Small-sized modularized support for pre-buried process pipeline and construction method of small-sized modularized support

By adopting small modular brackets and construction methods in pipeline construction, the pollution and installation difficulties caused by cross-construction are solved, and a better construction environment and weld quality are achieved, and the construction period is shortened.

CN119957730APending Publication Date: 2025-05-09CHINA NUCLEAR IND FIFTH CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411940743.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-26
Publication Date
2025-05-09

AI Technical Summary

Technical Problem

The existing technology has cross-construction in pipeline construction, which may cause pipeline pollution and installation difficulties. The on-site welds require non-destructive testing, and there are uncontrollable factors.

Method used

The small modular brackets and construction methods of the pre-embedded pipeline are adopted. By modular assembly of pipelines at the assembly site, the combined structure of columns, beams and pipe cards is used to realize the positioning and fixing of the pipelines, reducing the complexity of on-site installation.

Benefits of technology

The construction environment is improved, the risk of contamination of pipeline installation on site is reduced, the welds are completed at the assembly site, the quality of welds is improved, the demand for on-site filming windows is reduced, and the construction period is shortened.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119957730A_ABST
    Figure CN119957730A_ABST
Patent Text Reader

Abstract

The invention discloses a small-sized modularized support for pre-burying a process pipeline and a construction method thereof, and the small-sized modularized support comprises two stand columns, a cross beam and a pipe clamp, the two ends of the cross beam are installed on the two stand columns in a sliding mode. The pipe clamp is arranged in a U shape, and the two ends of the pipe clamp are installed on the cross beam in a sliding mode. According to the application of the small-sized modularized support for the pre-buried process pipeline and the construction method of the small-sized modularized support, the small-sized modularized installation method for the pre-buried process pipeline is utilized, pipeline modularized assembly is carried out on an assembly site, the construction environment is improved, the situation that the pipeline is polluted during site installation is reduced or avoided, and the construction efficiency is improved. Welding seams are completed in an assembling site, the construction environment is better, the welding seam quality can be improved, and the requirement for on-site shooting windows is reduced; construction and assembly can be conducted in advance, the situation of personnel accumulation at the same operation point is greatly avoided, and the on-site cross construction time with civil engineering is shortened; the overall work efficiency is improved and the construction period is effectively shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field related to pipeline construction, and in particular to a small modular bracket for pre-buried process pipelines and a construction method thereof. Background Art

[0002] The normal construction logic of CAP1000 pre-buried pipelines is to prefabricate process pipe sections, tie lower-layer steel bars, install prefabricated process pipelines, and finally tie upper-layer steel bars. Since the upper and lower-layer steel bars are tied continuously, there is not much window for installing pre-buried pipelines after the lower-layer steel bars are tied. The steel bar tying and process pipeline installation are concentrated in one time period, and there is cross-construction, which may cause pipeline pollution and installation difficulties. At the same time, since the process pipelines are equipped with some on-site welds, the welds need non-destructive testing, there are uncontrollable factors, and the on-site construction time is uncontrollable. Summary of the invention

[0003] In view of this, in order to solve the above problems, the object of the present invention is to provide a small modular bracket for pre-buried process pipelines, characterized in that it includes:

[0004] Two columns, beam, pipe clamp;

[0005] The two ends of the crossbeam are slidably mounted on the two upright posts;

[0006] The pipe clamp is arranged in a "U" shape, and both ends of the pipe clamp are slidably mounted on the cross beam.

[0007] The above-mentioned small modular bracket for pre-buried process pipelines is characterized in that a base is installed at the bottom end of each of the columns.

[0008] The above-mentioned small modular bracket for pre-buried process pipelines is characterized in that each of the columns is provided with a waist hole in the longitudinal direction, and the crossbeam is slidably installed in the two waist holes through a bolt pair.

[0009] The above-mentioned small modular bracket for pre-buried process pipelines is characterized in that two mounting holes are provided on the crossbeam, and the two ends of the pipe clamp are slidably installed in the two mounting holes.

[0010] A construction method for a small modular bracket for pre-buried process pipelines, characterized in that it comprises the above-mentioned small modular bracket for pre-buried process pipelines,

[0011] Step 1: According to the scope of the pre-buried pipelines in the construction area, according to the pipelines in the same plane or the same vertical plane, and the actual hoisting space on site, several modularizable ranges are divided, and the design coordinate points are set within the modularizable ranges;

[0012] Step 2: According to the divided modular ranges, prefabricate several pipeline segments in the workshop and assemble them in the construction area. Select a relative positioning point and coordinate system direction on any pipeline segment, corresponding to the design coordinate point, set the inflection point position on the pipeline segment, and mark it;

[0013] Step 3: placing the pipe section in step 2 on the beams of the plurality of brackets, fixing the pipe section with the pipe clamps of the plurality of brackets, adjusting the relative position of the beam relative to the two columns, and adjusting the relative position of the pipe clamp relative to the beam;

[0014] Step 4: Assemble the remaining pipeline segments with the pipeline segment in step 3 through the inflection point of the laying-out to form a modular pipeline;

[0015] Step 5: According to the size and shape of the modular pipeline, several lifting points are set on the modular pipeline, and lifting analysis is performed. When the on-site conditions are met, the modular pipeline is lifted;

[0016] Step six: Place the modular pipeline into the modular range.

[0017] The above-mentioned construction method of a small modular bracket for pre-buried process pipelines is characterized in that in step one, a BIM model is used to analyze and divide several modularizable ranges in advance.

[0018] The above-mentioned construction method of a small modular bracket for pre-buried process pipelines also includes the following steps between step four and step five: re-measure the assembled modular pipeline as a whole to ensure that the position errors of the endpoints and the turning points of the layout are within the range of design requirements.

[0019] The above-mentioned construction method of a small modular bracket for pre-buried process pipelines also includes the following steps after step six: re-testing and fixing the modular pipelines placed in the modular range to ensure that the final installation position of the modular pipelines is within the design allowable error range.

[0020] Compared with the prior art, the above technical solution has the following positive effects:

[0021] Through the application of the present invention, a small modular bracket for pre-buried process pipelines and a construction method thereof are provided. The present invention utilizes the small modular installation method for pre-buried process pipelines to perform modular assembly of pipelines at an assembly site, thereby improving the construction environment, reducing or avoiding the contamination of pipelines during on-site installation, and completing the welds at the assembly site. The construction environment is better, which is conducive to improving the quality of welds and reducing the need for on-site filming windows. The assembly can be carried out in advance, which greatly avoids the accumulation of personnel at the same work point and shortens the cross-construction time with civil engineering at the site. The overall work efficiency is improved and the construction period is effectively shortened. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 Schematic diagram of modular pipeline in the present invention.

[0023] Figure 2 It is a schematic diagram of a small modular bracket for pre-buried process pipelines in the present invention.

[0024] Figure 3 It is a side view of a small modular bracket for pre-buried process pipelines in the present invention.

[0025] Figure 4 for Figure 2 Magnified image of AA.

[0026] 1. Column; 2. Beam; 3. Pipe clamp; 4. Base; 5. Waist hole; 6. Bolt pair; 7. Pipe section; 8. Modular pipeline. DETAILED DESCRIPTION

[0027] The present invention will be further described below in conjunction with the accompanying drawings and specific implementations, but they are not intended to limit the present invention.

[0028] The structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the present invention, so they have no substantial technical significance. Any modification of the structure, change of the proportional relationship or adjustment of the size, without affecting the effects and purposes that can be achieved by the present invention, should still fall within the scope of the technical contents disclosed by the present invention. At the same time, the terms such as "upper", "lower", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description, and are not used to limit the scope of the implementation of the present invention. The change or adjustment of their relative relationship should also be regarded as the scope of the implementation of the present invention without substantially changing the technical contents.

[0029] like Figures 1 to 4 As shown, a small modular bracket for pre-buried process pipelines according to a preferred embodiment is shown, which includes: two columns 1, a cross beam 2, and a pipe clamp 3.

[0030] The two ends of the cross beam 2 are slidably mounted on the two upright columns 1 ; the pipe clamp 3 is arranged in a "U" shape, and the two ends of the pipe clamp 3 are slidably mounted on the cross beam 2 .

[0031] In actual use, the main pipeline 7 is placed on the cross beam 2, the cross beam 2 supports the main pipeline 7, and the pipe clamp 3 can fix the main pipeline 7 placed on the cross beam 2. The two columns 1 and the cross beam 2 are made of angle steel.

[0032] The present invention also has the following implementation modes based on the above:

[0033] Further, a small modular bracket for pre-buried process pipelines is provided, wherein a base 4 is installed at the bottom end of each column 1. Specifically, the column 1 is supported on the ground by the base 4.

[0034] Further, a small modular bracket for pre-buried process pipelines, wherein each column 1 is provided with a waist hole 5 in the longitudinal direction, and the crossbeam 2 is slidably installed in two waist holes 5 through a bolt pair. Specifically, when the bolt pair is loosened, the crossbeam 2 can slide up and down in the waist holes on the two columns 1, and when the crossbeam 2 is adjusted to a fixed position, the bolt pair is tightened.

[0035] Further, a small modular bracket for pre-buried process pipelines is provided, wherein two mounting holes are provided on the crossbeam 2, and two ends of the pipe clamp 3 are slidably mounted in the two mounting holes. Specifically, the supporting lateral position of the main pipeline 7 is adjusted by the lateral position of the pipe clamp 3 in the mounting hole.

[0036] A construction method for a small modular bracket for pre-buried process pipelines, comprising the above-mentioned small modular bracket for pre-buried process pipelines,

[0037] Step 1: According to the scope of the pre-buried pipelines in the construction area, according to the pipelines in the same plane or the same vertical plane, and the actual hoisting space on site, several modular ranges are divided, and the design coordinate points are set within the modular range; specifically, first a modular range is divided in the construction area where the pre-buried pipelines need to be buried;

[0038] Step 2: According to the divided modular ranges, prefabricate several pipeline segments 7 in the workshop and assemble them in the construction area. Select a relative positioning point and coordinate system direction on any pipeline segment 7, corresponding to the design coordinate point, set the layout inflection point position on the pipeline segment 7, and mark it; secondly, according to the modular range, set the size, shape, etc. of several pipeline segments 7, and prefabricate several pipeline segments 7 in the workshop.

[0039] Step 3: Place the pipe segment 7 in step 2 on the crossbeams 2 of several supports, fix the pipe segment 7 with the pipe clamps 3 of several supports, adjust the relative position of the crossbeam 2 to the column 1, and adjust the relative position of the pipe clamp 3 to the crossbeam 2, so as to adjust the slope and installation direction of the pipe segment 7; specifically, support the pipe segment 7 by several crossbeams 2, and fix the pipe segment 7 by the pipe clamps 3 on several crossbeams 2. When the longitudinal position of the pipe segment 7 needs to be adjusted, slide the crossbeam 2 up and down in the two waist holes 5 of the two columns 1, and when the crossbeam 2 is moved to the desired position, fix the crossbeam 2 by the bolt pair 6, so that the position of the crossbeam 2 does not change. When the transverse position of the pipe segment 7 needs to be adjusted, since the two installation holes set on the crossbeam 2 are also waist holes, move the pipe clamp 3 on the crossbeam 2 left and right, and fix the pipe clamp 3 after adjusting it to the desired transverse position, so that the transverse position of the pipe clamp 3 changes. Therefore, the pipeline section 7 can be adjusted by the crossbeam 2 and the pipe clamp 3. When the slope of the pipeline section 7 is adjusted, the transverse sections 2 supported at different positions of the pipeline section 7 can be located at different horizontal heights.

[0040] Step 4: Assemble the remaining pipe segments 7 with the pipe segment 7 in step 3 through the inflection point position of the line laying out to form a modular pipe 8; specifically, only the installation direction, slope, etc. of one pipe segment 7 need to be adjusted. When the adjustment of the pipe segment 7 is completed, the remaining pipe segments can be welded and assembled on the pipe segment 7.

[0041] Step 5: According to the size and shape of the modular pipeline 8, several lifting points are set on the modular pipeline 8, and lifting analysis is performed. When the on-site conditions are met, the modular pipeline 8 is lifted; specifically, multiple lifting points are set on the assembled modular pipeline 8, and the modular pipeline 8 is lifted according to the multiple lifting points to prevent the modular pipeline 8 from deformation.

[0042] Step 6: Place the modular pipe 8 into the modular range.

[0043] Furthermore, a construction method for a small modular bracket for pre-buried process pipelines is characterized in that in step one, a BIM model is used to analyze and divide several modularizable ranges in advance. Specifically, the BIM model is used to analyze the pipelines on the same plane in the construction area in advance, and they are divided into modular pipelines 8 in combination with the hoistable space. The welds of the modular pipelines 8 are all prefabricated welds, which expands the prefabrication depth, and the division principle can be as follows: on planes or vertical surfaces without space restrictions, the modular pipelines 8 that can be assembled are as large as possible; if there are space restrictions, such as in steel plate walls, the modular pipelines 8 that can be assembled should consider the inner width of the steel plate wall, so that the hoisting is met and the end of the pipeline is about 50mm out of the steel plate wall after the pipeline is in place to facilitate subsequent construction; box module pipelines.

[0044] Furthermore, a construction method for a small modular support for pre-buried process pipelines further includes the following step between step 4 and step 5: retesting the assembled modular pipeline as a whole to ensure that the position errors of the endpoints and the turning points of the laying out are within the range required by the design. Specifically, the accuracy of the construction is ensured by retesting.

[0045] Furthermore, a construction method of a small modular support for pre-buried process pipelines further includes the following steps after step 6: retesting and fixing the modular pipelines 8 placed in the modular range to ensure that the final installation position of the modular pipelines 8 is within the design allowable error range. Specifically, by repeatedly retesting the modular pipelines 8, displacement of the small modular pipelines 8 during casting is effectively prevented.

[0046] The above description is only a preferred embodiment of the present invention, and does not limit the implementation mode and protection scope of the present invention. For those skilled in the art, it should be aware that all solutions obtained by equivalent substitutions and obvious changes made using the description and illustrations of the present invention should be included in the protection scope of the present invention.

Claims

1. A small modular bracket for pre-buried process pipelines, characterized in that: include: Two columns, beam, pipe clamp; The two ends of the crossbeam are slidably mounted on the two upright posts; The pipe clamp is arranged in a "U" shape, and both ends of the pipe clamp are slidably mounted on the crossbeam.

2. A small modular bracket for pre-buried process pipelines according to claim 1, characterized in that: A base is installed at the bottom end of each column.

3. A small modular bracket for pre-buried process pipelines according to claim 1, characterized in that: Each of the upright columns is provided with a waist hole in the longitudinal direction, and the crossbeam is slidably mounted on the two waist holes through a bolt pair.

4. A small modular bracket for pre-buried process pipelines according to claim 1, characterized in that: The crossbeam is provided with two mounting holes, and the two ends of the pipe clamp are slidably mounted in the two mounting holes.

5. A construction method for a small modular support for pre-buried process pipelines, characterized in that: A small modular bracket for pre-buried process pipelines comprising any one of claims 1 to 4, Step 1: According to the scope of the pre-buried pipelines in the construction area, according to the pipelines in the same plane or the same vertical plane, and the actual hoisting space on site, several modularizable ranges are divided, and the design coordinate points are set within the modularizable ranges; Step 2: According to the divided modular ranges, prefabricate several pipeline segments in the workshop and assemble them in the construction area. Select a relative positioning point and coordinate system direction on any pipeline segment, corresponding to the design coordinate point, set the inflection point position on the pipeline segment, and mark it; Step 3: placing the pipe section in step 2 on the beams of the plurality of brackets, fixing the pipe section with the pipe clamps of the plurality of brackets, adjusting the relative position of the beam relative to the two columns, and adjusting the relative position of the pipe clamp relative to the beam; Step 4: Assemble the remaining pipeline segments with the pipeline segment in step 3 through the inflection point of the laying-out to form a modular pipeline; Step 5: According to the size and shape of the modular pipeline, several lifting points are set on the modular pipeline, and lifting analysis is performed. When the on-site conditions are met, the modular pipeline is lifted; Step six: Place the modular pipeline into the modular range.

6. The construction method of a small modular support for pre-buried process pipelines according to claim 5 is characterized in that: In step one, the BIM model is used to analyze and divide the project into several modular areas in advance.

7. According to the construction method of a small modular bracket for pre-buried process pipelines as described in claim 5, the following step is also included between step four and step five: re-measure the assembled modular pipeline as a whole to ensure that the position errors of the endpoints and the turning points of the layout are within the range of design requirements.

8. According to the construction method of a small modular bracket for pre-buried process pipelines according to claim 5, the following step is also included after step six: re-testing and fixing the modular pipelines placed in the modular range to ensure that the final installation position of the modular pipelines is within the design allowable error range.