A construction overall progress plan compiling method, system and device

By building a template library for the overall construction schedule, the inefficiency caused by manual input in existing technologies has been solved, enabling the rapid compilation and chart generation of the overall construction schedule for pumped storage power stations, and improving the work efficiency of designers.

CN122334799APending Publication Date: 2026-07-03POWERCHINA ZHONGNAN ENG
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
POWERCHINA ZHONGNAN ENG
Filing Date
2026-03-31
Publication Date
2026-07-03

Smart Images

  • Figure CN122334799A_ABST
    Figure CN122334799A_ABST
Patent Text Reader

Abstract

This invention discloses a method, system, and equipment for compiling a comprehensive construction schedule, belonging to the field of pumped storage power station construction schedules. The method replaces the cumbersome process of manually setting logical relationships by establishing a template library for the comprehensive construction schedule of pumped storage power stations, based on the logical relationships between construction procedures and processes, and between individual buildings. This method provides users with a reference during operation, is simple and easy to learn, greatly improves the work efficiency of schedule designers, and enables the rapid compilation of comprehensive construction schedules and the rapid generation of related charts.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of construction schedule and relates to a method, system and equipment for scheduling a construction master schedule. Background Technology

[0002] A pumped-storage power station construction master schedule is a planning document that coordinates and arranges the construction progress and procedures from commencement to completion. It includes the project preparation period, the main construction period, and the completion period. In terms of structural components, the pumped-storage power station construction master schedule includes diversion works, upper reservoir works, lower reservoir works, water conveyance works, and powerhouse works.

[0003] In the feasibility study phase of a project, developing a master construction schedule is a crucial method for schedule analysis. Currently, commonly used software for developing master construction schedules includes Oracle Primavera P6, Project, and Zebra Schedule. However, these methods require manual input of resource information, project list details, and logical relationships, resulting in a large workload, inconvenient modifications, incomplete information for calculating project duration, and a high risk of errors, omissions, and missing items. Therefore, a new technical solution is urgently needed to effectively address these issues and achieve efficient, convenient, and error-free master construction schedule development for pumped storage power stations. Summary of the Invention

[0004] The present invention aims to provide a method, system and equipment for scheduling a construction master schedule, wherein the method enables efficient, convenient and error-free scheduling of a pumped storage power station construction master schedule.

[0005] To achieve the above objectives, the technical solution adopted by this invention is: a method for arranging a construction schedule, comprising:

[0006] S1. Construct a template library for the overall construction schedule; wherein, the template library includes node projects and individual projects; each individual project includes several individual buildings, the logical relationships between individual buildings, and the construction schedule of the individual project; the logical relationships between individual buildings include the logical relationships between individual buildings within the same individual project and the logical relationships between individual buildings across individual projects;

[0007] S2. Based on the template library, select the individual projects and individual buildings involved in the actual project;

[0008] S3. Preset the reservoir closure time and reservoir gate closing time in the node project corresponding to the actual project;

[0009] S4. Based on the node projects corresponding to the actual project, establish the logical relationship between the individual buildings involved in the actual project, and combine the construction progress of the individual projects to obtain the overall construction schedule of the actual project.

[0010] S5. Update the overall construction schedule of the actual project until the overall project schedule target of the actual project is met;

[0011] S6. Based on the overall construction schedule obtained in step S5, generate a construction schedule Gantt chart, a construction intensity statistics table, a project quantity summary table, and parameter charts.

[0012] The solution provided by this invention establishes a template library for the overall construction schedule of pumped storage power stations. Actual projects can select relevant individual projects and buildings from this library, replacing the tedious process of manually entering the names of individual projects and buildings. This provides users with basic references for modifications, and the operation is simple and easy to learn, greatly improving the work efficiency of schedule designers. The solution provided by this invention enables rapid compilation of the overall construction schedule and achieves a universal design for the output of the overall construction schedule, quickly generating corresponding strength curves.

[0013] According to embodiments of the present invention, the present invention can be further optimized, and the optimized technical solution is as follows:

[0014] In one preferred embodiment, step S1, the construction process of the template library, specifically includes:

[0015] A1. Collect individual project data; wherein, the individual project data includes basic data; the basic data includes project location and quantity; the quantity is the calculated quantity and characteristic quantity of the construction process; the calculated quantity is the physical quantity of the individual project during construction; the characteristic quantity is the geometric characteristic parameter characterizing the structure and construction scale of the individual project;

[0016] A2. Construct the logical relationships between the construction procedures and between the individual buildings; based on the construction period quota, obtain the construction progress indicators of the construction procedures, the construction progress indicators including construction intensity; wherein, the individual buildings are decomposed into multiple construction procedures according to the construction process;

[0017] A3. Based on the construction period of the construction process, the logical relationship between the construction processes, and the logical relationship between the individual buildings, the construction progress of the individual project is obtained; wherein, the construction period of the construction process = the characteristic engineering quantity of the construction process. The construction intensity.

[0018] Compared with the schedule planning schemes provided by existing technologies, the engineering quantity categories of this invention include calculated engineering quantities and characteristic engineering quantities. By adding characteristic engineering quantities, the template library makes the calculation of the construction period more intuitive and convenient.

[0019] In one preferred embodiment, the calculated engineering quantities include excavation volume, filling volume, and concrete pouring volume; the characteristic engineering quantities include slope excavation height, tunnel length, dam filling height, and panel concrete area.

[0020] In one preferred embodiment, step S2 further includes: if the individual project and / or individual building involved in the actual project is not recorded in the template library, then the unrecorded individual project and / or individual building is added to the template library.

[0021] In one preferred embodiment, the node project includes project commencement, preparatory project, preparatory project, commencement of main project, reservoir closure, reservoir gate closure, commissioning of the first generating unit, and project completion.

[0022] In one preferred embodiment, the logical relationships include: a first relationship, a second relationship, a third relationship, and a fourth relationship; the first relationship is that a subsequent process can only begin after the preceding process is completed; the second relationship is that the completion of a subsequent process depends on the completion of the preceding process; the third relationship is that the start of a subsequent process depends on the start of the preceding process; and the fourth relationship is that a subsequent process can only be completed when the preceding process begins.

[0023] In one preferred embodiment, the individual building is a single-level directory structure, a two-level directory structure, or a multi-level directory structure.

[0024] In this invention, individual buildings are divided according to the relevant regulations and specifications for pumped storage power stations. They can be single-level, two-level, or multi-level directory structures to adapt to the arrangement needs of actual projects.

[0025] In one preferred embodiment, step S5 involves updating the overall construction schedule of the actual project, specifically including adjusting the construction schedule of individual projects of the actual project or the reservoir closure time and reservoir gate closing time in the corresponding node projects of the actual project.

[0026] Based on the same concept, the present invention also provides a system for scheduling the overall construction schedule of a pumped storage power station, comprising:

[0027] The template library construction module is used to build a template library for the overall construction schedule; wherein, the template library includes node projects and individual projects; the individual project includes several individual buildings and the logical relationships between individual buildings; the logical relationships between individual buildings include the logical relationships between individual buildings within the same individual project and the logical relationships between individual buildings across individual projects;

[0028] The actual project setting module is used to select individual projects and individual buildings involved in the actual project based on the template library; and to preset the reservoir closure time and reservoir gate closing time in the node project corresponding to the actual project.

[0029] The overall construction schedule update module is used to establish the logical relationship between the individual buildings involved in the actual project based on the node projects corresponding to the actual project, and obtain the overall construction schedule plan of the actual project; it is used to update the overall construction schedule plan of the actual project until the overall project schedule target of the actual project is met.

[0030] The chart generation module is used to generate a construction progress Gantt chart, a construction intensity statistics table, a project quantity summary table, and parameter charts based on the obtained overall construction schedule.

[0031] Based on the same concept, the present invention also provides an electronic device, including a memory, a processor, and a computer program or instructions stored in the memory, wherein the processor executes the computer program or instructions to implement the method for scheduling the overall construction schedule of a pumped storage power station as described above.

[0032] Compared with the prior art, the beneficial effects of the present invention are:

[0033] This invention provides a method, system, and equipment for compiling a comprehensive construction schedule for pumped storage power stations. The method replaces the cumbersome process of manually setting logical relationships by establishing a template library for the comprehensive construction schedule of pumped storage power stations, based on the logical relationships between construction procedures and processes, and between individual buildings. This method provides users with a reference during operation, is simple and easy to learn, and is more user-friendly for beginners compiling comprehensive construction schedules. It significantly improves the work efficiency of schedule designers, enabling rapid compilation of comprehensive construction schedules and rapid generation of related charts. Attached Figure Description

[0034] Figure 1 This is a flowchart of the method for scheduling the overall construction schedule of a pumped storage power station according to an embodiment of the present invention;

[0035] Figure 2 This is a flowchart illustrating the design of the template library for the overall construction schedule of a pumped storage power station according to an embodiment of the present invention.

[0036] Figure 3 This is a flowchart illustrating the overall construction schedule of a new pumped storage power station project according to an embodiment of the present invention. Detailed Implementation

[0037] The present invention will now be described in detail with reference to the accompanying drawings and embodiments. It should be noted that, unless otherwise specified, the embodiments and features described herein can be combined with each other.

[0038] Example 1

[0039] like Figure 1 As shown in Example 1, this embodiment provides a method for scheduling the overall construction schedule of a pumped storage power station. The specific steps are as follows:

[0040] S1. Construct a template library for the overall construction schedule; wherein, the template library includes node projects and individual projects; each individual project includes several individual buildings and the logical relationships between them; the logical relationships between individual buildings include the logical relationships between individual buildings within the same individual project and the logical relationships between individual buildings across different individual projects; the construction process of the template library specifically includes:

[0041] A1. Collect data on individual projects; wherein, the data on individual projects includes basic data; the basic data includes project location and quantity; the quantity includes calculated quantity and characteristic quantity of construction procedures; the calculated quantity is the physical quantity of the project during construction; the characteristic quantity is the geometric characteristic parameter characterizing the structure and construction scale of the individual project;

[0042] A2. Construct the logical relationships between the construction procedures and between the individual buildings; based on the construction period quota, obtain the construction progress indicators of the construction procedures, the construction progress indicators including construction intensity; wherein, the individual buildings are decomposed into multiple construction procedures according to the construction process;

[0043] A3. Based on the construction period of the construction process, the logical relationship between the construction processes, and the logical relationship between the individual buildings, the construction progress of the individual project is obtained; wherein, the construction period of the construction process = the characteristic engineering quantity of the construction process. The construction intensity of the construction process is determined based on the construction period quota. Since the progress indicators and construction intensity in the construction period quota are based on characteristic quantities, characteristic quantities are added to the template library to make the construction period calculation more intuitive and convenient.

[0044] In this embodiment 1, the node project includes project commencement, preparatory project, preparatory project, commencement of main project, reservoir closure, reservoir gate closure, commissioning of the first generating unit, and project completion.

[0045] The calculated engineering quantities include excavation volume, filling volume, and concrete pouring volume; the characteristic engineering quantities include slope excavation height, tunnel length, dam filling height, and panel concrete area.

[0046] In this embodiment 1, the logical relationships include: a first relationship, a second relationship, a third relationship, and a fourth relationship;

[0047] The first relationship is that a subsequent process can only begin after the preceding process has been completed;

[0048] The second relationship is that the completion of a subsequent process depends on the completion of the preceding process;

[0049] The third relationship is that the start of a subsequent process depends on the start of the preceding process;

[0050] The fourth relationship is that a subsequent process can only be completed when the preceding process has started.

[0051] S2. Based on the template library, select the individual projects and individual buildings involved in the actual project;

[0052] In this embodiment 1, if the individual project and / or individual building involved in the actual project is not recorded in the template library, then the unrecorded individual project and / or individual building is added to the template library. The individual building can be a single-level directory structure, a two-level directory structure, or a multi-level directory structure.

[0053] S3. Preset the reservoir closure time and reservoir gate closing time in the node project corresponding to the actual project;

[0054] S4. Based on the node projects corresponding to the actual project, establish the logical relationship between the individual buildings involved in the actual project to obtain the overall construction schedule of the actual project;

[0055] S5. Update the overall construction schedule of the actual project until the overall project schedule target of the actual project is met;

[0056] Update the overall construction schedule of the actual project, specifically including: adjusting the construction schedule of individual projects of the actual project or the reservoir closure time and reservoir gate closing time of the corresponding node projects of the actual project.

[0057] S6. Based on the overall construction schedule obtained in step S5, generate a construction schedule Gantt chart, a construction intensity statistics table, a project quantity summary table, and parameter charts.

[0058] In existing technologies, the strength data corresponding to some engineering quantities needs to be obtained by manually selecting the corresponding buildings and performing cumulative calculations after exporting all strength data. In the pumped storage power station construction schedule planning method provided in Embodiment 1, after the overall construction schedule is completed, it allows for the selection of some or all buildings, and then the engineering quantities of the selected buildings are automatically calculated to generate strength data charts, specifically including monthly and annual strength tables. For example, to obtain the construction intensity of the open excavation of the upper reservoir, only the upper reservoir needs to be selected for the single building, and the construction process needs to be selected as open excavation. The output strength data includes monthly and annual construction intensities for open excavation, earthwork filling, rock excavation, and concrete construction. Corresponding strength curves are generated based on the construction intensity statistics table.

[0059] The method for compiling the overall construction schedule of a pumped storage power station provided in Example 1, based on relevant regulations and standards, enables the creation of a template library, improves the initial scheduling efficiency of the overall construction schedule of conventional pumped storage structures, and allows users to easily and quickly modify and optimize the schedule according to project characteristics.

[0060] Example 2

[0061] Figure 2 This document presents a flowchart for designing a template library for the overall construction schedule of a pumped storage power station. The following section combines... Figure 2 The design process of the construction schedule template library in Example 2 is explained below. The specific steps are as follows:

[0062] Step A01: Collect basic data of individual buildings to obtain individual project data; the basic data includes project location and project quantity.

[0063] A single building is an important component of a construction project, possessing independent construction conditions and complete functionalities. It serves as the basic unit for construction units to prepare construction organization plans and organize construction. In this embodiment 2, a single building includes several individual buildings; each individual building can be decomposed into multiple construction procedures according to the construction process. Each construction procedure, as the smallest work unit, has a quantity attribute, which includes calculated quantities and characteristic quantities. Calculated quantities are the physical quantities of the single building during construction; characteristic quantities are geometric feature parameters that characterize the structure and construction scale of the single building.

[0064] Based on the engineering components of a pumped storage power station, a single building can be a single-level, two-level, or multi-level structure. The corresponding construction procedures include open excavation, tunnel excavation, earthwork filling, and concrete pouring. Calculated quantities include, but are not limited to, excavation volume, filling volume, and concrete pouring volume, all in cubic meters. Characteristic quantities include, but are not limited to, slope excavation height, tunnel length, dam filling height, and concrete panel area, all in meters or square meters. Compared to existing technologies, the basic data collected for a single building in this embodiment 2 is more comprehensive.

[0065] Step A02: Construct a single project schedule library.

[0066] In the individual project schedule database, corresponding schedule database data is configured for each individual project, including the logical relationships between construction procedures, the construction progress indicators of construction procedures, and the logical relationships between individual buildings.

[0067] Based on the construction procedures and technologies of individual buildings, logical relationships are established between construction processes, between individual buildings, and process delays. The definition of logical relationships includes the following four types:

[0068] ① Finish-Start (FS): A subsequent process can only begin after the preceding process has been completed.

[0069] ② Finish-Finish (FF): The completion of a subsequent process depends on the completion of the preceding process;

[0070] ③ Start-Start (SS): The start of a subsequent process depends on the start of the preceding process;

[0071] ④ Start-Finish (SF): A subsequent process can only be completed when the preceding process has started.

[0072] The construction procedures for individual buildings can be obtained from regulations and standards such as the "Design Code for Pumped Storage Power Stations", "Construction Period Quota for Hydropower (including Pumped Storage EPC) Projects" and "Guidelines for the Compilation of Overall Construction Schedule for Pumped Storage Power Station Projects".

[0073] Based on the construction period quota, the construction progress indicators of the construction process are obtained, and the construction progress indicators are matched with the characteristic engineering quantities of the corresponding individual buildings to determine the construction period and construction progress of the individual buildings and corresponding individual projects; the construction of the individual project progress database is completed; among them, the construction period quota refers to the standard construction time specified by the standard for completing the corresponding engineering content, construction process or engineering quantity, and is the basis for calculating the construction period; the construction progress indicators refer to the quantitative indicators used to reflect the construction progress status of the project, including but not limited to the planned start time, planned end time, construction period, construction intensity, etc.

[0074] The construction technology of pumped storage power stations includes civil engineering and electromechanical installation. Civil engineering includes open-cut construction, tunnel excavation, anchor spraying support, dam filling, concrete pouring, and steel pipe installation. Electromechanical installation includes primary electrical systems, secondary electrical systems, and mechanical systems, including transformer installation, secondary cable installation, and pump and turbine installation.

[0075] Step A03: Obtain the construction progress of the individual project.

[0076] The individual project data and the individual project schedule database are preprocessed separately. The preprocessing includes data filtering and editing to ensure the accuracy of the project quantities.

[0077] Divide the characteristic engineering quantity corresponding to the construction process by the construction intensity to obtain the construction period of the construction process. Combine the logical relationship between the construction processes and the logical relationship between individual buildings to obtain the construction progress of the individual project.

[0078] Based on the common individual structures of pumped storage power stations, the above steps can be used to establish a template library for the overall construction schedule of pumped storage power stations.

[0079] Example 3

[0080] like Figure 3 As shown in Example 3, this embodiment provides a method for scheduling the overall construction schedule of a new pumped storage power station project. The specific steps are as follows:

[0081] Step 1: Create a new project using the template library.

[0082] Based on the template library of the overall construction schedule for pumped storage power stations provided in Example 2, select the individual projects and individual buildings involved in the actual new construction project.

[0083] Step 2: Set the logical relationships between individual buildings in the actual new project according to the node project settings.

[0084] Nodes are used to control construction progress and represent key milestone targets. Node projects are engineering contents within the project schedule that represent key milestones and control the construction period, used to identify important control objectives during project implementation. For pumped storage power station projects, node projects include project commencement, preparatory work, preparatory work, commencement of main construction, upper reservoir closure, lower reservoir closure, upper reservoir gate closure, lower reservoir gate closure, commissioning of the first generating unit, and project completion. Based on the project's planned commencement and completion dates, the planned duration of preparatory work, the planned duration of preparatory work, and information on individual buildings, the closure and gate closure times are preset. The node requirement for the overall project schedule target is the commissioning time of the first generating unit. The closure time includes the closure time of the upper and lower reservoirs of the pumped storage power station, and the gate closure time includes the gate closure time of the upper and lower reservoirs.

[0085] Step 3: The construction progress of each individual project is linked to the actual milestone targets of the new project. For example, if a milestone target has a logical relationship with both individual project A and individual project B, the relationship between individual project A and individual project B is indirectly established by linking this milestone target with individual project A and individual project B using any of the four logical relationships provided in Example 2. By linking multiple individual projects sequentially, the overall construction schedule plan for the project can be formed and obtained.

[0086] Through intelligent calculation of the critical path schedule, the initial overall construction schedule for the actual new project is obtained. The critical path is the path with the longest total work duration in the entire project; the critical path schedule refers to the project schedule corresponding to the critical path in the project plan, and its changes directly affect the overall project duration.

[0087] The overall project schedule target is the overall project schedule control target, and the milestone targets are the phased milestone targets obtained by decomposing the overall project schedule target. The achievement of several milestone targets together support the achievement of the overall project schedule target.

[0088] Step 4: Automatically generate a construction schedule Gantt chart based on the actual construction schedule data of the new project. Adjust the construction schedule of individual projects or the construction intensity of individual operations according to the critical path and free float, so that the overall construction schedule changes. Iteratively update the calculation until a construction schedule that meets the overall project schedule target is generated.

[0089] Specifically, after intelligent calculation, if the critical path and nodes meet the overall project schedule target, then step 5 is executed; if any critical path or node does not meet the requirements, then the construction schedule of the individual project is adjusted; if the node does not meet the requirements, but the logical relationship in the construction schedule of the individual project is correct and the schedule indicators have been adjusted to the optimal, then the node target is adjusted, for example, adjusting the reservoir closure time and reservoir gate closing time in the node project corresponding to the actual new project.

[0090] Step 5: Based on the latest Gantt chart of the overall construction schedule after iteration, the main quantities of some or all individual buildings can be output as needed. A bar chart of quantities and a strength data table can be generated according to the schedule time, showing the strength data by year and month, the total amount, etc., which provides convenience for subsequent work such as earthwork balance and concrete aggregate calculation.

[0091] When creating an actual project, for individual buildings that are missing from the template library, you can add the following information: project name, planned start time, planned end time, quantity, duration, logical relationships, etc., to complete and arrange the missing individual buildings and update them to the template library.

[0092] If the overall construction schedule for Project A has already been completed, and Project B contains the same individual structures as Project A—for example, both projects have concrete-faced dams for both upper and lower reservoirs and two-stage vertical shafts for their water conveyance systems, differing only in dam height and shaft depth—then the source files for Project A can be used to import the updated bill of quantities for Project B, generating the initial overall construction schedule for Project B with a single click. The source files for Project A include individual project data, an individual project schedule library, and individual project construction schedules.

[0093] Example 4

[0094] This embodiment 4 also provides a system for scheduling the overall construction schedule of a pumped storage power station, including:

[0095] The template library construction module is used to build a template library for the overall construction schedule; wherein, the template library includes node projects and individual projects; the individual project includes several individual buildings and the logical relationships between individual buildings; the logical relationships between individual buildings include the logical relationships between individual buildings within the same individual project and the logical relationships between individual buildings across individual projects;

[0096] The actual project setting module is used to select individual projects and individual buildings involved in the actual project based on the template library; and to preset the reservoir closure time and reservoir gate closing time in the node project corresponding to the actual project.

[0097] The overall construction schedule update module is used to establish the logical relationship between the individual buildings involved in the actual project based on the node projects corresponding to the actual project, and obtain the overall construction schedule plan of the actual project; it is used to update the overall construction schedule plan of the actual project until the overall project schedule target of the actual project is met.

[0098] The chart generation module is used to generate a construction progress Gantt chart, a construction intensity statistics table, a project quantity summary table, and parameter charts based on the obtained overall construction schedule.

[0099] The system provided in this embodiment 4 enables progress management, generates charts in different formats, and then compiles the relevant charts to obtain a construction progress report, thus completing the preparation of the overall construction schedule.

[0100] This embodiment 4 also provides an electronic device, which includes: a memory, a processor, and a computer program or instructions stored in the memory. The processor executes the computer program or instructions to implement the pumped storage power station construction schedule arrangement method in embodiment 1.

[0101] Although not shown, the electronic device includes a processor that can perform various appropriate operations and processes based on programs and / or data stored in read-only memory (ROM) or loaded from a storage portion into random access memory (RAM). The processor can be a multi-core processor or may contain multiple processors. In some embodiments, the processor may include a general-purpose main processor and one or more specialized coprocessors, such as a central processing unit, graphics processing unit (GPU), neural network processor (NPU), digital signal processor (DSP), etc. Various programs and data required for device operation are also stored in RAM. The processor, ROM, and RAM are interconnected via a bus. Input / output (I / O) interfaces are also connected to the bus.

[0102] The processor and memory described above are used together to execute programs / instructions stored in the memory. When the program / instructions are executed by the computer, they can implement the methods, steps, or functions described in the above embodiments.

[0103] The above embodiments should be understood as being used only to illustrate the present invention more clearly, and not to limit the scope of the present invention. After reading the present invention, any modifications of the present embodiments by those skilled in the art will fall within the scope defined by the appended claims.

Claims

1. A method of making a master schedule, characterized by, include: S1. Construct a template library for the overall construction schedule; wherein, the template library includes node projects and individual projects; each individual project includes several individual buildings, the logical relationships between individual buildings, and the construction schedule of the individual project; the logical relationships between individual buildings include the logical relationships between individual buildings within the same individual project and the logical relationships between individual buildings across individual projects; S2. Based on the template library, select the individual projects and individual buildings involved in the actual project; S3. Preset the reservoir closure time and reservoir gate closing time in the node project corresponding to the actual project; S4. Based on the node projects corresponding to the actual project, establish the logical relationship between the individual buildings involved in the actual project, and combine the construction progress of the individual projects to obtain the overall construction schedule of the actual project. S5. Update the overall construction schedule of the actual project until the overall project schedule target of the actual project is met; S6. Based on the overall construction schedule obtained in step S5, generate a construction schedule Gantt chart, a construction intensity statistics table, a project quantity summary table, and parameter charts.

2. The construction master schedule planning method of claim 1, wherein, In step S1, the construction process of the template library specifically includes: A1. Collect data on individual projects; wherein, the data on individual projects includes basic data; the basic data includes project location and quantity; the quantity includes calculated quantity and characteristic quantity of construction procedures; the calculated quantity is the physical quantity of the project during construction; the characteristic quantity is the geometric characteristic parameter characterizing the structure and construction scale of the individual project; A2. Construct the logical relationships between the construction procedures and between the individual buildings; based on the construction period quota, obtain the construction progress indicators of the construction procedures, the construction progress indicators including construction intensity; wherein, the individual buildings are decomposed into multiple construction procedures according to the construction process; A3. Based on the construction period of the construction process, the logical relationship between the construction processes, and the logical relationship between the individual buildings, the construction progress of the individual project is obtained; wherein, the construction period of the construction process = the characteristic engineering quantity of the construction process. The construction intensity.

3. The method for arranging the overall construction schedule according to claim 2, characterized in that, The calculated engineering quantities include excavation volume, filling volume, and concrete pouring volume; the characteristic engineering quantities include slope excavation height, tunnel length, dam filling height, and panel concrete area.

4. The method for arranging the overall construction schedule according to claim 2, characterized in that, Step S2 further includes: if the individual project and / or individual building involved in the actual project is not recorded in the template library, then the unrecorded individual project and / or individual building is added to the template library.

5. The method for arranging the overall construction schedule according to claim 1, characterized in that, The key milestones include project commencement, preparatory work, preparatory work, commencement of main construction, reservoir closure, reservoir gate closure, commissioning of the first generating unit, and project completion.

6. The method for arranging the overall construction schedule according to claim 1, characterized in that, The logical relationships include: first relationship, second relationship, third relationship, and fourth relationship; The first relationship is that a subsequent process can only begin after the preceding process has been completed; The second relationship is that the completion of a subsequent process depends on the completion of the preceding process; The third relationship is that the start of a subsequent process depends on the start of the preceding process; The fourth relationship is that a subsequent process can only be completed when the preceding process has started.

7. The method for arranging the overall construction schedule according to claim 1, characterized in that, The individual building has a single-level directory structure, a two-level directory structure, or a multi-level directory structure.

8. The method for arranging the overall construction schedule according to claim 1, characterized in that, In step S5, the overall construction schedule of the actual project is updated, which specifically includes: adjusting the construction schedule of individual projects of the actual project or the reservoir closure time and reservoir gate closing time of the corresponding node projects of the actual project.

9. A construction master schedule scheduling system, characterized in that, include: The template library construction module is used to build a template library for the overall construction schedule; wherein, the template library includes node projects and individual projects; the individual project includes several individual buildings and the logical relationships between individual buildings; the logical relationships between individual buildings include the logical relationships between individual buildings within the same individual project and the logical relationships between individual buildings across individual projects; The actual project setting module is used to select individual projects and individual buildings involved in the actual project based on the template library; and to preset the reservoir closure time and reservoir gate closing time in the node project corresponding to the actual project. The overall construction schedule update module is used to establish the logical relationship between the individual buildings involved in the actual project based on the node projects corresponding to the actual project, and obtain the overall construction schedule plan of the actual project; it is used to update the overall construction schedule plan of the actual project until the overall project schedule target of the actual project is met. The chart generation module is used to generate a construction progress Gantt chart, a construction intensity statistics table, a project quantity summary table, and parameter charts based on the obtained overall construction schedule.

10. An electronic device comprising a memory, a processor, and a computer program or instructions stored in the memory, characterized in that, The processor executes the computer program or instructions to implement the construction schedule arrangement method as described in any one of claims 1 to 8.