A construction method for jacking up a bridge structure by using an air bag jacking module
By using an airbag lifting module with an airtight, isolated load-bearing air chamber, combined with load diffusion and guiding limit components, the air chamber status can be monitored and adjusted in real time. This solves the problems of insufficient synchronous control and safety in bridge lifting construction, and achieves stable lifting and safe lowering of the bridge structure.
Patent Information
- Application Number
- CN202611556577.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-09
- Publication Date
- 2026-11-10
AI Technical Summary
Existing bridge jacking construction methods suffer from several problems, including high requirements for equipment layout space, difficulty in synchronous control of multi-point jacking, difficulty in accurately controlling the stress state of flexible airbags, and insufficient jacking safety after local air chamber depressurization.
An airbag lifting module with multiple airtightly isolated load-bearing air chambers is adopted. The stress stability of the airbag is improved by load diffusion components and guide limiting components. The displacement deviation of the lifting point is used as the main control quantity and the pressure of the load-bearing air chamber is used as the constraint quantity. The air intake and exhaust volume of the air chamber is adjusted in real time. Combined with bridge attitude monitoring and mechanical locking measures, multi-point coordinated lifting of the bridge structure is achieved.
The synchronous control and safe jacking of bridge structures under complex conditions have improved the adaptability and safety of jacking construction and reduced construction risks.
Smart Images

Figure CN123064100A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to a bridge jacking method, and more particularly to a construction method for jacking a bridge structure using an airbag jacking module. Background Technology
[0002] In bridge elevation adjustment, structural correction, and repair and reinforcement processes, it is often necessary to lift the entire or partial superstructure of the bridge to a certain height. Current bridge lifting methods mostly employ hydraulic jacks in conjunction with temporary support systems to achieve multi-point lifting. This method has high requirements for lifting space, reaction support conditions, and equipment layout. Under conditions of limited space under the beam, irregular support surfaces, or simultaneous multi-point lifting, construction layout and synchronous control are quite challenging. Airbags, with their small thickness, large bearing area, adaptability to irregular contact surfaces, and continuous displacement adjustment through inflation and deflation, can serve as flexible load-bearing units for bridge lifting. However, existing airbag lifting technologies mostly focus on simple inflation and deflation control of single or multiple airbags. While basic forms such as multi-bag synchronous lifting, ordinary valve control, and multi-layer or compartmentalized airbags are relatively common, existing technologies still suffer from problems such as rapid decrease in the load-bearing capacity of the lifting point after a single airbag ruptures, lateral expansion and eccentric loading during airbag inflation, difficulty in ensuring synchronous displacement of multiple lifting points relying solely on pressure control, and a lack of reliable load-bearing maintenance and fault isolation measures in case of abnormal pressure loss. Therefore, the technical problem this invention aims to solve is: addressing the issues of limited lifting space, coupled loads and deformations at each lifting point, and the synchronous control and failure safety problems caused by the flexible bearing characteristics of airbags during multi-point bridge lifting. This invention provides a construction method for graded bridge lifting using airbag lifting modules with independent bearing air chambers. By real-time monitoring of the displacement and air chamber pressure at each lifting point, and using displacement deviation as the primary control basis and air chamber pressure as a safety constraint, the inflation and deflation states of each air chamber are independently adjusted. This achieves coordinated multi-point lifting of the bridge structure while maintaining necessary bearing capacity in the event of local air chamber depressurization or abnormal lifting conditions, thereby improving the synchronicity, adaptability, and safety of bridge lifting construction. Summary of the Invention
[0003] Purpose of the invention: The present invention aims to provide a construction method for lifting bridge structures using an airbag lifting module, in order to solve the problems in existing bridge lifting construction such as high requirements for equipment layout space, difficulty in synchronous control of multi-point lifting, difficulty in accurately controlling the stress state of flexible airbags, and insufficient lifting safety after local air chamber depressurization.
[0004] The technical solution adopted in this invention is a construction method for lifting a bridge structure using an airbag lifting module, comprising the following steps: Step 1: Based on the support reaction force of the bridge structure to be lifted, the bearing area of the beam, and the allowable differential displacement, determine multiple lifting points and the target lifting displacement of each lifting point. Step 2: Install an airbag lifting module at each of the lifting points. The airbag lifting module includes a flexible inflatable carrier and a load diffusion component disposed above the flexible inflatable carrier. The flexible inflatable carrier includes at least two carrier air chambers that are airtightly isolated from each other. Each carrier air chamber has an independently controllable air inlet and outlet port. Step 3: Connect the multiple airbag lifting modules to the multi-point synchronous lifting control system, and obtain the gas pressure of each bearing air chamber and the actual lifting displacement of each lifting point through pressure sensors and displacement sensors respectively. Step 4: Pre-inflate each airbag lifting module to make the load diffusion component contact the corresponding pressure-bearing area of the bridge structure, and determine the initial bearing state of each lifting point based on the pressure and displacement response during the pre-inflation process. Step 5: Inflate and lift multiple airbag lifting modules in stages according to the preset displacement increment. In each lifting stage, the displacement deviation between the target displacement and the measured displacement of each lifting point is used as the main control quantity, and the gas pressure of each bearing air chamber is used as the constraint quantity. Adjust the air intake and / or exhaust volume of the corresponding bearing air chamber respectively so that each lifting point is lifted synchronously according to the predetermined displacement relationship. Step 6: After the bridge structure reaches the target lifting height, the bridge structure will undergo elevation adjustment and structural modification operations. Step 7: After the operation is completed, the multiple airbag lifting modules are vented in stages, and the venting volume of the corresponding bearing air chamber is coordinated and adjusted according to the measured displacement of each lifting point, so that the bridge structure descends synchronously and the bridge load is transferred to the permanent support structure.
[0005] Furthermore, the airbag lifting module also includes a load-bearing base disposed below the flexible inflatable carrier, and a guide limiting component disposed around the flexible inflatable carrier. The guide limiting component is used to limit the lateral expansion and lateral movement of the flexible inflatable carrier during the inflation process, and to allow the load diffusion component to move along the lifting direction.
[0006] Furthermore, the load diffusion assembly includes one or more pressure plates corresponding to the bridge web, diaphragm, bearing area and / or other designed pressure-bearing areas, to transfer the lifting force generated by the airbag lifting module to the predetermined pressure-bearing area of the bridge structure.
[0007] Furthermore, during the pre-inflation process, the pressure and displacement changes of each lifting point are acquired, and the airbag lifting module is determined to be in an uncontacted state, a normal contact state, or an abnormal off-center load state based on the correspondence between the pressure and displacement changes. After confirming that each lifting point has reached the predetermined contact state, the formal lifting begins.
[0008] Furthermore, during the staged lifting process, the intake and exhaust volume of the corresponding bearing air chamber is adjusted according to the deviation between the measured displacement of each lifting point and the reference displacement. When the measured displacement of a certain lifting point is greater than the reference displacement, its intake volume is reduced and / or exhaust is performed. When the measured displacement of a certain lifting point is less than the reference displacement, its intake volume is increased, so as to control the difference in displacement between each lifting point within the preset allowable range.
[0009] Furthermore, during the bridge jacking process, the gas pressure of each bearing air chamber in the same airbag jacking module is monitored. When any bearing air chamber experiences abnormal pressure loss or the pressure difference between different bearing air chambers exceeds a preset threshold, the abnormal bearing air chamber is isolated from the gas source, and the remaining bearing air chambers are kept under pressure to limit the sudden descent of the corresponding jacking point.
[0010] Furthermore, during the bridge jacking process, the transverse tilt angle, longitudinal tilt angle and / or control section strain of the bridge structure are monitored simultaneously. When the bridge attitude parameters, structural response parameters or the differential displacement between adjacent jacking points exceed the preset threshold, at least some of the airbag jacking modules are stopped from continuing to inflate and the current jacking state is maintained.
[0011] Furthermore, the airbag lifting module is equipped with a mechanical locking component that changes the support position according to the lifting height. After the predetermined lifting height is completed, the mechanical locking component forms a vertical load-bearing path independent of the flexible inflatable bearing body. After the bridge structure reaches the target lifting height, the mechanical locking component and / or the temporary rigid support structure bear at least part of the static load of the bridge structure.
[0012] Beneficial Effects: Compared with existing bridge jacking construction methods, this invention employs an airbag jacking module with multiple airtight, isolated load-bearing chambers. This allows for bridge structure jacking even under conditions of limited space at the bottom of the beam and complex bearing surface conditions. Load diffusion and guiding / limiting components enhance the stability of the airbag stress and the jacking process. During jacking, displacement deviation at each jacking point is used as the primary control variable, and the pressure of the load-bearing chamber is used as the constraint variable. The air intake and exhaust volumes of each chamber are independently adjusted, thereby improving the synchronous control accuracy of multi-point jacking. Simultaneously, the initial contact and off-center load states of each jacking point are identified during the pre-inflation process. In the event of abnormal depressurization in a local chamber, the faulty chamber is isolated, and the remaining chambers are used to maintain the necessary load-bearing capacity. Combined with bridge attitude and structural response monitoring and mechanical locking load-bearing measures, the construction risks caused by airbag depressurization, asynchronous jacking, and long-term pressure maintenance are reduced, thus improving the adaptability, safety, and reliability of the entire bridge jacking and synchronous beam lowering process. Attached Figure Description
[0013] Figure 1 This is a diagram showing the overall layout of the bridge's airbag multi-point lifting system. Figure 2 This is a cross-sectional structural diagram of the airbag lifting module; Figure 3 Diagram of independent bearing air chamber and air circuit control principle; Figure 4 Block diagram of a multi-point synchronous lifting control system; Figure 5 Diagram of the mechanical locking structure of the airbag lifting module; Figure 6 This is a flowchart of the construction method of the present invention. Detailed Implementation
[0014] The present invention will be further described below with reference to the accompanying drawings and specific embodiments. It should be noted that the following embodiments are only used to illustrate the technical solution of the present invention and are not intended to limit the scope of protection of the present invention. Adjustments can be made to the number of airbag lifting modules, the arrangement of lifting points, the number of bearing air chambers, the air path connection form, and control parameters without departing from the basic concept of the present invention; all of these adjustments can be applied to the present invention.
[0015] like Figure 1 As shown, this embodiment takes the use of an airbag lifting module to adjust the elevation of the bridge superstructure as an example. The bridge structure 1 to be adjusted is supported by multiple piers 2 and permanent bearings 3. Before construction, based on the bridge design data and on-site measurement results, the current elevation, longitudinal slope, transverse slope, and settlement of each support point of the bridge structure 1 are measured, and the target elevation to be achieved at each support position is determined according to the target alignment of the bridge. Based on the difference between the current elevation and the target elevation at each support position, multiple lifting points 4 and the target lifting displacement corresponding to each lifting point 4 are determined. For the overall equal-height lifting of the bridge, the target lifting displacement of each lifting point 4 is the same or basically the same; for the adjustment of the longitudinal slope, transverse slope, or uneven settlement of the bridge, different target lifting displacements are set for each lifting point 4, thereby using differentiated lifting at different positions to adjust the spatial position and alignment of the bridge structure 1.
[0016] Based on the distribution of the support reaction force of bridge structure 1, the bearing pressure area at the bottom of the beam, and the allowable differential displacement during the jacking process, multiple jacking points 4 are set near each pier 2 along the transverse and / or longitudinal direction of the bridge. Each jacking point 4 is equipped with at least one airbag jacking module 5. The multiple airbag jacking modules 5 are connected to the air supply system 6 through air passages and are coordinated and controlled by a multi-point synchronous jacking control system 7. The jacking points 4 are preferably located near the bridge web, diaphragms, permanent supports 3, or other structural areas that can reliably transmit the vertical jacking reaction force.
[0017] like Figure 2As shown, the airbag lifting module 5 includes a load-bearing base 51, a flexible inflatable support body 52, a load diffusion component 53, and a guide and limiting component 54 disposed around the flexible inflatable support body 52. The load-bearing base 51 is disposed on the pier 2, the cap beam, or a separately disposed temporary support structure; the flexible inflatable support body 52 is disposed between the load-bearing base 51 and the load diffusion component 53; the load diffusion component 53 is disposed above the flexible inflatable support body 52 and can move relative to the load-bearing base 51 along the bridge lifting direction as the flexible inflatable support body 52 inflates.
[0018] The load diffusion component 53 can be an integral pressure plate or composed of multiple interconnected pressure plates. Its upper part corresponds to the web, diaphragm, permanent support 3 or other designed pressure-bearing areas of the bridge structure 1. It is used to increase the effective pressure-bearing area between the airbag lifting module 5 and the bridge structure 1, and to transfer the lifting force generated by the flexible inflatable carrier 52 to the predetermined pressure-bearing area of the bridge structure 1.
[0019] The flexible inflatable support body 52 is provided with at least a first support air chamber 521 and a second support air chamber 522. The first support air chamber 521 and the second support air chamber 522 are airtightly isolated from each other and are each provided with an independent inlet and outlet port. In other embodiments, the flexible inflatable support body 52 may also be provided with three or more airtightly isolated support air chambers. Each support air chamber can be inflated, pressurized, and deflated independently to independently adjust the working state of each air chamber according to the actual displacement and load-bearing state of the corresponding position during the lifting process.
[0020] The guide and limit component 54 is disposed around the flexible inflatable support body 52 and forms a guide space that allows the load diffusion component 53 to move vertically. The guide and limit component 54 is used to limit the flexible inflatable support body 52 from excessive lateral expansion, lateral movement or local extrusion under high pressure inflation, so as to improve the stability of the airbag lifting module 5 during the bridge elevation adjustment process.
[0021] like Figure 3 As shown, the first bearing air chamber 521 and the second bearing air chamber 522 are connected to the air supply device 63 via the first air passage 61 and the second air passage 62, respectively. The first air passage 61 is equipped with a first control valve 611 and a first pressure sensor 612, and the second air passage 62 is equipped with a second control valve 621 and a second pressure sensor 622. The first control valve 611 and the second control valve 621 are used to control the intake and / or exhaust volume of the corresponding bearing air chambers, respectively. Each air passage may also be equipped with an isolation valve and a safety relief valve.
[0022] Displacement sensors are installed at each lifting point 4 to acquire the vertical displacement of the bridge structure 1 at the corresponding position. One or more tilt sensors are also installed on the bridge structure 1 to acquire the longitudinal and lateral tilt angles of the bridge structure 1. If necessary, strain sensors can be installed at key control sections of the bridge structure 1. The first pressure sensor 612, the second pressure sensor 622, the displacement sensor, the tilt sensor, and the strain sensor are all communicatively connected to the controller 71. The controller 71 coordinates and controls the air intake and exhaust states of different load-bearing air chambers in each airbag lifting module 5 based on the collected data.
[0023] After the airbag lifting module 5 is installed, it is first pre-inflated. The controller 71 controls the air supply system 6 to inflate the first and second load-bearing air chambers 521 and 522 with a small initial flow rate, causing the flexible inflatable load-bearing body 52 to gradually expand and push the load diffusion component 53 towards the bottom of the bridge structure 1. During the pre-inflation process, the measurement data of the first pressure sensor 612, the second pressure sensor 622, and the displacement sensor are continuously collected. The contact state between the airbag lifting module 5 and the bridge structure 1 is determined based on the correspondence between the pressure changes and displacement changes at each lifting point 4.
[0024] When the pressure in the bearing chamber gradually increases and the corresponding lifting point 4 produces a continuous and stable vertical displacement response, it is considered that the lifting point 4 has entered a normal bearing state. When the pressure in the bearing chamber increases but the corresponding displacement changes abnormally, or when a significant pressure difference appears between the first bearing chamber 521 and the second bearing chamber 522 within the same airbag lifting module 5, it is determined that the corresponding lifting point 4 may have uneven contact, local off-center loading, or installation abnormalities, and the formal lifting is suspended for adjustment of the lifting point 4. After all lifting points 4 reach the predetermined contact and bearing state, the formal elevation adjustment stage begins.
[0025] Before the formal jacking, the total jacking displacement is divided into multiple jacking stages based on the target jacking displacement of each jacking point 4, and a predetermined stage target displacement is set for each jacking stage. For the overall equal-height lifting of the bridge, each jacking point 4 is controlled according to the same or basically the same stage target displacement; for the adjustment of the bridge's longitudinal slope, different stage target displacements are set for each longitudinal support position according to the target longitudinal slope; for the adjustment of the bridge's transverse slope, different stage target displacements are set for different transverse jacking points 4 at the same pier 2 according to the target transverse slope.
[0026] like Figure 4As shown, during the formal jacking process, the controller 71 uses the deviation between the stage target displacement of each jacking point 4 and the measured displacement measured by the displacement sensor as the main control quantity, and uses the pressure of the bearing air chamber measured by the first pressure sensor 612 and the second pressure sensor 622 as the constraint quantity to adjust the opening of the first control valve 611 and the second control valve 621 respectively, thereby controlling the intake and / or exhaust volume of the first bearing air chamber 521 and the second bearing air chamber 522.
[0027] When the measured displacement of a certain lifting point 4 is less than its corresponding stage target displacement, the controller 71 increases the air intake of the corresponding bearing air chamber of the lifting point 4; when the measured displacement of a certain lifting point 4 is greater than its corresponding stage target displacement, the air intake of the corresponding bearing air chamber is reduced, and if necessary, the corresponding bearing air chamber is controlled to exhaust a small amount of air. By independently adjusting multiple airbag lifting modules 5, each lifting point 4 is raised step by step according to the predetermined target displacement relationship, thereby gradually adjusting the bridge structure 1 from its original elevation and spatial attitude to the predetermined target state.
[0028] When the overall height of the bridge is adjusted, the controller 71 mainly limits the synchronous displacement deviation between different jacking points 4, so that the bridge structure 1 rises in a basically parallel manner. When the longitudinal slope of the bridge is adjusted, each longitudinal jacking point 4 gradually forms the target longitudinal slope according to the different cumulative jacking displacements determined in advance. When the transverse slope of the bridge is adjusted, different jacking points 4 on the same cross section are jacked differently according to the height difference relationship corresponding to the target transverse slope, so that the bridge structure 1 is gradually adjusted to the target transverse posture.
[0029] During the lifting process, when the pressure difference between the first bearing air chamber 521 and the second bearing air chamber 522 exceeds the first preset threshold, the controller 71 adjusts the working state of the two bearing air chambers by adjusting the opening of the first control valve 611 and / or the second control valve 621; when the pressure difference further exceeds the second preset threshold, or when a rapid depressurization is detected in any bearing air chamber, the corresponding lifting point 4 is stopped from continuing to lift, and the isolation valve corresponding to the abnormal bearing air chamber is closed to isolate the abnormal bearing air chamber from the air supply system 6, while keeping the remaining normal bearing air chambers under pressure to limit the sudden descent of the corresponding lifting point 4.
[0030] Meanwhile, the controller 71 continuously acquires the longitudinal and lateral attitude of the bridge structure 1 through the tilt sensor, and can monitor the structural response of the key control sections of the bridge structure 1 through the strain sensor. When the longitudinal tilt angle, lateral tilt angle, strain of the control section, or instantaneous differential displacement between adjacent lifting points 4 of the bridge structure 1 exceeds the corresponding preset safety threshold, the controller 71 stops at least part of the airbag lifting modules 5 from continuing to inflate, and maintains the current lifting state until the abnormal cause is eliminated and the structural state meets the conditions for continuing lifting before proceeding to the next lifting stage.
[0031] like Figure 5 As shown, the airbag lifting module 5 can also be equipped with a mechanical locking assembly 55. The mechanical locking assembly 55 is disposed between the load-bearing base 51 and the load diffusion assembly 53, and includes multiple locking positions 551 arranged along the lifting direction and locking elements 552 that can cooperate with different locking positions 551. After each or several lifting stages are completed, the locking elements 552 are moved into the locking position 551 corresponding to the current lifting height, thereby forming a vertical load-bearing path between the load-bearing base 51 and the load diffusion assembly 53 that is independent of the flexible inflatable carrier 52.
[0032] Repeatedly perform graded inflation, displacement adjustment, pressure monitoring, and mechanical locking until each jacking point 4 reaches its predetermined target jacking displacement. After the bridge structure 1 reaches the target elevation, remeasure the elevation of the bridge deck control points, longitudinal slope, transverse slope, and relative height difference of each support point. If there is still a deviation exceeding the allowable range between the measured elevation and the target elevation, fine-tune small displacements are performed using the corresponding airbag jacking module 5 until the elevation and overall alignment of the bridge structure 1 meet the predetermined requirements.
[0033] After bridge structure 1 reaches the target elevation and completes fine-tuning, the permanent support structure is height-compensated based on the adjusted support height of bridge structure 1. In this embodiment, a height compensation component can be installed at the corresponding position of the permanent support 3. The height compensation component can be a height adjustment pad, a height adjustment support, a heightened support pad stone, or other permanent load-bearing structure capable of compensating for the bridge elevation adjustment. The height of the height compensation component is determined based on the actual elevation adjustment of the corresponding support point, so that bridge structure 1 maintains the adjusted target elevation and spatial posture after being re-supported by the permanent support structure.
[0034] After the height compensation components are installed or constructed and reach the design load-bearing conditions, the beams are lowered and the load is transferred in stages. The beam lowering process is carried out in the reverse order of the lifting process. When the mechanical locking component 55 is set, the corresponding airbag lifting module 5 is first controlled to inflate appropriately to bear the current load, then the locking piece 552 at the current locking position 551 is released, and then the gas in the first load-bearing air chamber 521 and the second load-bearing air chamber 522 is slowly discharged according to the preset descent displacement.
[0035] During the lowering process, the controller 71 continues to use the measured displacement of each lifting point 4 as the main feedback quantity to adjust the exhaust volume of each bearing air chamber, so that each lifting point 4 descends in a coordinated manner according to the adjusted target bridge alignment. For bridges with adjusted longitudinal or transverse slopes, the predetermined relative elevation relationship between each support point is maintained during load transfer to prevent changes in the completed longitudinal or transverse slope of the bridge due to different exhaust speeds at different lifting points 4.
[0036] As each airbag lifting module 5 releases air in stages, the load on the bridge structure 1 is gradually transferred from the airbag lifting module 5 to the permanent supports 3 equipped with height compensation components. Once it is confirmed that each permanent support 3 is stably under load, the gas inside the flexible inflatable bearing body 52 is further released, and its load-bearing function is relieved.
[0037] After the load transfer is completed, the elevation, longitudinal slope, transverse slope, and relative height difference of each support point of bridge structure 1 are measured again, and the stress and contact status of permanent bearing 3 and height compensation components are checked. When the final elevation and alignment of bridge structure 1 in the permanent support state meet the design requirements, the airbag lifting module 5, air supply system 6, temporary monitoring equipment, and other temporary components are removed, thereby completing the bridge elevation adjustment construction.
[0038] This embodiment uses bridge elevation adjustment as an example for illustration. Elevation adjustment can involve raising the entire bridge structure 1 to the same height, or it can involve adjusting the longitudinal slope, transverse slope, or correcting uneven settlement by using different lifting displacements at different support locations. This invention is not limited to the specific bridge type and number of lifting points mentioned above. The number, arrangement, and target displacement of each lifting point 4 of the airbag lifting modules 5 can be adjusted according to the bridge structure, support conditions, and elevation adjustment requirements.
[0039] like Figure 6 As shown, a construction method for lifting a bridge structure using an airbag lifting module includes the following steps: Step 1: Based on the support reaction force of the bridge structure to be lifted, the bearing area of the beam, and the allowable differential displacement, determine multiple lifting points and the target lifting displacement of each lifting point. Step 2: Install an airbag lifting module at each of the lifting points. The airbag lifting module includes a flexible inflatable carrier and a load diffusion component disposed above the flexible inflatable carrier. The flexible inflatable carrier includes at least two carrier air chambers that are airtightly isolated from each other. Each carrier air chamber has an independently controllable air inlet and outlet port. Step 3: Connect the multiple airbag lifting modules to the multi-point synchronous lifting control system, and obtain the gas pressure of each bearing air chamber and the actual lifting displacement of each lifting point through pressure sensors and displacement sensors respectively. Step 4: Pre-inflate each airbag lifting module to make the load diffusion component contact the corresponding pressure-bearing area of the bridge structure, and determine the initial bearing state of each lifting point based on the pressure and displacement response during the pre-inflation process. Step 5: Inflate and lift multiple airbag lifting modules in stages according to the preset displacement increment. In each lifting stage, the displacement deviation between the target displacement and the measured displacement of each lifting point is used as the main control quantity, and the gas pressure of each bearing air chamber is used as the constraint quantity. Adjust the air intake and / or exhaust volume of the corresponding bearing air chamber respectively so that each lifting point is lifted synchronously according to the predetermined displacement relationship. Step 6: After the bridge structure reaches the target lifting height, the bridge structure will undergo elevation adjustment and structural modification operations. Step 7: After the operation is completed, the multiple airbag lifting modules are vented in stages, and the venting volume of the corresponding bearing air chamber is coordinated and adjusted according to the measured displacement of each lifting point, so that the bridge structure descends synchronously and the bridge load is transferred to the permanent support structure.
Claims
1. A construction method for lifting a bridge structure using an airbag lifting module, characterized in that: Includes the following steps: Step 1: Based on the support reaction force of the bridge structure to be lifted, the bearing area of the beam, and the allowable differential displacement, determine multiple lifting points and the target lifting displacement of each lifting point. Step 2: Install an airbag lifting module at each of the lifting points. The airbag lifting module includes a flexible inflatable carrier and a load diffusion component disposed above the flexible inflatable carrier. The flexible inflatable carrier includes at least two carrier air chambers that are airtightly isolated from each other. Each carrier air chamber has an independently controllable air inlet and outlet port. Step 3: Connect the multiple airbag lifting modules to the multi-point synchronous lifting control system, and obtain the gas pressure of each bearing air chamber and the actual lifting displacement of each lifting point through pressure sensors and displacement sensors respectively. Step 4: Pre-inflate each airbag lifting module to make the load diffusion component contact the corresponding pressure-bearing area of the bridge structure, and determine the initial bearing state of each lifting point based on the pressure and displacement response during the pre-inflation process. Step 5: Inflate and lift multiple airbag lifting modules in stages according to the preset displacement increment. In each lifting stage, the displacement deviation between the target displacement and the measured displacement of each lifting point is used as the main control quantity, and the gas pressure of each bearing air chamber is used as the constraint quantity. Adjust the air intake and / or exhaust volume of the corresponding bearing air chamber respectively so that each lifting point is lifted synchronously according to the predetermined displacement relationship. Step 6: After the bridge structure reaches the target lifting height, the bridge structure will undergo elevation adjustment and structural modification operations. Step 7: After the operation is completed, the multiple airbag lifting modules are vented in stages, and the venting volume of the corresponding bearing air chamber is coordinated and adjusted according to the measured displacement of each lifting point, so that the bridge structure descends synchronously and the bridge load is transferred to the permanent support structure.
2. The construction method for lifting a bridge structure using an airbag lifting module according to claim 1, characterized in that: The airbag lifting module also includes a load-bearing base disposed below the flexible inflatable carrier, and a guide and limiting component disposed around the flexible inflatable carrier. The guide and limiting component is used to limit the lateral expansion and lateral movement of the flexible inflatable carrier during the inflation process, and to allow the load diffusion component to move along the lifting direction.
3. The construction method for lifting a bridge structure using an airbag lifting module according to claim 2, characterized in that: The load diffusion assembly includes one or more pressure plates corresponding to the bridge web, diaphragm, bearing area and / or other designed pressure-bearing areas, to transfer the lifting force generated by the airbag lifting module to the predetermined pressure-bearing area of the bridge structure.
4. A construction method for lifting a bridge structure using an airbag lifting module according to claim 3, characterized in that: During the pre-inflation process, the pressure and displacement changes of each lifting point are acquired, and the airbag lifting module is determined to be in an uncontacted state, a normal contact state, or an abnormal off-center load state based on the correspondence between the pressure and displacement changes. After confirming that each lifting point has reached the predetermined contact state, the formal lifting begins.
5. A construction method for lifting a bridge structure using an airbag lifting module according to claim 4, characterized in that: During the staged lifting process, the intake and exhaust volume of the corresponding bearing air chamber is adjusted according to the deviation between the measured displacement of each lifting point and the reference displacement. When the measured displacement of a certain lifting point is greater than the reference displacement, its intake volume is reduced and / or exhaust is performed. When the measured displacement of a certain lifting point is less than the reference displacement, its intake volume is increased, so as to control the difference in displacement between each lifting point within the preset allowable range.
6. A construction method for lifting a bridge structure using an airbag lifting module according to claim 5, characterized in that: During the bridge jacking process, the gas pressure of each bearing air chamber in the same airbag jacking module is monitored. When any bearing air chamber experiences abnormal pressure loss or the pressure difference between different bearing air chambers exceeds a preset threshold, the abnormal bearing air chamber is isolated from the gas source, and the remaining bearing air chambers are kept under pressure to limit the sudden drop of the corresponding jacking point.
7. A construction method for lifting a bridge structure using an airbag lifting module according to claim 6, characterized in that: During the bridge jacking process, the transverse tilt angle, longitudinal tilt angle and / or control section strain of the bridge structure are monitored simultaneously. When the bridge attitude parameters, structural response parameters or the differential displacement between adjacent jacking points exceed the preset threshold, at least some airbag jacking modules are stopped from continuing to inflate and the current jacking state is maintained.
8. A construction method for lifting a bridge structure using an airbag lifting module according to claim 7, characterized in that: The airbag lifting module is equipped with a mechanical locking component that changes the support position according to the lifting height. After the predetermined lifting height is completed, the mechanical locking component forms a vertical load-bearing path independent of the flexible inflatable bearing body. After the bridge structure reaches the target lifting height, the mechanical locking component and / or the temporary rigid support structure bear at least part of the static load of the bridge structure.