Inlaying type steel corridor safety hoisting device and method

By using the combination of main and auxiliary double lifting points and crawling mechanism in building lifting, the problem of suspension steel rope shaking is solved, and efficient, safe lifting and precise installation of the steel corridor is achieved.

CN120328375APending Publication Date: 2025-07-18四川路航建设工程有限责任公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510625527.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-05-15
Publication Date
2025-07-18

AI Technical Summary

Technical Problem

When existing building lifting equipment is hoisted with multi-layer or super-high-rise joint structures, the suspension steel rope is too long and causes shaking, affecting construction safety and quality.

Method used

The tower crane structure and lifting frame are arranged in pairs, and the load is dispersed using main and auxiliary double lifting points. Combined with the hydraulic lifter and clamping mechanism, the crawling mechanism achieves accurate positioning in segments and efficient installation of the inlayed rods.

Benefits of technology

It improves the balance and safety of the lifting process, ensures the forming quality of the steel corridor, and improves the efficiency of high-altitude assembly and installation accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120328375A_ABST
    Figure CN120328375A_ABST
Patent Text Reader

Abstract

The invention provides an inlaying type steel corridor safety hoisting device and method, relates to the building steel structure installation construction technology, particularly discloses two tower crane structures arranged in pairs, and further comprises two hoisting frames installed between the two tower crane structures, hoisting supports are installed on the two hoisting frames, hydraulic lifters are installed on the hoisting supports, and the hydraulic lifters are installed on the hoisting supports. A first lifting rope is installed in the hydraulic lifting device, a connector detachably connected with the steel corridor is installed on the first lifting rope, a second lifting rope detachably connected with the steel corridor is installed at the lifting end of the tower crane structure, and holding and clamping mechanisms used for holding and clamping the steel corridor are installed on the lifting frames. A crawling mechanism moving in the extending direction of the lifting frame is arranged in the holding and clamping mechanism. The arranged first lifting rope is responsible for main body lifting, the second lifting rope assists in posture adjustment, the weight of the steel corridor is dispersed, single-point overload is avoided, and the balance of the corridor in the lifting process can be guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of the installation and construction of building steel structures, and more particularly, to an embedded steel corridor safety hoisting device and method. Background Art

[0002] With the development of the construction industry, high-rise and super-high-rise buildings have developed rapidly in China, and their functions and shapes have become increasingly complex. As an external building structure, the aerial connected structure has a broad view and excellent fire-fighting capabilities. Such connected structures are characterized by high structural height, large span, and great installation difficulty. The existing multi-story corridor installation device hoists and fixes the corridor separately through the hoisting equipment installed on the top of the building. When installing the corridor at a lower or higher position, the suspension steel rope is too long, which will cause vibration during the hoisting process, resulting in severe shaking under this influence and affecting the progress of the construction. Summary of the Invention

[0003] The purpose of the present invention is to provide an embedded steel corridor safety hoisting device and method, which can solve the problems raised in the above background art in view of the deficiencies of the prior art.

[0004] The technical solution of the present invention is realized as follows:

[0005] The present invention provides an embedded steel corridor safety hoisting device, which includes two tower crane structures arranged in pairs, and also includes two lifting frames installed between the two tower crane structures. Lifting brackets are installed on both of the two lifting frames, a hydraulic lifter is installed on the lifting bracket, a first lifting rope is installed in the hydraulic lifter, a connector detachably connected to the steel corridor is installed on the first lifting rope, a second lifting rope detachably connected to the steel corridor is installed at the hoisting end of the tower crane structure, clamping mechanisms for clamping the steel corridor are installed on both of the lifting frames, and a crawling mechanism moving along the extending direction of the lifting frame is arranged in the clamping mechanism.

[0006] In some technical solutions of the present invention, the clamping frame mechanism includes a pair of frames and a connecting frame. Both of the two frames are installed on the side wall of the connecting frame, a control mechanism for controlling the relative movement of the two connecting frames is arranged in the connecting frame, and a plurality of retaining frames are installed on the opposite side walls of the frames. The retaining frames are detachably connected to the members inside the steel corridor.

[0007] In some technical solutions of the present invention, a plurality of mounting seats corresponding to the retaining frames one by one are installed on the side wall of the frame, and an adjusting mechanism for controlling the mounting seat to move in the vertical direction or the horizontal direction is arranged in the frame.

[0008] In some technical solutions of the present invention, the retaining frame is rotatably arranged on the side wall of the mounting seat, and a blocking mechanism for controlling the deflection of the retaining frame is arranged on the mounting seat.

[0009] In some technical solutions of the present invention, the crawling mechanism includes a mounting bracket installed on the fixed end of the clamping mechanism. A through groove is vertically formed on the side wall of the mounting bracket, a part of the lifting bracket is embedded in the through groove, and roller structures in contact with the outer side wall of the lifting bracket are installed on two opposite side walls of the through groove.

[0010] In some technical solutions of the present invention, a locking rod is installed at the bottom of the through groove. Limit rods are rotatably arranged at both ends of the locking rod. A number of blocking blocks are installed on the side wall of the lifting bracket along its extending direction. An adjusting structure for controlling the two limit rods to rotate counterclockwise is provided in the locking rod.

[0011] In some technical solutions of the present invention, a bidirectional push rod is provided in the locking rod. Locking holes are formed at the rotation centers of the two limit rods, and limit blocks adapted to the locking holes are installed on the telescopic ends of the bidirectional push rod.

[0012] In some technical solutions of the present invention, a number of stabilizing brackets are detachably arranged between the two lifting brackets. A lifting mechanism for driving the stabilizing bracket to lift along the extending direction of the lifting bracket is provided on the side wall of the stabilizing bracket.

[0013] In some technical solutions of the present invention, the distance between any two adjacent blocking blocks is adjustable.

[0014] An embedded steel corridor hoisting method, and its hoisting steps are as follows:

[0015] Install tower crane structures in pairs on the cement foundation ground;

[0016] Install a lifting bracket in parallel between the two tower crane structures, and install a triangular lifting bracket and a hydraulic lifter on the lifting bracket to form a frame-type support system;

[0017] Synchronously lift the main section of the steel corridor through the first lifting rope and the second lifting rope to disperse the load and adjust the attitude;

[0018] During the lifting process, the clamping mechanism clamps the steel corridor members, and gradually climbs along the lifting bracket through the crawling mechanism, and segmentally locks the blocking blocks to achieve precise positioning;

[0019] When the design elevation is reached, unload the first lifting rope, and the main section of the steel corridor is temporarily fixed by the second lifting rope and the clamping mechanism;

[0020] Repeat the hoisting process to lift the segmented steel corridor to the assembly height;

[0021] Utilize the installation channel space formed by the clamping mechanism to embed the segmented steel corridor into the main section of the steel corridor;

[0022] The operator installs the embedded members with the assistance of the clamping mechanism to complete the connection between the main section and the segmented section;

[0023] Adjust the position of the cage through the position adjustment mechanism to adapt to the deviation of the steel corridor members, and position the installation of the segmented steel corridor and the main steel corridor;

[0024] After all the segmented hoisting is completed, gradually unload the second lifting rope, and the steel corridor is completely supported by the clamping mechanism and the stabilizing frame;

[0025] Check the installation quality of the connection nodes and the inlaid members, and perform secondary fastening if necessary;

[0026] Remove the tower crane, lifting frame and auxiliary equipment to complete the construction.

[0027] Compared with the prior art, the present invention has at least the following advantages or beneficial effects: The first lifting rope is responsible for the main body lifting, and the second lifting rope is used to assist in adjusting the attitude. In this way, the first lifting rope at the hoisting end of the tower crane and the second lifting rope in the hydraulic lifter form a "main and auxiliary double lifting points", dispersing the weight of the steel corridor, avoiding single-point overload, and ensuring the balance of the corridor during hoisting. Clamping mechanisms for clamping the steel corridor are installed on the lifting frames, and a crawling mechanism moving along the extending direction of the lifting frame is provided inside the clamping mechanism; When the steel corridor moves to the designed elevation of the corridor under the lifting of the above structure, the passage formed inside the clamping mechanism can provide construction space for installing the inlaid members on the main steel corridor at high altitude, preventing the construction position of the operators from being limited when installing the inlaid members at high altitude, resulting in deviations in the installation of the inlaid members and the steel corridor and affecting the forming quality of the steel corridor. The clamping mechanism cooperates with the crawling mechanism to gradually move along the vertical direction, realizing segmented precise positioning, controlling the installation of the steel corridor in stages, and improving the installation quality. And the provided clamping structure can guide the steel corridor to move along the extending direction of the lifting frame, avoiding its shaking due to wind force or other factors during hoisting, and improving the safety during hoisting. Through the coordinated operation of two tower crane structures and combined with the synchronous lifting function of the hydraulic lifter, the steel corridor is hoisted in segments to the target height. After the main steel corridor is hoisted, the first lifting rope and the main steel corridor are unloaded, and the main steel corridor is temporarily fixed at the target height by the second lifting rope and the clamping structure; Subsequently, the remaining segmented steel corridors are hoisted again to the assembly height by the tower crane structure, and the segmented steel corridors enter the installation passage inside the clamping structure. Then, the operators, with the assistance of the clamping structure, splice the segmented steel corridors and the inlaid members with the main steel corridor at high altitude, improving the assembly efficiency of the steel corridor at high altitude for this structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a schematic diagram of the overall structure of the present invention.

[0029] Figure 2 It is a schematic diagram of the combined structure of the clamping structure and the steel corridor in the present invention.

[0030] Figure 3This is a top view structural schematic diagram of the clamping structure and the crawling structure in the present invention.

[0031] Figure 4 This is a right-side combined structural schematic diagram of the clamping structure in the present invention.

[0032] Figure 5 This is a half-sectional structural schematic diagram of the crawling structure in the present invention.

[0033] Figure 6 This is an installation structural schematic diagram of the hoop in the present invention.

[0034] Reference numerals: 1, tower crane structure; 2, stabilizing frame; 3, lifting frame; 4, blocking block; 5, steel link corridor; 6, lifting support; 7, hydraulic lifter; 8, mounting frame; 9, frame body; 10, connecting frame; 11, roller structure; 12, hoop; 13, bolt member; 14, scissor structure; 15, mounting seat; 16, hydraulic telescopic rod; 17, blocking mechanism; 18, retaining frame; 19, limiting rod; 20, two-way push rod; 21, locking rod. Detailed Description of the Invention

[0035] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Apparently, the described embodiments are some, but not all, of the embodiments of the present invention. The components of the embodiments of the present invention usually described and illustrated in the accompanying drawings here can be arranged and designed in various different configurations.

[0036] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed present invention, but merely represents selected embodiments of the present invention. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present invention without creative efforts fall within the scope of protection of the present invention.

[0037] Embodiment

[0038] The present invention provides an embedded steel link corridor 5 hoisting device, and the steel link corridor 5 is installed between two columnar buildings, such as Figures 1-6As shown in the figure, it includes two tower crane structures 1 arranged in pairs. The tower crane structures 1 are fixed on the cement foundation ground through bolt structures to ensure the load-bearing capacity of the tower crane and prevent the tower crane from tipping over. It also includes two lifting frames 3 installed between the two tower crane structures 1. The lifting frames 3 are parallel to the two tower crane structures 1, and the lifting frames 3 are also fixed on the cement foundation ground through bolts. The set lifting frames 3 are of a frame structure. Lifting brackets 6 are installed on both of the two lifting frames 3. The lifting brackets 6 are of a triangular structure, which can improve their load-bearing capacity for the corridor when hoisting the steel connecting corridor 5. A hydraulic lifter 7 is installed on the lifting bracket 6. The hydraulic lifter 7 is a conventional technical means. A first lifting rope is installed inside the hydraulic lifter 7, and a connector detachably connected to the steel connecting corridor 5 is installed on the first lifting rope. A second lifting rope detachably connected to the steel connecting corridor 5 is installed at the hoisting end of the tower crane structure 1. The set first lifting rope is responsible for the main lifting, and the second lifting rope assists in adjusting the attitude. In this way, the first lifting rope at the hoisting end of the tower crane and the second lifting rope inside the hydraulic lifter 7 form a "main and auxiliary double lifting points" to disperse the weight of the steel connecting corridor 5, avoid single-point overload, and ensure the balance of the corridor during the hoisting process. Clamping mechanisms for clamping the steel connecting corridor 5 are installed on both of the lifting frames 3, and a crawling mechanism moving along the extending direction of the lifting frame 3 is arranged inside the clamping mechanism; when the steel connecting corridor 5 moves to the designed elevation of the corridor under the lifting of the above-mentioned structure, the channel formed inside the clamping mechanism can provide construction space for the installation of the inlaid members on the main section of the steel connecting corridor 5 at high altitude, preventing the construction position of the operators from being limited when installing the inlaid members at high altitude, resulting in deviations in the installation of the inlaid members and the steel connecting corridor 5 and affecting the forming quality of the steel connecting corridor 5. The clamping mechanism cooperates with the crawling mechanism to gradually move along the vertical direction to achieve segmented precise positioning, control the installation of the steel connecting corridor 5 in stages, and improve the installation quality. And the set clamping structure can guide the steel connecting corridor 5 to move along the extending direction of the lifting frame 3, avoid its shaking during the hoisting process due to wind or other factors, and improve the safety during hoisting. Through the coordinated operation of the two tower crane structures 1 and combined with the synchronous lifting function of the hydraulic lifter 7, the steel connecting corridor 5 is hoisted in segments to the target height. After the hoisting of the main section of the steel connecting corridor 5 is completed, the first lifting rope is unloaded from the main section of the steel connecting corridor 5, and the main section of the steel connecting corridor 5 is temporarily fixed at the target height by the second lifting rope and the clamping structure; then the remaining segmented steel connecting corridors 5 are hoisted to the assembling height again by the tower crane structure 1, and the segmented steel connecting corridors 5 enter the installation channel inside the clamping structure. Subsequently, the operators assist by the clamping structure to splice the segmented steel connecting corridors 5 and the inlaid members with the main section of the steel connecting corridor 5 at high altitude, improving the efficiency of the high-altitude splicing of the steel connecting corridor 5 by this structure.

[0039] In some technical solutions of the present invention, the holding frame mechanism includes a frame body 9 and a connecting frame 10 arranged in pairs, and the two frame bodies 9 are installed on the side walls of the connecting frame 10, and the connecting frame 10 is provided with a control mechanism for controlling the relative movement of the two connecting frames 10. A plurality of retaining frames 18 are installed on the opposite side walls of the frame body 9, and the retaining frames 18 are telescopic rod structures. The retaining frames 18 are detachably connected to the rods of the main steel corridor or the segmented steel corridor in the steel corridor 5, so that the installation of the two can be positioned. A clamp 12 is installed on the free end of the retaining frame 18, and the rods in the steel corridor 5 are embedded in the annular area of the clamp 12. The two are fixedly connected by bolts and another clamp 12. The clamping mechanism clamps the rods of the steel corridor 5 through the frame body 9 and the retaining frames 18, so that the steel corridor 5 and the lifting frame 3 temporarily become a whole, thereby improving the load resistance of the steel corridor 5 during hoisting.

[0040] Preferably, the control mechanism is a scissors-type structure, and two guide grooves respectively matched with the frame body 9 are provided on the side walls of the connecting frame 10. A sliding seat matched with the guide groove is integrally formed on the frame body 9, and a guide wheel matched with the guide groove is installed on the sliding seat, which can ensure that the frame body 9 moves smoothly in the guide groove. The scissors-type structure is connected to the two frames 9, and the two frames 9 can be controlled to move away from or towards each other through the scissors-type structure.

[0041] Preferably, the control mechanism can also be two hydraulic telescopic rods 16 respectively connected to the frame 9, and the main body of the hydraulic telescopic rod 16 is fixed in the guide groove. Not shown in the drawings.

[0042] In some technical solutions of the present invention, a plurality of mounting seats 15 corresponding to the retaining frames 18 are installed on the side walls of the frame 9, and a positioning mechanism for controlling the vertical or horizontal movement of the mounting seats 15 is provided in the frame 9. The positioning mechanism is two hydraulic telescopic rods 16 arranged in pairs, and the main bodies of the hydraulic telescopic rods 16 are rotatably arranged on the frame 9. A driving motor connected to the rotating shaft of the hydraulic telescopic rod 16 is installed on the frame 9, and the driving motor is a servo motor. The telescopic end of the hydraulic telescopic rod 16 is hinged to the mounting seat 15 through a pin shaft. The design of the above structure can ensure that the clamping mechanism automatically adapts to the position deviation of the rods of the steel corridor 5, and the inclined rods in the steel corridor 5 can also be clamped to prevent the rods from twisting under the clamping of the clamping structure, affecting the strength of its own steel structure, and ensuring uniform clamping force.

[0043] In some technical solutions of the present invention, the cage 18 is rotatably arranged on the side wall of the mounting seat 15, and a blocking mechanism 17 for controlling the deflection of the cage 18 is arranged on the mounting seat 15. The blocking mechanism 17 is a ratchet structure installed between the mounting seat 15 and the rotating shaft of the cage 18, which can prevent itself from rotating in the reverse direction after the position of the cage 18 is adjusted, improve the stability of the cage 18 during its own movement, dynamically lock the position of the cage 18 during the lifting process, and prevent deviation.

[0044] In some technical solutions of the present invention, the crawling mechanism includes a mounting frame 8 installed on the fixed end of the clamping mechanism. The mounting frame 8 is integrally formed with the connecting frame 10. A through groove is vertically opened on the side wall of the mounting frame 8, and a part of the lifting frame 3 is embedded in the through groove. Roller structures 11 in contact with the outer side wall of the lifting frame 3 are installed on two opposite side walls of the through groove. The clamping mechanism can move along the lifting frame 3 through the roller structures 11 in the crawling mechanism, which can reduce the moving friction and improve the smoothness of the operation of the above structure.

[0045] In some technical solutions of the present invention, a locking rod 21 is installed at the bottom of the through groove. Limiting rods 19 are rotatably arranged at both ends of the locking rod 21. A plurality of blocking blocks 4 are installed on the side wall of the lifting frame 3 along its extending direction. An adjusting structure for controlling the two limiting rods 19 to rotate counterclockwise is arranged in the locking rod 21. The locking rod 21 cooperates with the blocking blocks 4 through the limiting rods 19 and realizes segmented locking or release under the restriction of the two-way push rod 20, and gradually adjusts the height of the steel link corridor 5.

[0046] In some technical solutions of the present invention, a two-way push rod 20 is arranged in the locking rod 21. Locking holes are opened at the rotation centers of the two limiting rods 19, and limiting blocks adapted to the locking holes are installed on the telescopic ends of the two-way push rod 20. The rotation of the limiting rods 19 is controlled by the two-way push rod 20 in the locking rod 21 and is clamped into the locking holes opened at the rotation centers of the limiting rods 19, so as to lock the clamping mechanism on the lifting frame 3 and ensure the smooth climbing or descending of the above structure.

[0047] In some technical solutions of the present invention, a plurality of stabilizing frames 2 are detachably arranged between the two lifting frames 3. A lifting mechanism for driving the stabilizing frame 2 to lift along the extending direction of the lifting frame 3 is arranged on the side wall of the stabilizing frame 2. The stabilizing frame 2 can reinforce the lifting frame 3 by moving along the extending direction of the lifting frame 3 through the lifting mechanism, ensure the stable distance between the two lifting frames 3, and reduce shaking. At least two stabilizing frames 2 form a multi-point support between the two lifting frames 3, enhancing the overall torsional resistance.

[0048] In some technical solutions of the present invention, the distance between any two adjacent blocking blocks 4 is adjustable. The design with adjustable distance between the blocking blocks 4 can adapt to the support requirements of link corridors with different spans. The blocking blocks 4 are detachably installed on the side wall of the lifting frame 3 through bolt parts 13.

[0049] A hoisting method for an embedded steel link corridor 5:

[0050] Foundation installation

[0051] Install the tower crane structure 1 in pairs on the cement foundation ground and fix it with bolts to ensure the load-bearing stability of the tower crane;

[0052] Install the lifting frame 3 in parallel between the two tower crane structures 1 and also fix it with bolts to form a frame-type support system;

[0053] Install the triangular lifting bracket 6 and the hydraulic lifter 7 on the lifting frame 3, and connect the first lifting rope (main lifting point) and the second lifting rope (auxiliary lifting point).

[0054] Hoisting of the main section of the steel link corridor 5

[0055] Synchronously lift the main section of the steel link corridor 5 through the first lifting rope (hydraulic lifter 7) and the second lifting rope (tower crane), and use the "main and auxiliary double lifting points" to disperse the load and adjust the attitude;

[0056] During the lifting process, the clamping mechanism clamps the members of the steel link corridor 5, and gradually climbs along the lifting frame 3 through the crawling mechanism, and the sectional locking stop block 4 is used to achieve precise positioning;

[0057] When the design elevation is reached, unload the first lifting rope, and the main section of the steel link corridor 5 is temporarily fixed by the second lifting rope and the clamping mechanism.

[0058] Hoisting of the sectional steel link corridor 5 and installation of the embedded members

[0059] Repeat the hoisting process to lift the sectional steel link corridor 5 to the assembly height;

[0060] Embed the sectional steel link corridor 5 into the main section by using the installation channel space formed by the clamping mechanism;

[0061] The operator installs the embedded members with the assistance of the clamping mechanism to complete the welding or bolt connection between the main section and the sectional section.

[0062] Dynamic position adjustment and reinforcement

[0063] Adjust the position of the holding frame 18 through the position adjustment mechanism (hydraulic telescopic rod 16 / drive motor) to adapt to the deviation of the members of the steel link corridor 5;

[0064] The stabilizing frame 2 is lifted along the extension direction of the lifting frame 3 and installed between the double lifting frames 3 to form multi-point support to enhance the torsional resistance;

[0065] Adjust the spacing of the stop blocks 4 according to the span of the link corridor to ensure the matching accuracy between the locking rod 21 and the limiting rod 19.

[0066] Unloading and finishing

[0067] After all segmented hoisting is completed, gradually unload the second lifting rope, and the steel link corridor 5 is completely supported by the clamping mechanism and the stabilizer 2;

[0068] Check the installation quality of the connection nodes and the filling members, and perform secondary fastening if necessary;

[0069] Dismantle the tower crane, the lifting frame 3 and the auxiliary equipment to complete the construction.

[0070] The above are only the preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention can have various changes and modifications. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims

1. An embedded steel link safety hoisting device, comprising two tower crane structures arranged in pairs, characterized in that, It also includes two lifting frames installed between two tower crane structures. Lifting brackets are installed on both of the two lifting frames. A hydraulic lifter is installed on the lifting bracket. A first lifting rope is installed in the hydraulic lifter. A connector detachably connected to the steel link corridor is installed on the first lifting rope. A second lifting rope detachably connected to the steel link corridor is installed at the lifting end of the tower crane structure. Clamping mechanisms for clamping the steel link corridor are installed on both of the lifting frames. A crawling mechanism moving along the extending direction of the lifting frame is arranged in the clamping mechanism.

2. The safety hoisting device for the embedded steel link corridor according to claim 1, characterized in that, The clamping frame mechanism includes paired frames and a connecting frame. Both of the two frames are installed on the side wall of the connecting frame. A control mechanism for controlling the relative movement of the two connecting frames is arranged in the connecting frame. A plurality of holding frames are installed on the opposite side walls of the frame. The holding frames are detachably connected to the members in the steel link corridor.

3. The safety hoisting device for the embedded steel link corridor according to claim 2, characterized in that A plurality of mounting seats corresponding to the holding frames one by one are installed on the side wall of the frame. An adjustment mechanism for controlling the vertical or horizontal movement of the mounting seat is arranged in the frame.

4. The safety hoisting device for the embedded steel corridor according to claim 3, characterized in that, The holding frame is rotatably arranged on the side wall of the mounting seat. A blocking mechanism for controlling the deflection of the holding frame is arranged on the mounting seat.

5. The safety hoisting device for the embedded steel link corridor according to claim 1 or 2, characterized in that, The crawling mechanism includes a mounting frame installed on the fixed end of the clamping mechanism. A through groove is vertically formed on the side wall of the mounting frame. A part of the lifting frame is embedded in the through groove. Roller structures in contact with the outer side wall of the lifting frame are installed on the opposite side walls of the through groove.

6. The safety hoisting device for the embedded steel corridor according to claim 5, characterized in that, A locking rod is installed at the bottom of the through groove. Limit rods are rotatably arranged at both ends of the locking rod. A plurality of blocking blocks are installed on the side wall of the lifting frame along its extending direction. An adjustment structure for controlling the counterclockwise rotation of the two limit rods is arranged in the locking rod.

7. The safety hoisting device for the embedded steel link corridor according to claim 5, characterized in that, A bidirectional push rod is arranged in the locking rod. Locking holes are formed at the rotation centers of the two limit rods. Limit blocks adapted to the locking holes are installed on the telescopic ends of the bidirectional push rod.

8. A safety hoisting device for an embedded steel corridor according to any one of claims 1-7, characterized in that, A plurality of stabilizing frames are detachably arranged between the two lifting frames. A lifting mechanism for driving the stabilizing frame to lift along the extending direction of the lifting frame is arranged on the side wall of the stabilizing frame.

9. The safety hoisting device for the embedded steel corridor according to claim 6, characterized in that The distance between any two adjacent blocking blocks is adjustable.

10. A hoisting method for an embedded steel corridor, characterized in that, It includes the complementary steel link corridor hoisting device according to any one of claims 1-9, and the hoisting steps are as follows: Pairwise install tower crane structures on the cement foundation ground; Parallelly install lifting frames between the two tower crane structures, and install triangular lifting brackets and hydraulic lifters on the lifting frames to form a frame-type support system; Synchronously lift the main section of the steel link corridor through the first lifting rope connected to the hydraulic lifter and the second lifting rope connected to the tower crane structure to disperse the load and adjust the attitude; During the lifting process, the clamping mechanism clamps the members of the steel link corridor, and gradually climbs along the lifting frame through the crawling mechanism, and segmentally locks the blocking blocks to achieve precise positioning; When reaching the designed elevation, unload the first lifting rope, and the main section of the steel link corridor is temporarily fixed by the second lifting rope and the clamping mechanism; Repeat the hoisting process to lift the segmented steel link corridor to the assembly height; Embed the segmented steel link corridor into the main section of the steel link corridor by using the installation channel formed by the clamping mechanism; The operator installs the embedded and repaired members with the assistance of the clamping mechanism to complete the connection between the main section and the segmented section; The position of the retainer is adjusted through the positioning mechanism to adapt to the deviation of the steel corridor rods and position the installation of the segmented steel corridor and the main section steel corridor; After all sections are hoisted, the second hoisting rope is gradually unloaded, and the steel corridor is completely supported by the clamping mechanism and the stabilizing frame; Check the installation quality of connection nodes and embedded rods, and perform secondary tightening if necessary; The tower crane, lifting frame and auxiliary equipment were removed to complete the construction.