and then generates a corresponding second operation mode. After the second operation mode is generated, it is reported to the general regulation point, so that the general regulation point can complete the splicing of the operation mode according to the second operation mode corresponding to each intermediate regulation point, thereby completing the online configuration of the operation mode. Through the implementation scheme of the working platform, the interactive process of the operation mode data is carried out online, realizing online data interaction and data sharing in the whole process of mode configuration, and improving the coordination and real-time performance between each node during the configuration process of the power grid operation mode.
[0142] As an optional implementation manner, the processing module determines a specific manner of the first operation mode through the total adjustment point, including:
[0143] By means of the total adjustment point, the operation mode data of the previous cycle is used as the initial data;
[0144] According to the operation status of the electrical equipment in this cycle, the initial data is adjusted to determine the first operation mode.
[0145] This implementation method calls the operating mode data of the previous cycle as the initial data of this cycle through the total adjustment point. If the operating conditions have not changed significantly, the operating mode data of the previous cycle can be directly used as the first operating mode of this cycle. If the expected operating conditions of the electrical equipment change during this cycle, the initial data is compiled accordingly to obtain the first operating mode, thereby improving the efficiency and effectiveness of the compilation of the first operating mode, and the compilation process is completed online, which is conducive to data modification and backtracking.
[0146] As an optional implementation manner, the processing module is further used for:
[0147] After determining the first operation mode, performing power flow calculation on the first operation mode;
[0148] The validity of the first operation mode is determined according to the result of the power flow calculation, and if the first operation mode is valid, the first operation mode is sent to each of the intermediate regulation points.
[0149] After determining the first operating mode, this embodiment performs power flow calculation, judges the effectiveness of the first operating mode based on the convergence of the power flow calculation, and sends it to each intermediate regulation point after determining that the first operating mode is effective. The power flow calculation can be implemented through the calculation module in the target configuration system, which is convenient for operation through the interface, thereby improving the effectiveness and efficiency of the first operating mode determination process.
[0150] As an optional implementation manner, the processing module processes the first operation mode through each of the intermediate adjustment points to generate a specific mode of the second operation mode, including:
[0151] Determining first target data in the first operation mode according to corresponding areas of each of the intermediate adjustment points;
[0152] The first target data is processed according to the target operation status of each electrical device in the corresponding area in this cycle to obtain a second operation mode.
[0153] In this embodiment, according to the area corresponding to each intermediate adjustment point, the first target data related to the corresponding area is obtained in the first operating mode through the total adjustment point or each intermediate adjustment point itself, and each intermediate adjustment point can only process the first target data, and compile the second operating mode according to the expected operating conditions of the electrical equipment in the corresponding area within this cycle, thereby improving the effectiveness of the second operating mode, reducing the amount of data in the processing process, and improving the compilation efficiency of the second operating mode.
[0154] As an optional implementation manner, the processing module is further configured to, before reporting the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points,
[0155] performing power flow calculation for the second operation mode;
[0156] Determining the validity of the second operation mode according to the result of the power flow calculation;
[0157] The step of reporting the determined second operation mode to the overall adjustment point includes:
[0158] If the second operating mode is valid, the second operating mode is uploaded to the master adjustment point.
[0159] After determining the second operating mode, this embodiment performs power flow calculation, judges the effectiveness of the second operating mode based on the convergence of the power flow calculation, and sends it to the general regulation point through the intermediate regulation point for aggregation after determining that the second operating mode is effective. The power flow calculation can be implemented through the calculation module in the target configuration system, which is convenient for operation through the interface, thereby improving the effectiveness and efficiency of the second operating mode determination process.
[0160] As an optional implementation manner, the processing module is used for the overall adjustment point to determine a specific method of the target operation mode according to the second operation mode of each of the intermediate adjustment points, including:
[0161] The overall adjustment point is spliced according to each of the second operating modes to determine a third operating mode;
[0162] The validity of the third operating mode is determined through power flow calculation. If the third operating mode is valid, the third operating mode is used as the target operating mode. If the third operating mode is invalid, the third operating mode is corrected and the corrected third operating mode is used as the target operating mode.
[0163] In this embodiment, after the general regulation point receives the second operating mode of each intermediate regulation point, it performs splicing to obtain the third operating mode and executes the power flow calculation. The validity of the third operating mode is judged according to the convergence of the power flow calculation, and after determining that the third operating mode is valid, it is used as the target operating mode of this cycle. The power flow calculation can be implemented through the calculation module in the target configuration system, which is convenient for operation through the interface, thereby improving the effectiveness and efficiency of the target operating mode determination process.
[0164] As an optional implementation manner, the processing module is further configured to, after the overall adjustment point determines the target operation mode according to the second operation mode of each of the intermediate adjustment points,
[0165] Triggering the master adjustment point to determine the second target data in the target operation mode according to the corresponding area of each of the intermediate adjustment points, and sending the second target data to each of the intermediate adjustment points;
[0166] And trigger each of the intermediate adjustment points to adjust the operating parameters of the electrical equipment in the corresponding area according to the second target data.
[0167] After determining the target operating mode, this embodiment splits the data in the target operating mode and sends it to the corresponding intermediate adjustment point. The intermediate adjustment point can adjust the operating parameters of each electrical equipment in this cycle according to the corresponding data, thereby improving the practicality of the target operating mode.
[0168] It should be noted that it should be understood that the division of the various modules of the above device is only a division of logical functions. In actual implementation, they can be fully or partially integrated into one physical entity, or they can be physically separated. And these modules can all be implemented in the form of software called by processing elements; they can also be all implemented in the form of hardware; some modules can also be implemented in the form of software called by processing elements, and some modules can be implemented in the form of hardware. For example, the processing module can be a separately established processing element, or it can be integrated in a chip of the above device. In addition, it can also be stored in the memory of the above device in the form of program code, and called and executed by a processing element of the above device. The function of the above-determined module. The implementation of other modules is similar. In addition, these modules can be fully or partially integrated together, or they can be implemented independently. The processing element here can be an integrated circuit with signal processing capabilities. In the implementation process, each step of the above method or each module above can be completed by an integrated logic circuit of hardware in the processor element or instructions in the form of software.
[0169] Indicatively, Figure 5 As shown, Figure 5 This is a schematic diagram of the internal structure of a computer device provided in an embodiment of the present application. The computer device 300 may be provided as a server. Figure 5 The computer device 300 includes a processing component 302, which further includes one or more processors, and a memory resource represented by a memory 301 for storing instructions executable by the processing component 302, such as an application. The application stored in the memory 301 may include one or more modules, each corresponding to a set of instructions. In addition, the processing component 302 is configured to execute the instructions to perform the text recognition method of any of the above embodiments.
[0170] The computer device 300 may further include a power supply component 303 configured to perform power management of the computer device 300, a wired or wireless network interface 304 configured to connect the computer device 300 to a network, and an input / output (I / O) interface 305. The computer device 300 may operate based on an operating system stored in the memory 301, such as Windows Server TM, Mac OS X TM, Unix TM, Linux TM, Free BSD TM, or the like.
[0171] Those skilled in the art will understand that Figure 5 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.
[0172] An embodiment of the present application provides a storage medium, in which computer-readable instructions are stored. When the computer-readable instructions are executed by one or more processors, the one or more processors execute a method provided in any embodiment.
[0173] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.
[0174] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The various embodiments can be combined as needed, and the same or similar parts can refer to each other.
[0175] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A method for online configuration of power grid operation mode, characterized in that: The method is applied to a target configuration system, the target configuration system includes a total adjustment point and a plurality of intermediate adjustment points, and the method includes: Determine a first operating mode through the master regulating point, and send the first operating mode to each of the intermediate regulating points; Processing the first operation mode through each of the intermediate adjustment points to generate a second operation mode; Reporting the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points; A target operating mode is determined through the overall adjustment point according to the second operating mode of each of the intermediate adjustment points.
2. The method according to claim 1, characterized in that Determining the first operating mode through the overall adjustment point includes: By means of the total adjustment point, the operation mode data of the previous cycle is used as the initial data; According to the operation status of the electrical equipment in this cycle, the initial data is adjusted to determine the first operation mode.
3. The method according to claim 2, characterized in that The method further comprises: After determining the first operation mode, performing power flow calculation on the first operation mode; The validity of the first operation mode is determined according to the result of the power flow calculation, and if the first operation mode is valid, the first operation mode is sent to each of the intermediate regulation points.
4. The method according to claim 1, characterized in that: The step of processing the first operation mode through each of the intermediate adjustment points to generate a second operation mode includes: Determining first target data in the first operation mode according to corresponding areas of each of the intermediate adjustment points; The first target data is processed according to the target operation status of each electrical device in the corresponding area in this cycle to obtain a second operation mode.
5. The method according to claim 1, characterized in that Before reporting the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points, the method further includes: performing power flow calculation for the second operation mode; Determining the validity of the second operation mode according to the result of the power flow calculation; The step of reporting the determined second operation mode to the overall adjustment point includes: If the second operating mode is valid, the second operating mode is uploaded to the master adjustment point.
6. The method according to claim 1, characterized in that The overall regulating point determines the target operating mode according to the second operating mode of each of the intermediate regulating points, including: The overall adjustment point is spliced according to each of the second operating modes to determine a third operating mode; The validity of the third operating mode is determined through power flow calculation. If the third operating mode is valid, the third operating mode is used as the target operating mode. If the third operating mode is invalid, the third operating mode is corrected and the corrected third operating mode is used as the target operating mode.
7. The method according to any one of claims 1 to 6, characterized in that: After the overall adjustment point determines the target operation mode according to the second operation mode of each of the intermediate adjustment points, the method further includes: The general regulating point determines the second target data in the target operation mode according to the corresponding areas of each of the intermediate regulating points, and sends the second target data to each of the intermediate regulating points; Each of the intermediate adjustment points adjusts the operating parameters of the electrical equipment in the corresponding area according to the second target data.
8. An online configuration device for power grid operation mode, characterized in that: The device is applied to a target configuration system, the target configuration system includes a total adjustment point and a plurality of intermediate adjustment points, and the device includes: A determination module, configured to determine a first operation mode through the overall adjustment point; A processing module, used for sending the first operation mode to each of the intermediate adjustment points; The processing module is further used to process the first operation mode through each of the intermediate adjustment points to generate a second operation mode; The processing module is further used to report the determined second operation mode to the overall adjustment point through each of the intermediate adjustment points; The processing module is further configured to determine a target operating mode according to the second operating mode of each of the intermediate regulating points through the overall regulating point.
9. A computer device, characterized in that: The method comprises one or more processors and a memory, wherein the memory stores computer-readable instructions, and when the computer-readable instructions are executed by the one or more processors, the steps of the method according to any one of claims 1 to 7 are performed.
10. A storage medium, characterized in that: The storage medium stores computer-readable instructions, and when the computer-readable instructions are executed by one or more processors, the one or more processors execute the steps of the method according to any one of claims 1 to 7.