Construction method for TBM construction tunnel to penetrate through strong rockburst section rock mass
By using the method of segmented excavation and crushing belt ring formation in TBM construction, the stress in the strong rock burst rock mass is released in advance, and the rock burst problem in the strong rock burst area during TBM construction is solved, which improves construction safety and progress, and reduces project costs.
Patent Information
- Application Number
- CN202411860426.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-17
- Publication Date
- 2025-03-18
AI Technical Summary
During the TBM construction process, strong rock bursts are a very challenging problem. The existing technology is difficult to effectively prevent the occurrence of rock bursts, resulting in damage to construction equipment, threats to life safety of personnel, delays in construction progress and high project costs.
The tunnel is excavated one by one by one by one by one by sectional excavation. During the excavation of each section of the tunnel, a broken belt circle is formed in the rock mass on the top of the tunnel, the arch shoulder and the outer part of the arch waist of the tunnel. The stress in the strong rock burst is released in advance through the crushing belt circle to reduce the chance of rock burst.
By releasing stress in strong rock bursts in advance, the chance of rock bursts occur during TBM construction is reduced, construction safety is improved, construction progress is ensured, and the impact of rock bursts on construction is significantly reduced.