Dropper maintenance spraying system of ship lock foundation pit pier column
By designing an automated ship lock foundation pit pier column dropper maintenance spray system, the automatic winding maintenance of the spray pipe and plastic film is achieved using ring guide rails and unicycle, the problems of poor consistency and high labor intensity caused by manual operation in the prior art are solved, and construction efficiency and maintenance effect are improved.
Patent Information
- Application Number
- CN202411968415.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-30
- Publication Date
- 2025-03-25
- Estimated Expiration
- 2044-12-30
AI Technical Summary
In the prior art, the winding maintenance of droppers and plastic films during pier casting construction requires manual operation, resulting in poor consistency, different maintenance effects, and high labor intensity and experience requirements, and lack of automated construction solutions.
A dropper maintenance spraying system for ship lock foundation pit pier columns is designed. By laying an annular guide rail and front and rear wheel plate trucks on the cantilever formwork platform, the automatic winding maintenance of the spray pipe and plastic film is achieved. The system includes a spray pipe winding roller, a plastic film winding roller and a water tank, and uses a power motor and an air pump to adjust the water outlet rate of the spray pipe and the tensioning force of the plastic film.
The automatic winding and maintenance of droppers and plastic film is realized, ensuring the consistency of tension between the spray pipe and plastic film, reducing the labor intensity and experience requirements of manual operation, and improving construction efficiency and maintenance effect.
Smart Images

Figure CN119686325A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of concrete construction, in particular to a drip pipe maintenance spraying system for a ship lock foundation pit pier. Background Art
[0002] For a long time, cantilever formwork has been mostly used for pier casting construction. Its working principle is: the bottom of the pier formwork is fixed on the cantilever platform, and the cantilever platform is fixed on the ground or on the outer wall of the next pier that has been cast and has sufficient stress to support the overall cantilever formwork, so as to achieve step-by-step casting of the pier from top to bottom.
[0003] However, the piers need to be cured as they are poured. The existing practice is to insert and extend the drip pipe in sections on the cantilever formwork platform. As the cantilever formwork platform is cast and raised, the drip pipe is manually wound around it, and then a layer of plastic film is manually wrapped around the outer periphery of the drip pipe. Since the drip pipe is connected in sections, it is necessary to manually repeatedly plug and unplug the water supply connection between the first-level drip pipe on the cantilever formwork platform and the water tank, and the winding spacing and winding tension of the drip pipe and the plastic film are controlled by manual experience, resulting in poor consistency and inconsistent maintenance effects. In addition, the labor intensity and experience requirements of the construction personnel are relatively high.
[0004] Therefore, how to design a drip pipe maintenance spray system for the piers of the ship lock foundation pit to realize the automated construction of drip pipe and plastic film winding maintenance as the cantilever formwork platform rises has become a technical problem to be solved urgently by people in this field. Summary of the invention
[0005] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention provides a drip pipe maintenance spraying system for a ship lock foundation pit pier, which can realize the automated construction of drip pipe and plastic film winding maintenance as the cantilever formwork platform rises, and has a simple structure and is easy to implement.
[0006] In order to solve the above problems, the present invention provides a drip pipe maintenance spraying system for the pier of the ship lock foundation pit. The drip pipe maintenance spraying system is arranged on the cantilever formwork platform of the pier in a circular direction. The drip pipe maintenance spraying system is synchronously wound around the outer periphery of the pier as the cantilever formwork rises to the pier that has been cast below the cantilever formwork platform, and the plastic film covering the drip pipe and the outer wall of the pier;
[0007] The drip tube maintenance spray system includes an annular guide rail fixed on the cantilever formwork platform, and front and rear wheelbarrows sliding in the annular guide rail; the front and rear wheelbarrows are provided with a spray pipe winding roller, a water tank and a plastic film winding roller in sequence from the front end in the driving direction to the rear end in the driving direction;
[0008] The spray pipe winding roller is rotatably arranged on the front and rear wheelbarrows, and the spray pipe wound on the spray pipe winding roller is provided with spray holes at intervals; the free end of the spray pipe is blocked and fixedly wound around the outer periphery of the pier, and the middle section of the spray pipe is sealed to penetrate the water tank and immersed below the liquid level in the water tank;
[0009] The plastic film winding roller is rotatably arranged on the front and rear wheelbarrows, and the plastic film with a free end wound around it is tied and fixed on the outer periphery of the pier column;
[0010] An air pump connected to the inside and outside of the water tank is fixed on the water tank. The air pump adjusts the positive and negative pressures and pressure inside the water tank to adjust the water outlet rate from the middle section to the free end of the spray pipe.
[0011] Preferably, the front and rear wheelbarrow comprises a vehicle board, a front wheel and a rear wheel, wherein the front wheel and the rear wheel are both constrained by the side walls of the annular guide rail and are connected to the center line of the bottom surface of the vehicle board through adaptive angle adjustment.
[0012] Preferably, a plurality of wheel frames are horizontally rotatably connected to the bottom surface of the vehicle plate, and the wheel frames respectively rotatably support the front single wheel and the rear single wheel on the vertical plane, and a plurality of guide wheels are horizontally rotatably connected at the corners of the side walls of the wheel frames; the guide wheels are rotatably supported on the vertical inner wall of the annular guide rail.
[0013] Preferably, a power motor and a battery are fixedly mounted on the wheel frame supporting the rear wheel; the power motor provides rotational power for the rear wheel; and the battery supplies power to the power motor and the air pump.
[0014] The advantages of the present invention compared with the prior art are:
[0015] The drip pipe maintenance spray system of the ship lock foundation pit pier of the present invention provides circumferential movement guidance relative to the pier for the front and rear wheelbarrows through the circumferential guide rails arranged on the cantilever formwork platform, and realizes the forward and turning movement of the vehicle plate through the wheel frame under the vehicle plate that can adaptively rotate and support the front single wheel and the rear single wheel. It is not affected by the cross-sectional shape of the pier and the layout shape of the circumferential guide rail, and avoids the problem of structural self-locking of the front and rear wheelbarrows in the circumferential guide rail due to too small a turning angle.
[0016] The present invention provides a drip pipe maintenance spray system for the piers of the ship lock foundation pit. The front and rear wheelbarrows are driven by a power motor to travel in a circular guide rail. During the travel, tension is provided for the plastic film and the spray pipe wrapped around the pier, and the spray pipe winding roller and the plastic film winding roller are driven to rotate and release automatically, thereby ensuring the consistency of the tension of the spray pipe and the plastic film winding. During the construction process, the positive and negative pressures and pressure of the gas in the water tank are controlled by an air pump, thereby realizing the water supply, water stop and spray water volume control from the middle section of the spray pipe to the winding section of the spray pipe pier, realizing a spray pipe to solve the spray maintenance function of the high pier, and avoiding the problem of large workload of segment splicing spray pipes;. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or technical descriptions will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0018] Figure 1 It is a schematic diagram of the construction posture of the present invention;
[0019] Figure 2 is a side view of the present invention;
[0020] Figure 3 It is a top view of the present invention (a schematic diagram of the motion posture of the circular guide rail and the front and rear wheelbarrows);
[0021] Figure 4 It is a schematic diagram of the straight-line driving posture of the wheel frame in the present invention;
[0022] Figure 5 It is a schematic diagram of the corner driving posture of the wheel frame in the present invention;
[0023] in Figure 2 and Figure 3 The direction indicated by the middle arrow is the direction of travel of the front and rear wheelbarrows;
[0024] In the figure: 1-cantilever formwork platform; 2-circular guide rail; 3-pier column; 4-front and rear wheelbarrows; 5-plastic film; 6-spray pipe; 7-spray pipe winding roller; 8-air pump; 9-water tank; 10-plastic film winding roller; 11-battery; 12-power motor; 13-wheel frame; 14-rear wheel; 15-guide wheel; 16-front wheel; 17-carriage plate. DETAILED DESCRIPTION
[0025] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.
[0026] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0027] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0028] Combination Figure 1 to Figure 5 The present invention provides a drip pipe maintenance spraying system for a ship lock foundation pit pier, wherein the drip pipe maintenance spraying system is arranged on a cantilever formwork platform 1 of a pier 3 in a circular direction, and the drip pipe maintenance spraying system is synchronously wound around the outer periphery of the pier as the cantilever formwork rises to the pier below the cantilever formwork platform and has been cast, and a plastic film 5 covering the drip pipe and the outer wall of the pier;
[0029] The drip tube maintenance spray system includes an annular guide rail 2 fixed on the cantilever formwork platform, and front and rear wheelbarrows 4 sliding in the annular guide rail; the front and rear wheelbarrows are provided with a spray pipe winding roller 7, a water tank 9 and a plastic film winding roller 10 in sequence from the front end in the driving direction to the rear end in the driving direction;
[0030] The spray pipe winding roller is rotatably arranged on the front and rear wheelbarrows, and spray holes are arranged at intervals on the spray pipe 6 wound on the spray pipe winding roller; the free end of the spray pipe is blocked and fixedly wound around the outer periphery of the pier, and the middle section of the spray pipe is sealed to penetrate the water tank and be immersed below the liquid level in the water tank;
[0031] The plastic film winding roller is rotatably arranged on the front and rear wheelbarrows, and the plastic film with a free end wound around it is tied and fixed on the outer periphery of the pier column;
[0032] An air pump 8 communicating with the inside and outside of the water tank is fixedly arranged on the water tank, and the air pump adjusts the positive and negative pressures and the pressure inside the water tank to adjust the water outlet rate from the middle section to the free end of the spray pipe.
[0033] Preferably, the front and rear wheelbarrow comprises a vehicle plate 17, a front wheel 16 and a rear wheel 14, wherein the front wheel and the rear wheel are both constrained by the side walls of the annular guide rail and are connected to the center line of the bottom surface of the vehicle plate through adaptive rotation angle adjustment.
[0034] Preferably, a plurality of wheel frames 13 are horizontally rotatably connected to the bottom surface of the vehicle plate, and the wheel frames respectively rotatably support the front single wheel and the rear single wheel on the vertical plane, and a plurality of guide wheels 15 are horizontally rotatably connected at the corners of the side walls of the wheel frames; the guide wheels are rotatably supported on the vertical inner wall of the annular guide rail.
[0035] Preferably, a power motor 12 and a battery 11 are fixedly mounted on the wheel frame supporting the rear wheel; the power motor provides rotational power for the rear wheel; and the battery supplies power to the power motor and the air pump.
[0036] In addition, the present invention preferably adopts mature products in the prior art for the power motor and the battery, and the connection structure for the power motor to provide rotational power for the rear unicycle adopts mature technical means in the prior art.
[0037] In addition, the present invention is preferred that, since the front single wheel and the rear single wheel are both rotatably connected to the center line of the bottom surface of the vehicle board, the bottom surface of the vehicle board needs to be slidably overlapped on the top surface of the annular guide rail to maintain the balance of the vehicle board.
[0038] In addition, in the present invention, preferably, the sealing connection method of sliding seals on both sides of the water tank and penetrating and connecting the spray pipe adopts mature technical means in the prior art.
[0039] The working principle of the present invention is:
[0040] The drip pipe maintenance spraying system for the pier column of the ship lock foundation pit of the present invention, when working:
[0041] 1. Manually pull out the ends of the spray pipe and plastic film to fix the ends of the two ends to the outer wall of the pier;
[0042] 2. When the cantilever casting formwork has finished casting a section of pier and is rising, the power motor starts to drive the front and rear wheelbarrows to travel in the circular guide rail. During the driving process, the spray pipe and the plastic film are pulled, driving the spray pipe winding roller and the plastic film winding roller to rotate. According to the driving direction of the front and rear wheelbarrows and the layout position of the spray pipe winding roller and the plastic film winding roller, the spray pipe is wound on the pier, and the spray pipe and the pier are covered with plastic film.
[0043] 3. When adjusting the flow of the sprinkler pipe, the following working conditions are included:
[0044] A. Rapid spraying: The air pump is started to fill the water tank with pressurized air, and the water tank is kept at a positive pressure. The water in the compressed water tank is injected into the spray pipe through the spray hole, and then flows into the spray pipe downstream of the water tank with the water's own weight. Finally, the water is sprayed out from the spray hole of the spray pipe wrapped around the pier downstream to achieve rapid maintenance of the pier. This working condition is suitable for the initial stage of spray maintenance of the pier, or when the temperature of the construction environment is high, or when the pier is high (the cantilever formwork platform is far away from the bottom of the pier, resulting in a long spray pipe).
[0045] B. Slow drip irrigation maintenance: turn off the air pump, and the air enters the water tank from the spray hole upstream of the water tank through the spray pipe. At the same time, the water in the water tank flows from the spray hole to the spray pipe downstream of the water tank to achieve slow long-term maintenance of the pier, avoid frequent water tank refilling, and avoid excessive water spraying leading to water accumulation under the pier, which causes waste of resources;
[0046] C. Stop spraying: Start the air pump to extract the air inside the water tank. At this time, the water tank maintains a negative pressure; the gas enters the water tank through the spray holes upstream and downstream of the water tank and the spray pipe, and is then discharged by the air pump, maintaining a negative pressure in the water tank to prevent water from flowing out through the spray pipe.
[0047] The present invention and its embodiments are described above, and such description is not restrictive. The drawings show only one embodiment of the present invention, and the actual structure is not limited thereto. In short, if ordinary technicians in the field are inspired by it, without departing from the purpose of the invention, they can design a structure and embodiment similar to the technical solution without creativity, which should belong to the protection scope of the present invention.
Claims
1. A drip pipe maintenance spray system for a ship lock foundation pit pier, characterized in that: The drip tube maintenance spray system is arranged on the cantilever formwork platform of the pier column in a circular direction, and the drip tube maintenance spray system is synchronously wound around the drip tube on the outer periphery of the pier column and the plastic film covering the drip tube and the outer wall of the pier column as the cantilever formwork rises to the cast pier column below the cantilever formwork platform; The drip tube maintenance spray system comprises an annular guide rail fixed on the cantilever formwork platform, and front and rear wheelbarrows sliding in the annular guide rail; the front and rear wheelbarrows are provided with a spray pipe winding roller, a water tank and a plastic film winding roller in sequence from the front end in the driving direction to the rear end in the driving direction; The spray pipe winding roller is rotatably arranged on the front and rear wheelbarrows, and spray holes are arranged at intervals on the spray pipe wound on the spray pipe winding roller; the free end of the spray pipe is blocked and fixedly wound around the outer periphery of the pier, and the middle section of the spray pipe is sealed to penetrate the water tank and immersed below the liquid level in the water tank; The plastic film winding roller is rotatably arranged on the front and rear wheelbarrows, and the plastic film with the free end wound on the plastic film winding roller is tied and fixed on the outer periphery of the pier column; An air pump connected to the inside and outside of the water tank is fixedly arranged on the water tank, and the air pump adjusts the positive and negative pressures and pressure inside the water tank to adjust the water outlet rate from the middle section to the free end of the spray pipe.
2. The drip pipe maintenance spray system for the pier of the ship lock foundation pit according to claim 1 is characterized by: The front and rear wheelbarrow comprises a vehicle board, a front wheel and a rear wheel. The front wheel and the rear wheel are both constrained by the side walls of the annular guide rail and are connected to the center line of the bottom surface of the vehicle board through adaptive rotation angle adjustment.
3. The drip pipe maintenance spray system for the pier of the ship lock foundation pit according to claim 2 is characterized by: A plurality of wheel frames are horizontally rotatably connected to the bottom surface of the vehicle plate, and the wheel frames respectively rotatably support the front single wheel and the rear single wheel on a vertical plane, and a plurality of guide wheels are horizontally rotatably connected at the corners of the side walls of the wheel frames; the guide wheels are rotatably supported on the vertical inner wall of the annular guide rail.
4. The drip pipe maintenance spray system for the pier of the ship lock foundation pit according to claim 3 is characterized by: A power motor and a battery are fixedly arranged on the wheel frame supporting the rear unicycle; the power motor provides rotational power for the rear unicycle; and the battery supplies power to the power motor and the air pump.
Citation Information
Patent Citations
Automatic spraying maintenance device for pier column
CN114351587A
Bridge substructure concrete curing equipment and method
CN117758625A
Automatic spray curing means of pier shaft
CN208362202U
Pier stud maintenance film covering device and pier stud maintenance construction device
CN210086079U
Pier column maintenance drip irrigation device
CN218667189U
Cited By
Cantilever formwork integrated maintenance water pipe
CN121571299A