High-altitude edge masonry construction protection device and construction method
By designing a high-altitude side masonry construction protection device including a protective net and suspension mechanism, the problems of safety risks and construction quality in high-altitude side construction are solved, and higher safety and construction standardization are achieved.
Patent Information
- Application Number
- CN202411604690.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-12
- Publication Date
- 2025-03-14
- Estimated Expiration
- 2044-11-12
AI Technical Summary
In high-rise building construction, high-altitude edge operations are involved during secondary structure construction, resulting in difficulty in ensuring safety risks and construction quality. The existing technology anti-fall nets are not set up firmly and have limited impact force.
A high-altitude edge masonry construction protection device is designed, including a protective net and a suspension mechanism with a lightweight and high-strength mesh structure. The suspension mechanism is fixed on each floor slab, the protective net is connected to the suspension mechanism, and an induction warning is set to remind the operators of safety.
Effectively reduce the safety risks of high-altitude side masonry construction, improve the safety awareness of workers, reduce the impact of falls, ensure construction quality, and improve the standardization level of on-site operations.
Smart Images

Figure CN119616237A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of civil engineering house building structure construction, and in particular to a high-altitude edge masonry construction protection device and a construction method. Background Art
[0002] In the construction of conventional multi-storey and high-rise reinforced concrete houses, after the main structure construction such as beams, slabs and columns is completed, secondary structure construction such as masonry, structural columns and plastering will be carried out. During the secondary structure construction, it is inevitable to work at high altitudes. If the external frames of the construction elevator and other parts are removed too early before the masonry construction is carried out, there will be safety risks such as objects hitting and people falling from high altitudes. If there are no safe and stable protective measures, the quality of masonry construction cannot be guaranteed.
[0003] The conventional practice of the existing technology is: before construction, pre-shift announcements and safety technology briefings and training are carried out to inform workers of the existing safety risks; horizontal anti-fall nets are set up on certain floors to provide a certain buffer for falling objects and people, thereby reducing safety risks.
[0004] The existing technology has the following shortcomings: the key points of attention given in pre-shift announcements and briefings are not completely consistent with the risks on site, and the workers have a low level of acceptance of the written briefings; a horizontal anti-fall net is set at certain intervals between floors, which results in excessive impact force. When the net is not securely set or the weight of the falling object is too heavy, its cushioning effect is limited. Summary of the invention
[0005] In view of the above shortcomings of the prior art, the purpose of the present invention is to provide a high-altitude edge masonry construction protection device and construction method, so as to reduce the safety risks during high-altitude edge masonry construction, enhance the safety awareness of workers, reduce the impact force of workers or objects falling, ensure the quality of masonry construction, and improve the standardization level of on-site operations.
[0006] The technical solution of the present invention is: a high-altitude edge masonry construction protection device, comprising:
[0007] The protective net is arranged on the building facade, vertically and in contact with the floor slab, and is a lightweight and high-strength mesh structure that can withstand the impact of an operator or an object falling accidentally and has a certain safety factor;
[0008] A suspension mechanism is fixed on all floors that need to be constructed and connected to the protection net. At least two suspension mechanisms are arranged on each floor.
[0009] According to a high-altitude edge masonry construction protection device provided in the present application, the suspension mechanism includes a suspension beam and a bracket, and the suspension beam is provided with a protection net connecting piece for connecting the protection net; the bracket is connected below the suspension beam and placed on the floor.
[0010] According to a high-altitude edge masonry construction protection device provided by the present application, the height of the bracket is adjustable, and the installation height of the suspension beam can be adjusted according to the waterproofing requirements of the floor masonry or the height of the flip beam. The bracket includes an upper bracket and a lower bracket, the upper bracket is connected to the suspension beam; the lower bracket is connected to the floor; the lower end of the upper bracket is vertically adjustably inserted into the upper end of the lower bracket.
[0011] According to a high-altitude edge masonry construction protection device provided in the present application, the upper bracket includes a cross-beam connecting tube and a first vertical connecting tube, the cross-beam connecting tube is connected to the suspension beam; one end of the first vertical connecting tube is connected to the cross-beam connecting tube, and the other end is vertically and adjustably inserted into the upper end of the lower bracket.
[0012] According to a high-altitude edge masonry construction protection device provided by the present application, the upper bracket also includes a first reinforcement member, and the reinforcement member is connected to the cross beam connecting pipe on one side and the first vertical connecting pipe on the other side.
[0013] According to a high-altitude edge masonry construction protection device provided by the present application, the lower support includes a floor connecting pipe and a second vertical connecting pipe, and the floor connecting pipe is connected to the floor; one end of the second vertical connecting pipe is connected to the floor connecting pipe, and the other end is sleeved on the first vertical connecting pipe.
[0014] According to a high-altitude edge masonry construction protection device provided by the present application, the lower bracket also includes a second reinforcement member, one end of the second reinforcement member is connected to the floor connecting pipe, and the other end is connected to the second vertical connecting pipe.
[0015] According to a high-altitude edge masonry construction protection device provided by the present application, the suspension mechanism also includes a counterweight bracket, the bracket is connected to the floor near the edge of the floor, and the counterweight bracket is connected to the floor away from the edge of the floor; the distance between the counterweight bracket and the bracket is greater than or equal to three times the distance between the bracket and the edge of the floor.
[0016] According to a high-altitude edge masonry construction protection device provided by the present application, the counterweight bracket is consistent with the bracket structure, and a counterweight rod is connected to the lower bracket of the counterweight bracket, and a counterweight block is connected to the counterweight rod.
[0017] According to a high-altitude edge masonry construction protection device provided by the present application, the suspension beam includes a front beam, a rear beam and a connecting beam, the front beam is provided with a protective net connecting piece, the front beam is connected to the bracket; the rear beam is connected to the counterweight bracket; one end of the connecting beam is laterally and adjustably inserted into the front beam, and the other end is laterally and adjustably inserted into the rear beam.
[0018] A high-altitude edge masonry construction protection device provided in the present application also includes a sensor alarm, which is fixed at the bottom of the floor or under the structural beam near the edge of the floor, and is used to use voice to provide safety reminders when the workers enter a certain range from the edge of the floor.
[0019] The present application also provides a construction method, which is applicable to any of the above-mentioned high-altitude edge masonry construction protection devices, including:
[0020] Install the suspension mechanism: determine the installation height of the suspension beam from the ground according to the waterproof requirements of the floor masonry or the height of the flip beam, and adjust the depth of the upper bracket inserted into the lower bracket according to the installation height; place the counterweight block with a total weight not less than the weight of objects or personnel during on-site construction on the counterweight rod; adjust the installation position of the bracket and the counterweight bracket according to the on-site conditions. Generally, the distance between the counterweight bracket and the bracket is greater than or equal to three times the distance between the bracket and the edge of the floor slab. After adjusting the distance, fix the bracket and the counterweight bracket on the floor slab; connect the front beam to the bracket, connect the rear beam to the counterweight bracket, insert one end of the connecting beam into the front beam and fix it, and insert the other end into the rear beam and fix it, and connect the protective net connector to the front beam; install no less than two pairs of the suspension mechanism on each floor according to the on-site conditions;
[0021] Install the sensor alarm and the protection net: fix the sensor alarm at the bottom of the floor or under the structural beam near the edge of the floor; connect the protection net with the protection net connector so that the protection net fits the edge of the floor;
[0022] Construction of the masonry or overturned beam at the bottom of the suspension beam: Masonry below the height of the suspension beam is built according to the conventional masonry construction process requirements. When the masonry is built to the suspension beam, a hole with a size that can ensure that the suspension mechanism and the protective net can be freely removed after the masonry construction is completed is reserved in combination with the position of the suspension beam. The reserved hole is reserved as much as possible according to the normal joint reservation requirements to allow the whole piece of masonry to be constructed, so as to ensure the quality of subsequent hole blocking;
[0023] Construction of masonry on the upper part of the suspension beam: constructing masonry higher than the height of the suspension beam according to conventional masonry construction process requirements;
[0024] Removing the masonry construction protection device: after all masonry construction except the reserved holes is completed and the mortar strength meets the requirements, remove the counterweight block, then move the suspension mechanism backward as a whole, move the bracket to the reserved hole, remove the protection net from the reserved hole, and remove the suspension mechanism after pulling it out of the reserved hole; remove the suspension mechanism of each layer from top to bottom in turn;
[0025] Seal the reserved opening: Seal the reserved opening from the inside using masonry and mortar of the same material.
[0026] The advantages of this application are:
[0027] 1. The high-altitude edge masonry construction protection device of this application adopts a combination of voice warning and safety protection net, which can effectively ensure the safe construction of operators and has high safety;
[0028] 2. The high-altitude edge masonry construction protection device of the present application can be assembled using construction site building materials, with a wide range of material acquisition channels, low device processing costs, and good economy;
[0029] 3. The high-altitude edge masonry construction protection device of the present application can be adjusted in length, height and spacing according to the on-site construction conditions, and can be used repeatedly, which is highly practical;
[0030] 4. The first reinforcement member of the present application can strengthen the stability of the upper bracket and improve the deformation resistance of the upper bracket;
[0031] 5. The second reinforcement member of the present application can strengthen the stability of the lower bracket and improve the anti-deformation ability of the lower bracket;
[0032] 6. In addition to the bracket, the suspension mechanism of the present application is also provided with the counterweight bracket. The double bracket structure can enhance the impact resistance of the suspension mechanism;
[0033] 7. The counterweight bracket of the present application is also provided with the counterweight block, which increases the mass of the counterweight bracket and can further improve the impact resistance of the suspension mechanism;
[0034] 8. The suspension beam of the present application is a split structure, the front beam and the rear beam are connected by a connecting beam, and the length of the suspension beam can be changed by adjusting the connection position of the connecting beam with the front beam and the rear beam, so as to adapt to different construction scenarios;
[0035] 9. The present application can adjust the installation height of the suspension beam by adjusting the height of the bracket, which can avoid conflicts with masonry waterproofing requirements or the height of the overturned beam; BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1This is a schematic diagram of the structure of the protective device for high-altitude edge masonry construction in this application;
[0037] Figure 2 This is a schematic diagram of the side structure of the high-altitude edge masonry construction protection device of this application;
[0038] Figure 3 This is a top view of the high-altitude edge masonry construction protection device of this application;
[0039] Figure 4 This is a schematic diagram of the structure of the suspension beam of this application;
[0040] Figure 5 This is a schematic diagram of the upper bracket structure of the bracket and counterweight bracket of this application;
[0041] Figure 6 This is a schematic diagram of the lower bracket structure of the bracket in this application;
[0042] Figure 7 This is a schematic diagram of the lower bracket structure of the counterweight bracket of this application;
[0043] Figure 8 This is a schematic diagram of the structure of the counterweight block of this application;
[0044] Among them: 1-suspension beam; 11-front beam; 12-rear beam; 13-connecting beam; 2-bracket; 21-upper bracket; 21a-crossbeam connecting pipe; 21b-first vertical connecting pipe; 21c-first reinforcement; 22-lower bracket; 22a-floor connecting pipe; 22b-second vertical connecting pipe; 22c-second reinforcement; 3-protective net connecting piece; 4-counterweight bracket; 41-counterweight rod; 42-counterweight block; 100-protective net; 200-suspension mechanism; 300-sensor alarm. DETAILED DESCRIPTION
[0045] The embodiments of the present invention are described in detail below, wherein the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.
[0046] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0047] In addition, the terms "first" and "second" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance or implicitly indicating the number of indicated technical features. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "multiple" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined. Moreover, the terms "include", "comprise" or any other variant thereof are intended to cover non-exclusive inclusion, so that the process, method, article or equipment including a series of elements includes not only those elements, but also other elements that are not explicitly listed, or also includes elements inherent to such process, method, article or equipment. In the absence of more restrictions, the elements defined by the sentence "include one..." do not exclude the presence of other identical elements in the process, method, article or equipment including the elements.
[0048] The present invention relates to a protective device and a construction method for high-altitude edge masonry construction. Compared with the prior art, the anti-fall protection measures of the present invention are more reliable. At the same time, the anti-fall protection measures are combined with voice warning reminders, which can effectively reduce the safety risks during high-altitude edge masonry construction, enhance the safety awareness of operators, ensure the quality of masonry construction, and improve the standardization level of on-site operations.
[0049] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments:
[0050] A protective device for high-altitude edge masonry construction, specifically, Figure 1-3 As shown, it includes a protective net 100 and a suspension mechanism 200. The protective net 100 is arranged on the facade of the building, vertically and in contact with the floor slab. It is a lightweight, high-strength, flexible mesh structure that can withstand the impact of an operator or an object accidentally falling and has a certain safety factor. The suspension mechanism 200 is located on the floor slab that needs to be constructed and is connected to the protective net 100. At least two suspension mechanisms 200 are arranged on each floor slab.
[0051] During actual installation, multiple suspension mechanisms 200 are first fixed on the floor to be constructed according to the construction situation, and then the protection net 100 is connected to the suspension mechanism 200. The connected protection net 100 is perpendicular to the floor and fits tightly with the edge of the floor.
[0052] In some embodiments, Figure 2 As shown, the above-mentioned suspension mechanism 200 is optimized. In this embodiment, the suspension mechanism 200 includes a suspension beam 1 and a bracket 2. The suspension beam 1 is provided with a protective net connecting member 3 for connecting the protective net 100; the bracket 2 is connected to the bottom of the suspension beam 1 and placed on the floor.
[0053] In fact, the protective net connector 3 in this embodiment is two U-shaped hooks with a diameter of 10 cm, which are placed side by side with a spacing of 20 cm and welded to the suspension beam 1. In particular, in the suspension mechanism 200 located on the roof of the construction building, the protective net connector 3 is welded above the suspension beam 1; in the suspension mechanism 200 located on the first floor of the construction building, the protective net connector 3 is welded below the suspension beam 1;
[0054] During actual installation, use a safety rope made of nylon or cotton material to fix the protective net 100 and the protective net connector 3 together, adjust the distance between the front end of the suspension mechanism 200 and the edge of the floor, so that the edge of the protective net 100 connected to the rear U-shaped hook fits with the edge of the floor.
[0055] In some embodiments, Figure 1 , 2 As shown, the bracket 2 is optimized. In this embodiment, the height of the bracket 2 is adjustable, and the installation height of the suspension beam 1 can be adjusted according to the waterproof requirements of the floor masonry or the height of the flip beam.
[0056] During actual construction, the masonry waterproofing requirements and the height of the flip beam will affect the installation height of the suspension beam 1. Different construction sites have different masonry waterproofing requirements and flip beam heights. This embodiment adjusts the installation height of the suspension beam 1 by adjusting the height of the bracket 2 to adapt to different construction conditions.
[0057] Furthermore, if Figure 5 , 6 As shown, the bracket 2 is optimized. In this embodiment, the bracket 2 includes an upper bracket 21 and a lower bracket 22. The upper bracket 21 is connected to the suspension beam 1; the lower bracket 22 is connected to the floor slab; the lower end of the upper bracket 21 is vertically and adjustably inserted into the upper end of the lower bracket 22.
[0058] During actual installation, the height of the bracket 2 is adjusted by adjusting the insertion depth of the upper bracket 21 and the lower bracket 22. The structure is simple, stable and controllable, and easy to install and disassemble.
[0059] In some embodiments, Figure 5 As shown, the upper bracket 21 is optimized. In this embodiment, the upper bracket 21 includes a cross-beam connecting tube 21a, a first vertical connecting tube 21b and a first reinforcement 21c. The cross-beam connecting tube 21a is connected to the suspension beam 1; one end of the first vertical connecting tube 21b is welded to the cross-beam connecting tube 21a, and the other end is vertically adjustably inserted into the upper end of the lower bracket 22; the first reinforcement 21c is welded to the cross-beam connecting tube 21a on one side and to the first vertical connecting tube 21b on the other side.
[0060] During actual installation, the cross beam connecting pipe 21a adopts a channel steel with a length of about 60 cm and a model of 90mm×90mm×4mm. A hole with a diameter of 20mm is opened in the center of both sides of the channel steel every 20 cm, which is convenient for connecting with the suspension beam 1 through bolts; the first vertical connecting pipe 21b adopts a square steel with a model of 70mm×70mm×4mm, and a hole with a diameter of 20mm is opened in the center line of the side every 10 cm, which is convenient for connecting with the lower bracket 22 and adjusting the height; the first reinforcement 21c adopts a triangular steel plate with a flank to strengthen the stability of the connection between the cross beam connecting pipe 21a and the first vertical connecting pipe 21b.
[0061] In some embodiments, Figure 6 , 7 As shown, the lower bracket 22 is optimized. In this embodiment, the lower bracket 22 includes a floor connecting pipe 22a, a second vertical connecting pipe 22b and a second reinforcement 22c. The floor connecting pipe 22a is fixedly connected to the floor; one end of the second vertical connecting pipe 22b is welded to the floor connecting pipe 22a, and the other end is sleeved on the first vertical connecting pipe 21b; one end of the second reinforcement 22c is welded to the floor connecting pipe 22a, and the other end is welded to the second vertical connecting pipe 22b.
[0062] During actual installation, the floor connecting pipe 22a adopts a square steel of about 1m in length and size 80mm×80mm×4mm; the second vertical connecting pipe 22b adopts a square steel of size 80mm×80mm×4mm, and a hole of 20mm in diameter is opened on the side center line every 10cm to facilitate connection with the first vertical connecting pipe 21b and adjust the height; the second reinforcement 22c adopts a square steel of about 50cm in length and size 40mm×40mm×4mm, forming a triangle with the floor connecting pipe 22a and the second vertical connecting pipe 22b for reinforcement.
[0063] In some embodiments, Figure 2 , 3 As shown, the suspension mechanism 200 is optimized. In this embodiment, the suspension mechanism 200 also includes a counterweight bracket 4. The bracket 2 is connected to the floor near the edge of the floor, and the counterweight bracket 4 is connected to the floor away from the edge of the floor; the distance between the counterweight bracket 4 and the bracket 2 is greater than or equal to three times the distance between the bracket 2 and the edge of the floor.
[0064] During actual installation, adding a counterweight bracket 4 can increase the impact resistance of the suspension mechanism 200; the distance between the counterweight bracket 4 and the bracket 2 is much greater than the distance between the bracket 2 and the edge of the floor slab, which can effectively increase the impact resistance torque of the counterweight bracket 4, thereby improving the reliability and safety of the protective device.
[0065] In some embodiments, Figure 7As shown, the counterweight bracket 4 is optimized. In this embodiment, the counterweight bracket 4 has the same structure as the bracket 2. Two counterweight rods 41 are connected to the lower bracket 22 of the counterweight bracket 4, and a plurality of counterweight blocks 42 are connected to the counterweight rods 41.
[0066] During actual installation, the floor connection pipe 22a of the counterweight bracket 4 is made of square steel of about 1.5m in length and model 80mm×80mm×4mm, and holes with a diameter of about 27mm are opened on the center line at about 25cm and 75cm on both sides of the center of the square steel; the counterweight rod 41 is made of a steel pipe with a diameter of 25mm, inserted into the opening of the floor connection pipe 22a of the counterweight bracket 4 and welded firmly, and a hole with a diameter of about 12cm is opened at about 5cm from the top of each steel pipe to facilitate the fixing of the counterweight block 42; the counterweight block 42 is prefabricated with concrete with a strength grade of not less than C25 and at least 2 steel bars in the middle, each block weighs about 25kg, and the center opening is convenient for stringing together through the counterweight rod 41. When conditions permit, the counterweight block 42 can be made of metal with high density and high hardness such as steel; after the counterweight block 42 is placed, a steel wire rope is used to pass through the hole on the floor connection pipe 22a and the top of the counterweight rod 41 to form a closed loop to fix the counterweight rod 41 and the counterweight block 42 together.
[0067] In some embodiments, Figure 4 As shown, the suspension beam 1 is optimized. In this embodiment, the suspension beam 1 includes a front beam 11, a rear beam 12 and a connecting beam 13. A protective net connecting member 3 is provided on the front beam 11. The front beam 11 is connected to the bracket 2; the rear beam 12 is connected to the counterweight bracket 4; one end of the connecting beam 13 is laterally adjustable and inserted into the front beam 11, and the other end is laterally adjustable and inserted into the rear beam 12.
[0068] During actual installation, the front beam 11 and the rear beam 12 are composed of square steels of about 1.5m in length and 80mm×80mm×4mm in size, and holes of 20mm in diameter are opened at the center lines of both sides of the square steels every 20cm; the connecting beam 13 is composed of square steels of about 4m in length and 70mm×70mm×4mm in size, and holes of 20mm in diameter are opened at the center lines of both sides of the square steels every 20cm; the insertion depth of the connecting beam 13 and the front beam 11 and the rear beam 12 can be adjusted through the holes on the square steels, thereby adjusting the length of the suspension beam 1 to adapt to different construction conditions.
[0069] In some embodiments, Figure 1 , 2 As shown, the high-altitude edge masonry construction protection device is optimized. In this embodiment, the high-altitude edge masonry construction protection device also includes a sensor alarm 300. The sensor alarm 300 is fixed at the bottom of the floor or under the structural beam near the edge of the floor, and is used to remind the workers when they enter a certain range from the edge of the floor.
[0070] In fact, in this embodiment, the sensor alarm 300 is an infrared sensor voice prompter powered by a rechargeable battery that can be purchased on the market. The sensor alarm 300 can be installed at the bottom of the floor or under the structural beam near the edge of the floor. Multiple sensor alarms 300 can be installed on the same construction floor; when construction workers enter within 1.5m from the edge of the floor, the sensor alarm 300 can sound an alarm to remind the construction workers to pay attention to safety, prevent falling, and wear safety protection equipment.
[0071] A construction method applicable to any of the above-mentioned high-altitude edge masonry construction protection devices, specifically, as follows:
[0072] Install the suspension mechanism 200: determine the installation height of the suspension beam 1 from the ground according to the waterproof requirements of the floor masonry or the height of the flip beam, adjust the depth of the upper bracket 21 inserted into the lower bracket 22 according to the installation height, and after adjustment, use Φ18 high-strength bolts and gaskets to fix the upper bracket 21 and the lower bracket 22; place a counterweight block 42 with a total weight not less than the weight of objects or personnel during on-site construction on the counterweight rod 41; adjust the installation position of the bracket 2 and the counterweight bracket 4 according to the on-site conditions. Generally, the distance between the counterweight bracket 4 and the bracket 2 is greater than or equal to three times the distance between the bracket 2 and the edge of the floor slab. After adjusting the distance, fix the bracket 2 and the counterweight bracket 4 on the floor slab; connect the front beam 11 to the bracket 2 by bolts, and the rear beam 12 to the counterweight bracket 4 by bolts. One end of the connecting beam 13 is inserted into the front beam 11 and fixed by bolts, and the other end is inserted into the rear beam 12 and fixed by bolts. Connect the protective net connector 3 to the front beam 11; install no less than two suspension mechanisms 200 on each floor according to the on-site conditions;
[0073] Install the sensor alarm 300 and the protection net 100: fix the sensor alarm 300 at the bottom of the floor or under the structural beam near the edge of the floor; connect the protection net 100 to the protection net connector 3 so that the protection net 100 fits the edge of the floor;
[0074] Construction of masonry or beam flipping at the bottom of the suspension beam 1: Masonry below the height of the suspension beam 1 is built according to the conventional masonry construction process requirements. When the masonry is built to the suspension beam 1, a hole with a reserved size can be ensured to ensure that the suspension mechanism 200 and the protective net 100 can be freely removed after the masonry construction is completed. The reserved hole should be reserved as much as possible according to the normal joint reservation requirements to ensure the quality of subsequent hole plugging;
[0075] Construction of masonry on the upper part of the suspension beam 1: build masonry higher than the height of the suspension beam 1 according to the conventional process requirements of masonry construction;
[0076] Removing the masonry construction protection device: After all masonry construction except the reserved holes is completed and the mortar strength meets the requirements, remove the counterweight block 42, then move the suspension mechanism 200 backward as a whole, move the bracket 2 to the reserved hole, remove the protection net 100 from the reserved hole, and remove the suspension mechanism 200 after pulling it out of the reserved hole; remove the suspension mechanism 200 of each layer from top to bottom;
[0077] Seal the reserved openings: Seal the reserved openings with masonry and mortar of the same material.
[0078] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A protective device for high-altitude edge masonry construction, characterized in that: include: A protective net (100), the protective net (100) being arranged on the facade of a building, vertically and in close contact with the floor slab, and being a lightweight, high-strength, flexible mesh structure capable of withstanding the impact of an operator or an object accidentally falling and having a certain safety factor; A hanging mechanism (200) is located on a floor slab to be constructed and is connected to the protective net (100), and at least two hanging mechanisms (200) are arranged on each floor slab.
2. A high-altitude edge masonry construction protection device as claimed in claim 1, characterized in that: The suspension mechanism (200) comprises a suspension beam (1) and a bracket (2); the suspension beam (1) is provided with a protective net connecting piece (3) for connecting the protective net (100); the bracket (2) is connected below the suspension beam (1) and is placed on the floor slab.
3. A protective device for high-altitude edge masonry construction as claimed in claim 2, characterized in that: The bracket (2) is height-adjustable, and the installation height of the suspension beam (1) can be adjusted according to the waterproofing requirements of the floor slab masonry or the height of the flip beam; the bracket (2) comprises an upper bracket (21) and a lower bracket (22), the upper bracket (21) is connected to the suspension beam (1); the lower bracket (22) is connected to the floor slab; the lower end of the upper bracket (21) is vertically and adjustably inserted into the upper end of the lower bracket (22).
4. A protective device for high-altitude edge masonry construction as claimed in claim 4, characterized in that: The upper bracket (21) further comprises a cross beam connecting tube (21a), a first vertical connecting tube (21b) and a first reinforcing member (21c); the cross beam connecting tube (21a) is connected to the suspension beam (1); one end of the first vertical connecting tube (21b) is connected to the cross beam connecting tube (21a), and the other end is vertically and adjustably inserted into the upper end of the lower bracket (22); the first reinforcing member (21c) is connected to the cross beam connecting tube (21a) on one side and to the first vertical connecting tube (21b) on the other side.
5. A protective device for high-altitude edge masonry construction as claimed in claim 4 or 5, characterized in that: The lower support (22) comprises a floor connecting pipe (22a), a second vertical connecting pipe (22b) and a second reinforcing member (22c); the floor connecting pipe (22a) is connected to the floor; one end of the second vertical connecting pipe (22b) is connected to the floor connecting pipe (22a), and the other end is sleeved on the first vertical connecting pipe (21b); one end of the second reinforcing member (22c) is connected to the floor connecting pipe (22a), and the other end is connected to the second vertical connecting pipe (22b).
6. A high-altitude edge masonry construction protection device as claimed in claim 1 or 2, characterized in that: The suspension mechanism (200) further comprises a counterweight bracket (4); the bracket (2) is connected to the floor slab at a position close to the edge of the floor slab, and the counterweight bracket (4) is connected to the floor slab at a position far from the edge of the floor slab; the distance between the counterweight bracket (4) and the bracket (2) is greater than or equal to three times the distance between the bracket (2) and the edge of the floor slab.
7. A protective device for high-altitude edge masonry construction as claimed in claim 7, characterized in that: The counterweight bracket (4) has the same structure as the bracket (2), and a counterweight rod (41) is connected to the lower bracket (22) of the counterweight bracket (4), and a counterweight block (42) is connected to the counterweight rod (41).
8. A high-altitude edge masonry construction protection device as described in any one of claims 2 to 5, characterized in that: The suspension beam (1) comprises a front beam (11), a rear beam (12) and a connecting beam (13); the front beam (11) is provided with a protective net connecting piece (3); the front beam (11) is connected to the bracket (2); the rear beam (12) is connected to the counterweight bracket (4); one end of the connecting beam (13) is transversely and adjustably inserted into the front beam (11), and the other end is transversely and adjustably inserted into the rear beam (12).
9. A high-altitude edge masonry construction protection device as claimed in claim 1, characterized in that: It also includes a sensor alarm (300), which is fixed at the bottom of the floor or under the structural beam near the edge of the floor, and is used to remind the operator when he enters a certain range from the edge of the floor.
10. A construction method applicable to the high-altitude edge masonry construction protection device according to any one of claims 1 to 9, characterized in that: include: Installing the suspension mechanism (200): determining the installation height of the suspension beam (1) from the ground according to the waterproofing requirements of the floor slab or the height of the flip beam, and adjusting the depth of the upper bracket (21) inserted into the lower bracket (22) according to the installation height; placing the counterweight block (42) with a total weight not less than the weight of an object or a person during on-site construction on the counterweight rod (41); and installing at least two sets of the suspension mechanism (200) on each floor according to on-site conditions; Installing the sensor alarm (300) and the protection net (100): fixing the sensor alarm (300) at the bottom of the floor or under the structural beam near the edge of the floor; connecting the protection net (100) to the protection net connector (3) so that the protection net (100) fits the edge of the floor; The bottom masonry or beam turning construction of the suspension beam (1): when the masonry is built to the suspension beam (1), a hole with a size reserved in combination with the position of the suspension beam (1) can ensure that the suspension mechanism (200) and the protective net (100) can be freely removed after the masonry construction is completed, and holes that can be used for the whole masonry construction are reserved as much as possible to ensure the quality of subsequent hole plugging; Construction of the upper masonry of the suspension beam (1): construction of masonry higher than the height of the suspension beam (1) according to conventional masonry construction process requirements; Removing the masonry construction protection device: after all masonry construction except the reserved holes is completed and the mortar strength meets the requirements, the suspension mechanism (200) is moved backward as a whole, so that the bracket (2) is moved to the reserved hole, the protection net (100) is removed, and the suspension mechanism (200) is pulled out of the reserved hole and then removed; the suspension mechanism (200) of each layer is removed in sequence from top to bottom; Seal the reserved openings: Seal the reserved openings with masonry and mortar of the same material.
Citation Information
Patent Citations
Safety protection net for high-rise building edge component construction and application method
CN108868175A
Anti-falling device for house building engineering
CN116591490A
Edge bracket type protection platform structure
CN117344956A
Building platform quick-mounting edge guardrail and mounting method thereof
CN118728119A
Safety anti-falling protection device for bridge construction
CN211665590U