Tunnel construction assembly line, steel arch construction method and waterproof cloth paving and hanging method
By designing a segmented tunnel construction assembly line, the lifting, suspension and walking mechanisms are used to achieve simultaneous lifting and equidistant arrangement of multiple steel arch frames, solving the problems of low construction efficiency and high control difficulty caused by lifting one by one, and achieving efficient, stable and safe tunnel construction.
Patent Information
- Application Number
- CN202510139337.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-08
- Publication Date
- 2025-05-02
AI Technical Summary
Since the steel arch frame adopts a one-by-one lifting installation mode, the existing tunnel construction assembly line has low efficiency in tunnel construction and high control difficulty, which affects the overall construction efficiency.
A tunnel construction assembly line is designed, including steel arch frame module, arch trench module, tarp laying module, cast lining module, maintenance module and groove formwork module. Through the cooperation of lifting mechanism, suspension mechanism and walking mechanism, multiple steel arch frames are lifted and arranged equidistantly, improving construction efficiency.
Through segmented construction and modular design, the palm surface construction efficiency and overall tunnel construction propulsion speed are improved, the time and difficulty of lifting operations are reduced, and the stability and safety of construction are improved.
Smart Images

Figure CN119914326A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel construction, and in particular to a tunnel construction assembly line, a steel arch construction method and a waterproof cloth laying method. Background Art
[0002] Tunnel engineering is an important part of modern infrastructure construction and is widely used in highways, railways, subways, water conservancy, energy and other fields. With the acceleration of urbanization and the increase in transportation demand, the demand for tunnel construction is also growing. In order to improve efficiency, tunnels usually have multiple sections to carry out tunnel construction with different processes to form an overall tunnel construction line to obtain higher comprehensive construction efficiency.
[0003] In a tunnel, the construction efficiency of the face is the core of the overall tunnel construction advancement efficiency. However, at present, the construction of the face steel arch frame still uses cranes or other lifting equipment to lift each section of the steel arch frame into place one by one, which is inefficient. In addition, in order to control the stability of the tunnel face construction support, the lifting personnel are required to actively control the spacing between the steel arch frames after lifting, which leads to slow lifting operations and high control difficulty, affecting the construction efficiency of the entire tunnel construction line. Summary of the invention
[0004] In view of this, it is necessary to provide a tunnel construction assembly line to solve the technical problem in the prior art that the tunnel construction assembly line adopts a one-by-one hoisting installation mode for the steel arch frame, which affects the efficiency of tunnel construction.
[0005] To achieve the above technical objectives, in a first aspect, the technical solution of the present invention provides a tunnel construction production line, comprising: a steel arch frame module, an inverted arch bridge module, a waterproof cloth laying module, a pouring lining module, a maintenance module and a trench template module which are set up in sections along the tunnel drilling direction, and are respectively used for the erection of the steel arch frame, the construction of the inverted arch bridge, the laying of waterproof cloth, the pouring of lining, the concrete maintenance and the trench construction;
[0006] The steel arch frame module includes a lifting mechanism, a suspension mechanism and a walking mechanism. The suspension mechanism is provided with a plurality of rotatable hooking parts for hooking the steel arch frame. The movable end of the lifting mechanism is movably connected with the suspension mechanism, and enables it to have a first position state of hooking the steel arch frame and tilting and stacking, and a second position state of hooking the steel arch frame and lifting it to an equidistant vertical position. The walking mechanism is used to drive the suspension mechanism to move along the axial direction of the tunnel in the second position state.
[0007] Furthermore, the waterproof cloth laying and hanging module includes a basic construction frame and a rolling mechanism. The rolling mechanism is installed on the basic construction frame and can move axially along the basic construction frame toward the tunnel, so as to roll the waterproof cloth along the inner circular surface of the tunnel.
[0008] Furthermore, the rolling mechanism includes a linear drive component, a guide frame, a rotary drive component and a laying roller. The linear drive component is installed on both sides of the foundation construction frame, the guide frame is installed between the movable ends of the two linear drives, and the rotary drive component is installed on the guide frame. The movable end of the rotary drive component is connected to the laying roller to drive the laying roller to roll the waterproof cloth along the inner circular surface of the tunnel.
[0009] Furthermore, the suspension mechanism includes a lifting base and a suspension frame, the hook portion is rotatably connected to the suspension frame, the suspension frame is detachably mounted on the lifting base, and the hook portion is U-shaped and is used to be mounted on the bottom of the dome of the steel arch frame.
[0010] Furthermore, the casting lining module includes a lining casting platform, and multiple layers of windows are provided on both sides of the lining casting platform, and casting pipelines are provided corresponding to each layer of windows from top to bottom for simultaneous casting on both sides.
[0011] Furthermore, the inverted arch trestle module includes an inverted arch casting platform and a vehicle turning platform arranged along the tunnel drilling direction. The inverted arch casting platform is used for gradually casting from the middle to both sides. The vehicle turning platform is connected with the top of the inverted arch casting platform and is used for the concrete pouring vehicle to drive to the top of the inverted arch casting platform to supply concrete to the dual-channel casting mechanism. The vehicle turning platform is provided with a rotating table for rotating the direction to turn the concrete pouring vehicle around.
[0012] Furthermore, the maintenance module includes a trolley body, a transverse movement mechanism and a spray mechanism. The transverse movement mechanism is installed on the top of the trolley body, and the movable end of the transverse movement mechanism is connected to the spray mechanism to drive the spray mechanism to perform reciprocating spray maintenance along the axial direction of the tunnel.
[0013] Furthermore, the groove formwork module includes a traveling vehicle body, a lifting mechanism and a groove steel formwork, the lifting mechanism is installed on both sides of the traveling vehicle body, and the groove steel formwork is connected to the movable end of the lifting mechanism one by one for groove casting and forming.
[0014] In a second aspect, the present invention further provides a steel arch construction method, which is used in any of the tunnel construction lines described above, comprising the following steps:
[0015] S1. Before the construction of the steel arch frame, it is pre-installed on the suspension mechanism and stacked in an inclined manner. The suspension mechanism is used as the carrier of the steel arch frame to transport it to the tunnel face area;
[0016] S2. During the construction of the steel arch frame, the steel arch frame is located in a first position state, in an inclined stacked state, and the suspension mechanism is lifted from the first position state to the second position state by the lifting mechanism, so that the steel arch frame is vertically erected at equal distances;
[0017] S3. In the second position state, the movable end of the walking mechanism is connected to the suspension mechanism, and multiple steel arch frames are arranged equidistantly and fed toward the tunnel face at the same time until they move to the corresponding construction position and cooperate with manual labor for subsequent construction.
[0018] In a third aspect, the present invention further provides a method for laying and hanging a waterproof cloth, which is used in any of the tunnel construction lines described above, and comprises the following steps:
[0019] S1. In the initial state, the rolling mechanism is placed outside the foundation construction frame and the waterproof cloth is rolled for the first time;
[0020] S2. After rolling the first waterproof cloth, the rolling mechanism moves toward the tunnel face relative to the foundation construction frame, and the workers reinforce the first rolled waterproof cloth on the foundation construction frame;
[0021] S3, when the rolling mechanism moves to the outside of the foundation construction frame, the second rolling of the waterproof cloth is carried out, and the reinforcement of the previously rolled waterproof cloth is carried out simultaneously;
[0022] S4. After the second waterproof sheet is rolled out, the foundation construction frame and the rolling mechanism move synchronously, moving outside the range of the last waterproof sheet laying, and the workers on the foundation construction frame perform preliminary reinforcement after the waterproof sheet is rolled out along the axial direction of the tunnel as the movement proceeds;
[0023] S5. When the rolling mechanism moves out of the range of the last tarpaulin laying, the next tarpaulin laying operation is carried out. At the same time, the workers will improve the reinforcement on the foundation construction frame based on the preliminary reinforcement during the moving process.
[0024] Compared with the prior art, the present invention has the following beneficial effects: segmented tunnel construction is constructed by means of a steel arch frame module, an inverted arch trestle module, a waterproof cloth laying module, a pouring lining module, a maintenance module and a trench formwork module, and a lifting mechanism, a hanging mechanism and a walking mechanism cooperate in the steel arch frame module to form a plurality of steel arch frames that are lifted simultaneously, and after lifting, they are arranged equidistantly, and the equidistant arrangement is maintained and moved to a fixed position, thereby improving the construction efficiency of the heading face and improving the overall tunnel construction advancement speed. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 is a schematic structural diagram of a tunnel construction line according to an embodiment of the present invention;
[0026] Figure 2is a schematic structural diagram of a first position state of a steel arch frame module according to an embodiment of the present invention;
[0027] Figure 3 is a schematic structural diagram of a second position state of a steel arch frame module according to an embodiment of the present invention;
[0028] Figure 4 is a structural schematic diagram of the steel arch frame module according to an embodiment of the present invention moving along the axial direction of the tunnel in the second position state;
[0029] Figure 5 is a schematic diagram of the overlapping structure of the waterproof cloth laying and hanging module according to an embodiment of the present invention;
[0030] Figure 6 2 is a schematic diagram of the separated structure of the waterproof cloth laying and hanging module according to an embodiment of the present invention;
[0031] In the figure: 1. Steel arch frame module; 11. Lifting mechanism; 12. Suspension mechanism; 121. Hooking part; 122. Base; 123. Suspension frame; 13. Walking mechanism; 101. Steel arch frame; 2. Inverted arch trestle module; 21. Inverted arch casting platform; 22. Vehicle turning platform; 221. Rotating table; 3. Waterproof cloth laying module; 31. Foundation construction frame; 32. Rolling mechanism; 321. Linear drive; 322. Guide frame; 323. Rotating drive; 324. Laying roller; 4. Casting lining module; 41. Lining casting platform; 42. Window; 5. Maintenance module; 51. Trolley body; 52. Transverse movement mechanism; 53. Spraying mechanism; 6. Grooved formwork module; 61. Traveling body; 62. Lifting mechanism; 63. Grooved steel formwork. DETAILED DESCRIPTION
[0032] The preferred embodiments of the present invention are described in detail below in conjunction with the accompanying drawings, wherein the accompanying drawings constitute a part of this application and are used together with the embodiments of the present invention to illustrate the principles of the present invention, but are not used to limit the scope of the present invention.
[0033] like Figure 1-4As shown, the present invention provides a tunnel construction production line, including: a steel arch frame module 1, an inverted arch bridge module 2, a waterproof cloth laying module 3, a casting lining module 4, a maintenance module 5 and a groove template module 6 which are set up in sections along the tunnel drilling direction, respectively used for the erection of the steel arch frame, the construction of the inverted arch bridge, the laying of waterproof cloth, the casting lining, the concrete maintenance and the groove construction, and the section-by-section construction is carried out. In addition, in order to improve the overall tunnel construction efficiency, the steel arch frame module 1 includes a lifting mechanism 11, a hanging mechanism 12 and a walking mechanism 13. The hanging mechanism 12 has a plurality of rotatable hooking parts 121 for hooking the steel arch frame. The movable end of the lifting mechanism 11 is movably connected to the hanging mechanism 12, and has the function of hooking the steel arch frame and tilting and stacking. The first position state, and the second position state of hooking the steel arch frame and lifting it to an equidistant vertical state, the walking mechanism 13 is used to drive the suspension mechanism 12 to move along the tunnel axis in the second position state, that is, with the cooperation of the lifting mechanism 11, the suspension mechanism 12 and the walking mechanism 13, multiple steel arch frames are lifted at the same time, and after lifting, they are arranged equidistantly, and the equidistant arrangement is maintained to move to a fixed position. The above structure and operation method avoid the slow progress caused by lifting the steel arch frames one by one, and after lifting, multiple steel arch frames are arranged equidistantly at the same time, forming a position restriction, and there is no need to perform additional slow lifting and moving during lifting to control the interval spacing, and measure and control the spacing. When moving to a fixed position, the moving speed can be increased and efficiently positioned to a fixed position. In addition, in the first position state, the steel arch frames are stacked in an inclined manner, saving space, and when loaded on the suspension mechanism 12, there is no need to lift too high a height, saving loading time. In addition, the use of a structure with direct support at the bottom prevents the steel arch from having a large shaking amplitude. Compared with lifting and moving by hoisting, it has higher stability and is less likely to collide with the rock wall, reducing the probability of causing dangerous accidents. It has the advantages of high efficiency and safety in the construction of the face.
[0034] It can be understood that the lifting mechanism 11 , the suspension mechanism 12 and the traveling mechanism 13 are all installed on the trolley body, forming the main construction equipment of the steel arch frame module 1 .
[0035] In one embodiment, to improve the efficiency of laying and hanging waterproof cloth, please refer to Figure 5 and Figure 6The waterproof cloth laying module 3 includes a basic construction frame 31 and a rolling mechanism 32. The rolling mechanism 32 is installed on the basic construction frame 31 and can move along the basic construction frame 31 toward the tunnel axis to roll the waterproof cloth along the inner circular surface of the tunnel. In the traditional operation mode, after laying the waterproof cloth, it is necessary to manually reinforce the waterproof cloth on the basic construction frame 31, while the traditional waterproof cloth rolling structure directly rolls back and forth on the outside of the basic construction frame 31, which is easy to interfere with the operating area reinforced by the workers, and has unsafe factors. In addition, after laying the waterproof cloth in an area, it needs to be moved. During the movement, the construction is stagnant and there is room for improvement in efficiency. Therefore, the foundation construction frame 31 is the main body, and the rolling mechanism 32 can slide along the foundation construction frame 31 and be positioned separately. At this time, after the first laying, it can slide and move outside the foundation construction frame 31 to avoid overlapping, which will interfere with the previous reinforcement during the next laying, and the previous reinforcement and the next laying can be carried out at the same time. In addition, the foundation construction frame 31 and the rolling mechanism 32 move at the same time. During the movement, since there is no rolling mechanism 32 to block the foundation construction frame 31, workers can perform preliminary reinforcement of the next laying of waterproof cloth during the movement. While improving construction safety, construction efficiency is also improved.
[0036] Furthermore, in order to achieve the purpose of enabling the rolling mechanism 32 to move along the foundation construction frame 31, the rolling mechanism 32 includes a linear drive 321, a guide frame 322, a rotary drive 323 and a laying roller 324. The linear drive 321 is installed on both sides of the foundation construction frame 31, the guide frame 322 is installed between the movable ends of the two linear drives 321, and the rotary drive 323 is installed on the guide frame 322, and its movable end is connected to the laying roller 324, which is used to drive the laying roller 324 to roll the waterproof cloth along the inner circular surface of the tunnel.
[0037] It can be understood that the linear drive component 321 can adopt a linear drive structure such as a screw guide rail, a hydraulic mechanism, etc.; the rotary drive component 323 adopts the industry's traditional double-layer compound track and double-row chain drive to move the laying roller 324 along the guide frame 322 to form a circular paving movement around the tunnel.
[0038] In a certain embodiment, in order to facilitate the replacement of the suspension mechanism 12 and form the transportation, installation and supply of multiple batches of steel arch frames, the suspension mechanism 12 includes a lifting base 122 and a suspension frame 123, the hook portion 121 is rotatably connected to the suspension frame 123, the suspension frame 123 is detachably installed on the lifting base 122, and the hook portion 121 is U-shaped and is used to be mounted on the bottom of the dome of the steel arch frame, wherein the number of suspension frames 123 and hook portions 121 is determined according to the number of steel arch frames that need to be installed simultaneously in a batch, and after the steel arch frame is installed and fixed, the lifting base 122 is lowered in height, and after being detached from the steel arch frame socket position, it can be detached from the steel arch frame after cooperating with the walking mechanism 13 to be translated and driven, and then separated.
[0039] It can be understood that the suspension frame 123 can be disassembled from the lifting base 122, and the steel arch frame can be installed on the suspension frame 123 for transportation, and then hoisted onto the lifting base 122, which can form a quick replacement and carry out the next wave of steel arch frame installation. After being installed in an open area outside the tunnel, it can be directly transported to the heading face to avoid the inconvenience of operation in the tunnel, thereby further improving the construction efficiency.
[0040] In one embodiment, to facilitate lining pouring, please refer to Figure 1 The casting lining module 4 includes a lining casting platform 41. Multiple layers of windows 42 are provided on both sides of the lining casting platform 41. A casting pipeline is provided corresponding to each layer of windows 42 from top to bottom for simultaneous casting on both sides. The casting efficiency is improved by casting on both sides of the layers and windows at the same time, and the problems of segregation and herringbone slope cold joints during casting are solved. The casting pipeline is passed into concrete from bottom to top in sequence according to the layers to form casting.
[0041] In one embodiment, in order to facilitate the construction of the inverted trestle, please refer to Figure 1 The inverted arch trestle module 2 includes an inverted arch pouring platform 21 and a vehicle turning platform 22 arranged along the tunnel drilling direction. The inverted arch pouring platform 21 is used for gradually pouring from the middle to both sides, and is equipped with a tamping mechanism to ensure the pouring quality. The vehicle turning platform 22 is connected with the top of the inverted arch pouring platform 21, and is used for the concrete pouring vehicle to drive to the top of the inverted arch pouring platform 21 to supply concrete to the double-channel pouring mechanism. A rotating table 221 is provided on the vehicle turning platform 22, which is used to rotate the direction to make the concrete pouring vehicle turn around.
[0042] In one embodiment, for ease of maintenance, please refer to Figure 1The maintenance module 5 includes a trolley body 51, a transverse mechanism 52 and a spray mechanism 53. The transverse mechanism 52 is installed on the top of the trolley body 51. The movable end of the transverse mechanism 52 is connected to the spray mechanism 53 to drive the spray mechanism 53 to perform reciprocating spray maintenance along the axial direction of the tunnel. The trolley body 51 can move in the tunnel, and the transverse mechanism 52 is used for the spray mechanism 53 to perform reciprocating atomizing spray maintenance along the length direction of the tunnel. The spray mechanism 53 is composed of an arc-shaped bracket and atomizing nozzles evenly distributed thereon.
[0043] In one embodiment, to facilitate trench construction, refer to Figure 1 The groove template module 6 includes a walking body 61, a lifting mechanism 62 and a groove steel template 63. The lifting mechanism 62 is installed on both sides of the walking body 61. The groove steel template 63 is connected to the movable end of the lifting mechanism 62 one by one for groove casting and forming. The lifting mechanism 62 is used to lower the groove steel template 63 for casting and forming, and the lifting mechanism 62 is used to lift the groove steel template 63 for demoulding, which can improve the efficiency of groove construction.
[0044] In a second aspect, the present invention further provides a steel arch construction method, which is used in the tunnel construction line described in any one of the above embodiments, comprising the following steps:
[0045] S1. Before the construction of the steel arch frame, it is pre-installed on the suspension mechanism 12 and stacked in an inclined manner, and the suspension mechanism 12 is used as a carrier of the steel arch frame to transport it to the tunnel face area;
[0046] S2. During the construction of the steel arch frame, the steel arch frame is located in a first position state, in an inclined stacked state, and the suspension mechanism 12 is lifted from the first position state to the second position state by the lifting mechanism 11, so that the steel arch frame is equidistantly erected;
[0047] S3. In the second position state, the movable end of the walking mechanism 13 is connected to the suspension mechanism 12, and multiple steel arch frames are arranged equidistantly and fed toward the tunnel face at the same time until they are moved to the corresponding construction position, and subsequent construction is carried out in cooperation with manual labor.
[0048] Furthermore, the suspension mechanism 12 is composed of a lifting base 122 and a suspension frame 123. After the steel arch frame is installed and fixed, the lifting base 122 is lowered in height, and after being detached from the socket position of the steel arch frame, it can be detached from the steel arch frame after being driven by the walking mechanism 13 for translation, and then separated.
[0049] Furthermore, in the subsequent replenishment of the steel arch frame, after the steel arch frame is installed in an open area outside the tunnel with another transport suspension frame 123, it is directly transported to the heading face and hoisted onto the lifting base 122, so that the steel arch frame can be quickly replenished for the next batch of construction.
[0050] In a third aspect, the present invention further provides a method for laying and hanging a waterproof cloth, which is used in the tunnel construction line according to any one of claims 2 to 8, and comprises the following steps:
[0051] S1, in the initial state, the rolling mechanism 32 is sleeved on the outside of the foundation construction frame 31, and the waterproof cloth is rolled for the first time;
[0052] S2, after rolling and spreading the first waterproof cloth, the rolling mechanism 32 moves toward the tunnel face relative to the foundation construction frame 31, and the workers reinforce the first rolled and spread waterproof cloth on the foundation construction frame 31;
[0053] S3, when the rolling mechanism 32 moves to the outside of the foundation construction frame 31, the second rolling of the waterproof cloth is carried out, and the reinforcement of the previously rolled waterproof cloth is carried out simultaneously;
[0054] S4, after the second waterproof cloth is rolled, the foundation construction frame 31 and the rolling mechanism 32 move synchronously, moving outside the range of the last waterproof cloth laying, and the workers on the foundation construction frame 31 perform preliminary reinforcement after the waterproof cloth is rolled along the axial direction of the tunnel as the movement moves;
[0055] S5. When the rolling mechanism 32 moves out of the last waterproof cloth laying range, the next waterproof cloth laying action is carried out, and the workers simultaneously carry out reinforcement improvement on the foundation construction frame 31 based on the preliminary reinforcement during the moving process.
[0056] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed by the present invention should be covered within the protection scope of the present invention.
Claims
1. A tunnel construction line, characterized in that: include: The steel arch frame module, inverted arch bridge module, waterproof cloth laying module, casting lining module, maintenance module and trench formwork module are set up in sections along the tunnel drilling direction, which are used for the erection of steel arch frame, construction of inverted arch bridge, laying of waterproof cloth, casting lining, concrete maintenance and trench construction respectively; The steel arch frame module includes a lifting mechanism, a suspension mechanism and a walking mechanism. The suspension mechanism is provided with a plurality of rotatable hooking parts for hooking the steel arch frame. The movable end of the lifting mechanism is movably connected with the suspension mechanism, and enables it to have a first position state of hooking the steel arch frame and tilting and stacking, and a second position state of hooking the steel arch frame and lifting it to an equidistant vertical position. The walking mechanism is used to drive the suspension mechanism to move along the axial direction of the tunnel in the second position state.
2. The tunnel construction line according to claim 1, characterized in that: The waterproof cloth laying module includes a basic construction frame and a rolling mechanism. The rolling mechanism is installed on the basic construction frame and can move along the basic construction frame toward the tunnel axis for rolling the waterproof cloth along the inner circular surface of the tunnel.
3. The tunnel construction line according to claim 2, characterized in that: The rolling mechanism includes a linear drive, a guide frame, a rotary drive and a laying roller. The linear drive is installed on both sides of the foundation construction frame. The guide frame is installed between the movable ends of the two linear drives. The rotary drive is installed on the guide frame, and its movable end is connected to the laying roller to drive the laying roller to roll the waterproof cloth along the inner circular surface of the tunnel.
4. The tunnel construction line according to claim 3, characterized in that: The suspension mechanism comprises a lifting base and a suspension frame, the hook part is rotatably connected to the suspension frame, the suspension frame is detachably mounted on the lifting base, and the hook part is U-shaped and is used to be sleeved on the dome bottom of the steel arch frame.
5. The tunnel construction line according to claim 4, characterized in that: The casting lining module comprises a lining casting platform, and multiple layers of windows are arranged on both sides of the lining casting platform, and casting pipelines are arranged corresponding to each layer of windows from top to bottom for simultaneous casting on both sides.
6. The tunnel construction line according to claim 5, characterized in that: The inverted arch trestle module includes an inverted arch pouring platform and a vehicle turning platform arranged along the tunnel drilling direction. The inverted arch pouring platform is used for gradually pouring from the middle to both sides. The vehicle turning platform is connected with the top of the inverted arch pouring platform and is used for the concrete pouring vehicle to drive to the top of the inverted arch pouring platform to supply concrete to the double-channel pouring mechanism. The vehicle turning platform is provided with a rotating table for rotating the direction to make the concrete pouring vehicle turn around.
7. The tunnel construction line according to claim 6, characterized in that: The maintenance module includes a trolley body, a transverse movement mechanism and a spray mechanism. The transverse movement mechanism is installed on the top of the trolley body. The movable end of the transverse movement mechanism is connected to the spray mechanism to drive the spray mechanism to perform reciprocating spray maintenance along the axial direction of the tunnel.
8. The tunnel construction line according to claim 7, characterized in that: The groove template module includes a traveling vehicle body, a lifting mechanism and a groove steel template. The lifting mechanism is installed on both sides of the traveling vehicle body. The groove steel templates are connected to the movable ends of the lifting mechanism one by one for groove casting and forming.
9. A steel arch construction method, characterized in that: The tunnel construction line according to any one of claims 1 to 8 comprises the following steps: S1. Before the construction of the steel arch frame, it is pre-installed on the suspension mechanism and stacked in an inclined manner. The suspension mechanism is used as the carrier of the steel arch frame to transport it to the tunnel face area; S2. During the construction of the steel arch frame, the steel arch frame is located in a first position state, in an inclined stacked state, and the suspension mechanism is lifted from the first position state to the second position state by the lifting mechanism, so that the steel arch frame is vertically erected at equal distances; S3. In the second position state, the movable end of the walking mechanism is connected to the suspension mechanism, and multiple steel arch frames are arranged equidistantly and fed toward the tunnel face at the same time until they move to the corresponding construction position and cooperate with manual labor for subsequent construction.
10. A method for laying and hanging a waterproof cloth, characterized in that: The tunnel construction line according to any one of claims 2 to 8 comprises the following steps: S1. In the initial state, the rolling mechanism is placed outside the foundation construction frame and the waterproof cloth is rolled for the first time; S2. After rolling the first waterproof cloth, the rolling mechanism moves toward the tunnel face relative to the foundation construction frame, and the workers reinforce the first rolled waterproof cloth on the foundation construction frame; S3, when the rolling mechanism moves to the outside of the foundation construction frame, the second rolling of the waterproof cloth is carried out, and the reinforcement of the previously rolled waterproof cloth is carried out simultaneously; S4. After the second waterproof sheet is rolled out, the foundation construction frame and the rolling mechanism move synchronously, moving outside the range of the last waterproof sheet laying, and the workers on the foundation construction frame perform preliminary reinforcement after the waterproof sheet is rolled out along the axial direction of the tunnel as the movement proceeds; S5. When the rolling mechanism moves out of the range of the last tarpaulin laying, the next tarpaulin laying operation is carried out. At the same time, the workers will improve the reinforcement on the foundation construction frame based on the preliminary reinforcement during the moving process.