A prefabricated building hybrid component

By adopting a double-layer interlocking structure and a node steel core tube design between precast concrete columns and beam segments, the construction difficulty and insufficient load-bearing capacity of the node area in prefabricated buildings are solved, achieving efficient and safe prefabricated installation.

CN123064249APending Publication Date: 2026-11-10STATE GRID FUJIAN POWER ELECTRIC CO ECONOMIC RESEARCH INSTITUTE +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611480433.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-22
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

In existing prefabricated buildings, the connection between precast concrete columns and beam segments in the joint area presents problems such as high construction difficulty, difficulty in ensuring welding quality, high risk of stress concentration, and insufficient load-bearing capacity.

Method used

The system adopts a double-layer interlocking structure connection method with precast concrete columns, node H-beams, and beam segment components. The first and second extensions are bolted to the flange plates, and combined with the web plate connectors, a Z-shaped staggered lap joint is formed to ensure a direct force path and avoid stress concentration. The node steel core cylinder is used to achieve hoisting alignment and reduce high-altitude operations.

Benefits of technology

It improves the assembly efficiency and reliability of nodes, reduces the risk of stress concentration, enhances the load-bearing capacity between precast concrete columns and beam segments, and achieves efficient and safe prefabricated installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123064249A_ABST
    Figure CN123064249A_ABST
Patent Text Reader

Abstract

This invention discloses a prefabricated building composite component, comprising a precast concrete column and a beam segment assembly. The precast concrete column is equipped with a node H-beam and a web connector. The node H-beam includes a first web, a first flange, and a second flange, with a first extension on the second flange. The beam segment assembly includes a beam end H-beam, which includes a second web, a third flange, and a fourth flange, with a second extension on the third flange. When the node H-beam and the beam end H-beam are connected, the first extension is bolted to the fourth flange, the second extension is bolted to the first flange, and the web connector is bolted to both the first and second webs. This invention effectively reduces the risk of stress concentration and significantly improves the assembly efficiency and reliability of the nodes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building technology, and in particular to a prefabricated building hybrid component. Background Technology

[0002] In prefabricated buildings, to ensure structural integrity, joint areas often require cast-in-place concrete or complex steel structure connections, making construction extremely difficult. Existing technologies have developed some steel-concrete composite structures, which combine the advantages of steel and concrete, effectively reducing cross-sectional dimensions.

[0003] However, in practical applications, the connection structure of the joint area between precast concrete columns and beam segments often adopts pure end plate bolt butt joint. Especially for H-shaped steel columns, their strong axis stiffness is large, making it easy to weld them to square end plates or steel plates; however, their weak axis stiffness is small, and the web edge is relatively thin. Direct welding to square end plates often cannot guarantee weld quality, resulting in serious stress concentration and local buckling risks, leading to a serious lack of joint bearing capacity in the weak axis direction. Summary of the Invention

[0004] The technical problem to be solved by the present invention is to provide a prefabricated building hybrid component that improves the load-bearing capacity between precast concrete columns and beam segments, while also having the convenience of prefabricated installation.

[0005] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is as follows: A prefabricated building composite component, comprising: A precast concrete column is provided with node H-beams and web plate connectors. The node H-beams include a first web plate, a first flange plate, and a second flange plate. The second flange plate is provided with a first extension. A beam segment assembly includes a beam-end H-beam, wherein the beam-end H-beam includes a second web, a third flange plate and a fourth flange plate, and the third flange plate is provided with a second extension. When the node H-beam and the beam end H-beam are connected, the first extension is bolted to the fourth flange plate, the second extension is bolted to the first flange plate, and the web plate connector is bolted to both the first web plate and the second web plate.

[0006] The beneficial effects of this invention are as follows: It provides a prefabricated building hybrid component, in which a first extension is provided on the first flange plate of the H-beam at the node of the precast concrete column; and a second extension is provided on the fourth flange plate of the H-beam at the beam end of the beam segment assembly. During installation, the first extension is bolted to the fourth flange plate, and the second extension is bolted to the first flange plate to complete the initial positioning. Then, the web plate connector is bolted to both the first and second web plates simultaneously. The double-layer interlocking structure reduces the risk of stress concentration and improves assembly efficiency. In addition, the direct bolting at the middle web plate position makes the force path more direct, avoiding stress loss and weakening between multiple layers of plates, effectively reducing the risk of stress concentration, and significantly improving the assembly efficiency and reliability of the node. Attached Figure Description

[0007] Figure 1 This is a structural schematic diagram of a prefabricated building hybrid component according to the present invention; Figure 2 This is a schematic diagram of the composition of a precast concrete column, a type of prefabricated building component, according to an embodiment of the present invention. Figure 3 This is a schematic diagram showing the connection position relationship of the beam-end H-beam, node H-beam, and web connector of a prefabricated building hybrid component according to an embodiment of the present invention. Figure 4 This is a schematic diagram of the internal composition of a beam segment assembly of a prefabricated building hybrid component according to an embodiment of the present invention; Figure 5 This is a schematic diagram of the node steel core cylinder of a prefabricated building hybrid component according to an embodiment of the present invention; Figure 6 This is a schematic diagram of the internal structure of the upper steel-concrete column segment of a prefabricated building hybrid component according to an embodiment of the present invention.

[0008] Label Explanation: 1. Precast concrete columns; 2. H-beams at beam ends; 11. Node H-beam; 12. Web plate connector; 13. Node steel core tube; 14. Upper steel-concrete column segment; 15. Lower steel-concrete column segment; 16. Spliced ​​end plate; 17. Column H-beam; 18. Column shear stud; 19. Column reinforcement; 20. Column stirrups; 21. Second web; 22. Third flange; 23. Fourth flange; 24. Second extension; 25. Beam shear stud; 26. Beam reinforcement; 27. Beam stirrups; 111. First web plate; 112. First flange plate; 113. Second flange plate; 114. First extension; 161. First stiffening rib; 171. Second stiffening rib. Detailed Implementation

[0009] To explain in detail the technical content, objectives, and effects of the present invention, the following description is provided in conjunction with the embodiments and accompanying drawings.

[0010] In prefabricated buildings, in order to ensure the integrity of the structure, the joint areas often need to be cast in place or connected by complex steel structures, which makes construction extremely difficult.

[0011] Therefore, some steel-concrete composite structures have emerged in the existing technology. This structure combines the advantages of steel and concrete, and can effectively reduce the cross-sectional dimensions. However, in practical applications, the connection construction of the joint areas often presents problems.

[0012] However, most current prefabricated joints use pure end plate bolt connections. This connection method has serious construction bottlenecks: on the one hand, it is extremely difficult to "blindly insert" bolts into holes at high altitudes. Deviations in the processing or installation dimensions of steel components can easily lead to misalignment of bolt holes. Workers often need to repeatedly pry, forcibly pull, or even enlarge the holes to insert the bolts, which is not only time-consuming and labor-intensive, but also requires repeated lifting and adjustment, greatly reducing assembly efficiency. On the other hand, traditional joints are often accompanied by a large amount of on-site welding and cutting work, which is not only greatly affected by the weather, but also involves a lot of hot work, which can easily cause safety hazards, completely violating the original intention of prefabricated buildings to "less welding, less cutting, and no on-site hot work".

[0013] Especially for H-shaped steel columns, their strong axis (flange direction) stiffness is large, making it easy to weld to square end plates or steel plates; however, their weak axis (web direction) stiffness is small, and the web edge is relatively thin. Direct welding to square end plates often cannot guarantee weld quality, resulting in serious stress concentration and local buckling risks, leading to a serious lack of joint bearing capacity in the weak axis direction.

[0014] Please refer to Figure 1 , Figure 2 , Figure 4 as well as Figure 5 To address at least the aforementioned problems, this invention proposes a prefabricated building hybrid component, comprising: A precast concrete column 1 is provided with a node H-beam 11 and a web plate connector 12. The node H-beam 11 includes a first web plate 111, a first flange plate 112 and a second flange plate 113. A first extension 114 is provided on the second flange plate 113. The beam segment assembly includes a beam end H-beam 2, which includes a second web 21, a third flange plate 22 and a fourth flange plate 23, with a second extension 24 provided on the third flange plate 22. When the node H-beam 11 and the beam end H-beam 2 are connected, the first extension 114 is bolted to the fourth flange plate, the second extension 24 is bolted to the first flange plate 112, and the web plate connector 12 is bolted to the first web plate 111 and the second web plate 21 at the same time.

[0015] Combination Figure 4 and Figure 5 As shown, both the first extension 114 and the second extension 24 of the web plate connector 12 are provided with multiple bolt fastening points. During installation, the first extension 114 overlaps below the fourth flange plate 23, and the two interlock to form a Z-shaped staggered overlap, with the bolt fastening points corresponding to each other to complete the bolt connection. The second extension 24 is close to the first flange plate 112, and similarly interlocks to form a Z-shaped staggered overlap; the bolt fastening points of the two also correspond to each other to complete the bolt connection. The web plate connector 12 is provided with two rows of bolt fastening points on the left and right sides, which are respectively aligned and connected with the bolt fastening points on the first web plate 111 and the second web plate 21. In this way, steel is used in the joint connection area, while the column is made of factory-precast concrete. This structure makes full use of the high tensile strength and reliable joint connection of steel, as well as the advantages of concrete in terms of good compressive performance, low cost, and excellent fire resistance, significantly reducing the amount of steel used in the overall structure.

[0016] Combination Figure 2 As shown, the prefabricated building hybrid component of the present invention not only avoids the stress abrupt change caused by traditional straight seam butt joints, making the stress transition smooth and significantly reducing the stress concentration coefficient, effectively reducing the risk of brittle fracture at the joint; more ingeniously, the Z-shaped interlocking itself constitutes a natural "self-positioning guiding structure". When the beam segment is hoisted, it only needs to slide naturally along the interlocking surface to achieve "alignment with the hole", completely eliminating the trouble of using pry bars to force leveling at high altitudes and repeatedly adjusting bolt holes, greatly improving the on-site assembly efficiency.

[0017] Traditional beam-column joints require additional upper and lower flange connecting plates, resulting in a large number of components and a high risk of cumulative errors when multiple steel plates are stacked. Furthermore, repeated hole alignment is necessary during assembly. This embodiment eliminates the need for traditional external upper and lower flange connecting plates by directly opening holes in the first extension 114 and the second extension 24, significantly reducing the number of independent components and on-site assembly procedures. Moreover, the Z-shaped interlocking surfaces directly adhere to the load-bearing structure, and high-strength bolts directly penetrate the steel base material for secure fastening. This more direct force path avoids stress loss and weakening between multiple layers of plates, effectively reducing the risk of stress concentration and significantly improving the assembly efficiency and reliability of the joint.

[0018] like Figure 1 As shown, using the same connection structure, at least two node H-beams 11 are arranged around the circumferential side of the precast concrete column 1; the node H-beams 11 correspond one-to-one with the beam segment components.

[0019] Not only that, such as Figure 2 and Figure 3 As shown, the precast concrete column 1 includes a node steel core cylinder 13, an upper steel-concrete column segment 14, and a lower steel-concrete column segment 15; both the upper steel-concrete column segment 14 and the lower steel-concrete column segment 15 are provided with column H-beams 17; the upper end of the node steel core cylinder 13 is fitted outside the column H-beams 17 of the upper steel-concrete column segment 14, and the lower end of the node steel core cylinder 13 is fitted outside the column H-beams 17 of the lower steel-concrete column segment 15.

[0020] The node steel core tube 13 is preferably made of cold-formed square tube or hot-rolled seamless square tube, and its cross-sectional dimensions are larger than those of the main body of the column H-beam 17 to form a sleeve guide structure. Its interior remains hollow to ensure that the main body of the column H-beam 17 can be smoothly inserted. The wall thickness of the node steel core tube 13 is greater than the flange thickness of the column H-beam 17.

[0021] In this way, the precast concrete column 1 can be smoothly inserted by simply lowering it vertically during hoisting, realizing the "fitting before tightening" process and completely solving the problem of "blindly inserting" bolts at high altitudes when connecting end plates in the traditional way. By controlling the reasonable anchorage length of the node steel core cylinder 13 and the column H-beam 17, as well as the reinforcement lap welding and anchorage length that meet the specifications, the stress transfer between the steel component and the concrete is uniform, and the two can truly work together to bear the load. Among them, the column H-beam 17 uses standard hot-rolled H-beams readily available in the market as the main body of the component. During factory prefabrication, only the longitudinal reinforcing bars and stirrups need to be welded to the surface of the steel section. There is no need for complicated node cutting, cutting, full welding and other cumbersome processes. On-site, there is almost zero cutting and zero hot work.

[0022] Furthermore, for the exposed area between node H-beam 11 and beam end H-beam 2, weathering steel or hot-dip galvanizing + coating double anti-corrosion treatment is adopted, and high-strength bolts are treated with Dacromet, which fundamentally solves the problem of easy corrosion of exposed nodes and greatly improves the durability of the structure throughout its entire life cycle.

[0023] To improve the overall load-bearing capacity of the precast concrete column 1, a second stiffening rib 171 is provided on the H-section steel 17 of the column; such as Figure 6 As shown, the second stiffening rib 171 has two types: a transverse plate and a vertical plate. The transverse plate is positioned between the web and the two flanges of the H-beam 17, and is perpendicular to both the web and the flanges. These three elements are perpendicular to each other, forming a stable cross-shaped reinforced section. The left and right sides of the vertical plate are connected to the two flanges of the H-beam 17, respectively, strengthening the welded base and force transmission path between the weak axis end of the H-beam 17 and the splice end plate 16, indirectly ensuring that the splice end plate 16 and its first stiffening rib 161 can reliably transmit force.

[0024] In some embodiments, such as Figure 2 and Figure 5 The precast concrete column 1 also includes a splicing end plate 16; the connection points between the node steel core cylinder 13 and the upper steel-concrete column segment 14, and the connection points between the node steel core cylinder 13 and the lower steel-concrete column segment 15, are all fitted with splicing end plates 16; the splicing end plate 16 corresponding to the upper steel-concrete column segment 14 is bolted to both the node steel core cylinder 13 and the upper steel-concrete column segment 14; the splicing end plate 16 corresponding to the lower steel-concrete column segment 15 is bolted to both the node steel core cylinder 13 and the lower steel-concrete column segment 15. For example... Figure 6 As shown, the splicing end plate 16 is provided with at least two first stiffening ribs 161.

[0025] like Figure 4 As shown, the beam segment assembly also includes beam reinforcement 26 and beam stirrups 27; the beam reinforcement 26 is laid on the third flange plate 22, and the beam stirrups 27 are arranged around the beam end H-beam 2; the beam stirrups 27 and beam reinforcement 26 are used together to form the concrete beam. Specifically, the beam reinforcement 26 uses HRB400 grade hot-rolled ribbed steel bars with a diameter not less than 16mm; the beam stirrups 27 preferably have a diameter of 8mm and a spacing of 100mm; the concrete cover thickness is preferably 30mm~50mm. The beam reinforcement 26 is connected to the beam end H-beam 2 by lap welding.

[0026] In some embodiments, the rigid components such as the splicing end plate 16, the first stiffening rib plate 161, and the second stiffening rib plate 171 in a prefabricated building composite component are made of atmospheric corrosion resistant steel (weathering steel), or have a hot-dip galvanized layer and an anti-corrosion coating on their surfaces in sequence; the high-strength bolts required for connection are preferably 10.9 grade hot-dip galvanized high-strength bolts, or are treated with Dacromet coating to improve the bolts' own corrosion resistance.

[0027] In addition, beam shear studs 25 are provided on the second web 21. Column shear studs 18 are provided on the web of the column H-beam 17. For example... Figure 4 As shown, the beam shear studs 25 are preferably cylindrical head weld studs, which are vertically welded to the surface of the second web 21 using an electric arc stud welding process and are evenly distributed along the beam length. Similarly, the column shear studs 18 also adopt the same welding process. The introduction of beam shear studs 25 and column shear studs 18 can form a mechanical interlocking effect of "steel stud-concrete" inside the concrete, tightly connecting the steel and concrete into one, and significantly enhancing the bonding performance between steel and concrete.

[0028] The steel core cylinder 13, upper steel-concrete column segment 14, lower steel-concrete column segment 15, and beam segment components of the prefabricated building composite component of the present invention are all prefabricated in the factory. The industrialized prefabrication and assembly construction steps are as follows: The first step is to prefabricate the steel frame in the factory: standard weathering H-beams are purchased as column H-beams 17; the second stiffening ribs 171 of the column H-beams 17 are welded in the factory; column reinforcing bars 19, column stirrups 20, and column shear studs 18 are welded to the column end anchorage section; beam reinforcing bars 26, beam stirrups 27, and beam shear studs 25 are welded to the beam end H-beams 2. An inverted Z-shaped flange, i.e., the second extension 24, is cut out of the beam end H-beams 2. At the same time, the node H-beams 11 of the same type are cut into node end Z-shaped flanges in the opposite direction to the beam end H-beams 2, i.e., the first extension 114; subsequently, the node H-beams 11 are welded to the node steel core cylinder 13 and the splicing end plate 16 in the factory, and the first stiffening ribs 161 are added to the splicing end plate 16.

[0029] The second step involves shot blasting to remove rust, hot-dip galvanizing, and anti-corrosion spraying on the exposed surfaces of the processed steel frame. Then, concrete formwork is erected in the factory, the steel frame with welded steel bars is placed in the formwork, and concrete of strength grade C40 or above is poured directly and cured to the design strength, thus forming precast steel-concrete composite beam and column segments.

[0030] The third step is on-site column assembly: the prefabricated upper concrete column, node steel core tube 13 and lower concrete column are transported to the site, the upper column segment is hoisted, and the upper concrete column and lower concrete column are naturally aligned by the guiding effect of node steel core tube 13. After fitting, the splicing end plate 16 is directly locked by high-strength bolts.

[0031] The fourth step is on-site beam assembly: the prefabricated beam segments are transported to the site and hoisted. The second extension 24 of the H-beam at the beam end is placed on the second flange plate 113 of the node H-beam 11 and positioned by its own weight. Then, high-strength bolts are directly inserted into the preset bolt holes for locking. At the same time, the first web plate 111 and the second web plate 21 are locked together by high-strength bolts through the web plate connecting plate.

[0032] The above description is merely an embodiment of the present invention and does not limit the patent scope of the present invention. Any equivalent modifications made based on the content of the present invention specification and drawings, or direct or indirect applications in related technical fields, are similarly included within the patent protection scope of the present invention.

Claims

1. A prefabricated building hybrid component, characterized in that, include: A precast concrete column (1) is provided with a node H-beam (11) and a web connector (12). The node H-beam (11) includes a first web (111), a first flange (112) and a second flange (113). The second flange (113) is provided with a first extension (114). The beam segment assembly includes a beam end H-beam (2), the beam end H-beam (2) includes a second web (21), a third flange (22) and a fourth flange (23), and the third flange (22) is provided with a second extension (24). When the node H-beam (11) and the beam end H-beam (2) are connected, the first extension (114) is bolted to the fourth flange plate (23), the second extension (24) is bolted to the first flange plate (112), and the web plate connector (12) is bolted to both the first web plate (111) and the second web plate (21).

2. The prefabricated building composite component according to claim 1, characterized in that, The first extension (114) and the third flange (22) are bolted together, as are the second extension (24) and the second flange (113).

3. A prefabricated building hybrid component according to claim 1, characterized in that, At least two of the node H-beams (11) are arranged around the circumferential side of the precast concrete column (1); The node H-beams (11) are connected one-to-one with the beam segment components.

4. A prefabricated building hybrid component according to claim 1, characterized in that, The precast concrete column (1) includes a node steel core cylinder (13), an upper steel-concrete column segment (14), and a lower steel-concrete column segment (15). Both the upper steel-concrete column segment (14) and the lower steel-concrete column segment (15) are provided with column H-beams (17). The upper end of the node steel core cylinder (13) is sleeved outside the column H-beam (17) of the upper steel-concrete column segment (14), and the lower end of the node steel core cylinder (13) is sleeved outside the column H-beam (17) of the lower steel-concrete column segment (15).

5. A prefabricated building hybrid component according to claim 4, characterized in that, The precast concrete column (1) also includes splicing end plates (16). The splicing end plate (16) is fitted at the connection point between the node steel core cylinder (13) and the upper steel-concrete column segment (14) and the connection point between the node steel core cylinder (13) and the lower steel-concrete column segment (15). The splicing end plate (16) of the upper steel-concrete column segment (14) is simultaneously bolted to the node steel core cylinder (13) and the upper steel-concrete column segment (14). The splicing end plate (16) of the lower steel-concrete column segment (15) is simultaneously bolted to the node steel core cylinder (13) and the lower steel-concrete column segment (15).

6. A prefabricated building hybrid component according to claim 5, characterized in that, The splicing end plate (16) is provided with at least two first stiffening ribs (161).

7. A prefabricated building hybrid component according to claim 4, characterized in that, The column H-beam (17) is provided with a second stiffening rib (171).

8. A prefabricated building hybrid component according to claim 4, characterized in that, The second web (21) is provided with beam shear studs (25).

9. A prefabricated building hybrid component according to claim 4, characterized in that, The web of the column H-beam (17) is provided with column shear studs (18).

10. A prefabricated building hybrid component according to claim 1, characterized in that, The beam segment assembly also includes beam reinforcement (26) and beam stirrups (27); The beam reinforcement (26) is laid on the third flange plate (22), and the beam stirrups (27) are arranged around the beam end H-beam (2); The beam stirrups (27) and the beam reinforcement (26) are used together to form a concrete beam.