Prefabricated water conservancy flood prevention retaining wall structure and construction method thereof
By designing a prefabricated water conservancy flood control retaining wall structure with groove frames, positioning frames, sliding holes and other components, the problem of sinking or inclination of the base when used on mud or sandy ground is solved, and the stable fixation of the base and the stability of the flood control wall are achieved.
Patent Information
- Application Number
- CN202510127338.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-04
- Publication Date
- 2025-03-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing prefabricated flood control wall base is prone to sink or tilt when used on mud or sandy ground, affecting the stability of the flood control wall.
A prefabricated water conservancy flood control retaining wall structure is designed, and its base has groove frames, positioning frames, sliding holes, round grooves, round hole rods, rotary rods, support frames, shrapnel and other components. Through the combination of these components, the base can be stably fixed under different ground conditions.
Through the cooperation of supporting frames, shrapnels and threaded rods, the base can be stably fixed under different ground conditions to avoid sinking or tilting, and improve the stability of the flood control wall.
Smart Images

Figure CN119640735A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of water conservancy flood control retaining wall, and in particular to a prefabricated assembled water conservancy flood control retaining wall structure and a construction method thereof. Background Art
[0002] Prefabricated flood walls are a type of flood prevention facility that is assembled on site using prefabricated components. This type of flood prevention wall is usually composed of a concrete base and an aluminum alloy wall. The flood prevention wall is prefabricated in the factory and assembled on site. The application scenarios of prefabricated flood prevention walls include urban river embankments, seawalls, underground culverts, subway entrances and exits, nuclear power plants and other places to prevent flooding and protect important facilities.
[0003] The current prefabricated flood control wall base is generally made of concrete, and the base is generally placed directly on the ground when in use to support and fix the flood control wall. However, when the concrete base is used on a muddy or sandy ground, the base will sink or tilt, affecting the stability of the flood control wall when in use. Summary of the invention
[0004] The object of the present invention is to provide a prefabricated assembled water conservancy flood control retaining wall structure and a construction method thereof, so as to solve the problems raised in the above-mentioned background technology.
[0005] In order to solve the above technical problems, the present invention is achieved through the following technical solutions: The present invention discloses a prefabricated assembled water conservancy flood control retaining wall structure and a construction method thereof, comprising a base, a groove frame fixedly connected to the top of the base, a positioning frame connected to the surface of the groove frame, a sliding hole provided on the upper surface of the base, a circular groove provided on the end of the base, a circular hole rod fixedly connected to the surface of the base, a rotating rod rotatably connected to the inner wall of the circular hole rod, a supporting frame fixedly connected to the end of the rotating rod, an elastic sheet fixedly connected to the surface of the base, an end of the elastic sheet away from the base is fixedly connected to the lower surface of the supporting frame, a baffle fixedly connected to the surface of the base, a flood retaining wall inserted into the inner wall of the groove frame, and a fixing component is arranged inside the base; The fixing component includes a threaded rod, an end of the threaded rod is rotatably connected to the inner wall of the base, an end of the threaded rod away from the base is fixedly connected to an adjusting wheel, the inner wall of the base is fixedly connected to a slide plate, the surface of the threaded rod is threadedly connected to a screw hole rack, the inner wall of the screw hole rack is rotatably connected to a round rod, the end of the round rod is fixedly connected to a groove wheel, the surface of the round rod is fixedly connected to a mounting frame, the surface of the mounting frame is fixedly connected to a plug plate, the surface of the screw hole rack is fixedly connected to a slide groove frame, the inner wall of the base is fixedly connected to a toothed plate, the surface of the base is provided with an extrusion component, and the surface of the flood retaining wall is provided with a stabilizing component.
[0006] Furthermore, the top of the flood retaining wall extends to the top outer end of the groove frame, and the number of the positioning frames is two, and the two positioning frames are symmetrically arranged with the groove frame as the center.
[0007] Furthermore, the end of the rotating rod passes through the round hole rod and extends to the outer end of the round hole rod, the bottom of the support frame extends to the bottom of the base, the bottom of the baffle contacts the top of the rotating rod, and the top of the spring is located on the lower surface of the base.
[0008] Furthermore, there are two slides, which are symmetrically arranged with the base as the center. The end of the threaded rod close to the adjusting wheel passes through the base and extends to the inside of the circular groove. The adjusting wheel is located inside the circular groove, and the tooth plate is located below the slide.
[0009] Furthermore, the inner wall of the slide slot frame is slidably connected to the surface of the skateboard, the end of the round rod passes through the screw hole frame and extends to the outer end of the screw hole frame, the inner wall of the groove wheel engages with the surface of the tooth plate, and the number of the screw hole frames is two, the two screw hole frames are symmetrically arranged with the base as the center, and the threads in the two screw hole frames are oppositely arranged.
[0010] Furthermore, the extrusion component includes a linkage plate, the bottom of the linkage plate is fixedly connected to the top of the screw hole frame, the end of the linkage plate away from the screw hole frame is fixedly connected to a cylindrical rod, the end of the cylindrical rod is rotatably connected to a tripod, the center of the tripod is hinged with an inclined frame, the inner wall of the positioning frame is slidably connected to a pressure plate, the surface of the pressure plate is fixedly connected to a sliding rod, the end of the sliding rod away from the pressure plate is fixedly connected to a triangular plate, the end of the triangular plate close to the sliding rod is fixedly connected to a spring, and the end of the spring away from the triangular plate is fixedly connected to the surface of the positioning frame.
[0011] Furthermore, one end of the slide rod away from the pressure plate passes through the positioning frame and extends to the outer end of the positioning frame, one end of the triangular plate away from the slide rod contacts the lower surface of the inclined frame, and the end of the cylindrical rod extends to the outer end of the base through the sliding hole.
[0012] Furthermore, the stabilizing component includes a fixing rod, an inner wall of the fixing rod is fixedly connected to the surface of the cylindrical rod, a semicircular frame is hinged on the upper surface of the fixing rod, a central frame is hinged at the center of the semicircular frame, an elastic rod is fixedly connected to the surface of the central frame, and a clamping plate is fixedly connected to one end of the elastic rod away from the central frame.
[0013] Furthermore, the fixing rod is located at the outer end of the base, the number of the semicircular frames is two, the two semicircular frames are symmetrically arranged with the base as the center, and the end of the clamping plate away from the elastic rod contacts the upper surface of the flood retaining wall.
[0014] Furthermore, a construction method of a prefabricated assembled water conservancy flood control retaining wall structure comprises the following steps: S1: When the base needs to be transported, the support frame is pulled to drive the rotating rod to rotate inside the round hole rod. When the support frame contacts the bottom of the baffle, the base can be transported by the support frame, which improves the convenience of the base during installation. When not in use, the support frame uses the elasticity of the spring to squeeze the surface of the base; S2: When the screw hole rack moves, the groove wheel is driven to move by the round rod, and the groove wheel drives the round rod to rotate by meshing with the tooth plate. The round rod pushes the plug plate to rotate downward through the mounting frame. When the plug plate is in a vertical state, the support frame is pushed to separate from the surface of the base. At this time, the base can be stepped on to move downward, and the base can squeeze the plug plate and insert it into the mud or sandy ground for fixation; S3: When the cylindrical rod moves, it will pull the center of the tripod downward. At this time, the tripod will squeeze the triangular plate through the inclined frame, and the triangular plate will push the pressure plate to move inside the groove frame through the sliding rod, thereby squeezing and fixing the flood retaining wall; S4: When the cylindrical rod moves, it pushes the semicircular frame through the fixed rod to cause deformation. At this time, the center of the semicircular frame will move toward the surface of the flood retaining wall. The center frame will compress the elastic rod through the movement of the semicircular frame, and the clamping plate will use the elasticity of the elastic rod to squeeze and fix the flood retaining wall.
[0015] The present invention has the following beneficial effects: in the technical solution of the present invention, when the base needs to be transported, the support frame is pulled to drive the rotating rod to rotate inside the round hole rod. When the support frame contacts the bottom of the baffle, the base can be transported by the support frame, thereby improving the convenience of the base during installation. When the support frame is not in use, the elasticity of the spring sheet is used to squeeze the surface of the base to start the support of the base. After the base is placed, the threaded rod is rotated inside the base by twisting the adjusting wheel. The threaded rod will push the two screw hole frames to move away from each other. The screw hole frames are moving When the screw hole frame moves, the groove wheel is driven to move by the round rod, and the groove wheel drives the round rod to rotate by engaging with the tooth plate. The round rod pushes the plug plate to rotate downward through the mounting frame. When the plug plate is in a vertical state, the support frame is pushed to separate from the surface of the base. At this time, the base can be stepped on to move downward, and the base can squeeze the plug plate and insert it into the mud or sandy ground for fixation, thereby improving the stability of the base when in use and preventing the base from tilting due to the subsidence of the mud ground.
[0016] When the screw hole frame moves, it will push the cylindrical rod to move inside the sliding hole through the linkage plate. When the cylindrical rod moves, it will pull the center of the tripod downward. At this time, the tripod will squeeze the triangle plate through the inclined frame. The triangle plate will push the pressure plate to move inside the groove frame through the sliding rod, thereby squeezing and fixing the flood retaining wall, thereby improving the convenience of assembling the flood retaining wall and the base.
[0017] When the cylindrical rod moves, it pushes the semicircular frame through the fixed rod to cause deformation. At this time, the center of the semicircular frame will move toward the surface of the flood retaining wall. The central frame will compress the elastic rod through the movement of the semicircular frame, and the clamping plate will use the elasticity of the elastic rod to squeeze and fix the flood retaining wall. At the same time, the elastic rod will transmit the pressure of the central frame to the clamping plate to squeeze and fix the flood retaining wall, thereby further improving the stability of the flood retaining wall when in use.
[0018] Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0020] Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 This is a schematic diagram of the flood retaining wall structure of the present invention; Figure 3 It is a schematic diagram of the base structure of the present invention; Figure 4 It is a schematic diagram of the overall structure of the fixing component of the present invention; Figure 5 It is another structural schematic diagram of the fixing component of the present invention; Figure 6 It is a schematic diagram of the overall structure of the extruded component of the present invention; Figure 7 Another structural schematic diagram of the extruded component of the present invention; Figure 8 It is a schematic diagram of the overall structure of the stabilizing component of the present invention; Fig. 9 It is a schematic diagram of the process structure of the present invention.
[0021] In the attached drawings, the list of components represented by each reference numeral is as follows: In the figure: 1, base; 2, flood retaining wall; 3, fixing component; 4, extrusion component; 5, stabilizing component; 6, baffle; 7, circular groove; 8, groove frame; 9, sliding hole; 10, positioning frame; 11, rotating rod; 12, supporting frame; 13, spring; 14, circular hole rod; 20, sliding plate; 21, threaded rod; 22, adjusting wheel; 23, tooth plate; 24, screw hole frame; 25, sliding groove frame; 26, groove wheel; 27, round rod; 28, plug plate; 29, mounting frame; 31, inclined frame; 32, spring; 33, triangular plate; 34, pressure plate; 35, sliding rod; 36, tripod; 37, cylindrical rod; 38, linkage plate; 40, fixing rod; 41, semicircular frame; 42, clamping plate; 43, center frame; 44, elastic rod. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0023] See also Figure 1-Figure 9 As shown, the present invention is a prefabricated assembled water conservancy flood control retaining wall structure and a construction method thereof, comprising a base 1, a groove frame 8 is fixedly connected to the top of the base 1, a positioning frame 10 is connected to the surface of the groove frame 8, a sliding hole 9 is opened on the upper surface of the base 1, a circular groove 7 is opened at the end of the base 1, a circular hole rod 14 is fixedly connected to the surface of the base 1, a rotating rod 11 is rotatably connected to the inner wall of the circular hole rod 14, a supporting frame 12 is fixedly connected to the end of the rotating rod 11, and a spring piece 13 is fixedly connected to the surface of the base 1, and the end of the spring piece 13 away from the base 1 is connected to the lower end of the supporting frame 12. The surface is fixedly connected. When the base 1 needs to be transported, the support frame 12 is pulled to drive the rotating rod 11 to rotate inside the round hole rod 14. When the support frame 12 contacts the bottom of the baffle 6, the base 1 can be transported by the support frame 12, which improves the convenience of the base 1 during installation. When not in use, the support frame 12 uses the elasticity of the spring sheet 13 to squeeze the surface of the base 1, which can start the support function of the base 1. The surface of the base 1 is fixedly connected with the baffle 6, the inner wall of the groove frame 8 is plugged with the flood retaining wall 2, and the interior of the base 1 is provided with a fixing component 3; The fixing component 3 includes a threaded rod 21, the end of the threaded rod 21 is rotatably connected to the inner wall of the base 1, the end of the threaded rod 21 away from the base 1 is fixedly connected to the adjusting wheel 22, the inner wall of the base 1 is fixedly connected to the slide plate 20, the surface of the threaded rod 21 is threadedly connected to the screw hole frame 24, the inner wall of the screw hole frame 24 is rotatably connected to the round rod 27, the end of the round rod 27 is fixedly connected to the groove wheel 26, the surface of the round rod 27 is fixedly connected to the mounting frame 29, the surface of the mounting frame 29 is fixedly connected to the plug plate 28, the surface of the screw hole frame 24 is fixedly connected to the slide frame 25, the inner wall of the base 1 is fixedly connected to the tooth plate 23, the surface of the base 1 is provided with an extrusion component 4, and the surface of the flood retaining wall 2 is provided with a stabilizing component 5.
[0024] The top of the flood retaining wall 2 extends to the top outer end of the groove frame 8. There are two positioning frames 10, and the two positioning frames 10 are symmetrically arranged with the groove frame 8 as the center.
[0025] The end of the rotating rod 11 passes through the round hole rod 14 and extends to the outer end of the round hole rod 14, the bottom of the support frame 12 extends to the bottom of the base 1, the bottom of the baffle 6 contacts the top of the rotating rod 11, and the top of the spring 13 is located on the lower surface of the base 1.
[0026] There are two slide plates 20, which are symmetrically arranged with the base 1 as the center. The end of the threaded rod 21 close to the adjusting wheel 22 passes through the base 1 and extends to the inside of the circular groove 7. The adjusting wheel 22 is located inside the circular groove 7, and the tooth plate 23 is located below the slide plate 20.
[0027] The inner wall of the slide slot frame 25 is slidably connected to the surface of the slide plate 20, and the end of the round rod 27 passes through the screw hole frame 24 and extends to the outer end of the screw hole frame 24. After the base 1 is placed, the threaded rod 21 is twisted and rotated inside the base 1 by adjusting the wheel 22. The threaded rod 21 will push the two screw hole frames 24 to move away from each other. When the screw hole frame 24 moves, it will drive the slide slot frame 25 to slide on the surface of the slide plate 20, thereby improving the stability of the screw hole frame 24 when moving. When the screw hole frame 24 moves, the groove wheel 26 moves through the round rod 27. The groove wheel 26 drives the round rod 27 to rotate by meshing with the tooth plate 23. The round rod 2 7 will push the plug plate 28 to rotate downward through the mounting frame 29. When the plug plate 28 is in a vertical state, the support frame 12 is pushed to separate from the surface of the base 1. At this time, the base 1 can be stepped on to move downward, and the base 1 can squeeze the plug plate 28 and insert it into the mud ground or sand and stone ground for fixation, thereby improving the stability of the base 1 when in use and preventing the base 1 from tilting due to the sinking of the mud ground. The inner wall of the groove wheel 26 is meshed with the surface of the tooth plate 23. There are two screw hole racks 24, which are symmetrically arranged with the base 1 as the center, and the threads in the two screw hole racks 24 are oppositely arranged.
[0028] The extrusion component 4 includes a linkage plate 38, the bottom of the linkage plate 38 is fixedly connected to the top of the screw hole frame 24, the end of the linkage plate 38 away from the screw hole frame 24 is fixedly connected to a cylindrical rod 37, the end of the cylindrical rod 37 is rotatably connected to a tripod 36, the center of the tripod 36 is hinged with an inclined frame 31, the inner wall of the positioning frame 10 is slidably connected to a pressure plate 34, the surface of the pressure plate 34 is fixedly connected to a sliding rod 35, the end of the sliding rod 35 away from the pressure plate 34 is fixedly connected to a triangular plate 33, the end of the triangular plate 33 close to the sliding rod 35 is fixedly connected to a spring 32, and the end of the spring 32 away from the triangular plate 33 is fixedly connected to the surface of the positioning frame 10.
[0029] One end of the slide rod 35 away from the pressure plate 34 passes through the positioning frame 10 and extends to the outer end of the positioning frame 10. One end of the triangular plate 33 away from the slide rod 35 contacts the lower surface of the inclined frame 31. When the screw hole frame 24 of the present invention moves, it will push the cylindrical rod 37 to move inside the sliding hole 9 through the linkage plate 38. When the cylindrical rod 37 moves, it will pull the center of the tripod 36 to move downward. At this time, the tripod 36 will squeeze the triangular plate 33 through the inclined frame 31. The triangular plate 33 will push the pressure plate 34 to move toward the inside of the groove frame 8 through the slide rod 35, thereby squeezing and fixing the flood retaining wall 2, improving the convenience of assembling the flood retaining wall 2 and the base 1, and the end of the cylindrical rod 37 extends to the outer end of the base 1 through the sliding hole 9.
[0030] The stabilizing component 5 includes a fixing rod 40, the inner wall of which is fixedly connected to the surface of the cylindrical rod 37, a semicircular frame 41 is hingedly connected to the upper surface of the fixing rod 40, a center frame 43 is hingedly connected to the center of the semicircular frame 41, an elastic rod 44 is fixedly connected to the surface of the center frame 43, and a clamping plate 42 is fixedly connected to the end of the elastic rod 44 away from the center frame 43.
[0031] The fixing rod 40 is located at the outer end of the base 1, and there are two semicircular frames 41, which are symmetrically arranged with the base 1 as the center. When the cylindrical rod 37 of the present invention moves, the semicircular frame 41 is pushed by the fixing rod 40 to deform. At this time, the center of the semicircular frame 41 will move toward the surface of the flood retaining wall 2, and the center frame 43 will compress the elastic rod 44 through the movement of the semicircular frame 41, and the clamping plate 42 will use the elasticity of the elastic rod 44 to squeeze and fix the flood retaining wall 2. At the same time, the elastic rod 44 will transmit the pressure of the center frame 43 to the clamping plate 42 to squeeze and fix the flood retaining wall 2, further improving the stability of the flood retaining wall 2 when in use. The end of the clamping plate 42 away from the elastic rod 44 is in contact with the upper surface of the flood retaining wall 2.
[0032] A construction method of a prefabricated assembled water conservancy flood control retaining wall structure comprises the following steps: S1: When the base 1 needs to be transported, the support frame 12 is pulled to drive the rotating rod 11 to rotate inside the round hole rod 14. When the support frame 12 contacts the bottom of the baffle 6, the base 1 can be transported by the support frame 12, which improves the convenience of the base 1 during installation. When not in use, the support frame 12 uses the elasticity of the spring sheet 13 to squeeze the surface of the base 1; S2: When the screw hole frame 24 moves, the groove wheel 26 is driven to move by the round rod 27, and the groove wheel 26 drives the round rod 27 to rotate by meshing with the tooth plate 23. The round rod 27 pushes the plug plate 28 to rotate downward through the mounting frame 29. When the plug plate 28 is in a vertical state, the support frame 12 is pushed to separate from the surface of the base 1. At this time, the base 1 can be stepped on to move downward, and the base 1 can squeeze the plug plate 28 to be inserted into the mud or sandy ground for fixing; S3: When the cylindrical rod 37 moves, it will pull the center of the tripod 36 to move downward. At this time, the tripod 36 will squeeze the triangular plate 33 through the inclined frame 31, and the triangular plate 33 will push the pressure plate 34 to move inside the groove frame 8 through the sliding rod 35, thereby squeezing and fixing the flood retaining wall 2; S4: When the cylindrical rod 37 moves, it pushes the semicircular frame 41 through the fixed rod 40 to cause deformation. At this time, the center of the semicircular frame 41 will move toward the surface of the flood retaining wall 2, and the center frame 43 will compress the elastic rod 44 through the movement of the semicircular frame 41, and the clamping plate 42 will use the elasticity of the elastic rod 44 to squeeze and fix the flood retaining wall 2.
[0033] When the base 1 needs to be transported during use, the support frame 12 is pulled to drive the rotating rod 11 to rotate inside the round hole rod 14. When the support frame 12 contacts the bottom of the baffle 6, the base 1 can be transported by the support frame 12, which improves the convenience of the base 1 during installation. When the support frame 12 is not in use, the elasticity of the spring sheet 13 is used to squeeze the surface of the base 1 to start the support function of the base 1. After the base 1 is placed, the threaded rod 21 is twisted by the adjusting wheel 22 to rotate inside the base 1, and the threaded rod 21 will push the two screw hole frames 24. When the screw hole frame 24 moves away from each other, it drives the slide frame 25 to slide on the surface of the slide plate 20, thereby improving the stability of the screw hole frame 24 when moving. When the screw hole frame 24 moves, it drives the groove wheel 26 to move through the round rod 27. The groove wheel 26 drives the round rod 27 to rotate by engaging with the tooth plate 23. The round rod 27 pushes the plug plate 28 to rotate downward through the mounting frame 29. When the plug plate 28 is in a vertical state, it pushes the support frame 12 to separate from the surface of the base 1. At this time, the base 1 can be stepped on to move downward, and the base 1 can squeeze the plug plate 28. The plate 28 is inserted into the mud or sandy ground for fixing, which improves the stability of the base 1 when in use and prevents the base 1 from tilting due to the sinking of the mud ground. When the screw hole frame 24 moves, it will push the cylindrical rod 37 to move inside the sliding hole 9 through the linkage plate 38. When the cylindrical rod 37 moves, it will pull the center of the tripod 36 to move downward. At this time, the tripod 36 will squeeze the triangular plate 33 through the inclined frame 31, and the triangular plate 33 will push the pressure plate 34 to move inside the groove frame 8 through the sliding rod 35, thereby squeezing the flood retaining wall 2. The fixing improves the convenience of assembling the flood retaining wall 2 and the base 1. When the cylindrical rod 37 moves, it pushes the semicircular frame 41 through the fixing rod 40 to cause deformation. At this time, the center of the semicircular frame 41 will move toward the surface of the flood retaining wall 2. The central frame 43 will compress the elastic rod 44 through the movement of the semicircular frame 41, and the clamping plate 42 will use the elasticity of the elastic rod 44 to squeeze and fix the flood retaining wall 2. At the same time, the elastic rod 44 will transmit the pressure of the central frame 43 to the clamping plate 42 to squeeze and fix the flood retaining wall 2, further improving the stability of the flood retaining wall 2 when in use.
[0034] The preferred embodiments of the present invention disclosed above are only used to help illustrate the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. A prefabricated assembled water conservancy flood control retaining wall structure, comprising a base (1), characterized in that: The top of the base (1) is fixedly connected to a groove frame (8), the surface of the groove frame (8) is connected to a positioning frame (10), the upper surface of the base (1) is provided with a sliding hole (9), the end of the base (1) is provided with a circular groove (7), the surface of the base (1) is fixedly connected to a circular hole rod (14), the inner wall of the circular hole rod (14) is rotatably connected to a rotating rod (11), the end of the rotating rod (11) is fixedly connected to a support frame (12), the surface of the base (1) is fixedly connected to a spring sheet (13), the end of the spring sheet (13) away from the base (1) is fixedly connected to the lower surface of the support frame (12), the surface of the base (1) is fixedly connected to a baffle (6), the inner wall of the groove frame (8) is plugged with a flood retaining wall (2), and the base (1) is provided with a fixing component (3) inside; The fixing component (3) comprises a threaded rod (21), the end of the threaded rod (21) being rotatably connected to the inner wall of the base (1), the end of the threaded rod (21) being fixedly connected to an adjusting wheel (22) away from the base (1), the inner wall of the base (1) being fixedly connected to a slide plate (20), the surface of the threaded rod (21) being threadably connected to a screw hole frame (24), the inner wall of the screw hole frame (24) being rotatably connected to a round rod (27), the end of the round rod (27) being fixedly connected to a groove wheel (26), the surface of the round rod (27) being fixedly connected to a mounting frame (29), the surface of the mounting frame (29) being fixedly connected to a plug plate (28), the surface of the screw hole frame (24) being fixedly connected to a slide groove frame (25), the inner wall of the base (1) being fixedly connected to a toothed plate (23), the surface of the base (1) being provided with an extrusion component (4), and the surface of the flood retaining wall (2) being provided with a stabilizing component (5).
2. The prefabricated assembled water conservancy flood control retaining wall structure according to claim 1 is characterized in that: The top of the flood retaining wall (2) extends to the top outer end of the groove frame (8), and the number of the positioning frames (10) is two, and the two positioning frames (10) are symmetrically arranged with the groove frame (8) as the center.
3. The prefabricated assembled water conservancy flood control retaining wall structure according to claim 2 is characterized in that: The end of the rotating rod (11) passes through the round hole rod (14) and extends to the outer end of the round hole rod (14); the bottom of the support frame (12) extends to the bottom of the base (1); the bottom of the baffle (6) contacts the top of the rotating rod (11); and the top of the spring sheet (13) is located on the lower surface of the base (1).
4. The prefabricated assembled water conservancy flood control retaining wall structure according to claim 3 is characterized by: The number of the slide plates (20) is two, and the two slide plates (20) are symmetrically arranged with the base (1) as the center. The end of the threaded rod (21) close to the adjusting wheel (22) passes through the base (1) and extends to the inside of the circular groove (7). The adjusting wheel (22) is located inside the circular groove (7), and the tooth plate (23) is located below the slide plate (20).
5. The prefabricated assembled water conservancy flood control retaining wall structure according to claim 4 is characterized in that: The inner wall of the slide groove frame (25) is slidably connected to the surface of the slide plate (20), the end of the round rod (27) passes through the screw hole frame (24) and extends to the outer end of the screw hole frame (24), the inner wall of the groove wheel (26) is meshed with the surface of the tooth plate (23), the number of the screw hole frames (24) is two, the two screw hole frames (24) are symmetrically arranged with the base (1) as the center, and the threads in the two screw hole frames (24) are arranged oppositely.
6. The prefabricated assembled water conservancy flood control retaining wall structure according to claim 5 is characterized in that: The extrusion component (4) comprises a linkage plate (38), the bottom of which is fixedly connected to the top of the screw hole frame (24), the end of the linkage plate (38) away from the screw hole frame (24) is fixedly connected to a cylindrical rod (37), the end of the cylindrical rod (37) is rotatably connected to a tripod (36), the center of the tripod (36) is hinged with an inclined plane frame (31), the inner wall of the positioning frame (10) is slidably connected to a pressure plate (34), the surface of the pressure plate (34) is fixedly connected to a sliding rod (35), the end of the sliding rod (35) away from the pressure plate (34) is fixedly connected to a triangular plate (33), the end of the triangular plate (33) close to the sliding rod (35) is fixedly connected to a spring (32), and the end of the spring (32) away from the triangular plate (33) is fixedly connected to the surface of the positioning frame (10).
7. The prefabricated assembled water conservancy flood control retaining wall structure according to claim 6 is characterized in that: One end of the slide bar (35) away from the pressure plate (34) passes through the positioning frame (10) and extends to the outer end of the positioning frame (10); one end of the triangular plate (33) away from the slide bar (35) contacts the lower surface of the inclined frame (31); and the end of the cylindrical rod (37) extends to the outer end of the base (1) through the slide hole (9).
8. The prefabricated assembled water conservancy flood control retaining wall structure according to claim 7 is characterized in that: The stabilizing component (5) comprises a fixing rod (40), the inner wall of which is fixedly connected to the surface of the cylindrical rod (37), a semicircular frame (41) is hingedly connected to the upper surface of the fixing rod (40), a central frame (43) is hingedly connected to the center of the semicircular frame (41), an elastic rod (44) is fixedly connected to the surface of the central frame (43), and a clamping plate (42) is fixedly connected to one end of the elastic rod (44) away from the central frame (43).
9. The prefabricated assembled water conservancy flood control retaining wall structure according to claim 8, characterized in that: The fixing rod (40) is located at the outer end of the base (1), the number of the semicircular frames (41) is two, and the two semicircular frames (41) are symmetrically arranged with the base (1) as the center, and the end of the clamping plate (42) away from the elastic rod (44) contacts the upper surface of the flood retaining wall (2).
10. The construction method of a prefabricated assembled water conservancy flood control retaining wall structure according to claim 9, characterized in that: The following steps are involved: S1: When the base (1) needs to be transported, the support frame (12) is pulled to drive the rotating rod (11) to rotate inside the round hole rod (14). When the support frame (12) contacts the bottom of the baffle (6), the base (1) can be transported by the support frame (12), thereby improving the convenience of the base (1) during installation. When not in use, the support frame (12) uses the elasticity of the spring sheet (13) to squeeze the surface of the base (1); S2: When the screw hole frame (24) moves, the groove wheel (26) is driven to move by the round rod (27), and the groove wheel (26) drives the round rod (27) to rotate by meshing with the tooth plate (23). The round rod (27) pushes the plug plate (28) to rotate downward through the mounting frame (29). When the plug plate (28) is in a vertical state, the support frame (12) is pushed to separate from the surface of the base (1). At this time, the base (1) can be stepped on to move downward, and the base (1) can squeeze the plug plate (28) and insert it into the mud ground or sand and stone ground for fixing; S3: When the cylindrical rod (37) moves, it pulls the center of the tripod (36) downward, and at this time, the tripod (36) squeezes the triangular plate (33) through the inclined frame (31), and the triangular plate (33) pushes the pressure plate (34) to move toward the inside of the groove frame (8) through the sliding rod (35), thereby squeezing and fixing the flood retaining wall (2); S4: When the cylindrical rod (37) moves, it pushes the semicircular frame (41) through the fixing rod (40) to cause deformation. At this time, the center of the semicircular frame (41) moves toward the surface of the flood retaining wall (2). The center frame (43) compresses the elastic rod (44) through the movement of the semicircular frame (41), and the clamping plate (42) uses the elasticity of the elastic rod (44) to compress and fix the flood retaining wall (2).