Construction method of caisson translation sliding plate device

By installing a skateboard device under the caisson base and using the winch wire rope traction technology, the problems of high investment cost, high operation difficulty and high safety risks in the existing caisson discharge technology are solved, and the caisson discharge is achieved safe, stable and efficient.

CN120061380AActive Publication Date: 2025-05-30NO 3 ENG COMPANY LTD OF CCCC FIRST HARBOR ENG COMPANY +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202510525285.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-04-25
Publication Date
2025-05-30
Estimated Expiration
2045-04-25

AI Technical Summary

Technical Problem

The existing caisson delivery technology has problems such as high investment cost, high operation difficulty and high safety risks, especially during caisson delivery with a smaller width and a height-to-face ratio greater than 1.

Method used

The caisson translation slide plate device is used. By passing the slide plate device under the caisson bottom plate, the balance beam is connected by a winch wire rope, and the support beam and its upper caisson are driven to slide along the track beam, and the rear track beam and limit rod are removed, and transported to the front connection until the caisson is transported to the designated position.

Benefits of technology

It realizes the safe, stable and efficient delivery of caissons, reduces construction costs and operation difficulties, and improves construction safety and equipment utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120061380A_ABST
    Figure CN120061380A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of caisson shipping, in particular to a construction method of a caisson translation sliding plate device. Comprising the steps of bonding sliding plates, jacking the caisson, laying track beams and limiting rods, arranging supporting beams and balance beams in a penetrating mode, falling the caisson back, lengthening the track beams, conducting traction through a winch, transferring the track beams and the limiting rods, and completing caisson translation. According to the construction method, construction operation is convenient, stress safety and gravity center stability of the caisson can be guaranteed by setting the width of the track beam regardless of the width of the caisson, meanwhile, all components on the caisson translation sliding plate device can be recycled, materials are saved, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of caisson transportation, and particularly relates to a construction method for a caisson translation skateboard device. Background Art

[0002] There are two traditional processes for caisson transportation: trolley transportation and airbag transportation. The trolley transportation process is mature, with high safety and easy operation, but it has a high investment cost and is generally applicable to professional permanent prefabrication yards. The airbag transportation has low requirements for the foundation, and the treatment cost of the prefabrication site is relatively low. However, the transportation operation is difficult and the construction safety is poor. Especially for caissons with a small width and a height-width ratio greater than 1, it is difficult to arrange airbags, the center of gravity of the caisson is high, and the safety risk is greater.

[0003] With the emergence of new materials, sliding friction can be used instead of rolling friction for caisson transportation. For example, in the article "Discussion on the Scheme of Sliding Plate Transportation of Large Components" published by Zhang Xiaoming in "China High-Tech Enterprises" NO.22, 2010, the construction technology of translating caissons with tetrafluoroethylene plates was discussed. However, the processed size of the tetrafluoroethylene plate is large and the lateral displacement is relatively large. The caisson moves laterally with the tetrafluoroethylene plate and is prone to collide with the limit block under the action of inertia. The actual movement direction of the caisson forms an angle with the designed forward axis, and the friction between the caisson and the limit block needs to be overcome during deviation correction. After the caisson moves again after deviation correction, the front end of the caisson is prone to deviate to the other limit block and collide with it under the action of inertia. Repeated adjustment in this way affects the traction translation speed of the caisson. In addition, the limit is made of precast blocks, and the size is also large, which is inconvenient for construction operation and has a high cost. Summary of the Invention

[0004] The purpose of the present invention is to provide a construction method for a caisson translation skateboard device in view of the technical problems existing in the above-mentioned existing methods.

[0005] To achieve the above purpose, the present invention adopts the following technical solutions: A construction method for a caisson translation skateboard device, characterized in that: a caisson translation skateboard device is penetrated under the caisson bottom plate, a balance beam is connected by a winch steel wire rope, and the support beam and the caisson above it are driven to slide forward along the track beam. After the caisson moves forward a certain distance, the track beam section and the limit rod behind the caisson are removed, transported to the front of the caisson to extend the track beam until the caisson is transported to the designated position. The construction method specifically includes the following steps: S1: Bond the skateboard; bond the lower skateboard on the top surface of the track beam, bond the upper skateboards on the bottom surfaces of the support beam and the balance beam respectively, and fix them between the baffles, 5-10 mm higher than the baffles, and slide along the lower skateboard; S2: Jack up the caisson; use a jack or an airbag to jack up the caisson, and the jacking height is greater than the standard section of the support beam and the track beam including the lower skateboard and the upper skateboard, 3-5 cm higher; S3: Lay the track beams and the limiting rods; longitudinally connect the track beam segments, connect the connecting plates between two segments by bolts, and the longitudinal length is greater than the length after the connection of the support beam and the balance beam; respectively pull the longitudinally connected track beam segments to the bottom of the caisson, and arrange limiting rods between the front and rear track beams of the caisson. The rectangular insertion plates of the limiting rods are respectively inserted into the rectangular jack holes at the lower flange plates between the two track beams. S4: Pass through the support beam and the balance beam; respectively pass the support beam and the balance beam through the upper flange plates of the track beams along the limiting plates, pull the support beam along the track beam to directly below the caisson, and connect the towing lugs of the support beam and the towing lugs of the balance beam by passing rigid pull rods through the pin shafts. S5: Lower the caisson; lower the caisson by operating the jacks or air bags and place it on the top surface of the support beam. S6: Extend the track beam; longitudinally extend the track beam segments, connect the connecting plates between two segments by bolts, and the total longitudinal length is greater than twice the length after the connection of the support beam and the balance beam. The front end is inserted into the limiting rod. S7: Winch traction; connect the winch steel wire rope to the towing lug on the front side of the balance beam, start the winch to drive the balance beam, the support beam and the upper caisson to slide forward along the track beam. S8: Transfer the track beam and the limiting rod; move the caisson forward, stop the traction when the balance beam reaches near the front end of the track beam, remove the track beam and the limiting rod behind the caisson, and transfer them to the front of the caisson. S9: The translation of the caisson is completed; repeat steps S6 - S8 until the caisson is transported to the designated position and the translation is completed; lift the caisson by using jacks or air bags, or lift the caisson by a crane ship, and then remove the caisson translation skateboard device for reuse.

[0006] In the step S1, the lower slide plate is a 2 - cm - thick tetrafluoroethylene plate, which is bonded to the top surface of the track beam by epoxy glue, and silicone grease is evenly applied on it to reduce the friction coefficient between the tetrafluoroethylene plates; the upper slide plate is a 2 - cm - thick tetrafluoroethylene plate, which is respectively bonded to the bottom surfaces of the support beam and the balance beam by epoxy glue.

[0007] In the steps S1 - S4, S6 - S8, the track beam is a double - web steel structure, with a single - section length of 4 - 6 m. Connecting plates are welded and fixed at both ends, and a set of rectangular jacks are arranged at equal distances from both ends. Each set of jacks is respectively arranged on the lower flange plates on both sides of the track beam; the track beam is arranged in longitudinal sections, and the connecting plates between two sections are connected by bolts; the width of the track beam can be calculated according to the self - weight of the caisson and the designed compressive strength of the skateboard to ensure that the safety factor of the skateboard load - bearing meets the requirements.

[0008] In the steps S3, S6, S8, the limiting rod is a square steel pipe structure, with rectangular insertion plates welded and fixed at both ends, which are respectively inserted into the rectangular jack holes at the lower flange plates between the two track beams; the longitudinal spacing of the limiting rods is 4 - 12 m to ensure that the distance between the track beams remains unchanged.

[0009] In the steps S1 to S7, the support beam is a double-web steel structure. Fixed baffles and towing lugs are welded to the outer sides of both ends of the support beam. The baffles ensure the fixed position of the upper slide plate during sliding, and the support beam moves along the track beam through the towing lugs. Rib plates and bolt-fixed limit plates are welded and fixed on both sides of the support beam. The rib plates improve the load-bearing capacity of the support beam. The longitudinal spacing of the limit plates is not greater than 1 / 2 of the length of the lower slide plate segment, ensuring that each segment of the lower slide plate is limited by two limit plates. The gap between the limit plates and the sides of the upper and lower slide plates, as well as the sides and bottom of the upper flange plate of the track beam, is 5 mm, ensuring that the support beam and the lower slide plate do not shift laterally on the track beam. The length of the support beam is greater than the width of the bottom plate in the advancing direction of the caisson.

[0010] In the steps S1, S3, S4, S6 to S8, the balance beam is a double-web steel structure. The two ends respectively correspond to the positions of each track beam. Fixed baffles and towing lugs are welded and fixed on both sides of the balance beam. A pair of limit plates are bolt-fixed on the lower flange plate of the balance beam. The baffles on both sides ensure the fixed position of the upper slide plate during sliding. The towing lugs on both sides are respectively connected to the support beam and the hoist wire rope. The gap between the limit plates and the sides of the upper and lower slide plates, as well as the sides and bottom of the upper flange plate of the track beam, is 5 mm, ensuring that the balance beam does not shift laterally on the track beam.

[0011] In the step S4, the rigid tie rod is a steel structure, corresponding to the position of each track beam, and is respectively connected to the towing lug of the support beam and the towing lug of the balance beam through pin shafts.

[0012] In the step S7, the hoist towing speed of the caisson does not exceed 1 m / min.

[0013] A caisson translation slide plate device adopted by the above construction method, characterized in that: it includes two track beams laid on a flat site and a slide plate mechanism connected to the track beams. A limit rod for maintaining the spacing is connected between the track beams. The slide plate mechanism includes a support beam, a balance beam, an upper slide plate and a lower slide plate. The lower slide plate is connected to the top surface of the track beam. The support beam is parallel to the track beam, connected to the top surface of the lower slide plate, used to carry the caisson, and its top surface is in direct contact with the outer wall or partition floor of the caisson. The balance beam is located in front of the support beam, perpendicular to the track beam, and the two ends are respectively connected to the top surface of the lower slide plate. One side is connected to the support beam through a rigid tie rod, and the other side is connected to the hoist wire rope. The upper slide plate is respectively connected to the bottom surfaces of the support beam and the balance beam, and the limit passes through the upper flange plate of the track beam and slides along the lower slide plate.

[0014] Using the construction method of the present invention, the hoist wire rope is connected to the balance beam, driving the support beam and the caisson above it to slide forward along the track beam, ensuring the synchronous forward movement of the support beams on each track beam without lateral movement. After the caisson has moved forward a certain distance, the track beam segments and the limit rods behind the caisson can be removed and transported to the front of the caisson to extend the track beam until the caisson is transported to the designated position. The recycling of the track beam segments and the limit rods can be realized for the transportation of a single caisson. Generally speaking, the construction operation is convenient. Regardless of the width of the caisson, by setting the width of the track beam, the force safety and the center of gravity stability of the caisson can be ensured. At the same time, all components on the translation skateboard device of the caisson can be recycled, saving materials and reducing the construction cost. Brief Description of the Drawings

[0015] Figure 1 It is a schematic diagram of the construction effect of the caisson translation skateboard device of the present invention.

[0016] Figure 2 It is a schematic diagram of the standard cross-section of the support beam and the track beam in the caisson translation skateboard device of the present invention.

[0017] Figure 3 It is a schematic diagram of the end cross-section of the support beam and the track beam in the caisson translation skateboard device of the present invention.

[0018] Figure 4 It is a schematic diagram of the cross-section of the balance beam and the rigid tie rod positions in the caisson translation skateboard device of the present invention.

[0019] Figure 5 It is a flow chart of the construction method of the present invention. Detailed Description of the Invention

[0020] The present invention will be further described in detail below with reference to the drawings and the specific embodiments.

[0021] Embodiment 1

[0022] As Figures 1 - 5 shown, a construction method of a caisson translation skateboard device includes the following steps: S1: Bond the skateboard. Bond the lower skateboard 6 to the top surface of the track beam 1 through epoxy glue, and bond the upper skateboards 7 to the bottom surfaces of the support beam 3 and the balance beam 4 respectively, and fix them between the support beam baffle 301 and the balance beam baffle 401, with a height 5-10 mm higher than the two baffles.

[0023] S2: Lift the caisson 8. Use a jack or an airbag to lift the caisson 8, and the lifting height is greater than the standard cross-section of the support beam 3 and the track beam 1 including the lower skateboard 6 and the upper skateboard 7, with a height 3-5 cm higher.

[0024] S3: Lay the track beam 1 and the limit rod 2. The track beam 1 is longitudinally connected in segments. The connecting plates 101 between two segments are bolted together to ensure that the longitudinal length is greater than the length after the connection of the support beam 3 and the balance beam 4. The longitudinally connected segments of the track beam are respectively pulled into the bottom of the caisson 8. Limit rods 2 are arranged between the front and rear track beams 1 of the caisson. The rectangular insertion plates 201 of the limit rods 2 are respectively inserted into the rectangular jack holes 102 at the lower flange plates between the two track beams.

[0025] S4: Insert the support beam 3 and the balance beam 4. The support beam 3 and the balance beam 4 are respectively inserted into the upper flange plate of the track beam 1 along the support beam limit plate 304 and the balance beam limit plate 403. The support beam 3 is pulled along the track beam 1 to be directly below the caisson 8. The support beam towing ear plate 302 and the balance beam towing ear plate 402 are connected by inserting a rigid pull rod 5 through a pin shaft.

[0026] S5: Lower the caisson 8. Lower the caisson 8 by operating the jack or the airbag and place it on the top surface of the support beam 3.

[0027] S6: Extend the track beam 1. The track beam 1 is longitudinally extended in segments. The connecting plates 101 between two segments are bolted together to ensure that the total longitudinal length is greater than twice the length after the connection of the support beam 3 and the balance beam 4. The front end should be inserted into the limit rod 2.

[0028] S7: Hoist winch traction. The hoist winch wire rope 9 is connected to the front-side towing ear plate 402 of the balance beam. Start the hoist winch to drive the balance beam 4, the support beam 3 and the caisson 8 above them to slide forward along the track beam 1.

[0029] S8: Transfer the track beam 1 and the limit rod 2. When the caisson 8 moves forward, stop the traction when the balance beam 4 reaches near the front end of the track beam 1. Remove the track beam 1 and the limit rod 2 behind the caisson and transfer them to the front of the caisson.

[0030] S9: The translation of the caisson 8 is completed. Repeat steps S6 - S8 until the caisson is transported to the designated position and the translation is completed. Use the jack or the airbag to lift the caisson 8, or use a crane ship to lift the caisson 8, and then remove the caisson translation skateboard device for reuse.

[0031] In the said step S1, the lower slide plate 6 is a 2-cm thick tetrafluoroethylene plate, on which silicone grease is evenly applied to reduce the friction coefficient between the tetrafluoroethylene plates. The upper slide plate 7 is a 2-cm thick tetrafluoroethylene plate and slides along the lower slide plate 6.

[0032] In the steps S1 to S4, S6 to S8, the track beam 1 is a double-web steel structure with a single-section length of 4 to 6 m. Fixed connection plates 101 are welded at both ends, and a set of rectangular jacks 102 are arranged at equal distances from both ends. Each set of jacks is respectively arranged on the lower flange plates on both sides of the track beam 1. The track beam 1 is arranged in sections longitudinally, and the connection plates between two sections are connected by bolts; the width of the track beam 1 can be calculated according to the self-weight of the caisson and the designed compressive strength of the slide plate to ensure that the safety factor of the slide plate load-bearing meets the requirements.

[0033] In the steps S3, S6, S8, the limit rod 2 is a square steel pipe structure, and rectangular insertion plates 201 are welded and fixed at both ends. The longitudinal spacing of the limit rods is 4 to 12 m to ensure that the distance between the track beams remains unchanged.

[0034] In the steps S1 to S7, the support beam 3 is a double-web steel structure, and support beam baffles 301 and support beam traction lugs 302 are welded on the outer sides of both ends. The baffle ensures that the position of the upper slide plate 7 is fixed during sliding, and the support beam 3 can be moved along the track beam 1 through the traction lug; ribs 303 are welded and fixed on both sides and limit support beam limit plates 304 are fixed by bolts. The ribs can improve the load-bearing capacity of the support beam 3. The longitudinal spacing of the limit plates should not be greater than 1 / 2 of the section length of the lower slide plate 6 to ensure that each section of the lower slide plate 6 has two limit plates for limiting. The gap between the support beam limit plate 304 and the sides of the upper and lower slide plates, as well as the sides and bottom of the upper flange plate of the track beam 1 is 5 mm to ensure that the support beam 3 and the lower slide plate 6 do not shift laterally on the track beam 1. The length of the support beam 3 is greater than the width of the bottom plate in the advancing direction of the caisson.

[0035] In the steps S1, S3, S4, S6 to S8, the balance beam 4 is a double-web steel structure, and both ends correspond to the position of each track beam 1. Balance beam baffles 401 and balance beam traction lugs 402 are welded on both sides respectively. A pair of balance beam limit plates 403 are fixed by bolts on the lower flange plate. The baffles on both sides ensure that the position of the upper slide plate 7 is fixed during sliding. The traction lugs on both sides are respectively connected to the support beam 3 and the hoist steel wire rope 9. The gap between the limit plates and the sides of the upper and lower slide plates, as well as the sides and bottom of the upper flange plate of the track beam 1 is 5 mm to ensure that the balance beam 4 does not shift laterally on the track beam 1.

[0036] In the step S4, the rigid tie rod 5 is a steel structure, corresponding to the position of each track beam 1, and is respectively connected to the support beam traction lug 302 and the balance beam traction lug 402 by pin shafts.

[0037] In the step S7, the hoist traction speed of the caisson sliding is not greater than 1 m / min.

[0038] Embodiment 2

[0039] As Figures 1 - 4As shown in the figure, a caisson translation skateboard device adopted in Embodiment 1 includes two track beams 1 laid on a flat site and a skateboard mechanism connected to the track beams 1. A limiting rod 2 for maintaining the spacing is connected between the track beams 1. The skateboard mechanism includes a support beam 3, a balance beam 4, an upper skateboard 7 and a lower skateboard 6. The lower skateboard 6 is connected to the top surface of the track beam 1. The support beam 3 is parallel to the track beam 1, connected to the top surface of the lower skateboard 6, used to carry the caisson 8, and its top surface is in direct contact with the outer wall of the caisson 8 or the bottom plate of the partition wall. The balance beam 4 is located in front of the support beam 3, perpendicular to the track beam 1, with both ends respectively connected to the top surface of the lower skateboard 6, one side connected to the support beam 3 through a rigid pull rod 5, and the other side connected to the hoist wire rope 9. The upper skateboard 7 is respectively connected to the bottom surfaces of the support beam 3 and the balance beam 4, and is limited to penetrate into the upper flange plate of the track beam 1 and slide along the lower skateboard 6.

[0040] The track beam 1 is a double-web steel structure, with a single-section length of 4 - 6 m. Fixed connection plates 101 are welded at both ends, and a set of rectangular jacks 102 are arranged at equal distances from both ends. Each set of jacks is respectively arranged on the lower flange plates on both sides of the track beam 1. The track beam 1 is arranged in sections longitudinally, and the connection plates 101 between two sections are connected by bolts. The width of the track beam 1 can be calculated according to the self-weight of the caisson and the designed compressive strength of the skateboard to ensure that the safety factor of the skateboard load-bearing meets the requirements.

[0041] The limiting rod 2 is a square steel pipe structure, with rectangular insertion plates 201 welded at both ends, which are respectively inserted at the positions of the rectangular jacks 102 on the lower flange plates between the two track beams 1. The longitudinal spacing of the limiting rods 2 is 4 - 12 m.

[0042] The support beam 3 is a double-web steel structure, with a length greater than the width of the bottom plate in the advancing direction of the caisson 8. Support beam baffles 301 and support beam towing lugs 302 are welded on the outer sides of both ends. The support beam baffle 301 is used for fixing the position when the upper skateboard 7 slides. The support beam towing lug 302 is connected to the balance beam 4 through a rigid pull rod 5. Rib plates 303 for improving the load-bearing capacity of the support beam 3 are welded on both sides of the support beam 3, and support beam limit plates 304 are connected by bolts. The longitudinal spacing of the support beam limit plates 304 is not greater than 1 / 2 of the section length of the lower skateboard 6. Each section of the lower skateboard 6 has at least two support beam limit plates 304 for limiting. The gaps between the support beam limit plates 304 and the sides of the upper and lower skateboards, as well as the sides and bottom surfaces of the upper flange plates of the track beam 1 are all 5 mm, so that the support beam 3 and the lower skateboard 6 do not shift on the track beam 1.

[0043] The balance beam 4 is a double-web steel structure, with both ends corresponding to the positions of each track beam 1. Balance beam baffles 401 and balance beam towing lugs 402 are welded on both sides respectively. The lower flange is connected to a pair of balance beam limit plates 403 by bolts. The balance beam baffles 401 on both sides are used to fix the position when the upper slide plate 7 slides. The balance beam towing lugs 402 on both sides are respectively connected to the rigid tie rod 5 and the hoist wire rope 9. The gap between the balance beam limit plate 403 and the side surfaces of the upper and lower slide plates, as well as the side and bottom surfaces of the upper flange of the track beam 1, is 5 mm, and the balance beam 4 does not shift on the track beam 1.

[0044] The rigid tie rod 5 is a steel structure, corresponding to the position of each track beam 1, and is connected to the support beam towing lug 302 and the balance beam towing lug 402 by pin shafts respectively.

[0045] The lower slide plate 6 is a 2-cm-thick tetrafluoroethylene plate, bonded to the top surface of the track beam 1 with epoxy glue, and silicone grease for reducing the friction coefficient between the tetrafluoroethylene plates is evenly applied on it.

[0046] The upper slide plate 7 is a 2-cm-thick tetrafluoroethylene plate, bonded to the bottom surfaces of the support beam 3 and the balance beam 4 with epoxy glue respectively, and fixed between the respective baffles of the two, protruding 5 - 10 mm above each baffle, and sliding along the lower slide plate 6.

[0047] The above are only preferred embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art within the technical scope disclosed by the present invention, according to the technical solution and inventive concept of the present invention, makes equivalent substitutions or changes, and shall be covered by the protection scope of the present invention.

Claims

1. A construction method for a caisson translation slide device, characterized in that: A caisson translation slide device is installed under the caisson bottom plate, and a winch wire rope is used to connect the balance beam to drive the support beam and the upper caisson to slide forward along the track beam. After the caisson moves forward for a certain distance, the track beam segment and the limit rod behind the caisson are removed and transported to the front of the caisson to extend the track beam until the caisson is transported to the designated location. The construction method specifically includes the following steps: S1: Bonding the slide plate; bond the lower slide plate to the top surface of the track beam, bond the upper slide plate to the bottom surfaces of the support beam and the balance beam respectively, and fix them between the baffles, 5-10mm higher than the baffles, and slide along the lower slide plate; S2: Lifting the caisson; the caisson is lifted by a jack or airbag, and the lifting height is greater than the standard section of the support beam and track beam including the lower and upper slide plates, and is 3-5 cm higher; S3: Laying track beams and limit rods; connecting track beam segments longitudinally, connecting the connecting plates between the two segments by bolts, and the longitudinal length is greater than the length of the support beam and the balance beam after connection; pulling the track beam longitudinal connecting segments into the bottom of the caisson respectively, setting limit rods between the front and rear track beams of the caisson, and inserting the rectangular plug plates of the limit rods into the rectangular plug holes of the lower flange plates between the two track beams respectively; S4: inserting the support beam and the balance beam; respectively inserting the support beam and the balance beam into the upper flange plate of the track beam along the limit plate, pulling the support beam along the track beam to the bottom of the caisson, and connecting the support beam traction lug plate and the balance beam traction lug plate through the pin shaft using a rigid pull rod; S5: Lower the caisson; lower the caisson by operating the jack or airbag and place it on the top surface of the support beam; S6: Extending the track beam; the track beam segment is extended longitudinally, and the connecting plates between the two sections are connected by bolts. The total longitudinal length is greater than twice the length of the support beam and the balance beam after connection, and a limit rod is inserted into the front end; S7: winch traction; the winch wire rope is connected to the traction ear plate on the front side of the balance beam, and the winch is started to drive the balance beam, the support beam and the upper caisson to slide forward along the track beam; S8: Transfer the track beam and the limit rod; the caisson moves forward, and the traction is stopped when the balance beam reaches the front end of the track beam, and the track beam and the limit rod behind the caisson are removed and transferred to the front of the caisson; S9: the caisson is moved horizontally; steps S6 to S8 are repeated until the caisson is shipped to the designated location and the movement is completed; the caisson is lifted by a jack or an air bag, or after the caisson is lifted by a crane ship, the caisson movement slide device is removed for reuse.

2. The construction method of a caisson translation slide device according to claim 1 is characterized in that: In step S1, the lower slide plate is a 2 cm thick polytetrafluoro plate, which is bonded to the top surface of the track beam by epoxy glue, and silicone grease is evenly applied on it to reduce the friction coefficient between the polytetrafluoro plates; the upper slide plate is a 2 cm thick polytetrafluoro plate, which is respectively bonded to the bottom surfaces of the support beam and the balance beam by epoxy glue.

3. The construction method of a caisson translation slide device according to claim 1 is characterized in that: In the steps S1 to S4 and S6 to S8, the track beam is a double-web steel structure with a single section length of 4 to 6 m, with fixed connecting plates welded at both ends, and a group of rectangular sockets are arranged equidistantly from both ends, and each group of sockets is arranged on the lower flange plates on both sides of the track beam; the track beam is arranged in sections in the longitudinal direction, and the connecting plates between the two sections are connected by bolts; the width of the track beam can be calculated according to the dead weight of the caisson and the designed compressive strength of the slide plate to ensure that the load-bearing safety factor of the slide plate meets the requirements.

4. The construction method of a caisson translation slide device according to claim 1 is characterized in that: In steps S3, S6 and S8, the limit rod is a square steel pipe structure, with rectangular plug plates welded on both ends, which are respectively inserted into the rectangular plug holes of the lower flange plate between the two track beams; the limit rods are arranged at a longitudinal spacing of 4 to 12 m to ensure that the spacing between the track beams remains unchanged.

5. The construction method of a caisson translation slide device according to claim 1 is characterized in that: In the steps S1 to S7, the support beam is a double-web steel structure, and fixed baffles and traction ear plates are welded on the outer sides of both ends of the structure. The baffles ensure that the upper slide plate is fixed in position when sliding, and the support beam is moved along the track beam by the traction ear plates; fixed ribs and bolt-fixed limit plates are welded on both sides of the support beam, and the ribs improve the bearing capacity of the support beam. The longitudinal spacing of the limit plates is not greater than 1 / 2 of the length of the lower slide plate segment, ensuring that each segment of the lower slide plate has two limit plates for limiting, and the gap between the limit plates and the sides of the upper and lower slide plates and the sides and bottom of the upper flange plate of the track beam is 5 mm, ensuring that the support beam and the lower slide plate do not shift sideways on the track beam; the length of the support beam is greater than the width of the bottom plate in the forward direction of the caisson.

6. The construction method of a caisson translation slide device according to claim 1 is characterized in that: In steps S1, S3, S4, S6-S8, the balance beam is a double-web steel structure, with its two ends corresponding to the position of each track beam, and fixed baffles and traction ear plates are welded on both sides respectively. A pair of limit plates are fixed to its lower flange plate by bolts, and the baffles on both sides ensure that the position of the upper slide plate is fixed when sliding, and the traction ear plates on both sides are respectively connected to the support beam and the winch wire rope. The gap between the limit plate and the side surfaces of the upper and lower slide plates and the side and bottom surfaces of the upper flange plate of the track beam is 5 mm, so as to ensure that the balance beam does not shift sideways on the track beam.

7. The construction method of a caisson translation slide device according to claim 1 is characterized in that: In step S4, the rigid pull rod is a steel structure, corresponds to the position of each track beam, and is respectively connected to the support beam traction ear plate and the balance beam traction ear plate through a pin shaft.

8. The construction method of a caisson translation slide device according to claim 1 is characterized in that: In step S7, the winch pulls the caisson to slide at a speed no greater than 1 m / min.

Citation Information

Patent Citations

  • High-speed train ballastless track bed concrete construction surface line-to-line transport device and method

    CN106994743A

  • Method for moving box girder and reducing friction coefficient of transverse beam moving track

    CN117127503A

  • Moving device for pouring combined steel formwork on upper portion of circular-arch culvert

    CN209144685U

  • Multi-box single-chamber steel box girder sliding construction support system

    CN214530220U

  • Sliding system of arch rib sections on top surface of steel box girder

    CN217174405U