A method of modular parallel construction of a blast furnace hot blast stove system

By using a modular parallel construction method, the construction site of the hot blast stove system is divided into in-situ construction and offline integration areas. Gantry cranes and SPMTs are used to realize the parallel construction of furnace shell sections and piping systems, which solves the problems of long construction cycle, high-altitude operations and equipment conflicts in traditional construction, and achieves fast and safe construction results.

CN123108219APending Publication Date: 2026-11-17SHANGHAI BAOYE GRP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611269142.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-20
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing hot blast stove systems suffer from problems such as long construction cycles, numerous high-altitude operations, low site utilization, and conflicts with lifting equipment, especially the lack of parallel construction methods in the construction of steel frames and piping systems.

Method used

The modular parallel construction method is adopted, dividing the construction site into two areas: in-situ construction and offline integration. A gantry crane is used for the segmented hoisting of the furnace shell and the transportation of refractory materials. In the offline area, a steel frame and pipeline system are pre-built to form an integrated structural module. The entire module is moved by SPMT and finally the interface connection is completed on the ground.

Benefits of technology

It shortened the construction period, reduced the amount of high-altitude work, improved site utilization, avoided conflicts between lifting equipment, and enhanced construction safety and the controllability of quality control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123108219A_ABST
    Figure CN123108219A_ABST
Patent Text Reader

Abstract

The application discloses a modular parallel construction method of a blast furnace hot blast stove system, and belongs to the technical field of construction of metallurgical industrial furnaces. The method divides a construction site into a first area for in-situ construction of a hot blast stove body and a second area for offline pre-assembly of a steel frame and a pipeline system; a gantry crane is arranged in the first area along the direction of a grate, segmented module hoisting of a furnace shell is completed, and the same gantry crane is used for transportation of refractory masonry materials; in the second area, a steel frame-pipeline integrated structure module is formed synchronously, and welding, flaw detection and corrosion prevention of the pipeline are completed offline; after completion of the two lines, the gantry crane is withdrawn to a non-interference position, the integrated structure module is integrally translated to the position by using an SPMT module transport vehicle or a sliding device, and after positioning review and fine positioning, the pipeline interface is closed. The application realizes true parallel construction of the hot blast stove body, the steel frame and the pipeline system, shortens the construction period, reduces high-altitude operation and avoids conflicts of hoisting equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of furnace and kiln construction technology in the metallurgical industry, specifically relating to a modular parallel construction method for blast furnace hot blast stove systems, which is particularly suitable for rapid, safe, and intensive construction in new hot blast stove projects and renovation projects of old hot blast stoves. Background Technology

[0002] Hot blast stoves are core heat exchange equipment in blast furnace ironmaking processes. A typical system includes multiple hot blast stove bodies, a combined steel frame, and a complex piping network, including main hot blast pipes, cold blast pipes, gas pipes, combustion air pipes, and flue gas pipes. Traditional hot blast stove systems are constructed using an in-situ sequential construction method, which presents the following technical problems: First, the construction period is long: the three main stages of furnace shell installation, steel frame construction, and pipeline installation are carried out sequentially, and any delay in any stage will affect the overall construction period. The construction period of typical projects is generally more than 6 months. Second, there is a lot of high-altitude work: the installation positions of steel frames and pipeline systems are usually 20-40m high, and a large number of welding, bolting, and inspection operations need to be completed at height, which poses significant safety hazards and makes quality control difficult. Third, the site utilization rate is low: the steel frame and pipeline occupy the area around the furnace shell for a long time, and the cross-operation of multiple disciplines leads to site congestion, limited material storage, and low logistics efficiency. Fourth, there is conflict of lifting equipment: large crawler cranes need to be frequently moved, and the three disciplines of furnace shell hoisting, frame installation, and pipeline hoisting compete for the same hoisting equipment resources, resulting in idle work and project delays.

[0003] In recent years, some projects have attempted to optimize the segmented hoisting of single hot blast stove shells using modular technology. However, existing technologies still do not address the offline integrated construction of the steel frame and piping system, nor do they resolve the spatial avoidance and timing coordination issues of collaborative operation between gantry cranes and modular sliding mechanisms (SPMT / sliding systems). In summary, existing technologies lack a modular construction method that can truly achieve parallel construction of the hot blast stove body, steel frame, and piping system, reduce high-altitude operations, and avoid equipment conflicts. Summary of the Invention

[0004] The present invention aims to provide a modular parallel construction method for blast furnace hot blast stove systems to solve the technical problems of long construction period, high-altitude operation, low site utilization and conflict of lifting equipment in the prior art.

[0005] To achieve the above objectives, this invention provides a modular parallel construction method for a blast furnace hot blast stove system. This method is used for the parallel construction of the hot blast stove body, steel frame, and piping system in new or renovated hot blast stove projects. It shortens the construction period and reduces high-altitude operations through dual-line parallel construction of the first area (in-situ construction) and offline integration of the second area, the full reuse of a single gantry crane, and the overall translation and positioning of the integrated structural module. The method includes the following steps: The site was divided into two zones: a first zone for in-situ construction of the furnace shell and a second zone for offline pre-assembly of the steel frame and piping system, with a reserved equipment transport channel between the two zones. In the first zone, gantry crane tracks were laid along the hot blast stove layout, and the gantry crane was installed. Within the first zone, the furnace shell was divided into several segmented modules along its height, and these modules were hoisted into place segment by segment using the gantry crane from bottom to top to form the hot blast stove body. The same gantry crane was also used for vertical material transport during the refractory lining stage inside the furnace. In the second zone, the steel frame was simultaneously erected, and the piping system was pre-installed on the steel frame, forming an integrated steel frame-pipeline structural module. The piping system underwent welding, flaw detection, and anti-corrosion treatment during the offline construction phase. Transport beams or sliding supports were pre-installed at the bottom of the steel frame. After the hot blast stove body was completed and the integrated structural module was constructed, the gantry crane was moved to a non-interference position, and the integrated structural module was moved horizontally to its designed position in the first zone using a SPMT module transport vehicle or sliding device. The pipe interfaces were then connected and fixed to the corresponding interfaces of the hot blast stove body, completing the overall construction.

[0006] Preferably, the lifting capacity Q of the gantry crane is determined according to Q≥K·Gmax, where Gmax is the weight of the largest furnace shell segment module, K is the safety factor and K≥1.25; the positioning is verified by three-dimensional laser scanning or total station before and after the overall translation, and fine-tuning jacks are set at the bottom of the integrated structural module for final precise positioning, with the positioning error controlled within ±5mm; after the interface connection is completed, pressure test and tightness test are carried out, and the test pressure is not less than 1.15 times the design pressure.

[0007] Compared with the prior art, the beneficial effects of the present invention are specifically reflected in the following aspects: Firstly, at the process architecture level, the three sequential links of furnace shell installation, steel frame construction, and pipeline installation are restructured into two parallel processes: "in-situ construction in the first area" and "offline integration in the second area". The site functions are divided according to the construction object, thus eliminating mutual waiting between links and cross-occupancy of the site from the perspective of construction organization. Secondly, in terms of equipment coordination, a single gantry crane runs through the entire process of segmented hoisting of the furnace shell and vertical transportation of refractory lining materials. Before the integrated structural module is moved, it moves to a non-interference position, so that the gantry crane and the module moving system are connected in time and avoid each other in space, thus avoiding the repeated entry and relocation conflicts of multiple large lifting equipment. Thirdly, in terms of quality, the welding, flaw detection and corrosion protection of the pipeline system are completed in a ground prefabrication environment. Combined with finite element verification and three-dimensional scanning, and the actual measurement and positioning of fine-tuning jacks, the quality control is transferred from restricted high-altitude operations to controllable ground operations, and from experience-based estimation to actual data measurement. Fourth, in terms of safety and schedule, the amount of high-altitude work for steel frame and pipeline systems is greatly reduced, and the parallel operation of the two lines directly compresses the overall construction period, resulting in a simultaneous decrease in safety risks and construction costs. Attached Figure Description

[0008] Figure 1 This is a module division diagram of a blast furnace hot blast stove provided in an embodiment of the present invention.

[0009] Figure 2 This is a modular construction elevation view of a hot blast stove system provided for an embodiment of the present invention.

[0010] Figure 3 This is a schematic diagram of the overall translation process of the integrated structural module provided in an embodiment of the present invention. Detailed Implementation

[0011] To further illustrate the technical means and effects of the present invention in achieving its intended purpose, the following detailed description of the specific implementation methods, structures, features, and effects of the present invention, in conjunction with the accompanying drawings and preferred embodiments, is provided below.

[0012] This embodiment uses a 2500m steel plant as an example. 3 Taking the construction of a blast furnace supporting system of three top-fired hot blast stoves as an example, the three hot blast stoves are arranged in a straight line (east-west direction), with each stove having a total shell height of 35m and the largest segment module weighing approximately 200t. On-site working space was limited, and safety management for high-altitude operations was strictly enforced. Figure 1 As shown, the hot blast stove system is divided into module one and module two. Module one is the hot blast stove body built in situ, and module two is the offline integrated steel frame-pipeline integrated structure module 5; the shaded part in the figure is the reserved furnace position.

[0013] S1. Site Zoning: After completing the site survey and overall construction layout, the construction site is divided into Area 1 and Area 2: Area 1 is the design installation location for 3 hot air furnaces, with an area of ​​approximately 40m × 30m; Area 2 is the vacant site adjacent to the north side of Area 1, with an area of ​​approximately 30m × 25m; an 8m wide equipment transportation channel 7 is reserved between the two areas.

[0014] S2. Gantry crane setup: (e.g., ...) Figure 2 As shown, a gantry crane track 31 is laid along the hot blast stove layout direction in the first area 1. The track span is 16m, and QU100 steel rails are used. The track foundation has been verified by load-bearing capacity calculation to meet the requirements for full-load operation and refractory material transportation. A gantry crane 3 with a lifting capacity of 250t and a lifting height of 40m is installed. The lifting capacity is determined by multiplying the weight of the largest furnace shell segment module of 200t by a safety factor of 1.25. The span of the gantry crane 3 covers the width of all hot blast stove positions and the operating space on both sides.

[0015] S3. The segmented modules are usually divided into 2-3 sections of furnace shell as one segmented module. In this embodiment, the 35m furnace shell is divided into three segments: lower (0-12m), middle (12-24m), and upper (24-35m). The gantry crane 3 is used to hoist the modules into place in sequence: first, the lower module is hoisted and aligned and fixed, then the middle module is hoisted and welded to the lower module, and finally the upper module is hoisted. After all the furnace shells are hoisted, they pass the verticality and concentricity tests. The same gantry crane 3 is used for the refractory material lining inside the furnace. The vertical transportation of refractory materials is completed by the gantry crane 3.

[0016] S4. Offline Integrated Construction of Steel Frame and Piping System: In Zone 2, a combined steel frame (total weight approximately 500t) for three hot blast stoves is constructed simultaneously with step S3. The hot blast main pipe (DN2600), cold blast pipe (DN1800), gas pipe (DN1600), and combustion air pipe (DN1400) are pre-installed on the steel frame, forming an integrated steel frame-piping structure module 5 with a total weight of approximately 800t. All pipes undergo welding, 100% radiographic testing, and anti-corrosion coating during the offline phase. Transport support beams are pre-installed at the bottom of the steel frame, with the beam spacing calculated to meet the requirements for SPMT lifting and transportation. Finite element analysis is then performed on the integrated structure module 5 to verify that, under SPMT lifting and transportation conditions, the maximum deformation of the steel frame is no greater than 10mm, the stress safety factor is no less than 1.5, the overturning safety factor is no less than 2.0, and the local bearing capacity of the transport support beams meets the requirements.

[0017] S5. Overall relocation: After the hot blast stove body is completed and the integrated structural module 5 is built, move the gantry crane 3 to a non-interference position and clear the equipment transport channel 7; Figure 3 As shown, a 32-axis SPMT modular vehicle 6 is used to move the integrated structural module 5 from the second area 2 to the designed position corresponding to the three hot blast stoves in the first area 1 at a speed of 3m / min by lifting the transport beam set at the bottom of the steel frame; the module's attitude and settlement are monitored in real time during the translation process.

[0018] S6. Precise Connection and Closure: After the pipes are moved into position, a total station is used for positioning verification. Sixteen 50t micro-adjustment jacks are used for final precise positioning, with the positioning error controlled within ±3mm. The pipe interfaces in the integrated structural module 5 are connected to the corresponding interfaces in the hot blast furnace body 4 via flanges or welding. After all interfaces are connected, an overall pressure test (test pressure is 1.15 times the design pressure) and a tightness test are conducted, and acceptance is passed. After closure, the misalignment of the pipe interfaces is no greater than 2mm. Finally, the gantry crane is removed or partially dismantled, construction waste is cleared, temporary facilities are dismantled, and the area is handed over for subsequent procedures.

[0019] Engineering Empirical Evidence and Beneficial Effects Analysis: In this embodiment, the overall construction period of the hot blast stove system was shortened from the originally planned 120 days to 78 days; the amount of high-altitude welding of the steel frame and piping system was reduced by approximately 65%, and the number of personnel involved in high-altitude operations was reduced by approximately 50%; a single 250t gantry crane completed all furnace shell hoisting and refractory material transportation, eliminating the need for frequent entry and exit of large crawler cranes; and the pressure test was passed on the first attempt. Compared with the traditional in-situ serial construction method, this embodiment shows that in the traditional method, the steel frame and piping are installed piece by piece at high altitude at the furnace shell installation location, with three stages of sequential waiting and frequent relocation of lifting equipment; this invention, through site zoning and offline integration, adds ground prefabrication, overall translation, and actual measurement and positioning stages, transferring high-altitude operations to the ground, reconstructing serial stages into parallel stages, and integrating multiple equipment competing for resources into one machine for reuse; thereby reducing mutual waiting between stages, the amount of high-altitude operations, and the number of times large equipment enters and exits, and simultaneously achieving improvements in construction period, safety, and quality control.

[0020] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make some modifications or alterations to the above-disclosed technical content to create equivalent embodiments without departing from the scope of the present invention. Any simple modifications, equivalent changes and alterations made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the scope of the present invention.

Claims

1. A modular parallel construction method for a blast furnace hot blast stove system, used for the parallel construction of the hot blast stove body, steel frame, and piping system in new or renovated hot blast stove projects. This method utilizes a dual-track parallel approach of in-situ construction in the first area and offline integration in the second area, the full-process reuse of a single gantry crane, and the overall translation and positioning of the integrated structural modules, thereby shortening the construction period and reducing high-altitude operations. Its characteristics are as follows: Includes the following steps: S1. Site Zoning: The construction site is divided into a first area and a second area. The first area is the designed installation location for the hot blast stove body, used for the in-situ construction of the furnace shell. The second area is an empty space adjacent to the first area, used for the offline pre-assembly of the steel frame and piping system. Equipment transportation channels are reserved between the first area and the second area. S2. Gantry crane installation: A gantry crane track is laid in the first area along the hot blast stove layout direction, and a gantry crane is installed on the gantry crane track; S3. In-situ modular construction of hot blast stove body: In the first area, the furnace shell of each hot blast stove is divided into several segment modules along the height direction. The gantry crane is used to hoist each segment module into place from bottom to top to form the hot blast stove body. After the furnace shell is hoisted, the same gantry crane is used for vertical transportation of materials during the refractory material masonry stage inside the furnace. S4. Offline integrated construction of steel frame and piping system: In the second area, the steel frame of the hot blast furnace system is built synchronously with step S3, and the piping system is pre-installed on the steel frame to form an integrated steel frame-piping structure module; the piping system completes welding, flaw detection and anti-corrosion treatment during the offline construction stage; transport beams or sliding supports are pre-set at the bottom of the steel frame. S5. Overall translation: After the hot blast stove body is completed and the integrated structural module is constructed, the gantry crane is moved to a non-interference position; using an SPMT module transport vehicle or sliding device, the integrated structural module is translated from the second area along the equipment transport channel to the designed position in the first area. S6. Precise docking and closure: Connect and fix the pipe interface of the integrated structural module that has been moved into place to the corresponding interface of the hot blast stove body to complete the overall construction of the hot blast stove system.

2. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: In step S2, the lifting capacity Q of the gantry crane is determined according to Q≥K·Gmax, where Gmax is the weight of the largest furnace shell segment module, K is the safety factor and K≥1.25; the span of the gantry crane covers the width of all hot blast furnace positions and the operating space on both sides; the track foundation of the gantry crane track is verified by bearing capacity calculation.

3. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: In step S3, the hot blast stove shell is divided into several sections along the height direction as a segmented module. After each segmented module is hoisted into place, it is welded together section by section. After passing the verticality and concentricity inspection, refractory material masonry is carried out.

4. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: In step S4, the pipeline system includes one or more of the following: hot air main pipe, cold air pipe, gas pipeline, combustion air pipeline and flue gas pipeline; each pipeline undergoes 100% radiographic testing and anti-corrosion coating during the offline construction phase.

5. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: Before step S5, the integrated structural module is verified by finite element analysis: under the lifting and transportation conditions, the maximum deformation of the steel frame is not greater than 10mm, the stress safety factor is not less than 1.5, the overturning safety factor is not less than 2.0, and the local bearing capacity of the transportation beam meets the requirements.

6. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: In step S5, when the SPMT module transport vehicle is used for translation, the translation is achieved by lifting the transport beam set at the bottom of the steel frame by the module vehicle; when the sliding device is used for translation, the translation is achieved along the preset sliding track; the path is checked and obstacles are cleared before and after translation, and the attitude and settlement of the integrated structural module are monitored in real time during the translation process.

7. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: In step S5, before and after the overall translation, a three-dimensional laser scan or total station is used for positioning verification, and a fine-tuning jack is set at the bottom of the integrated structural module for final precise positioning, with the positioning error controlled within ±5mm.

8. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: In step S6, the pipe interface and the corresponding interface of the hot air furnace body are connected by flange or welded together; after the interface connection is completed, a pressure test and a tightness test are carried out, and the test pressure of the pressure test is not less than 1.15 times the design pressure.

9. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: The hot blast stove system includes 2-4 hot blast stoves, the steel frame is a combined frame, and the integrated structural module includes the combined frame and its supporting piping system.

10. The modular parallel construction method for a blast furnace hot blast stove system according to claim 1, characterized in that: The gantry crane is reused throughout the entire process of vertical material transport from the furnace shell segment module hoisting through the refractory lining stage inside the furnace until the integrated structural module is moved as a whole, at which point it is moved to a non-interference position by means of whole machine relocation or partial dismantling.