Construction site demolition follow-up method and system based on synthetic aperture radar interference technology

Through the following up method for demolition on site based on synthetic aperture radar interference technology, the problem of inaccurate monitoring of construction site demolition progress in the existing technology is solved, and accurate monitoring and management of construction site demolition progress is achieved, thereby reducing labor waste and overtime.

CN119600439APending Publication Date: 2025-03-11HUNAN LIANZHI BRIDGE & TUNNEL TECH
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411643146.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-18
Publication Date
2025-03-11

AI Technical Summary

Technical Problem

The existing technology lacks a systematic follow-up method for construction site demolition, resulting in inaccurate reporting and incomplete on-site progress, resulting in waste of manpower and overtime.

Method used

The construction site demolition follow-up method based on synthetic aperture radar interference technology is adopted. By generating predetermined repeated track paths, the construction site is initially and secondary imaging, elevation change information and deformation information are generated, the demolition progress is analyzed and the construction site demolition process is adjusted.

Benefits of technology

Accurate monitoring and management of construction site demolition progress, reduce labor waste and overtime, and strengthen the full coverage and non-contact observation capabilities of construction sites.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119600439A_ABST
    Figure CN119600439A_ABST
Patent Text Reader

Abstract

The invention discloses a construction site demolition follow-up method and system based on a synthetic aperture radar interference technology. Comprising the following steps: performing primary earth imaging operation on a to-be-demolited construction site according to a generated predetermined repeated track path, and generating a primary site image of the to-be-demolited construction site; performing secondary earth imaging operation on the to-be-demolited construction site to generate a secondary site image of the to-be-demolited construction site; comparing the actual track path of the primary earth imaging operation with the actual track path of the secondary earth imaging operation to generate actual track path coincidence degree data; if the actual track path overlap ratio data is greater than a specified value, executing subsequent steps, and if the actual track path overlap ratio data is smaller than the specified value, re-executing the ground imaging operation; and according to the generated primary field image and the generated secondary field image, performing image processing on the primary field image and the secondary field image, and analyzing and adjusting the demolition process of the construction site.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of engineering management technology, and in particular to a method and system for following up on construction site demolition based on synthetic aperture radar interferometry technology. Background Art

[0002] The existing technology does not have a systematic method for following up on construction site demolition. All of them rely on manual reporting, on-site inspections by personnel or camera monitoring to obtain the demolition progress of the construction site. The reporting is inaccurate, and the on-site progress is not fully reflected. The subsequent work arrangements are not accurate, and there is often a waste of manpower or overtime work to meet the deadline.

[0003] It should be noted that the above information disclosed in this background technology section is only used to understand the background technology of the present invention concept, and therefore may contain information that does not constitute prior art.

[0004] Application Contents

[0005] In view of the deficiencies in the prior art, the present application discloses a construction site demolition follow-up method and system based on synthetic aperture radar interferometry technology, which can solve the problems existing in the prior art.

[0006] To achieve the above objectives, this application is implemented through the following technical solutions:

[0007] The method for following up on construction site demolition based on synthetic aperture radar interferometry technology comprises the following steps:

[0008] Generate a predetermined repetitive track path based on the drawings of the construction site to be demolished;

[0009] Performing an initial ground imaging operation on the construction site to be demolished according to the generated predetermined repeated track path to generate an initial on-site image of the construction site to be demolished;

[0010] Performing a secondary ground imaging operation on the construction site to be demolished according to the generated predetermined repeated track path to generate a secondary on-site image of the construction site to be demolished;

[0011] comparing an actual orbital path of the first earth imaging operation with an actual orbital path of the second earth imaging operation to generate actual orbital path coincidence data;

[0012] If the actual orbital path overlap data is greater than the specified value, the subsequent steps are executed; if the actual orbital path overlap data is less than the specified value, the ground imaging operation is re-executed;

[0013] According to the generated primary on-site image and secondary on-site image, image processing is performed on the primary on-site image and the secondary on-site image to generate elevation change information and deformation information of the on-site image;

[0014] According to the generated elevation change information and deformation information, the completion amount, remaining amount and demolition progress of the construction site are analyzed;

[0015] Adjust the demolition progress of the construction site according to the completed amount, remaining amount and demolition progress of the construction site.

[0016] According to a preferred technical solution, the predetermined repeated track path is set as a single path extending continuously in one direction along a specified direction.

[0017] According to a preferred technical solution, the predetermined repetitive track path continuously extends from a designated starting position of the construction site to be demolished to a designated ending position of the construction site to be demolished.

[0018] According to a preferred technical solution, the predetermined repeated track path is configured as a plurality of paths extending unidirectionally along a specified direction.

[0019] According to a preferred technical solution, the plurality of predetermined repetitive track paths are arranged in parallel with each other, and the plurality of predetermined repetitive track paths jointly cover the construction site to be demolished within a specified plane.

[0020] In addition, the present application also discloses a construction site demolition follow-up system based on synthetic aperture radar interferometry technology, which includes:

[0021] A synthetic aperture radar module, wherein the synthetic aperture radar module is used to perform a primary ground imaging operation on the construction site to be demolished to generate a primary site image of the construction site to be demolished, and to perform a secondary ground imaging operation on the construction site to be demolished to generate a secondary site image of the construction site to be demolished;

[0022] A recording module, the recording module is used to record the actual orbital path of the initial earth imaging operation and the actual orbital path of the secondary earth imaging operation;

[0023] A processing module is used to compare the actual track path of the initial ground imaging operation and the actual track path of the secondary ground imaging operation to generate actual track path coincidence data, perform image processing on the initial site image and the secondary site image to generate elevation change information and deformation information of the site image, and adjust the demolition progress of the construction site according to the generated elevation change information and deformation information analysis.

[0024] The preferred technical solution also includes a first guide mark and a second guide mark, wherein the first guide mark is used to mark a designated starting position of the construction site to be demolished, and the second guide mark is used to mark a designated ending position of the construction site to be demolished.

[0025] A preferred technical solution further includes a guiding unit, and a plurality of the guiding units are used to guide the synthetic aperture radar module to move in a specified direction.

[0026] The present application discloses a construction site demolition follow-up method and system based on synthetic aperture radar interferometry technology, which has the following advantages:

[0027] Methods The construction site is observed by using synthetic aperture radar interferometry (InSAR). When the same target area on the ground is scanned, the elevation information and deformation information of the target area on the surface can be extracted by imaging and geometric transformation using imaging geometric relationships, and the construction site scene can be restored. Managers can analyze the pictures to obtain the completion amount, remaining amount, demolition progress, and whether there are safety hazards. The use of synthetic aperture radar interferometry technology has full coverage of the construction site, more accurate monitoring (the error can be accurate to 0.1 meters), and can observe surface deformation in a large range, traceable, and non-contact manner to obtain the most realistic scene on site. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.

[0029] Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.

[0030] Figure 1 It is a schematic diagram of an embodiment of the present application. DETAILED DESCRIPTION

[0031] In order to make the purpose, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments.

[0032] Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making any creative work shall fall within the scope of protection of this application.

[0033] Example 1

[0034] like Figure 1 As shown, the construction site demolition follow-up method based on synthetic aperture radar interferometry technology described in this application includes the following steps:

[0035] The predetermined repetitive track path is generated according to the drawings of the construction site to be demolished. It is easy to understand that the predetermined repetitive track path is to make the site image generated by the same sensor or similar sensor in the parallel track twice imaging process more accurate.

[0036] In one embodiment, the predetermined repetitive track path is set as a single path extending continuously in a specified direction. The predetermined repetitive track path extends continuously from a specified starting position of the construction site to be demolished to a specified ending position of the construction site to be demolished.

[0037] It is easy to understand that during the ground imaging operation process, a more continuous and smooth on-site image can be obtained through a single continuously extended path, and the idle interval time of the imaging process can be reduced, which is conducive to improving the efficiency of imaging.

[0038] In another embodiment, the predetermined repetitive track path is configured as a plurality of paths extending unidirectionally along a specified direction. The plurality of predetermined repetitive track paths are arranged parallel to each other, and the plurality of predetermined repetitive track paths jointly cover the site to be demolished in a specified plane.

[0039] It is easy to understand that in the process of ground imaging operation, a more comprehensive on-site image can be obtained through multiple one-way extending paths, and the movement logic in the imaging process is simpler and more direct, which is conducive to reducing the occurrence of path errors in the presentation process.

[0040] An initial ground imaging operation is performed on the construction site to be demolished according to the generated predetermined repeated track path to generate an initial on-site image of the construction site to be demolished.

[0041] A secondary ground imaging operation is performed on the construction site to be demolished according to the generated predetermined repeated track path to generate a secondary on-site image of the construction site to be demolished.

[0042] The actual orbital path of the first ground imaging operation is compared with the actual orbital path of the second ground imaging operation to generate actual orbital path coincidence data. If the actual orbital path coincidence data is greater than a specified value, the subsequent steps are executed; if the actual orbital path coincidence data is less than the specified value, the ground imaging operation is re-executed.

[0043] It is easy to understand that after obtaining the first and second on-site images, it is necessary to confirm whether the on-site images can be directly synthesized, spliced ​​or compared. Calculating the actual orbital path overlap during the ground imaging operation is a more appropriate method. The specified value can be determined according to the actual progress requirements. For example, when the accuracy requirement is high, 90% can be selected.

[0044] According to the generated primary site image and secondary site image, image processing is performed on the primary site image and the secondary site image to generate elevation change information and deformation information of the site image. According to the generated elevation change information and deformation information, the completion amount, remaining amount and demolition progress of the construction site demolition are analyzed. According to the completion amount, remaining amount and demolition progress of the construction site demolition, the demolition progress of the construction site is adjusted.

[0045] Example 2

[0046] The construction site demolition follow-up system based on synthetic aperture radar interferometry technology described in this application includes:

[0047] A synthetic aperture radar module is used to perform a primary ground imaging operation on a construction site to be demolished to generate a primary site image of the construction site to be demolished, and to perform a secondary ground imaging operation on the construction site to be demolished to generate a secondary site image of the construction site to be demolished.

[0048] A recording module is used to record an actual orbital path of a primary earth imaging operation and an actual orbital path of a secondary earth imaging operation.

[0049] A processing module is used to compare the actual track path of the initial ground imaging operation and the actual track path of the secondary ground imaging operation to generate actual track path coincidence data, perform image processing on the initial site image and the secondary site image to generate elevation change information and deformation information of the site image, and adjust the demolition progress of the construction site according to the generated elevation change information and deformation information analysis.

[0050] The preferred technical solution also includes a first guide mark and a second guide mark, wherein the first guide mark is used to mark a designated starting position of the construction site to be demolished, and the second guide mark is used to mark a designated ending position of the construction site to be demolished.

[0051] A preferred technical solution further includes a guiding unit, and a plurality of the guiding units are used to guide the synthetic aperture radar module to move in a specified direction.

[0052] It should be noted that, in this article, relational terms are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations.

[0053] Moreover, the terms "comprises," "comprising," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements but also other elements not expressly listed, or also includes elements inherent to such process, method, article, or apparatus.

[0054] Without more constraints, an element defined by the phrase "comprising a..." does not exclude the existence of other identical elements in the process, method, article or apparatus comprising the element.

[0055] Obviously, those skilled in the art should understand that the above-mentioned modules or steps of the present application can be implemented using a general-purpose computing device, and they can be concentrated on a single computing device or distributed on a network composed of multiple computing devices.

[0056] Optionally, they can be implemented using program codes executable by a computing device, so that they can be stored in a storage device and executed by the computing device, or they can be made into individual integrated circuit modules, or multiple modules or steps therein can be made into a single integrated circuit module for implementation.

[0057] The invention is not limited to any specific combination of hardware and software.

[0058] The above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.

Claims

1. A construction site demolition follow-up method based on radar interferometry technology, wherein: The following steps are involved: Generate a predetermined repetitive track path based on the drawings of the construction site to be demolished; Performing an initial ground imaging operation on the construction site to be demolished according to the generated predetermined repeated track path to generate an initial on-site image of the construction site to be demolished; Performing a secondary ground imaging operation on the construction site to be demolished according to the generated predetermined repeated track path to generate a secondary on-site image of the synthetic hole on the construction site to be demolished; comparing an actual orbital path of the first earth imaging operation with an actual orbital path of the second earth imaging operation to generate actual orbital path coincidence data; If the actual orbital path overlap data is greater than the specified value, the subsequent steps are executed; if the actual orbital path overlap data is less than the specified value, the ground imaging operation is re-executed; According to the generated primary on-site image and secondary on-site image, image processing is performed on the primary on-site image and the secondary on-site image to generate elevation change information and deformation information of the on-site image; According to the generated elevation change information and deformation information, the completion amount, remaining amount and demolition progress of the construction site are analyzed; Adjust the demolition progress of the construction site according to the completed amount, remaining amount and demolition progress of the construction site.

2. The construction site demolition follow-up method based on synthetic aperture radar interferometry technology according to claim 1, wherein: The predetermined repeated orbit path is set as a single path extending continuously in one direction along a designated direction.

3. The construction site demolition follow-up method based on synthetic aperture radar interferometry technology according to claim 2, wherein: The predetermined repetitive track path extends continuously from a designated starting position of the construction site to be demolished to a designated ending position of the construction site to be demolished.

4. The construction site demolition follow-up method based on synthetic aperture radar interferometry technology according to claim 1, wherein: The predetermined repeated orbital paths are arranged as a plurality of paths extending unidirectionally along a designated direction.

5. The construction site demolition follow-up method based on synthetic aperture radar interferometry technology according to claim 4, wherein: The plurality of predetermined repeated track paths are arranged in parallel with each other, and the plurality of predetermined repeated track paths jointly cover the construction site to be demolished within a designated plane.

6. Construction site demolition follow-up system based on synthetic aperture radar interferometry technology, including: include: A synthetic aperture radar module, wherein the synthetic aperture radar module is used to perform a primary ground imaging operation on the construction site to be demolished to generate a primary site image of the construction site to be demolished, and to perform a secondary ground imaging operation on the construction site to be demolished to generate a secondary site image of the construction site to be demolished; A recording module, the recording module is used to record the actual orbital path of the initial earth imaging operation and the actual orbital path of the secondary earth imaging operation; A processing module is used to compare the actual track path of the initial ground imaging operation and the actual track path of the secondary ground imaging operation to generate actual track path coincidence data, perform image processing on the initial site image and the secondary site image to generate elevation change information and deformation information of the site image, and adjust the demolition progress of the construction site according to the generated elevation change information and deformation information analysis.

7. The construction site demolition follow-up system based on synthetic aperture radar interferometry technology according to claim 6, wherein: It also includes a first guide mark and a second guide mark, wherein the first guide mark is used to mark a designated starting position of the construction site to be demolished, and the second guide mark is used to mark a designated ending position of the construction site to be demolished.

8. The construction site demolition follow-up system based on synthetic aperture radar interferometry technology according to claim 6, wherein: It also includes a guiding unit, wherein a plurality of the guiding units are used to guide the synthetic aperture radar module to move along a specified direction.

Citation Information

Patent Citations

  • Land requisition and demolition application management system based on BIM + GIS technology

    CN110362895A

  • Radiometric calibration method and device for synthetic aperture radar

    CN113702933A