Assembly type light partition wall mounting structure and mounting method
Through the connection between upper and lower pendants and rotary clips, the problem that the existing lightweight partition wall installation method cannot be disassembled or replaced in a single piece is solved, and the rapid installation and convenient disassembly of lightweight partition walls are achieved, reducing the cost of secondary transformation.
Patent Information
- Application Number
- CN202510075846.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-17
- Publication Date
- 2025-03-18
- Estimated Expiration
- 2045-01-17
AI Technical Summary
The existing lightweight partition wall installation method requires the partition wall body to be damaged when it is removed or replaced, and cannot be disassembled or replaced in a single piece, which limits the turnover and use of wall panels and secondary replacement.
The lightweight partition wall is quickly installed by clamping the upper and lower pendants, and connected to the ground through rotary clips to ensure that the wall can be disassembled and replaced independently to avoid damage to the wall.
It realizes the rapid installation and easy disassembly of lightweight partition walls, reduces the cost of secondary transformation, and supports later maintenance and upgrades.
Smart Images

Figure CN119640994A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, in particular to an assembly of a lightweight partition wall installation structure and an installation method. Background Art
[0002] As a new type of industry in the construction field, prefabricated buildings are widely used in the modern construction industry due to their characteristics of large-scale standardized production, low construction intensity, energy conservation and environmental protection. As the most commonly used structure in prefabricated buildings, lightweight partition boards have the advantages of light weight, high strength, multiple environmental protection, thermal insulation, sound insulation, etc. They can be widely used in internal partitions of office, business, residential buildings and other building structures. When installing common lightweight partition walls, pipe clamps are usually used for fixing. When the pipe clamps are in use, a hammer is used to hit one end of the pipe clamp with a round hole to the top of the wall, and then the steel plate part of the pipe clamp is fixed to the roof or the ground. However, when the partition wall fixed in this way is later dismantled or replaced, the partition wall body needs to be destroyed before it can be dismantled. It is impossible to dismantle or replace a single partition wall, and the turnover and secondary replacement of wall panels are not utilized. Based on the above problems, the present invention proposes an assembled lightweight partition wall installation structure and installation method. Summary of the invention
[0003] In view of the deficiencies in the prior art, the purpose of the present invention is to provide an assembled lightweight partition wall installation structure and installation method, which has the characteristics of easy disassembly and assembly, no damage to the wall, convenient later maintenance and upgrading, and reduced secondary transformation costs.
[0004] The technical solution adopted by the present invention to solve its technical problem is: A prefabricated lightweight partition wall installation structure includes a prefabricated wall module, the prefabricated wall module includes a lightweight partition wall, the lightweight partition wall is placed between the roof and the ground, and also includes a hanger, the top of the lightweight partition wall is connected to the roof through the hanger; sound insulation cotton is respectively arranged on both sides of the hanger between the top of the lightweight partition wall and the roof; a sealing strip is filled between the bottom of the lightweight partition wall and the ground, and the two sides of the prefabricated wall module are respectively covered with gypsum boards.
[0005] Compared with the prior art, the preferred solution adopted by the present invention is: The present invention adopts the method of upper and lower hanging parts being connected, so that the lightweight partition wall can be quickly installed in place, which simplifies the assembly process and effectively shortens the installation period; each lightweight partition wall is an independent module, and the wall does not need to be destroyed during disassembly and replacement, which is convenient for the later replacement and recycling of the lightweight partition wall, easy for maintenance and upgrading, and reduces the cost of secondary transformation.
[0006] Further, the preferred embodiment adopted by the present invention is: The hanger comprises an upper hanger and a lower hanger. The upper hanger is arranged at the installation position of the roof corresponding to the lightweight partition wall, and the lower hanger is arranged on the top of the lightweight partition wall. The upper hanger is clamped with the lower hanger.
[0007] The upper hanger includes an upper fixed plate and an L-shaped upper clamping plate, and the lower hanger includes a lower fixed plate and an L-shaped lower clamping plate. The upper clamping plate is connected to the upper fixed plate through its vertical section, and the end of the transverse section of the upper clamping plate protrudes upward to form an upper clamping block; the lower clamping plate is connected to the lower fixed plate through its vertical section, and the end of the transverse section of the lower clamping plate protrudes downward to form a lower clamping block, and the upper clamping block and the lower clamping block are matched and clamped.
[0008] The upper surface of the upper clamping block and the lower surface of the lower clamping block are respectively arranged as inclined surfaces adapted to each other.
[0009] The inclination angle of the upper surface of the upper clamping block and the inclination angle of the lower surface of the lower clamping block are both 12°.
[0010] A rotating clamp is arranged at the bottom of the lightweight partition wall, and the rotating clamp is rotatably connected to the ground.
[0011] A through hole is arranged at the center of the rotating clamp, and the rotating clamp is connected to the ground via a screw passing through the through hole.
[0012] The rotating clamp is a rectangular structure, and positioning plates are respectively arranged on two opposite corners of the rotating clamp. The rotating clamp is connected to the lightweight partition wall by screws penetrating the positioning plates.
[0013] The present invention also relates to a method for installing an assembled lightweight partition wall, and the specific steps are as follows: S1. Determine the installation position of the upper hanging parts on the roof according to the installation position of the lightweight partition wall, install the upper hanging parts on the roof, and then install the lower hanging parts on the top of the lightweight partition wall; S2. Determine the installation position of the rotating fixture according to the installation position of the lightweight partition wall, connect the rotating fixture to the ground through screws, and ensure that the rotating fixture is fixed to the ground but not tightened, and ensure that the rotating fixture can rotate around the screws; S3. Use the hoisting equipment to place the lightweight partition wall vertically, and then adjust the position of the rotating clamp so that the rotating clamp is perpendicular to the installation position of the lightweight partition wall; S4, start the hoisting equipment, move the lightweight partition wall to the installation position, make the lower hanger gradually approach the upper hanger until the two intersect, continue to move the lightweight partition wall, make the upper clamping block move inward along the lower clamping block, until it can no longer move inward, and then fine-tune the height of the lightweight partition wall downward to make the upper clamping block engage with the lower clamping block; S5, rotating the rotating clamp until the two positioning plates are respectively attached to the front and back sides of the lightweight partition wall, and then using screws to fix the lightweight partition wall and the positioning plates on both sides respectively; S6. Fill the space between the roof and both sides of the top hanging parts of the lightweight partition wall with sound insulation cotton, and fill the space between the lightweight partition wall and the ground with sealing strips; S7. Cover both sides of the prefabricated partition wall module with a layer of gypsum board and the installation is completed.
[0014] This method can be completed by simply assembling the lightweight partition wall between the roof and the ground using hanging parts on site, which can quickly achieve the installation effect, effectively shorten the construction period, reduce installation costs and effectively improve the recycling utilization rate. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a structural schematic diagram of the present invention; Figure 2 It is a schematic diagram of the installation structure of the lightweight partition wall in the present invention; Figure 3 is a schematic structural diagram of an upper hanging member in an embodiment of the present invention; Figure 4 is a schematic structural diagram of the lower hanging member in an embodiment of the present invention; Figure 5 It is a schematic diagram of the structure of the cooperation between the upper hanging piece and the lower hanging piece in an embodiment of the present invention; Figure 6 is a schematic structural diagram of a rotating clamp in an embodiment of the present invention; Explanation of the accompanying drawings: 1. Roof; 2. Ground; 3. Lightweight partition wall; 4. Hanging part; 41. Upper hanging part; 411. Upper fixing plate; 412. Upper clamping plate; 4121. Upper clamping block; 42. Lower hanging part; 421. Lower fixing plate; 422. Lower clamping plate; 4221. Lower clamping block; 5. Rotating clamp / 51. Through hole; 52. Positioning plate; 6. Sound insulation cotton; 7. Sealing strip; 8. Gypsum board. DETAILED DESCRIPTION
[0016] The present invention is further described below in conjunction with specific embodiments, the purpose of which is only to provide a better understanding of the content of the present invention. Therefore, the examples given do not limit the protection scope of the present invention.
[0017] like Figures 1 to 6 As shown, an assembled lightweight partition wall installation structure includes an assembled wall module, and the assembled wall module is composed of a lightweight partition wall 3, a hanger 4, and a rotating clamp 5. The lightweight partition wall 3 is placed between the roof 1 and the ground 2, and the top of the lightweight partition wall 3 is connected to the roof 1 through the hanger 4, and the bottom of the lightweight partition wall 3 is connected to the ground 2 through the rotating clamp 5.
[0018] The hanger 4 consists of an upper hanger 41 and a lower hanger 42 . The upper hanger 41 is installed on the roof 1 , and the lower hanger 42 is installed on the lightweight partition wall 3 .
[0019] The upper hanger 41 is composed of an upper fixing plate 411 and an L-shaped upper clamping plate 412, and the lower hanger 42 is composed of a lower fixing plate 421 and an L-shaped lower clamping plate 422. The upper fixing plate 411 is connected and fixed to the roof 1 by screws, and the lower fixing plate 421 is fixed and connected to the upper end surface of the lightweight partition wall 3 by screws.
[0020] The upper clamping plate 412 and the lower clamping plate 422 are both composed of a vertical section and a horizontal section. The upper clamping plate 412 is connected to the upper fixing plate 411 through its vertical section, and the end of the horizontal section of the upper clamping plate 412 protrudes upward to form an upper clamping block 4121. The lower clamping plate 422 is connected to the lower fixing plate 421 through its vertical section, and the end of the horizontal section of the lower clamping plate 422 protrudes downward to form a lower clamping block 4221. The upper clamping block 4121 is engaged with the lower clamping block 4221.
[0021] In this embodiment, the upper surface of the upper clamping block 4121 and the lower surface of the lower clamping block 4221 are respectively configured as inclined surfaces that are mutually connected to facilitate the snap-fitting between the two; and the inclination angle of the inclined surface of the upper clamping block 4121 and the inclination angle of the inclined surface of the lower clamping block 4221 are both 12°.
[0022] The rotating clamp 5 is cut from a rectangular steel plate, and a circular through hole 51 is opened at the center of the rotating clamp 5. The rotating clamp 5 is installed on the ground 2 by screws; two diagonal parts of the rotating clamp 5 are respectively fixedly connected with positioning plates 52. In this embodiment, the two positioning plates 52 are respectively placed on the two long sides of the rotating clamp 5, and the positioning plates 52 are perpendicular to the rectangular steel plate. The rotating clamp 5 is connected to the lightweight partition wall 3 by screws penetrating the positioning plates 52.
[0023] In this embodiment, sound insulation cotton 6 is arranged on both sides of the hanger 4 between the top of the lightweight partition wall 3 and the roof 1; a sealing strip 7 is filled between the bottom of the lightweight partition wall 3 and the ground 2, and the two sides of the assembled wall module are covered with gypsum boards 8 respectively.
[0024] Based on the above-mentioned assembled lightweight partition wall installation structure, the specific installation method steps are as follows: S1. Determine the installation position of the upper hanger 41 on the roof 1 according to the installation position of the lightweight partition wall 3, and install the upper hanger 41 on the roof 1, and then install the lower hanger 42 on the top of the lightweight partition wall 3; when installing the upper hanger 41 and the lower hanger 42, use screws to fix the upper fixing plate 411 and the lower fixing plate 421 to the top of the roof 1 or the lightweight partition wall 3 respectively.
[0025] S2. Determine the installation position of the rotating clamp 5 according to the installation position of the lightweight partition wall 3, connect the rotating clamp 5 to the ground 2 through screws, and ensure that the rotating clamp 5 is fixed to the ground 2 but not tightened during installation, so that the rotating clamp 5 can rotate around the screws.
[0026] S3. Use a hoisting device to vertically place the lightweight partition wall 3, and then adjust the position of the rotating clamp 5 so that the rotating clamp 5 is perpendicular to the installation position of the lightweight partition wall 3.
[0027] S4. Start the lifting equipment and move the lightweight partition wall 3 to the installation position, so that the lower hanger 42 gradually approaches the upper hanger 41 until the two intersect, and continue to move the lightweight partition wall 3, so that the upper clamping block 4121 moves inward along the lower clamping block 4221 until it can no longer move inward, and then fine-tune the height of the lightweight partition wall 3 downward so that the upper clamping block 4121 is clamped with the lower clamping block 4221.
[0028] S5, rotating the rotating clamp 5 until the two positioning plates 52 are respectively attached to the front and back surfaces of the lightweight partition wall 3, and then fixing the lightweight partition wall 3 and the positioning plates 52 on both sides respectively with screws.
[0029] S6, sound insulation cotton 6 is filled between the roof 1 and both sides of the top hanging part 4 of the lightweight partition wall 3, and sealing strip 7 is filled between the lightweight partition wall 3 and the ground 2.
[0030] S7. Cover both sides of the assembled partition wall module with a layer of gypsum board 8, and the installation is completed.
[0031] The lightweight partition wall in the present invention is completed within the project. After being transported to the site, it only needs to be assembled at the installation site with the help of hangers and rotating clamps to quickly achieve the installation effect, which effectively shortens the construction period, reduces the work intensity of construction personnel, and improves the installation quality; and each lightweight partition wall is an independent module, which can be disassembled and replaced separately without affecting other lightweight partition walls and without destroying the wall, which is convenient for the maintenance and upgrading of the later building, helps the turnover use of the lightweight partition wall, and reduces the cost of secondary transformation in the later period.
[0032] The above description is only the preferred embodiment of the present invention, and does not limit the scope of rights of the present invention. All equivalent changes made by using the contents of the present invention specification and its drawings are included in the scope of rights of the present invention.
Claims
1. An assembled lightweight partition wall installation structure, comprising an assembled wall module, wherein the assembled wall module comprises a lightweight partition wall, and the lightweight partition wall is placed between a roof and a ground, and is characterized in that: It also includes hanging parts, through which the top of the lightweight partition wall is connected to the roof; sound insulation cotton is arranged on both sides of the hanging parts between the top of the lightweight partition wall and the roof; a sealing strip is filled between the bottom of the lightweight partition wall and the ground, and both sides of the assembled wall module are covered with gypsum boards.
2. The assembled lightweight partition wall installation structure according to claim 1 is characterized in that: The hanger comprises an upper hanger and a lower hanger. The upper hanger is arranged at the installation position of the roof corresponding to the lightweight partition wall, and the lower hanger is arranged on the top of the lightweight partition wall. The upper hanger is clamped with the lower hanger.
3. The assembled lightweight partition wall installation structure according to claim 2 is characterized in that: The upper hanger includes an upper fixed plate and an L-shaped upper clamping plate, and the lower hanger includes a lower fixed plate and an L-shaped lower clamping plate. The upper clamping plate is connected to the upper fixed plate through its vertical section, and the end of the transverse section of the upper clamping plate protrudes upward to form an upper clamping block; the lower clamping plate is connected to the lower fixed plate through its vertical section, and the end of the transverse section of the lower clamping plate protrudes downward to form a lower clamping block, and the upper clamping block and the lower clamping block are matched and clamped.
4. The assembled lightweight partition wall installation structure according to claim 3 is characterized in that: The upper surface of the upper clamping block and the lower surface of the lower clamping block are respectively arranged as inclined surfaces adapted to each other.
5. The assembled lightweight partition wall installation structure according to claim 4 is characterized in that: The inclination angle of the upper surface of the upper clamping block and the inclination angle of the lower surface of the lower clamping block are both 12°.
6. The assembled lightweight partition wall installation structure according to claim 1 is characterized in that: A rotating clamp is arranged at the bottom of the lightweight partition wall, and the rotating clamp is rotatably connected to the ground.
7. The assembled lightweight partition wall installation structure according to claim 6 is characterized in that: A through hole is arranged at the center of the rotating clamp, and the rotating clamp is connected to the ground via a screw passing through the through hole.
8. The assembled lightweight partition wall installation structure according to claim 7 is characterized in that: The rotating clamp is a rectangular structure, and positioning plates are respectively arranged on two opposite corners of the rotating clamp. The rotating clamp is connected to the lightweight partition wall by screws penetrating the positioning plates.
9. A method for installing an assembled lightweight partition wall, characterized in that: The assembled lightweight partition wall installation structure according to any one of claims 1 to 8 is applied, and the specific steps are as follows: S1. Determine the installation position of the upper hanging parts on the roof according to the installation position of the lightweight partition wall, install the upper hanging parts on the roof, and then install the lower hanging parts on the top of the lightweight partition wall; S2. Determine the installation position of the rotating fixture according to the installation position of the lightweight partition wall, connect the rotating fixture to the ground through screws, and ensure that the rotating fixture is fixed to the ground but not tightened, and ensure that the rotating fixture can rotate around the screws; S3. Use the hoisting equipment to place the lightweight partition wall vertically, and then adjust the position of the rotating clamp so that the rotating clamp is perpendicular to the installation position of the lightweight partition wall; S4, start the hoisting equipment, move the lightweight partition wall to the installation position, make the lower hanger gradually approach the upper hanger until the two intersect, continue to move the lightweight partition wall, make the upper clamping block move inward along the lower clamping block, until it can no longer move inward, and then fine-tune the height of the lightweight partition wall downward to make the upper clamping block engage with the lower clamping block; S5, rotating the rotating clamp until the two positioning plates are respectively attached to the front and back sides of the lightweight partition wall, and then using screws to fix the lightweight partition wall and the positioning plates on both sides respectively; S6. Fill the space between the roof and both sides of the top hanging parts of the lightweight partition wall with sound insulation cotton, and fill the space between the lightweight partition wall and the ground with sealing strips; S7. Cover both sides of the prefabricated partition wall module with a layer of gypsum board and the installation is completed.
Citation Information
Patent Citations
Pre-fabricated building removable partition, wall splicing structure, and construction method
CN105464251A
Fossil fragments and partition wall
CN207974287U
Modularized integrated wall structure
CN221502370U
Method for forming partition wall
JP1995268993A
KR20210003617A
Cited By
Assembly type partition wall system with suspended upper portion
CN224578901U