Efficient lifting tool and method for ALC battens

By designing an efficient lifting tool for ALC strips including fixed pulleys, retracting and laying devices, steel pipe frames and buffering guide devices, the problem of low construction efficiency of ALC strips is solved, and an efficient, stable and safe lifting process is achieved.

CN119528032APending Publication Date: 2025-02-28THE SECOND CONSTR OF CHINA CONSTR EIGHTH ENG DIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411910264.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-24
Publication Date
2025-02-28

AI Technical Summary

Technical Problem

During the construction process, ALC strips have large weight, wide area and difficult construction, resulting in low construction efficiency. It is necessary to design an efficient lifting tool that is simple to operate, saves time and effort.

Method used

An efficient lifting tool for ALC strips including fixed pulleys, retracting and laying devices, steel pipe frames and buffering guides is designed. Through the cooperation of the wire rope and fixed pulley, the efficient lifting of the strips is achieved by using the hoist to collect and laying devices, and the stability and safety of the lifting are improved through the buffer guide and anti-collision sensor.

Benefits of technology

This tool can significantly improve the construction efficiency of ALC strips, save manpower and material resources, ensure the stability and safety of the lifting process, and reduce the risk of strip damage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119528032A_ABST
    Figure CN119528032A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of ALC batten hoisting, and particularly relates to an efficient ALC batten hoisting tool and method.The device comprises a fixed pulley, a take-up and pay-off device, a steel pipe frame and a buffer guiding device.The vertical projection of the lower portion of the steel pipe frame is rectangular, the rectangular projection of the upper portion of the steel pipe frame is triangular, and the fixed pulley is arranged at the top end of the steel pipe frame; the take-up and pay-off device is arranged on the steel pipe frame, a steel wire rope is connected into the take-up and pay-off device and connected with the fixed pulley in a matched mode, and the buffering guide device is arranged on the side, close to the fixed pulley, of the steel pipe frame in the horizontal direction. The method comprises the steps of releasing a steel wire rope hanging strip plate, starting a winch for hoisting, buffering and righting in case of deviation during ascending, fixing after transferring in place, untying and winding a rope, and resetting a tool. Compared with the prior art, manpower and material resources can be saved, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of ALC strip board hoisting, and in particular to an ALC strip board high-efficiency hoisting tool and method. Background Art

[0002] With the continuous progress and development of society, the construction industry is also experiencing unprecedented changes. In this process, the emergence of various new technologies and new materials has provided strong support for the development of the construction industry. As a new type of building material, ALC strips have the advantages of good durability, green environmental protection, fire retardant, sound insulation and noise reduction, light weight and high strength, convenient construction, and economic savings. It has gradually been widely used in the construction industry.

[0003] However, compared with traditional building materials, ALC strips have the disadvantages of being heavy, large in area, and difficult to construct. Therefore, it is necessary to design a lifting tool that is simple to operate, saves time and effort, and improves construction efficiency. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present invention develops an ALC strip board high-efficiency lifting tool and method, which can save manpower and material resources and improve construction efficiency.

[0005] The technical solution to the technical problem solved by the present invention is: an ALC slat efficient lifting tool, comprising a fixed pulley, a wire-retracting device, a steel pipe rack and a buffer guide device, the lower part of the steel pipe rack having a vertical projection of a rectangle, and the upper rectangular projection of a triangle, the fixed pulley being arranged at the top of the steel pipe rack, the wire-retracting device being arranged on the steel pipe rack, and having a steel wire rope connected thereto, the steel wire rope being cooperatively connected to the fixed pulley, and the buffer guide device being arranged on one side of the steel pipe rack close to the fixed pulley in the horizontal direction.

[0006] Preferably, the wire-retracting and -releasing device is a winch.

[0007] Preferably, a handrail is provided on the steel pipe frame.

[0008] Preferably, a rectangular tube capable of increasing the stability of the steel pipe rack is connected to the bottom of the steel pipe rack.

[0009] Preferably, a universal wheel is connected to the bottom of the rectangular tube.

[0010] Preferably, a counterweight is provided at the bottom of the steel pipe frame.

[0011] Preferably, an anti-collision sensor is provided on one side of the steel pipe rack close to the fixed pulley in the horizontal direction.

[0012] Preferably, the buffer guide device is arranged in an array, including a spring cylinder, a guide rod and a top block, the spring cylinder is connected to a steel pipe frame, the guide rod is connected to the spring cylinder, the steel pipe frame is provided with a through hole, the guide rod passes through the through hole, and the top block is connected to one end of the guide rod away from the spring cylinder.

[0013] Preferably, guide wheels are arranged on the guide rods to provide buffering and reduce friction during the lifting and lowering of the ALC slats.

[0014] An efficient hoisting method for ALC strips, using an efficient hoisting tool for ALC strips to hoist the ALC strips, specifically comprising the following steps: Step 1: Slowly release one end of the wire rope from the winch. The operator holds the free end of the wire rope and passes it through the fixed pulley. Then he walks to the ALC slat to be lifted and hangs the wire rope on the ALC slat. Protect the contact between the wire rope and the slat to prevent scratching the surface of the slat. Step 2: Start the winch, the winch starts to reel in, the wire rope gradually tightens, and the ALC slat is lifted off the ground through the connection with the fixed pulley. If the ALC slat tilts at this time, stop the lifting in time and adjust the wire rope binding position; Step 3: As the slats continue to rise, when the slats are close to the side of the fixed pulley in the horizontal direction of the steel pipe rack, if there is a slight deviation, the guide rod, under the elastic force of the spring tube, drives the top block and the guide wheel to buffer and straighten the slats, and uses the guide wheel to reduce the friction between the slats and the device, and then starts to transfer. At the same time, the anti-collision sensor monitors the surrounding environment in real time. Once it senses that there is an obstacle approaching the lifting path, it immediately sends an alarm signal to the operator, and the operator quickly stops lifting; Step 4: Push the handrail, unlock the universal wheel, move the lifting tool, adjust the position of the ALC slats, and after the slats are lifted to the predetermined installation height and horizontal position, stop the winch and the construction personnel quickly fix the slats; Step 5: After confirming that the ALC slats are firmly installed, untie the wire rope from the slats, operate the winch to slowly release the rope, retract the wire rope to its initial state, move the lifting tool to the starting point of the next lifting, and prepare for the lifting operation of the next ALC slat.

[0015] The effects provided in the summary of the invention are only the effects of the embodiments, rather than all the effects of the invention. The above technical solution has the following advantages or beneficial effects: 1. The present invention is easy to assemble, simple to use, highly flexible to operate, low in cost and highly stable, and can improve construction efficiency and save manpower and material resources; 2. By setting up the rectangular tube, during the hoisting process, the steel pipe frame bears the weight from the slats and transmits the force to the steel pipe frame through the fixed pulley and wire rope. The rectangular tube is responsible for providing lateral support and balance to resist the lateral force that may occur during the hoisting process; 3. By setting up anti-collision sensors, it is possible to detect obstacles ahead when the ALC strips block the operator's line of sight, thus preventing collisions and damage to the ALC strips; 4. By setting up the buffer guide device, on the one hand, it can play a buffering role when the ALC slats tilt and collide with the steel pipe rack during the transportation process, preventing the damage of the ALC slats. On the other hand, it can provide a guiding role when the ALC slats shake during the lifting and lowering process, reducing the friction between the ALC slats and the top block, and better protecting the ALC slats. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a front view of the present invention; Figure 2 A bottom view of the present invention; Figure 3 The overall structure of the present invention Figure 1 ; Figure 4 for Figure 3 A partial enlarged view of the middle A area; Figure 5 The overall structure of the present invention Figure 2 ; Figure 6 for Figure 5 A partial enlarged view of the middle A area; Figure 7 This is a state diagram of hoisting ALC slats according to the present invention.

[0017] Among them: 1. fixed pulley; 2. wire rope; 3. handrail; 4. winch; 5. steel pipe rack; 6. counterweight; 7. rectangular tube; 8. universal wheel; 9. anti-collision sensor; 10. buffer guide device; 101. spring cylinder; 102. guide rod; 103. top block; 104. guide wheel. DETAILED DESCRIPTION

[0018] In order to clearly illustrate the technical features of the present invention, the present invention is described in detail below through specific implementation methods and in conjunction with the accompanying drawings.

[0019] Example 1 See also Figures 1 to 7A high-efficiency lifting tool for ALC slats includes a fixed pulley 1, a wire-retracting device, a steel pipe rack 5 and a buffer guide device 10. The lower vertical projection of the steel pipe rack 5 is a rectangle, and the upper rectangular projection is a triangle. The fixed pulley 1 is arranged at the top of the steel pipe rack 5, and the wire-retracting device is arranged on the steel pipe rack 5. A steel wire rope 2 is connected inside the steel pipe rack 5. The steel wire rope 2 is connected to the fixed pulley 1 in a cooperative manner. The buffer guide device 10 is arranged on the side of the steel pipe rack 5 close to the fixed pulley 1 in the horizontal direction.

[0020] like Figure 1 , Figure 3 , Figure 5 and Figure 7 As shown, the wire-reeling and -unreeling device is a winch 4 .

[0021] like Figure 1 , Figure 3 , Figure 5 and Figure 7 As shown, a handrail 3 is provided on the steel pipe frame 5 .

[0022] like Figure 3 and Figure 5 As shown, a rectangular tube 7 is connected to the bottom of the steel pipe frame 5 to increase the stability of the steel pipe frame 5 .

[0023] like Figure 1 , Figure 3 , Figure 5 and Figure 7 As shown, a universal wheel 8 is connected to the bottom of the rectangular tube 7.

[0024] like Figure 2 , Figure 3 and Figure 5 As shown, a counterweight block 6 is arranged at the bottom of the steel pipe frame 5 .

[0025] like Figure 1 , Figure 3 and Figure 7 As shown, an anti-collision sensor 9 is provided on one side of the steel pipe frame 5 close to the fixed pulley 1 in the horizontal direction.

[0026] like Figures 3 to 6 As shown, the buffer guide device 10 is arranged in an array, including a spring cylinder 101, a guide rod 102 and a top block 103. The spring cylinder 101 is connected to the steel pipe frame 5, and the guide rod 102 is connected to the spring cylinder 101. The steel pipe frame 5 is provided with a through hole, and the guide rod 102 passes through the through hole. The top block 103 is connected to one end of the guide rod 102 away from the spring cylinder 101.

[0027] like Figure 3 and Figure 4 As shown, the guide rod 102 is provided with a guide wheel 104, which can provide a buffer and reduce friction during the process of lifting and lowering the ALC slats.

[0028] An efficient hoisting method for ALC strips, using an efficient hoisting tool for ALC strips to hoist the ALC strips, specifically comprising the following steps: Step 1: Slowly release one end of the wire rope 2 from the winch 4. The operator holds the free end of the wire rope 2 and passes it through the fixed pulley 1. Then, he walks to the ALC slat to be hoisted and hangs the wire rope 2 on the ALC slat. The contact point between the wire rope 2 and the slat is well protected to prevent scratching the surface of the slat. Step 2: Start the winch 4, the winch 4 starts to reel in, the wire rope 2 is gradually tightened, and the ALC slat is lifted off the ground through the connection with the fixed pulley 1. If the ALC slat tilts at this time, stop the lifting in time and adjust the binding position of the wire rope 2; Step 3: As the slats continue to rise, when the slats are close to the side of the steel pipe frame 5 close to the fixed pulley 1 in the horizontal direction, if there is a slight deviation, the guide rod 102, under the elastic force of the spring tube 101, drives the top block 103 and the guide wheel 104 to buffer and straighten the slats, and uses the guide wheel 104 to reduce the friction between the slats and the device, and then starts to transfer. At the same time, the anti-collision sensor 9 monitors the surrounding environment in real time. Once it senses that there is an obstacle approaching near the lifting path, it immediately sends an alarm signal to the operator, and the operator quickly stops lifting; Step 4: Push the handrail 3, unlock the universal wheel 8, move the lifting tool, adjust the position of the ALC slats, and after the slats are lifted to the predetermined installation height and horizontal position, stop the operation of the winch 4, and the construction personnel quickly fix the slats; Step 5: After confirming that the ALC slats are firmly installed, untie the binding between the wire rope 2 and the slats, operate the winch 4 to slowly release the rope, retract the wire rope 2 to the initial state, move the lifting tool to the starting point of the next lifting, and prepare for the lifting operation of the next ALC slat.

[0029] Principle and operation process The lower part of the steel pipe frame 5 is vertically projected into a rectangle, and the upper part is triangular. The rectangular structure is conducive to providing a stable support plane at the bottom, evenly dispersing the weight of the equipment and various forces generated during the lifting process; the upper triangular structure can enhance the ability of the entire frame to resist the lateral force brought by the fixed pulley 1. The fixed pulley 1 is placed on the top of the steel pipe frame 5, changing the direction of the tension of the wire rope 2. One end of the wire rope 2 is connected to the winch 4, and the other end is hung with the ALC strip.

[0030] The buffer guide device 10 array is distributed on one side of the steel pipe frame 5 close to the fixed pulley 1. The spring cylinder 101 serves as an elastic energy storage element. When the ALC slats are slightly offset or shaken during lifting due to factors such as wind force and uneven lifting speed, and touch the buffer guide device 10, the guide rod 102 is forced to compress the spring cylinder 101, and the spring absorbs the impact energy to buffer the collision force; at the same time, the top block 103 and the guide wheel 104 at the end of the guide rod 102 work together to straighten the slats with the help of the rebound force of the spring cylinder 101, reducing the shaking without damaging the ALC slats. The guide wheel 104 can also effectively reduce the friction resistance between the slats and the device to avoid surface scratches.

[0031] The anti-collision sensor 9 installed on the steel pipe rack 5 captures the reflected signal when obstacles appear around the lifting path. Once the distance is too close and there is a risk of collision, the alarm system is immediately triggered to send out sound and light warnings to the operator. The operator can then brake the winch 4 in time and stop the lifting action, ensuring the safety of personnel, equipment and building structures on the construction site.

[0032] The counterweight block 6 added at the bottom of the steel pipe frame 5 can adjust the center of gravity of the entire lifting tool. When lifting ALC slats of different weights, the counterweight blocks 6 of different weights can be selected to offset the overturning moment caused by the eccentricity of the slats and the lifting eccentricity, so that the equipment always remains stable.

[0033] On one hand, the rectangular tube 7 can enhance the bottom structural rigidity of the steel tube frame 5 to resist the lateral tension and torsion generated by lifting; on the other hand, it can serve as a carrier of the universal wheel 8.

[0034] When carrying out the hoisting work, the operator controls the winch 4 to start, releases one end of the wire rope 2, and after releasing a sufficient length, holds the free end of the wire rope 2, places the wire rope 2 along the groove of the fixed pulley 1, and reaches the ALC slat to be hoisted after the hand-held wire rope 2 passes through the fixed pulley 1; when it arrives next to the ALC slat, the ALC slat is hung according to the preset hoisting point position of the slat, and then the hoisting is started, and the operator starts the winch 4, the winch 4 starts to reel in at a uniform speed, and the wire rope 2 is gradually tightened, and the tension is converted into a vertical lifting force through the fixed pulley 1, and the ALC slat is slowly lifted off the ground; if the slat is found to be tilted or shaking, the pause button is immediately pressed to stop the hoisting, and the operator adjusts the hanging position of the wire rope 2. After the adjustment is completed, the winch 4 is started again to slowly lift the slat; as the slat continues to rise, when the slat is close to the side of the steel pipe frame 5 close to the fixed pulley 1 in the horizontal direction, if there is a slight deviation, the guide rod 102 in the ALC Under the pressure of the C strip, the pressure is transmitted to the spring tube 101. At this time, the spring tube 101 is in a stressed state and stores energy at the same time. The top block 103 presses against the strip, and the guide wheel 104 rolls accordingly to buffer the impact of the collision. The strip is straightened with the help of the spring's rebound force to reduce the friction resistance and ensure that the strip rises along the vertical path. At the same time, once the anti-collision sensor 9 senses that an obstacle is approaching near the lifting path, the sensor instantly triggers the alarm system and sounds an alarm. After hearing the alarm, the operator observes the surrounding environment in time to ensure that the lifting work continues along the safe route. The lifting tool is pushed to the bottom of the predetermined installation position of the ALC strip. After reaching the predetermined position, the winch 4 is stopped, and the construction personnel carry out the fixed installation of the ALC strip. After confirming that the ALC strip is firmly installed, the wire rope 2 is untied from the strip, and then the rope is slowly retracted to the initial state. After retracting the wire rope 2, the lifting tool is moved to the starting point of the next lifting through the universal wheel 8.

[0035] Although the above describes the specific implementation mode of the present invention in conjunction with the accompanying drawings, it is not intended to limit the scope of protection of the present invention. Based on the technical solution of the present invention, various modifications or variations that can be made by those skilled in the art without creative work are still within the scope of protection of the present invention.

Claims

1. An ALC slat efficient lifting tool, characterized by: The invention comprises a fixed pulley (1), a wire-retracting and releasing device, a steel pipe frame (5) and a buffer guide device (10), wherein the lower part of the steel pipe frame (5) is vertically projected into a rectangle, and the upper part of the rectangle is projected into a triangle, the fixed pulley (1) is arranged at the top of the steel pipe frame (5), the wire-retracting and releasing device is arranged on the steel pipe frame (5), and a steel wire rope (2) is connected inside the steel pipe frame, the steel wire rope (2) is cooperatively connected to the fixed pulley (1), and the buffer guide device (10) is arranged on one side of the steel pipe frame (5) close to the fixed pulley (1) in the horizontal direction.

2. The ALC slat efficient lifting tool according to claim 1 is characterized in that: The wire-retracting and -releasing device is a winch (4).

3. The ALC slat efficient lifting tool according to claim 2 is characterized in that: The steel pipe frame (5) is provided with a handrail (3).

4. The ALC strip high-efficiency lifting tool according to claim 3 is characterized in that: The bottom of the steel pipe frame (5) is connected to a rectangular tube (7) capable of increasing the stability of the steel pipe frame (5).

5. The ALC slat efficient lifting tool according to claim 4 is characterized in that: A universal wheel (8) is connected to the bottom of the rectangular tube (7).

6. The ALC slat efficient lifting tool according to claim 5 is characterized in that: A counterweight block (6) is arranged at the bottom of the steel pipe frame (5).

7. The ALC slat efficient lifting tool according to claim 6, characterized in that: An anti-collision sensor (9) is provided on one side of the steel pipe frame (5) close to the fixed pulley (1) in the horizontal direction.

8. The ALC slat efficient lifting tool according to claim 7, characterized in that: The buffer guide device (10) is arranged in an array, and comprises a spring cylinder (101), a guide rod (102) and a top block (103); the spring cylinder (101) is connected to a steel pipe frame (5); the guide rod (102) is connected to the spring cylinder (101); a through hole is provided on the steel pipe frame (5); the guide rod (102) passes through the through hole; and the top block (103) is connected to an end of the guide rod (102) away from the spring cylinder (101).

9. The ALC slat efficient lifting tool according to claim 8, characterized in that: The guide rod (102) is provided with a guide wheel (104), which can provide a buffer and reduce friction during the process of lifting and lowering the ALC strip.

10. An efficient hoisting method for ALC slats, characterized by: The method of hoisting the ALC slats using the ALC slats high-efficiency hoisting tool described in claim 9 specifically comprises the following steps: Step 1: Slowly release one end of the steel wire rope (2) from the winch (4). The operator holds the free end of the steel wire rope (2) and passes it through the fixed pulley (1). The operator walks to the ALC slat to be lifted and hangs the steel wire rope (2) on the ALC slat. The contact area between the steel wire rope (2) and the slat is well protected to prevent scratching the surface of the slat. Step 2: Start the winch (4), the winch (4) starts to reel in, the wire rope (2) is gradually tightened, and the ALC slat is lifted off the ground through the connection with the fixed pulley (1). If the ALC slat tilts at this time, the lifting is stopped in time to adjust the binding position of the wire rope (2); Step 3: As the slats continue to rise, when the slats approach the side of the steel pipe frame (5) that is close to the fixed pulley (1) in the horizontal direction, if there is a slight deviation, the guide rod (102) drives the top block (103) and the guide wheel (104) to buffer and straighten the slats under the elastic force of the spring tube (101), and the friction between the slats and the device is reduced by the guide wheel (104), and then the transportation begins. At the same time, the anti-collision sensor (9) monitors the surrounding environment in real time. Once it senses that there is an obstacle approaching near the lifting path, it immediately sends an alarm signal to the operator, and the operator quickly stops lifting; Step 4: Push the handrail (3), unlock the universal wheel (8), move the lifting tool, adjust the position of the ALC slats, and after the slats are lifted to the predetermined installation height and horizontal position, stop the winch (4) and the construction personnel quickly fix the slats; Step 5: After confirming that the ALC slats are firmly installed, untie the wire rope (2) from the slats, operate the winch (4) to slowly release the rope, retract the wire rope (2) to the initial state, move the lifting tool to the starting point of the next lifting, and prepare for the lifting operation of the next ALC slat.