Multifunctional steel truss construction device and construction method thereof

By designing a multi-functional steel mesh construction device, including an adjustable support cylinder and an overhead platform, the problems of ball hinge installation quality and construction efficiency in steel mesh construction are solved, and more efficient and high-quality construction is achieved.

CN119900400APending Publication Date: 2025-04-29CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202510183180.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-02-19
Publication Date
2025-04-29

AI Technical Summary

Technical Problem

In steel mesh construction, it is difficult to ensure quality of the ball hinge installation, especially due to the narrow space and difficulty in installing traditional jacks, resulting in low construction efficiency and difficult to ensure installation quality of the back welding.

Method used

A multifunctional steel mesh construction device is designed, including a base plate, a support cylinder, a lifting device and an overhead platform. The installation height of the steel mesh is adjusted by the lifting device, the support cylinder height can be adjusted to support the steel mesh, and the construction personnel are flat-welded ball hinges through the overhead platform.

Benefits of technology

It realizes flexible adjustment of the installation height of the steel mesh, improves the installation quality and construction efficiency of the ball hinge, and avoids installation difficulties caused by narrow space in traditional construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119900400A_ABST
    Figure CN119900400A_ABST
Patent Text Reader

Abstract

The invention discloses a multifunctional steel net rack construction device and a construction method thereof. The construction device comprises a bottom plate, a supporting cylinder, a lifting device and an overhead platform, and the lifting device is detachably connected to the bottom plate and used for adjusting the mounting height of a steel net rack; the supporting cylinder is fixed to the bottom plate in a height-adjustable mode and used for supporting the steel net rack after the steel net rack is lifted in place, a mounting space for containing the lifting device is formed in the supporting cylinder, an extending opening for the lifting device to extend out is formed in the top end of the supporting cylinder, and the supporting cylinder is fixed to the bottom plate in a height-adjustable mode and used for supporting the steel net rack after the steel net rack is lifted in place. One side of the supporting cylinder is provided with a pick-and-place opening for putting in and taking out the lifting device, and the periphery of the top of the supporting cylinder is connected with at least one connecting lug at intervals; the overhead platform is used for a worker to install a spherical hinge on the steel net rack, one side of the overhead platform is selectively and detachably connected to the multiple connecting lugs, and the construction efficiency is improved by arranging the construction device.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a multifunctional steel grid construction device and a construction method thereof. Background Art

[0002] With the vigorous development of the construction industry, more and more large-scale factory buildings use steel grid structures for support. It is difficult to ensure the installation quality of the steel grid when it is assembled on site, especially the positioning and installation of the ball joint on the steel grid. Since the steel grid is installed on the masonry structure, when the installation elevation of the ball joint needs to be adjusted, the traditional construction method is to support multiple jacks between the steel grid and the masonry structure. However, due to the narrow space between the steel grid and the masonry structure, the installation of the jack is very difficult, and even large hoists are needed to lift the steel grid, resulting in low construction efficiency. In addition, due to the high installation height of the ball joint, the installation of the ball joint mostly adopts the overhead welding construction method, and overhead welding is the most difficult to ensure installation quality. Summary of the invention

[0003] The purpose of the present invention is to overcome the defects of the prior art and provide a multifunctional steel grid construction device and a construction method thereof, which is convenient for adjusting the installation height of the steel grid and also allows construction personnel to use flat welding when installing ball joints, thereby improving the construction quality.

[0004] To achieve the above-mentioned purpose, the technical solution adopted by the present invention is a multifunctional steel grid construction device, including a base plate, a support tube, a lifting device and an overhead platform, wherein: the lifting device is detachably connected to the base plate and is used to adjust the installation height of the steel grid; the support tube is height-adjustably fixed to the base plate, and is used to support the steel grid after the steel grid is lifted into place, and an installation space for accommodating the lifting device is formed inside the support tube, and an extension port for extending the lifting device is provided at the top of the support tube, and a receiving and placing port for placing and removing the lifting device is provided on one side of the support tube, and at least one connecting ear is connected to the top of the support tube at intervals; the overhead platform is used for personnel to install the ball joint on the steel grid, and one side of the overhead platform is selectively detachable and connected to multiple connecting ears.

[0005] A further improvement of the multifunctional steel truss construction device of the present invention is that the support cylinder includes a fixed cylinder and a plurality of movable cylinders stacked on the top of the fixed cylinder to adjust the overall height of the support cylinder, the cross-sections of the fixed cylinder and the movable cylinder are both U-shaped, the U-shaped opening of the fixed cylinder is formed as the taking and releasing port, the outer periphery of each of the movable cylinders is connected to at least one of the connecting ears, and the stacking direction of the movable cylinders on the fixed cylinder is adjustable.

[0006] A further improvement of the multifunctional steel grid construction device of the present invention is that a support rod for supporting the ground is connected to the bottom of the overhead platform, and a connecting rod is connected to one side of the overhead platform, and the connecting rod is detachably connected to the connecting ear.

[0007] A further improvement of the multifunctional steel grid construction device of the present invention is that an inverted U-shaped clip for snapping into the connecting ear is connected to the bottom of one end of the connecting rod relatively far from the overhead platform.

[0008] A further improvement of the multifunctional steel grid construction device of the present invention is that the support rod is a telescopic rod.

[0009] A construction method of a multifunctional steel grid comprises the following steps:

[0010] Step 1: providing the above-mentioned multifunctional steel grid construction device;

[0011] Step 2: Place the steel grid on top of the support tube;

[0012] Step 3: Start the lifting device to lift the steel grid to the designed installation height;

[0013] Step 4: Adjust the height of the support tube until the support tube is supported at the bottom of the steel grid;

[0014] Step 5: retract the lifting device and remove the lifting device from the access opening of the support tube;

[0015] Step 6: Connect the overhead platform to the connecting ear where the ball joint is to be installed;

[0016] Step 7: Provide a ladder, set up the ladder on the overhead platform, and have construction workers enter the overhead platform through the ladder to weld the ball joint.

[0017] Compared with the prior art, the advantages of the present invention are:

[0018] 1. By setting the support tube, the installation and disassembly of the lifting device is facilitated without affecting the jacking of the lifting device.

[0019] 2. By setting up an overhead platform, it is convenient for construction workers to stand on the overhead platform to perform flat welding on the ball joint. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0021] Figure 1 It is a structural schematic diagram of the use status of the multifunctional steel grid construction device of the present invention.

[0022] Figure 2 It is a schematic diagram of the overhead platform structure of the multifunctional steel grid construction device of the present invention.

[0023] Figure 3 It is a schematic diagram of the support tube structure of the multifunctional steel grid construction device of the present invention.

[0024] Figure 4 It is a schematic diagram of the U-shaped pad unit structure of the multifunctional steel grid construction device of the present invention.

[0025] In the figure: 1. base plate; 2. fixed cylinder; 3. lifting device; 4. movable cylinder; 5. support plate; 6. steel grid; 7. ball joint; 8. overhead platform; 9. connecting rod; 10. support rod; 11. reinforcement rod; 12. fence; 13. inverted U-shaped card; 14. U-shaped support plate; 15. connecting ear. DETAILED DESCRIPTION

[0026] The following describes the embodiments of the present invention through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention.

[0027] The multifunctional steel grid construction device and the construction method thereof of the present invention are further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0028] See also Figure 1 to Figure 4 As shown, a multifunctional steel grid construction device comprises a base plate 1, a support tube, a lifting device 3 and an overhead platform 8, wherein: the lifting device 3 is detachably connected to the base plate 1 and is used to adjust the installation height of the steel grid 6; the support tube is height-adjustably fixed to the base plate 1, and is used to support the steel grid 6 after the steel grid 6 is lifted into place, an installation space for accommodating the lifting device 3 is formed inside the support tube, a protruding opening for extending the lifting device 3 is provided at the top of the support tube, a receiving and placing opening for placing and removing the lifting device 3 is provided on one side of the support tube, and at least one connecting ear 15 is connected to the top of the support tube at intervals around it; the overhead platform 8 is used for personnel to install the ball joint 7 on the steel grid 6, and one side of the overhead platform 8 is selectively detachably connected to a plurality of the connecting ears 15.

[0029] By connecting a plurality of the connecting ears 15 at intervals around the top of the support tube, it is convenient to install the overhead platform 8 at different positions of the support tube to meet the installation requirements of the ball joint 7 at different positions.

[0030] Specifically, the bottom of the steel grid 6 is connected to a support plate 5 . When the lifting device 3 is working, it passes through the extension opening and supports the bottom of the support plate 5 to lift the steel grid 6 .

[0031] Specifically, the lifting device 3 includes a jack, which is placed on the base plate 1. When the jack is not in operation, the output end of the jack is located in the extension port.

[0032] Specifically, there are multiple support tubes, and the overall height is adjusted by stacking multiple support tubes up and down, and the lifting device 3 is detachably connected to the topmost support tube.

[0033] Preferably, the support cylinder includes a fixed cylinder 2 and a plurality of movable cylinders 4 stacked on the top of the fixed cylinder 2 to adjust the overall height of the support cylinder. The cross-sections of the fixed cylinder 2 and the movable cylinder 4 are both U-shaped. The U-shaped opening of the fixed cylinder 2 forms the taking-in and putting-out port. The outer periphery of each of the movable cylinders 4 is connected with at least one of the connecting ears 15, and the stacking direction of the movable cylinders 4 on the fixed cylinder 2 is adjustable.

[0034] The overall height of the support tube is adjusted by increasing or decreasing the number of stacked movable tubes 4. After the overall height of the support tube is adjusted, a plurality of movable tubes 4 are welded and fixed to form a whole, thereby improving the structural stability.

[0035] By adjusting the stacking direction of the fixing tube 2 , it is convenient to adjust the position of the connecting ear 15 , so that the overhead platform 8 can be connected to the designed position for flat welding of the ball joint 7 .

[0036] Specifically, a U-shaped support plate 14 is connected to the top of the fixed cylinder 2 , and a plurality of the movable cylinders 4 are stacked on the top of the U-shaped support plate 14 . The U-shaped support plate 14 overlaps with the orthographic projection of the fixed cylinder 2 .

[0037] By providing the U-shaped support plate 14 , the stability of the fixing tube 2 is improved.

[0038] Preferably, the bottom of the overhead platform 8 is connected to a support rod 10 for supporting the ground, and one side of the overhead platform 8 is connected to a connecting rod 9, and the connecting rod 9 is detachably connected to the connecting ear 15.

[0039] Specifically, a plurality of reinforcement rods 11 are connected between the support rod 10 and the connecting rod 9 .

[0040] By providing the reinforcement rod 11 , the stability of the overhead platform 8 is improved.

[0041] Specifically, a fence 12 is connected to the outer periphery of the top of the overhead platform 8 .

[0042] By providing the fence 12 , the safety of construction workers is improved when they are working on the overhead platform 8 .

[0043] Preferably, an inverted U-shaped clip 13 for clipping to the connecting ear 15 is connected to the bottom of the end of the connecting rod 9 relatively far away from the overhead platform 8 .

[0044] Preferably, the support rod 10 is a telescopic rod.

[0045] Since a plurality of movable cylinders 4 are stacked up and down, and a plurality of connecting ears 15 are located at different elevations, the overhead platform 8 can always be kept in a horizontal state by adjusting the length of the support rod 10 .

[0046] Specifically, there are two support rods 10 , and the two support rods 10 are supported to the ground in a herringbone shape.

[0047] A construction method of a multifunctional steel grid comprises the following steps:

[0048] Step 1: providing the above-mentioned multifunctional steel grid construction device;

[0049] Step 2: Place the steel grid 6 on the top of the support tube;

[0050] Step 3: Start the lifting device 3 to lift the steel grid 6 to the designed installation height;

[0051] Step 4: Adjust the height of the support tube until the support tube is supported at the bottom of the steel grid 6;

[0052] Step 5: Contract the lifting device 3 and take the lifting device 3 out of the access opening of the support tube;

[0053] Step 6: Connect the overhead platform 8 to the connecting ear 15 at the position where the ball joint 7 is to be installed;

[0054] Step 7: Provide a ladder, set the ladder on the overhead platform 8, and have the construction workers enter the overhead platform 8 through the ladder to flat-weld the ball joint 7.

[0055] Specifically, after executing the above step 4 and before executing the above step 5, the support tube is fixed to the steel grid 6 by welding.

[0056] It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the present invention, so they have no substantial technical significance. Any modification of the structure, change of the proportion relationship or adjustment of the size should still fall within the scope of the technical content disclosed by the present invention without affecting the effects and purposes that can be achieved by the present invention. At the same time, the terms such as "upper", "lower", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description, and are not used to limit the scope of the implementation of the present invention. The change or adjustment of their relative relationship should also be regarded as the scope of the implementation of the present invention without substantially changing the technical content.

[0057] The above is only a preferred embodiment of the present invention, and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technician familiar with this profession can make some changes or modifications to equivalent embodiments of equivalent changes using the technical contents disclosed above without departing from the scope of the technical solution of the present invention. However, any simple modification, equivalent change and modification made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still fall within the scope of the technical solution of the present invention.

Claims

1. A multifunctional steel grid construction device, characterized in that: It includes a base plate, a support tube, a lifting device and an overhead platform, wherein: the lifting device is detachably connected to the base plate and is used to adjust the installation height of the steel grid frame; the support tube is height-adjustably fixed to the base plate, and is used to support the steel grid frame after the steel grid frame is lifted into place, an installation space for accommodating the lifting device is formed inside the support tube, the top of the support tube is provided with an extension port for the lifting device to extend out, one side of the support tube is provided with a placement port for placing and taking out the lifting device, and at least one connecting ear is connected to the top of the support tube at intervals; the overhead platform is used for personnel to install the ball joint on the steel grid frame, and one side of the overhead platform is selectively detachable and connected to a plurality of the connecting ears.

2. The multifunctional steel grid construction device according to claim 1, characterized in that: The support tube includes a fixed tube and a plurality of movable tubes stacked on the top of the fixed tube to adjust the overall height of the support tube. The cross-sections of the fixed tube and the movable tube are both U-shaped. The U-shaped opening of the fixed tube forms the taking-in and putting-out port. The outer periphery of each of the movable tubes is connected with at least one connecting ear, and the stacking direction of the movable tubes on the fixed tube is adjustable.

3. The multifunctional steel grid construction device according to claim 1, characterized in that: The bottom of the overhead platform is connected with a support rod for supporting the ground, and one side of the overhead platform is connected with a connecting rod, and the connecting rod is detachably connected to the connecting ear.

4. The multifunctional steel grid construction device according to claim 3, characterized in that: An inverted U-shaped clip for being clipped to the connecting ear is connected to the bottom of one end of the connecting rod relatively far from the overhead platform.

5. The multifunctional steel grid construction device according to claim 3, characterized in that: The support rod is a telescopic rod.

6. A construction method of a multifunctional steel grid, characterized in that: Includes steps: Step 1: providing the multifunctional steel grid construction device as claimed in claim 1; Step 2: Place the steel grid on top of the support tube; Step 3: Start the lifting device to lift the steel grid to the designed installation height; Step 4: Adjust the height of the support tube until the support tube is supported at the bottom of the steel grid; Step 5: retract the lifting device and remove the lifting device from the access opening of the support tube; Step 6: Connect the overhead platform to the connecting ear where the ball joint is to be installed; Step 7: Provide a ladder, set up the ladder on the overhead platform, and have construction workers enter the overhead platform through the ladder to weld the ball joint.

Citation Information

Patent Citations

  • Overall jacking construction method for large-area bolt-sphere net rack

    CN105220769A

  • Photovoltaic panel auxiliary installation device for photovoltaic support and installation method thereof

    CN117800266A

  • Using method of precast beam overall releasing and tensioning device

    CN118219416A

  • Suspension type steel crawling ladder

    CN209494204U