Data center project total package management system and method

By designing the data center project general contract management system in communication engineering project management, the problems of complex management and low efficiency in the existing technology are solved, dynamic management and automatic progress adjustment of engineering projects are realized, and management efficiency and effect are improved.

CN119599241APending Publication Date: 2025-03-11中邮建技术有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411418391.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-11
Publication Date
2025-03-11

AI Technical Summary

Technical Problem

The existing communication engineering project management has problems such as large scale, short construction period, many interspersed processes, and large personnel flow, resulting in complex management, high cost, low efficiency, untimely information acquisition, and unsatisfactory management results.

Method used

Design a data center project general contract management system, including project management module, warehousing management module, document management module, personnel management module and system management module, to realize dynamic management of engineering projects, automatically adjust project progress, and improve management efficiency.

Benefits of technology

Through the automated management system, the efficiency of project management is improved, information communication between various departments is simplified, management costs are reduced, and management results are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119599241A_ABST
    Figure CN119599241A_ABST
Patent Text Reader

Abstract

The invention discloses a data center engineering total package management system and method, and the system can automatically carry out the corresponding adjustment of an engineering progress through the arrangement of a project management module, a warehouse management module, a document management module, a personnel management module and a system management module, achieves the dynamic management of an engineering project, and improves the management efficiency. The management efficiency of the engineering project is improved, meanwhile, the engineering management efficiency is improved, an administrator and a constructor exchange information through the control module, and information communication among departments is facilitated. The invention further relates to a project total package management method. The engineering management efficiency can be improved, an administrator and a constructor exchange information through the control module, information communication among departments is facilitated, the engineering progress can be automatically and correspondingly adjusted, dynamic management of the engineering project is achieved, and the management efficiency of the engineering project is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of communication technology, and in particular to a data center engineering general contracting management system and method. Background Art

[0002] With the continuous advancement of the national informatization strategy, the communications industry has maintained rapid development in recent years. As an important link in the development of communications engineering, the project management level, especially the quality management and control level, plays a vital role.

[0003] The communications industry is a national foundation and pillar industry. my country is in an important period of economic restructuring. The construction of a broadband network that is "high-speed, smooth, covers urban and rural areas, high-quality, low-cost, and convenient" will effectively drive economic development, support the "Internet +" action plan, promote industrialization, informatization, new urbanization and rural modernization, and stimulate overall economic vitality. Fixed broadband networks are the foundation of the entire Internet. The total demand for bandwidth is rising steadily. Mobile Internet and the Internet of Things will become the main driving force for the development of mobile communications. The development of mobile Internet has brought about an explosive growth in traffic, promoting a new round of changes in mobile communications technology and industry. The communications industry will usher in a long period of rapid development.

[0004] The construction of communication projects is the cornerstone of the development of the communication industry. Without the construction of communication infrastructure, there will be no development of the communication industry. Communication project management is an important part of the construction of communication projects. Existing projects have problems such as large scale, short construction period, many interspersed processes, and high personnel turnover. There are many changing factors in project management, and the management process is relatively complex. In addition, the construction process involves the mutual cooperation of multiple departments. In traditional management, the use of manual management of engineering projects is costly and inefficient, information is not obtained in time, and the final management effect is not ideal, which affects the normal operation of the project. Therefore, it is urgent to use information technology to improve quality and reduce consumption, improve efficiency, and make engineering project management information-based and automated. Summary of the invention

[0005] The first purpose of the present invention is to provide a data center engineering general contracting management system and method. By setting up a project management module, a warehouse management module, a document management module, a personnel management module and a system management module, the project progress can be automatically adjusted accordingly to achieve dynamic management of engineering projects, thereby improving the efficiency of engineering project management and the efficiency of engineering management. Administrators and construction personnel exchange information through the control module to facilitate information communication between departments.

[0006] In order to achieve the purpose of the above invention, a data center engineering general contracting management system and method of the present invention includes a project management module, a warehouse management module, a document management module, a personnel management module and a system management module;

[0007] The project management module is used to manage the progress, quality and safety of the project, as well as project changes;

[0008] The warehouse management module is used to manage the detailed information of material storage registration, conduct regular inventory, and check the material inventory quantity;

[0009] The document management module is used to manage bidding documents, tender documents, form templates, contract information, special plans, completion documents, work instructions, rules and regulations, and excellent photos and videos;

[0010] The personnel management module is used to conduct performance appraisals on employees, confirm wages, and manage clocking in and out;

[0011] The system management module is used to authorize developers to perform access control based on resources, roles, and permissions.

[0012] Further, the project management module includes a progress management unit, a problem quality, a safety management unit and a change management unit;

[0013] The progress management unit specifically includes: work plan, the project manager edits and modifies the progress plan, displays the progress plan by milestone nodes according to the level, and updates it in real time; actual progress reporting, each professional administrator fills in the daily cumulative completion rate on the mobile phone, and the system updates the milestone node progress chart according to the report, displays the forward line, and the system will remind if the progress is not updated on the day; daily personnel ledger, team members fill in the outline of the work of the day before 21:00 every day, which serves as the basis for the immediate superior to judge the busy and idle status, and export report information by day, week, and month;

[0014] The problem quality and safety management unit specifically includes: a problem list, which records problems that have not been solved in real time, clarifies the problem content, solver, and solution time limit, and pushes them; before the closed loop, daily reminders, after the closed loop, selected cases are collected in the case library folder and designated for study;

[0015] The change management unit specifically includes: change item ledger, adding change items, recording the content, basis, person in charge and other information of the change items, and displaying the change order status to determine whether to upload; change order upload, the full set of information of the single change, after collection, the administrator scans and uploads it, and the project manager or cost estimator reviews and confirms it; change reminder, if the change order is not uploaded one week after the change item is submitted, the system will remind you every week; approval flow, used for closed management.

[0016] Furthermore, the warehouse management module includes an on-site material storage unit, an on-site material storage unit and an inventory counting unit;

[0017] The on-site material storage unit specifically includes: after the materials arrive at the site, they are stored in the warehouse, and detailed information such as the name, model, price, supplier, storage location and attachment information of the materials are registered during storage, and a watermark camera is supported to take photos to record the current storage time and status;

[0018] The on-site material outbound unit specifically includes: outbound materials according to the material application form, viewing the current inventory quantity, the inventory quantity automatically decreases after outbound, and supports watermark camera to take photos to record the current outbound time and content for approval flow;

[0019] The inventory counting unit specifically includes: system reminder for regular inventory counting, inventory counting at handover, and uploading of inventory counting results.

[0020] Further, the document management module includes a download unit, a full-text index unit, a file upload unit, a project summary unit and a designated learning unit;

[0021] The download unit specifically includes: classifying and grading the bidding documents, tender documents, form templates, contract materials, special plans, completion documents, work instructions, rules and regulations, and excellent photo and video files, and supporting personnel to upload them to corresponding folders according to authorization, and also supports downloading files to local computers;

[0022] The full-text indexing unit specifically includes: employees perform fuzzy queries on all files in the system, search for required files based on keywords, perform accurate searches on all aspects of file resources based on file names and extended attribute keywords, and perform attribute searches based on file creator names, file sizes, creation times, and file tags;

[0023] The file uploading unit specifically includes: first, the project preparation stage, the establishment of the project department, uploading of the project bid materials, the implementation of the project department station, then the design briefing, drawing review, construction drawing deepening, workload clarification, meeting minutes and construction drawings uploaded according to different professional labels, and in CAD format, and finally the preparation of the start-up materials, including the start-up report, the preparation and submission of the construction organization plan and the preparation and submission of special plans; then comes the completion acceptance stage, and the project testing, including comprehensive hardware acceptance, third-party testing, problem cancellation, reminder of remaining problems, problem case summary upload, cancellation summary report, all actions are completed, and the completion materials, settlement documents, and audit results are uploaded for acceptance; finally, it comes to the warranty stage, including providing maintenance orders and maintenance completion confirmation orders to ensure the return of the warranty money;

[0024] The project summary unit specifically includes: selecting the required files, generating a project summary report with one click, and supporting downloading of project summary files;

[0025] The designated learning unit specifically includes: designating files for corresponding personnel to study, including work groups, and prompting whether they have read them, and scrolling prompts for the list of unread personnel.

[0026] Furthermore, the personnel management module includes a working hours unit, a points calculation unit, a laborer wage confirmation unit, an evaluation and assessment unit, a blacklist management unit, an employee clock-in unit and an assessment management unit;

[0027] The working time unit specifically includes: the working hours are calculated by the photo taking time of the watermark camera, and the list is presented to the direct superior management personnel for confirmation or reduction at 8:30 the next day. The working hours are publicized in the form of a table. If there is a complaint, it can be adjusted again within 7 days;

[0028] The points calculation unit specifically includes: points for each team member = working hours * busy / idle status * work ability * organizational division of labor coefficient. The points are publicized in the form of a table within the same level of the project team. This indicator is used as an important basis for assessment. The evaluation of the work ability of each team member is evaluated once a month by the direct superior, and the budget points of the previous month are evaluated first in the current month;

[0029] The laborer wage confirmation unit specifically includes: issuing employee wage confirmation sheets every month, and employees handwriting their signatures before submitting records;

[0030] The assessment and evaluation units specifically include: monthly assessment, including excellent, competent, basically competent, and incompetent;

[0031] The employee clock-in unit specifically includes: using a watermark camera to take a photo to clock in, the system obtains the clock-in times and clock-in time, if the number of clock-ins per day is less than two, the system will give a reminder, and the employee will sign the attendance at the end of the month; leave application function, employees or labor submit leave applications, and the approver has the authority to approve; health status, employees report their daily health status, and the approver has the authority to approve; card replacement approval; approval flow, including initiator-professional person in charge-project manager;

[0032] The assessment management unit specifically includes: the administrator checks the daily report and working hours list of the direct subordinates, and confirms or reduces them, and makes an evaluation of the busy and idle status.

[0033] Furthermore, the system management module includes a personnel authority management unit, a personnel organizational structure unit, and other system management content units;

[0034] The personnel authority management unit specifically includes: combining resources, roles, and authority authorizations into a authority group to facilitate developers to perform more flexible access control;

[0035] The personnel organization structure unit specifically includes: each member who joins the team needs to be assigned a main attribute of the organization division of labor, and the attribute corresponds to the organization division of labor coefficient.

[0036] Specifically, it also includes data acquisition equipment, communication equipment and a data center; the data acquisition equipment transmits information to the communication equipment, the communication equipment transmits data to the data center, and the data acquisition equipment, communication equipment and data center are supplied with required electrical energy through energy supply equipment.

[0037] The present invention also proposes a project general contracting management method, which comprises the following steps:

[0038] Step 1: Evaluate the attendance rate of management personnel and construction personnel, obtain the construction plan of the project, and generate task items arranged in chronological order;

[0039] Step 2: Monitor the construction environment, obtain the real-time progress of each discipline, compare the current progress with the planned progress, and issue timeout reminders at nodes;

[0040] Step 3: Click on a point to view the real-time monitoring screen of the camera, connect to the camera manufacturer, and display the camera location globally;

[0041] Step 4: Control safety and quality issues at the construction site, raise issues, make corrections in a timely manner, record issues that are not resolved in real time, and make corrections within a time limit;

[0042] Step 5: Summarize the problem cases and generate a report and upload it, which will be used as a designated file for employees to study later.

[0043] The data center engineering general contracting management system and method provided by the present invention have the following advantages compared with the prior art:

[0044] (1) The present invention can improve the efficiency of project management. Administrators and construction personnel can exchange information through the control module, which facilitates information communication between departments.

[0045] (2) The present invention can automatically make corresponding adjustments to the project progress, realize dynamic management of the project, and improve the efficiency of project management. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] Figure 1 The structure diagram of a data center project general contracting management system and method according to the present embodiment is shown. DETAILED DESCRIPTION

[0047] The present invention is further described below in conjunction with specific embodiments.

[0048] Example 1

[0049] A data center engineering general contracting management system and method, including project management and single project management;

[0050] Project management includes full-view large screen and project management;

[0051] The full-view screen specifically includes: echars map, project coordinates, progress of each project and the number of all projects, total contract amount. By using echars map, it is more three-dimensional and technological than ordinary maps, showing the location of each project on the map, and also showing the number of projects in each city;

[0052] Project management specifically includes: project addition, deletion, modification, viewing functions and approval process, which requires three levels of approval for modification and deletion.

[0053] Single project management includes large visualization screens and various management systems;

[0054] The visualization screen specifically includes: project overview, which is used to display the names of each unit and their responsibilities, start time, contract expiration time, total contract amount, and number of days of construction; personnel situation, which is used to display the attendance rate of management personnel and construction personnel; environmental monitoring, which is used to extract PM2.5, PM10, noise, and wind speed monitoring from the original system, view statistical analysis by month and day, and reserve interfaces; implementation progress, which is used to display the real-time progress of each discipline, compare the existing progress with the planned progress, and issue timeout reminders at nodes; safety and quality issues, which are visualized in multiple dimensions such as the category and status of the problem; camera dotting, which connects to camera manufacturers, and displays the camera location globally. Click on the point to view the real-time monitoring screen of the camera; change type statistics, which are used to statistically analyze the change order type, and can intuitively display the type with the most changes, which is convenient for subsequent analysis and judgment; on-site material in and out of the warehouse quantity statistics, which are used to display the in and out quantities of various materials in real time; alarm notification, for alarm information notifications such as environmental monitoring values ​​and camera monitoring, and quickly handle the alarm content.

[0055] Each management system specifically includes: project management module, warehouse management module, document management module, personnel management module and system management module;

[0056] Project management module, used to manage the project progress, problem quality and safety, as well as project changes, including progress management unit, problem quality, safety management unit and change management unit;

[0057] The progress management unit specifically includes: work plan, the project manager can edit and modify the progress plan, display the progress plan by milestone nodes according to the level, and update it in real time; actual progress report, each professional administrator can fill in the daily cumulative completion rate on the mobile phone, the system can update the milestone node progress chart according to the report, and display the forward line. If the progress is not updated on the same day, the system will remind you; daily personnel ledger, team members fill in the outline of the work of the day before 21:00 every day, which serves as the basis for the immediate superior to judge the busy and idle status, and the report information can be exported by day, week, and month;

[0058] The problem quality and safety management unit specifically includes: a problem list, which records problems that have not been solved in real time, clarifies the problem content (photos can be uploaded), the solver, the time limit for solving the problem, and pushes them; before the closed loop, daily reminders are issued, and after the closed loop, the problem can be selected to be collected in the case library folder, and can be designated for study;

[0059] The change management unit specifically includes: change item ledger, which can add change items, record the content, basis, person in charge and other information of the change items, and display the change order status to determine whether to upload; change order upload, the administrator scans and uploads the full set of information of the single change after collecting it, and the project manager or cost estimator reviews and confirms it; change reminder, if the change order is not uploaded one week after the change item is submitted, the system will remind you every week; approval flow, which is used for closed management;

[0060] The warehouse management module is used to manage the detailed information of material storage registration, conduct regular inventory, and check the material inventory quantity, including on-site material storage unit, on-site material storage unit and inventory counting unit;

[0061] The on-site material storage unit specifically includes: after the materials arrive at the site, they are stored in the warehouse, and detailed information such as the name, model, price, supplier, storage location, and attachment information of the materials are registered during storage. It also supports taking photos with a watermark camera to record the current storage time and status;

[0062] The on-site material outbound unit specifically includes: outbound materials according to the material application form, the current inventory quantity can be viewed, the inventory quantity is automatically reduced after outbound, and the watermark camera is supported to take photos to record the current outbound time and content for approval flow;

[0063] The inventory counting unit specifically includes: system reminders for regular inventory counting, inventory counting at handover, and uploading of inventory counting results;

[0064] Document management module, used to manage bidding documents, tender documents, form templates, contract materials, special plans, completion documents, work instructions, rules and regulations, and excellent photos and videos, including download unit, full-text index unit, file upload unit, project summary unit and designated learning unit;

[0065] The download unit specifically includes: classification and hierarchical management of bidding documents, tender documents, form templates, contract information, special plans, completion documents, work instructions, rules and regulations, excellent photos and videos, etc., and supports personnel to upload to the corresponding folder according to authorization, and also supports downloading files to local computers;

[0066] The full-text indexing unit specifically includes: employees can perform fuzzy queries on all files in the system, search for required files based on keywords, conduct all-round and accurate searches on file resources based on keywords such as file name and extended attributes, and search based on attributes such as the file creator's name, file size, creation time, and file tags;

[0067] The file upload unit specifically includes: first, the project preparation stage, the establishment of the project department, uploading of project bid materials, and the implementation of the project department resident, followed by design disclosure, drawing review, construction drawing deepening, workload clearance, meeting minutes and construction drawings uploaded according to different professional labels, and in CAD format, and finally, preparation of commencement materials, including commencement report, preparation and submission of construction organization plan, and preparation and submission of special plans; then comes the completion acceptance stage, and project testing, including comprehensive hardware acceptance, third-party testing, problem cancellation, reminder of outstanding problems, upload of problem case summary, and cancellation summary report, all actions are completed, and completion materials, settlement documents, and audit results are uploaded for acceptance; finally, it comes to the warranty stage, including providing maintenance orders and maintenance completion confirmation orders to ensure the return of warranty funds;

[0068] The project summary unit specifically includes: selecting the required files, generating a project summary report with one click, and supporting the downloading of project summary files;

[0069] The specific features of designated learning units include: you can designate files for corresponding personnel to learn, including teams, and prompt whether they have read them, and scroll through the list of unread personnel to prompt;

[0070] The personnel management module is used to conduct performance appraisals on employees, confirm wages, and manage clocking in and out, including a working hours unit, a points calculation unit, a laborer wage confirmation unit, an evaluation and assessment unit, a blacklist management unit, an employee clocking in unit, and an evaluation management unit;

[0071] The working hours unit specifically includes: the working hours are calculated by the photo taking time of the watermark camera, and the list is presented to the immediate superior management personnel for confirmation or reduction at 8:30 the next day. The working hours are publicized in the form of a table. If there is a complaint, it can be adjusted again once within 7 days;

[0072] The specific calculation unit of points includes: points for each team member = working hours * busy / idle status * work ability (evaluated by the direct superior) * organizational division of labor coefficient. The points are publicized in the form of a table within the same level of the project team (organizational division of labor coefficient at the same level). This indicator is used as an important basis for assessment. The evaluation of the work ability of each team member is conducted once a month by the direct superior, and the budget points of the previous month are evaluated first in the current month;

[0073] The laborer wage confirmation unit specifically includes: issuing employee wage confirmation sheets every month, and employees handwriting their signatures before submitting records;

[0074] The specific evaluation and assessment units include: monthly evaluation, including excellent, competent, basically competent, and incompetent;

[0075] The employee punch-in unit specifically includes: using the watermark camera to take photos and punch in, the system can obtain the number of punch-ins and the punch-in time, if the number of punch-ins per day is less than two, the system will give a reminder, and the employee will sign the attendance at the end of the month; leave function, employees or labor submit leave applications, and the approver has the authority to approve; health status, employees report their daily health status, and the approver has the authority to approve; card replacement approval; approval flow, including initiator-professional person in charge-project manager;

[0076] The assessment management unit specifically includes: the administrator can view the daily report and working hours list of the direct subordinates, and confirm or reduce them, and make an evaluation of the busy and idle status;

[0077] System management module, used to authorize developers to perform access control based on resources, roles, and permissions, including personnel permission management unit, personnel organizational structure unit, and other system management content units;

[0078] The personnel authority management unit specifically includes: combining resources, roles, and authority authorization into a authority group to facilitate developers to perform more flexible access control;

[0079] The personnel organizational structure unit specifically includes: each member who joins the team needs to be assigned a main attribute of organizational division of labor, which corresponds to the organizational division of labor coefficient.

[0080] The mobile terminal includes message notification module, communication platform module, workbench module and personal center module;

[0081] Message notification module, used for process notification, learning notification, rectification notification, etc.;

[0082] The communication platform module is used to publish videos / pictures / texts. Personnel can publish pictures and videos on their own and share them on the public platform, which can also be viewed by other project team members; comment / like, comment on and like the information published by other personnel; guidance center, the administrator collects cases with many likes and comments, or typical significance, into the corresponding professional folder of the guidance center, i.e. the document management module, for employees to refer to and learn from;

[0083] The workbench module is used to fill in daily reports. Employees fill in their work content every day, and display employee score rankings on a daily, weekly, and monthly basis to manage problems. First, raise a problem. Once a problem is found, you can quickly take a photo, clarify the problem content (photos can be uploaded), the person who will solve it, and the time limit for solving it, and then send it to the relevant personnel. Then, rectify the problem. The person who found the problem raises it, and the person who specifies the problem will rectify it. After the rectification is completed, the message is fed back to the initiator, forming a closed loop, and a ledger is generated on the web end.

[0084] The personal center module is used to display personal information, labor payroll signatures, etc.

[0085] A project general contracting management system of this embodiment also includes data acquisition equipment, communication equipment and a data center; the data acquisition equipment transmits information to the communication equipment, the communication equipment transmits data to the data center, and the data acquisition equipment, communication equipment and data center are supplied with required electrical energy through the energy supply equipment.

[0086] Example 2

[0087] This embodiment also proposes a project general contracting management method, which includes the following steps:

[0088] Step 1: Evaluate the attendance rate of management personnel and construction personnel, obtain the construction plan of the project, and generate task items arranged in chronological order;

[0089] Step 2: Monitor the construction environment, obtain the real-time progress of each discipline, compare the current progress with the planned progress, and issue timeout reminders at nodes;

[0090] Step 3: Click on a point to view the real-time monitoring screen of the camera, connect to the camera manufacturer, and display the camera location globally;

[0091] Step 4: Control safety and quality issues at the construction site, raise issues, make corrections in a timely manner, record issues that are not resolved in real time, and make corrections within a time limit;

[0092] Step 5: Summarize the problem cases and generate a report and upload it, which will be used as a designated file for employees to study later.

[0093] The specific implementation scheme described above further describes in detail the purpose, technical scheme and beneficial effects of the present invention. It should be understood that the above is only a specific implementation scheme of the present invention and is not intended to limit the scope of the present invention. Any equivalent changes and modifications made by any technician in the field without departing from the concept and principle of the present invention should fall within the scope of protection of the present invention.

Claims

1. A data center project general contracting management system, characterized in that: Including project management module, warehouse management module, document management module, personnel management module and system management module; The project management module is used to manage the progress, quality and safety of the project, as well as project changes; The warehouse management module is used to manage the detailed information of material storage registration, conduct regular inventory, and check the material inventory quantity; The document management module is used to manage bidding documents, tender documents, form templates, contract information, special plans, completion documents, work instructions, rules and regulations, and excellent photos and videos; The personnel management module is used to conduct performance appraisals on employees, confirm wages, and manage clocking in and out; The system management module is used to authorize developers to perform access control based on resources, roles, and permissions.

2. A data center project general contracting management system according to claim 1, characterized in that: The warehouse management module includes an on-site material storage unit, an on-site material storage unit and an inventory counting unit; The on-site material storage unit specifically includes: after the materials arrive at the site, they are stored in the warehouse, and detailed information such as the name, model, price, supplier, storage location and attachment information of the materials are registered during storage, and a watermark camera is supported to take photos to record the current storage time and status; The on-site material outbound unit specifically includes: outbound materials according to the material application form, viewing the current inventory quantity, the inventory quantity automatically decreases after outbound, and supports watermark camera to take photos to record the current outbound time and content for approval flow; The inventory counting unit specifically includes: system reminder for regular inventory counting, inventory counting at handover, and uploading of inventory counting results.

3. A data center project general contracting management system according to claim 1, characterized in that: The document management module includes a download unit, a full-text index unit, a file upload unit, a project summary unit and a designated learning unit; The download unit specifically includes: classifying and grading the bidding documents, tender documents, form templates, contract materials, special plans, completion documents, work instructions, rules and regulations, and excellent photo and video files, and supporting personnel to upload them to corresponding folders according to authorization, and also supports downloading files to local computers; The full-text indexing unit specifically includes: employees perform fuzzy queries on all files in the system, search for required files based on keywords, perform accurate searches on all aspects of file resources based on file names and extended attribute keywords, and perform attribute searches based on file creator names, file sizes, creation times, and file tags; The file uploading unit specifically includes: first, the project preparation stage, the establishment of the project department, uploading of the project bid materials, the implementation of the project department station, then the design briefing, drawing review, construction drawing deepening, workload clarification, meeting minutes and construction drawings uploaded according to different professional labels, and in CAD format, and finally the preparation of the start-up materials, including the start-up report, the preparation and submission of the construction organization plan and the preparation and submission of special plans; then comes the completion acceptance stage, and the project testing, including comprehensive hardware acceptance, third-party testing, problem cancellation, reminder of remaining problems, problem case summary upload, cancellation summary report, all actions are completed, and the completion materials, settlement documents, and audit results are uploaded for acceptance; finally, it comes to the warranty stage, including providing maintenance orders and maintenance completion confirmation orders to ensure the return of the warranty money; The project summary unit specifically includes: selecting the required files, generating a project summary report with one click, and supporting downloading of project summary files; The designated learning unit specifically includes: designating files for corresponding personnel to study, including work groups, and prompting whether they have read them, and scrolling prompts for the list of unread personnel.

4. A data center project general contracting management system according to any one of claims 1 to 3, characterized in that: The personnel management module includes a working hours unit, a points calculation unit, a laborer wage confirmation unit, an evaluation and assessment unit, a blacklist management unit, an employee clock-in unit and an assessment management unit; The working time unit specifically includes: the working hours are calculated by the photo taking time of the watermark camera, and the list is presented to the direct superior management personnel for confirmation or reduction at 8:30 the next day. The working hours are publicized in the form of a table. If there is a complaint, it can be adjusted again within 7 days; The points calculation unit specifically includes: points for each team member = working hours * busy / idle status * work ability * organizational division of labor coefficient. The points are publicized in the form of a table within the same level of the project team. This indicator is used as an important basis for assessment. The evaluation of the work ability of each team member is evaluated once a month by the direct superior, and the budget points of the previous month are evaluated first in the current month; The laborer wage confirmation unit specifically includes: issuing employee wage confirmation sheets every month, and employees handwriting their signatures before submitting records; The assessment and evaluation units specifically include: monthly assessment, including excellent, competent, basically competent, and incompetent; The employee clock-in unit specifically includes: using a watermark camera to take a photo to clock in, the system obtains the clock-in times and clock-in time, if the number of clock-ins per day is less than two, the system will give a reminder, and the employee will sign the attendance at the end of the month; leave application function, employees or labor submit leave applications, and the approver has the authority to approve; health status, employees report their daily health status, and the approver has the authority to approve; card replacement approval; approval flow, including initiator-professional person in charge-project manager; The assessment management unit specifically includes: the administrator checks the daily report and working hours list of the direct subordinates, and confirms or reduces them, and makes an evaluation of the busy and idle status.

5. A data center project general contracting management system according to claim 1, characterized in that: The system management module includes a personnel authority management unit, a personnel organizational structure unit and other system management content units; The personnel authority management unit specifically includes: combining resources, roles, and authority authorizations into a authority group to facilitate developers to perform more flexible access control; The personnel organization structure unit specifically includes: each member who joins the team needs to be assigned a main attribute of the organization division of labor, and the attribute corresponds to the organization division of labor coefficient.

6. A data center project general contracting management system according to claim 1, characterized in that: It also includes data acquisition equipment, communication equipment and a data center; the data acquisition equipment transmits information to the communication equipment, the communication equipment transmits data to the data center, and the data acquisition equipment, communication equipment and data center are supplied with required electrical energy through energy supply equipment.

7. A data center project general contracting management method, characterized in that: The steps include: Step 1: Evaluate the attendance rate of management personnel and construction personnel, obtain the construction plan of the project, and generate task items arranged in chronological order; Step 2: Monitor the construction environment, obtain the real-time progress of each discipline, compare the current progress with the planned progress, and issue timeout reminders at nodes; Step 3: Click on a point to view the real-time monitoring screen of the camera, connect to the camera manufacturer, and display the camera location globally; Step 4: Control safety and quality issues at the construction site, raise issues, make corrections in a timely manner, record issues that are not resolved in real time, and make corrections within a time limit; Step 5: Summarize the problem cases and generate a report and upload it, which will be used as a designated file for employees to study later.