A prefabricated large-scale construction scaffold for pipe-mounted operations and its construction method

By using prefabricated large-scale construction scaffolds for in-pipe operations, and utilizing detachable connections and enclosed operation modes, the problems of high safety risks, difficult dismantling, and long cycles associated with high-altitude welding have been solved. This has enabled rapid installation and dismantling, as well as the repeated turnover of components, thereby improving construction safety and efficiency.

CN123109069APending Publication Date: 2026-11-17CHINA RAILWAY CONSTR CORP (INT) LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611520200.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-29
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing large load-bearing supports involve a large amount of high-altitude welding work, high safety risks, are difficult to dismantle, cannot reuse components, and have a long construction cycle.

Method used

The system employs a prefabricated large-scale construction scaffold with in-pipe operation. It achieves a completely weld-free and enclosed operation through detachable support columns, connecting units, and operating units. Installation and disassembly are carried out using detachable horizontal support components and cross diagonal bracing components. Ladders and operating platforms are installed inside the support columns, allowing workers to complete connection and disassembly operations inside the pipe.

Benefits of technology

It enables fully enclosed operations within the pipe, eliminating the risk of falls from heights, avoiding high-altitude welding and gas cutting for dismantling, allowing components to be reused, shortening the construction cycle, and improving construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109069A_ABST
    Figure CN123109069A_ABST
Patent Text Reader

Abstract

This invention relates to the technical field of construction of tall load-bearing structures, specifically to a prefabricated large-scale construction scaffold and construction method for in-pipe operation, comprising multiple support columns, connecting units, and operating units. The support columns are arranged at intervals along the longitudinal and transverse directions; each support column is detachably connected from multiple standard pipe segments along its height; the connecting unit includes detachably connected horizontal support members and cross bracing members disposed between adjacent support columns; the operating platform is located below the operating hole, providing a platform for workers to stand and perform installation or disassembly operations on the horizontal support members and cross bracing members via the operating hole. Therefore, an alternating operation mode of layer-by-layer erection and connection is formed, the overall stability of the scaffold is established layer by layer in real time, realizing fully enclosed in-pipe operation, fully prefabricated rapid installation and disassembly, and reusable components.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the technical field of construction of tall load-bearing structures, and more specifically, to a prefabricated large-scale construction support and construction method for pipe-mounted operations. Background Technology

[0002] In the construction of tall load-bearing structures, especially in the construction of the bridge deck system of high-tower bridges such as cable-stayed bridges and suspension bridges, it is usually necessary to erect large temporary load-bearing supports between two towers for the construction of the crossbeams and section 0 of the cable-stayed bridge. These load-bearing supports are often erected on the inner side of the tower crossbeams or on the top surface of the corbels, and the height of the load-bearing supports can reach tens of meters or more, which are typical high-altitude, large-span, heavy-load temporary structures.

[0003] Currently, the erection of such large load-bearing supports mainly adopts on-site welded steel pipe supports. These supports use steel pipe columns as the main vertical supports, with horizontal connections and diagonal braces forming rigid nodes with the steel pipe columns through on-site welding. During construction, workers must rely on external ladders to perform extensive welding work at heights of hundreds of meters. The welding quality of key load-bearing nodes is significantly affected by the high-altitude working environment (such as wind, temperature, and confined working space), making quality control difficult and non-destructive testing and acceptance inconvenient. Furthermore, workers can only move up and down using external ladders, resulting in extremely limited working space and a very high safety risk level for working near edges at heights. During dismantling, because the components are welded together, they cannot be easily disassembled; gas cutting is usually required to cut and dismantle the nodes. The dismantled components often interfere with the external working platform, further increasing on-site safety risks. In addition, the overall construction cycle for this type of support is long. Although the initial component processing cost is relatively low, the later installation and dismantling processes are time-consuming and consume a large amount of manpower, materials, and equipment. Summary of the Invention

[0004] This invention solves the technical problems of large-scale high-altitude welding operations, high safety risks, difficult dismantling, and non-reusability of components in large load-bearing supports, and achieves the construction effect of no welding throughout the process, closed operation inside the pipe, and rapid assembly and dismantling of fully prefabricated components.

[0005] To address the aforementioned problems, this invention provides a prefabricated large-scale construction scaffold for pipe-based operations, used in the construction of tall structures to support the load of cast-in-place superstructure construction, comprising: Multiple support columns are arranged at intervals in the longitudinal and transverse directions; each support column is detachably connected from multiple standard pipe segments along the height direction, and the bottom of the side wall of the lowest standard pipe segment in each support column is provided with an access port for workers to enter the interior of the support column. The connecting unit includes a horizontal support member and a cross brace member that are detachably connected between adjacent support columns. An operating hole is provided on the side wall of the support column at the installation position corresponding to the horizontal support member and the cross brace member. The operating unit includes an operating platform and a ladder located inside the support column. The ladder is arranged along the axial direction of the support column. The operating platform is located below the operating hole and is used for workers to stand and install or disassemble the horizontal support and the cross bracing through the operating hole.

[0006] Preferably, two adjacent standard pipe segments on each of the support columns are detachably connected by flanges and connecting bolts.

[0007] Preferably, the standard pipe segments at the same horizontal height in each of the supporting pipe columns together constitute a standard pipe segment layer; the horizontal support member is provided between adjacent supporting pipe columns in the same standard pipe segment layer, and the supporting pipe column is provided with a connecting seat, and the end of the horizontal support member is detachably connected to the connecting seat by adjusting bolts.

[0008] Preferably, the cross bracing member is a pair of cross bracing rods arranged in a cross manner. The pair of bracing rods are located between adjacent support columns within the same standard pipe section layer. An inclined sleeve is fixed on the side wall of the support column. The two ends of the bracing rods pass through the corresponding sleeves and extend into the interior of two adjacent support columns, and are detachably connected to the support columns through a connecting assembly.

[0009] Preferably, the connecting assembly includes a pad and a connecting sleeve, the connecting sleeve being located inside the support column and threaded to one end of the diagonal brace passing through the sleeve, and the pad being clamped between the connecting sleeve and the sleeve.

[0010] Preferably, the horizontal support is a steel beam, and lifting points are provided at both ends of the horizontal support. The lifting points are arranged near the operating hole and are used to remove the lifting load after the equipment is lifted into place.

[0011] Preferably, the operating platform includes a mounting steel pipe and a platform plate, wherein the mounting steel pipe is horizontally inserted through and fixed to the side wall of the supporting column, and the platform plate is horizontally laid on the mounting steel pipe.

[0012] Preferably, the interior of the support column is provided with multiple fall-prevention safety nets spaced apart along its axial direction, and the fall-prevention safety nets are located below the operating platform.

[0013] Preferably, the bottom of the support column is provided with a leveling joint, which is located below the inlet. The lower end of the leveling joint is fixed to the foundation embedded plate and is used to adjust the installation elevation and verticality of the support column.

[0014] This invention also provides a construction method for a prefabricated large-scale construction scaffold for pipe-mounted operations, comprising the following steps: Step 1: Install the foundation embedded plate on the concrete foundation between the two bridge towers; Step 2: Fix the prefabricated leveling joint to the top surface of the foundation embedded plate; Step 3: Hoist and fix the standard pipe section onto the leveling joint as the base section; Step 4: The workers enter the support column through the entrance of each of the basic sections, climb the ladder to the operating platform at the corresponding operating hole, and install horizontal support components and cross diagonal bracing components between adjacent support columns in the same standard pipe section layer through the operating hole. Step 5: Hoist and splice the standard pipe segments sequentially on top of the foundation segment and connect and fix them. Repeat Step 4 until the support column is erected to the design height. Step Six: Lay steel beams and bottom formwork on top of the uppermost standard pipe segment, and carry out the bridge deck concrete pouring construction; Step 7: After the construction is completed, the workers enter the interior of each of the supporting columns again through the entrance, climb the ladder to the operating platform corresponding to the operating hole, and disassemble the horizontal support and the cross bracing in sequence through the operating hole; Step 8: Dismantle each of the standard pipe sections from top to bottom to complete the overall dismantling of the support.

[0015] The beneficial effects of this invention are as follows: This invention provides a prefabricated large-scale construction scaffold for in-pipe operations. The support column has an entry point at its bottom, an internal ladder and operating platform, and operating holes on its side walls. Workers can enter the support column and reach the operating platforms via the ladders, then install and dismantle horizontal support components and cross braces through the operating holes. The entire operation is conducted within the enclosed space inside the support column, eliminating the need for external edge work and thus preventing falls from heights. Furthermore, the horizontal support components and cross braces are detachable, eliminating the need for on-site welding and gas cutting. Each component can be disassembled into standard parts for repeated use. Each support column is composed of multiple detachable standard pipe segments. The installation of each standard pipe segment completes the installation of the connecting components for that layer, forming an alternating layer-by-layer erection and connection pattern, ensuring the overall stability of the scaffold is established layer by layer. Therefore, this invention solves the technical problems of difficult quality control in high-altitude welding, high risks associated with edge work, and difficult and time-consuming dismantling, achieving fully enclosed in-pipe operations, rapid prefabricated installation and dismantling, and reusable components.

[0016] The construction method of the prefabricated large construction support for pipe operation in this embodiment has the same beneficial effects as the above-mentioned prefabricated large construction support for pipe operation, and will not be repeated here. Attached Figure Description

[0017] Figure 1 This is a schematic diagram of a prefabricated large construction support for pipe operation in one embodiment of the present invention.

[0018] Figure 2 for Figure 1 Enlarged view of the connection point of a standard pipe segment.

[0019] Figure 3 This is a schematic diagram of an axial section of a standard pipe segment in one embodiment of the present invention.

[0020] Figure 4 This is a diagram showing the installation and use of the cross brace on the support column in one embodiment of the present invention.

[0021] Explanation of reference numerals in the attached figures: 1-Supporting pipe column; 10-Standard pipe section; 101-Inlet; 21-Horizontal support; 22-Crossing brace; 23-Operating hole; 31-Operating platform; 32-Ladder; 210-Connecting seat; 221-Diagonal brace; 222-Sleeve; 223-Plate; 224-Connecting sleeve; 211-Lifting point; 311-Installation steel pipe; 312-Platform plate; 33-Fall safety net; 4-Leveling joint. Detailed Implementation

[0022] To make the above-mentioned objects, features, and advantages of the present invention more apparent and understandable, specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings. Although some embodiments of the present invention are shown in the drawings, it should be understood that the present invention can be implemented in various forms and should not be construed as limited to the embodiments set forth herein. Rather, these embodiments are provided to provide a more thorough and complete understanding of the present invention. It should be understood that the accompanying drawings and embodiments of the present invention are for illustrative purposes only and are not intended to limit the scope of protection of the present invention.

[0023] The term "comprising" and its variations as used herein are open-ended, meaning "including but not limited to"; the term "based on" means "at least partially based on"; the term "one embodiment" means "at least one embodiment"; the term "another embodiment" means "at least one additional embodiment"; the term "some embodiments" means "at least some embodiments"; and the term "optionally" means "optional embodiments". Definitions of other terms will be given in the following description. It should be noted that the concepts of "first," "second," etc., mentioned in this invention are used only to distinguish different devices, modules, or units, and are not intended to limit the order of functions performed by these devices, modules, or units or their interdependencies.

[0024] It should be noted that the terms "a" and "a plurality of" used in this invention are illustrative rather than restrictive. Those skilled in the art should understand that, unless otherwise expressly indicated in the context, they should be understood as "one or more".

[0025] To address the problems existing in the aforementioned related technologies, this embodiment provides a prefabricated large-scale construction support for pipe-mounted operations and a construction method thereof.

[0026] See Figures 1 to 4 As shown, this embodiment of the invention provides a prefabricated large-scale construction support for pipe-based operations, used in the construction of tall structures to support the cast-in-place construction load of the superstructure, including multiple supporting pipe columns 1, connecting units and operating units. Each support column 1 is arranged at intervals along the longitudinal and transverse directions; each support column 1 is detachably connected from multiple standard pipe segments 10 along the height direction, and the bottom of the side wall of the lowest standard pipe segment 10 in each support column 1 is provided with an entry port 101 for workers to enter the interior of the support column 1; the connection unit includes a detachably connected horizontal support member 21 and a cross brace member 22 disposed between adjacent support columns 1, and an operation hole 23 is provided on the side wall of the support column 1 at the installation position corresponding to the horizontal support member 21 and the cross brace member 22; the operation unit includes an operation platform 31 and a ladder 32 disposed inside the support column 1, the ladder 32 is arranged along the axial direction of the support column 1, and the operation platform 31 is located below the operation hole 23 for workers to stand on and to install or disassemble the horizontal support member 21 and the cross brace member 22 through the operation hole 23.

[0027] It should be noted that this invention can be used for the construction of bridge deck systems between bridge towers, but is not limited to this. It can also be applied to the cast-in-place construction of various tall structures such as high-rise buildings, high tower structures, and large stadiums.

[0028] In this embodiment, each support column 1 has an entry port 101 at the bottom of the side wall of the lowest standard pipe section 10 for workers to enter the interior of the support column 1. The interior of the support column 1 has a ladder 32 arranged along its axial direction and an operating platform 31 at the corresponding operating hole 23 position. The side wall of the support column 1 has operating holes 23 at the installation positions of the horizontal support member 21 and the cross brace member 22. After entering the interior of the support column 1 through the entry port 101, the workers can climb the ladder 32 to reach the operating platform 31 at various height positions and install or disassemble the horizontal support member 21 and the cross brace member 22 through the operating holes 23. Therefore, the workers are always in the enclosed space inside the support column 1 during the entire installation and disassembly process, without having to work in the high-altitude edge environment outside the support column 1, thus eliminating the risk of falling from height from the source. Meanwhile, since the horizontal support component 21 and the cross bracing component 22 are both connected to the support column 1 via detachable connections, no on-site welding is required. This avoids the adverse effects of wind, temperature, and limited operating space on weld quality in high-altitude welding operations. It also eliminates the need for gas cutting during dismantling; the components can be disassembled into standard parts simply by loosening the connectors inside the support column 1, and each part can be reused. Each support column 1 is composed of multiple standard pipe segments 10 detachably connected along the height direction. Each time a standard pipe segment 10 is erected, the horizontal support component 21 and the cross bracing component 22 are installed within that standard pipe segment layer, forming an alternating layer-by-layer erection and connection pattern. This allows the overall stability of the support structure to be established layer by layer during the erection process. In summary, this invention solves the technical problems of difficulty in guaranteeing high-altitude welding quality, high safety risks in high-altitude edge operations, and difficult dismantling with long construction cycles. It achieves fully enclosed operation within the pipe throughout the entire process, rapid assembly and dismantling, and reusable components.

[0029] In one embodiment of the present invention, two adjacent standard pipe segments 10 on each support column 1 are detachably connected by flanges and connecting bolts.

[0030] It should be noted that the standard pipe sections 10 are connected by flanges and bolts, allowing the lengthening of the support column 1 in the vertical direction to be completed entirely by bolt assembly, eliminating the need for on-site welding. This avoids the adverse effects of high-altitude welding environments (such as wind, temperature, and confined working space) on weld quality, ensuring the connection quality of the extended joints. Furthermore, each standard pipe section 10 can be positioned and secured during installation simply by fitting the flange face and tightening the bolts, without waiting for the weld to cool or undergoing non-destructive testing. The installation time for a single section is significantly shorter than that of welded connections, resulting in high construction efficiency. During dismantling, only the connecting bolts at the flanges inside the support column 1 need to be loosened to disassemble each standard pipe section 10 from top to bottom, without the need for gas cutting. The standard pipe sections 10 can be reused as reusable components. Furthermore, the connection nodes formed by flanges and connecting bolts have clearly defined stress performance, which is basically equivalent to the rigid connection characteristics of welded nodes. They can reliably transmit axial force, bending moment and shear force, and meet the structural stress requirements under ultra-high altitude, large span and heavy load conditions.

[0031] In one embodiment of the present invention, standard pipe segments 10 located at the same horizontal height in each support column 1 constitute a standard pipe segment layer; a horizontal support member 21 is provided between adjacent support columns 1 in the same standard pipe segment layer, and a connecting seat 210 is provided on the support column 1. The end of the horizontal support member 21 is detachably connected to the connecting seat 210 by adjusting bolts.

[0032] Specifically, the connecting seat 210 is welded and fixed to the outer surface of the side wall of the support column 1, and the connecting seat 210 has bolt holes for cooperating with the adjusting bolts; the end of the horizontal support member 21 is provided with a connecting lug, and the adjusting bolt passes through the connecting lug and the bolt holes on the connecting seat 210 to lock and fix the horizontal support member 21 between two adjacent support columns 1. Furthermore, the connecting seat 210 is located near the joint of two adjacent standard pipe sections 10, so that the installation height of the horizontal support member 21 matches the height of the flange connection node between the standard pipe sections 10, which facilitates the installation operation of the horizontal support member 21 and the adjacent standard pipe section 10 through the same operating hole 23, further reducing the number of operating holes 23 and simplifying the processing technology of the support column 1.

[0033] It should be noted that, by utilizing the adjustable characteristics of the adjusting bolts, the length of the horizontal support member 21 can be finely adjusted during installation to accommodate changes in installation dimensions caused by errors in the spacing of the support columns 1 or construction deviations, ensuring precise alignment and reliable connection of each connection node. Since horizontal support members 21 are provided between adjacent support columns 1 within the same standard pipe segment layer, each standard pipe segment layer forms an independent horizontal frame layer after erection. As the system is erected layer by layer upwards, the overall integrity of the support gradually increases with the increase of standard pipe segment layers. The horizontal support members 21 of each layer can effectively constrain the relative displacement between each support column 1, improving the overall lateral stiffness of the support in both the transverse and longitudinal directions.

[0034] In one embodiment of the present invention, the cross bracing member 22 is a pair of cross bracing rods 221 arranged in a cross manner. The pair of cross bracing rods 221 are arranged between adjacent support columns 1 in the same standard pipe section layer. An inclined sleeve 222 is fixed on the side wall of the support column 1. The two ends of the cross bracing rod 221 pass through the corresponding sleeve 222 and extend into the interior of the two adjacent support columns 1, and are detachably connected to the support column 1 through a connecting component.

[0035] It should be noted that, since the cross bracing member 22 consists of a pair of cross bracing rods 221 arranged in a cross shape, the two bracing rods 221 are distributed in an X-shape within the same standard pipe section layer, forming a stable triangular force system together with the horizontal support member 21. This creates effective geometric constraints between the support pipe columns 1 in both the horizontal and vertical directions, improving the lateral stiffness and overall stability of the support structure in both the longitudinal and transverse directions. Because inclined sleeves 222 are fixed to the side walls of the support pipe columns 1, with the inclination angle of the sleeves 222 matching the installation angle of the bracing rods 221, the two ends of the bracing rods 221 pass through the corresponding sleeves 222 and extend into the interiors of two adjacent support pipe columns 1. During installation, the sleeves 222 guide and position the bracing rods 221, ensuring that after the cross arrangement, the ends of the bracing rods 221 are precisely aligned with the corresponding sleeves 222 on the adjacent support pipe columns 1, thus guaranteeing the installation accuracy and the clarity of the force path of the bracing rods 221. Meanwhile, since the diagonal brace 221 is detachably connected to the support column 1 via a connecting assembly, and the operating position of the connecting assembly is located inside the support column 1, workers can tighten or loosen the connecting assembly at the end of the diagonal brace 221 through the operating hole 23 inside the support column 1, eliminating the need for high-altitude welding or bolting operations outside the support column 1, further reducing the frequency of high-altitude edge work. Because both ends of the diagonal brace 221 are locked and fixed inside the support column 1 via the connecting assembly, workers can also loosen the connecting assembly inside the support column 1 to pull the diagonal brace 221 out of the sleeve 222 during dismantling. The dismantled diagonal brace 221 and the connecting assembly can be reused as standard components.

[0036] In one embodiment of the present invention, the connecting assembly includes a pad 223 and a connecting sleeve 224. The connecting sleeve 224 is located inside the support column 1 and is threaded to one end of the diagonal brace 221 that passes through the sleeve 222. The pad 223 is clamped between the connecting sleeve 224 and the sleeve 222.

[0037] It should be noted that since the connecting sleeve 224 is located inside the support column 1 and is threaded to the end of the diagonal brace 221 that passes through the sleeve 222, the operator can directly screw the connecting sleeve 224 inside the support column 1 to achieve the fastening or loosening of the end of the diagonal brace 221 and the support column 1. There is no need to operate on the end of the diagonal brace 221 outside the support column 1, which avoids high-altitude edge work and eliminates the need for welding for fixing. Meanwhile, since the pad 223 is clamped between the connecting sleeve 224 and the sleeve 222, when the operator screws the connecting sleeve 224 inside the support column 1, the connecting sleeve 224 moves towards the sleeve 222 relative to the diagonal brace 221, pressing the pad 223 between the connecting sleeve 224 and the sleeve 222. This clamping force is transmitted to the sleeve 222 through the pad 223, and then to the side wall of the support column 1 through the sleeve 222, thereby applying an axial preload to the diagonal brace 221. This eliminates the fit gap between the diagonal brace 221 and the sleeve 222, as well as the assembly gap between each connecting node, so that the cross diagonal brace 22 can play a supporting role in the support structure immediately, improving the overall rigidity and resistance to lateral deformation of the support. Furthermore, since the connecting sleeve 224 and the diagonal brace 221 are connected by threads, during disassembly, it is only necessary to untighten the connecting sleeve 224 by reverse screwing it inside the support column 1, and then pull the diagonal brace 221 out of the sleeve 222. The disassembled diagonal brace 221, connecting sleeve 224 and pad 223 can all be reused as standard components.

[0038] In one embodiment of the present invention, the horizontal support member 21 is a steel beam, and the two ends of the horizontal support member 21 are respectively provided with lifting points 211. The lifting points 211 are arranged near the operating hole 23 and are used to remove the lifting load after the hoisting is in place.

[0039] Specifically, the horizontal support member 21 is an I-beam or H-beam, and the lifting point 211 is a lifting lug welded and fixed to the upper flange or web of the end of the horizontal support member 21. The lifting lug is provided with a lifting hole for shackles or wire ropes to pass through. The lifting lug is set on the side near the operating hole 23, so that the operator can access the lifting lug and complete the hanging and releasing of the lifting device through the operating hole 23 inside the support column 1.

[0040] It should be noted that, since the horizontal support member 21 is provided with lifting points 211 at both ends, and the lifting points 211 are located close to the operating hole 23, after the horizontal support member 21 is hoisted into place, the operators can directly release the lifting equipment (such as shackles, wire ropes or slings) on the lifting points 211 through the operating hole 23 inside the support column 1. There is no need for the operators to perform the lifting equipment release operation in the high-altitude environment outside the support column 1, nor is there a need to wait for the external operators to cooperate in unloading the hoisting load after the horizontal support member 21 is in place, which reduces the frequency of high-altitude edge operations and the cross-operation time between different types of work. Meanwhile, since the lifting points 211 are located at both ends of the horizontal support member 21, the horizontal support member 21 is lifted in a horizontal posture during the lifting process. The position of the lifting points 211 is adapted to the center of gravity position of the horizontal support member 21, ensuring the stability of the horizontal support member 21 during the lifting process. This makes it easier for operators to observe the alignment of the end of the horizontal support member 21 with the connecting seat 210 through the operating hole 23 and to guide the installation, thus improving the accuracy and efficiency of the lifting and positioning.

[0041] In one embodiment of the present invention, the operating table 31 includes a mounting steel pipe 311 and a platform plate 312. The mounting steel pipe 311 is horizontally inserted through the side wall of the support column 1 and fixed, and the platform plate 312 is horizontally laid on the mounting steel pipe 311.

[0042] It should be noted that since the installation steel pipe 311 of the operating platform 31 is horizontally inserted through and fixed to the side wall of the support column 1, the installation steel pipe 311 utilizes the pipe wall of the support column 1 as a support foundation. There is no need to additionally install vertical columns or cantilever supports inside the support column 1 to support the operating platform 31. The structure is simple and the load-bearing capacity is reliable. During installation, it is only necessary to insert the installation steel pipe 311 into the pre-set holes on the side wall of the support column 1 and fix it. No welding is required, resulting in high installation efficiency. Since the platform plate 312 is horizontally laid on the installation steel pipe 311, the platform plate 312 is horizontally supported by the installation steel pipe 311, forming a stable operating support surface. The laying height of the platform plate 312 is adapted to the position of the operating hole 23 (i.e., the top surface of the platform plate 312 is lower than the lower edge of the operating hole 23). When the operator stands on the platform plate 312, the height of their hands for operation matches the position of the operating hole 23, facilitating precise operation through the operating hole 23 and improving the accuracy and efficiency of the operation. Meanwhile, since the installation steel pipe 311 of the operating platform 31 is horizontally inserted through and fixed on the side wall of the support column 1, the load-bearing capacity of the operating platform 31 is determined by the cross-sectional dimensions of the installation steel pipe 311 and the wall strength of the support column 1. The load-bearing capacity is clear and can withstand the weight of the operators and tools as well as the dynamic load generated during operation, thus ensuring the safety of the operation inside the pipe.

[0043] In one embodiment of the present invention, a plurality of fall-prevention safety nets 33 are provided at intervals along the axial direction inside the support column 1, and the fall-prevention safety nets 33 are located below the operating platform 31.

[0044] Furthermore, the vertical spacing between two adjacent fall arrest safety nets 33 is 2m. The fall arrest safety nets 33 are made of flexible materials (such as high-strength polyester fiber or nylon rope nets), which have a certain elastic deformation capacity and buffer energy absorption characteristics. The edges of the fall arrest safety nets 33 are fixed to the supporting steel pipes, which are horizontally inserted into and fixed to the side wall of the supporting column 1.

[0045] It should be noted that multiple fall protection safety nets 33 are arranged in stages along the height direction inside the support column 1. If workers slip, lose their hands, or drop their tools while climbing the ladder 32, the fall protection safety nets 33 can provide tiered interception of personnel or tools along the fall path, preventing personnel from falling directly from the height of the ladder to the bottom of the support column 1, which greatly reduces the risk of falls during vertical transportation and passage within the pipe.

[0046] In one embodiment of the present invention, a leveling joint 4 is provided at the bottom of the support column 1. The leveling joint 4 is located below the inlet 101. The lower end of the leveling joint 4 is fixed to the foundation embedded plate and is used to adjust the installation elevation and verticality of the support column 1.

[0047] Furthermore, the leveling joint 4 is a factory-prefabricated component, including an upper connecting plate, a lower connecting plate, and an adjustment assembly (adjusting bolts and adjusting nuts). The upper connecting plate is fixedly connected to the lower end of the lowest standard pipe section 10, the lower connecting plate is fixed to the foundation embedded plate, and the adjustment assembly is set between the upper connecting plate and the lower connecting plate to adjust the height and level of the upper connecting plate relative to the lower connecting plate.

[0048] It should be noted that, since the bottom of the support column 1 is equipped with a leveling joint 4, and the lower end of the leveling joint 4 is fixed to the foundation embedded plate, the leveling joint 4 serves as a transitional connection between the support column 1 and the foundation embedded plate. This allows for precise adjustment of the installation elevation and verticality of the support column 1 before the support structure is erected. Especially in ultra-high-altitude, large-span bridge construction scenarios where the tower height exceeds 100 meters and the beam span exceeds 30 meters, construction errors in the foundation embedded plate, local unevenness of the concrete foundation, and relative height differences between multiple support columns 1 can all affect the overall load-bearing performance and stability of the support structure. The leveling joint 4, without altering the foundation embedded plate itself, allows for independent elevation and verticality adjustments to each support column 1, ensuring that the top of each support column 1 is located at the same design elevation plane and that the axis of each support column 1 remains vertical. This ensures that the flatness of the steel beams laid on top of the support structure and the bottom formwork meets the precision requirements for the bridge deck concrete pouring.

[0049] This invention also provides a construction method for a prefabricated large-scale construction scaffold for pipe-mounted operations, comprising the following steps: Step 1: Install the foundation embedded plate on the construction foundation; Step 2: Fix the prefabricated leveling joint 4 to the top surface of the foundation embedded plate; Step 3: Hoist and fix the standard pipe section 10 onto the leveling joint 4 as the base section; Step 4: The workers enter the support column 1 through the entrance 101 of each basic section, climb the ladder 32 to the operating platform 31 at the corresponding operating hole 23, and install horizontal support members 21 and cross diagonal bracing members 22 between adjacent support columns 1 in the same standard pipe section layer through the operating hole 23. Step 5: Install and connect standard pipe segments 10 sequentially on top of the foundation segment, and repeat Step 4 until the support column 1 is erected to the design height. Step Six: Lay steel beams and bottom formwork on top of the uppermost standard pipe section 10, and carry out the upper structure concrete pouring construction; Step 7: After the construction is completed, the workers enter the interior of each support column 1 again through the entrance 101, climb the ladder 32 to the operating platform 31 at the corresponding operating hole 23, and disassemble the horizontal support 21 and the cross diagonal brace 22 in sequence through the operating hole 23. Step 8: Remove each standard pipe section 10 from top to bottom to complete the overall removal of the support.

[0050] The construction method of the prefabricated large construction support for pipe operation in this embodiment has the same beneficial effects as the above-mentioned prefabricated large construction support for pipe operation, and will not be repeated here.

[0051] While the present invention has been disclosed above, its scope of protection is not limited thereto. Those skilled in the art can make various changes and modifications without departing from the spirit and scope of the present invention, and all such changes and modifications will fall within the scope of protection of the present invention.

Claims

1. A prefabricated large-scale construction scaffold for pipe-based operations, used in the construction of tall structures to support the load of cast-in-place superstructure construction, characterized in that... include: Multiple support columns (1) are arranged at intervals along the longitudinal and transverse directions; each support column (1) is detachably connected from multiple standard pipe segments (10) along the height direction, and the bottom of the side wall of the lowest standard pipe segment (10) of each support column (1) is provided with an entry port (101) for workers to enter the interior of the support column (1). The connecting unit includes a horizontal support member (21) and a cross brace member (22) that are detachably connected between adjacent support columns (1). An operating hole (23) is provided on the side wall of the support column (1) at the installation position corresponding to the horizontal support member (21) and the cross brace member (22). The operating unit includes an operating platform (31) and a ladder (32) located inside the support column (1). The ladder (32) is arranged along the axial direction of the support column (1). The operating platform (31) is located below the operating hole (23) and is used for workers to stand and install or disassemble the horizontal support (21) and the cross bracing (22) through the operating hole (23).

2. The prefabricated large-scale construction support for pipe operations according to claim 1, characterized in that, Each of the two adjacent standard pipe segments (10) on each of the support columns (1) is detachably connected by flanges and connecting bolts.

3. The prefabricated large-scale construction support for pipe operations according to claim 1, characterized in that, The standard pipe segments (10) located at the same horizontal height in each of the supporting pipe columns (1) together constitute a standard pipe segment layer; the horizontal support member (21) is provided between adjacent supporting pipe columns (1) in the same standard pipe segment layer, and a connecting seat (210) is provided on the supporting pipe column (1). The end of the horizontal support member (21) is detachably connected to the connecting seat (210) by adjusting bolts.

4. The prefabricated large-scale construction support for pipe operations according to claim 3, characterized in that, The cross bracing member (22) is a pair of cross bracing rods (221). The pair of bracing rods (221) are located between adjacent support columns (1) in the same standard pipe section layer. An inclined sleeve (222) is fixed on the side wall of the support column (1). The two ends of the bracing rod (221) pass through the corresponding sleeve (222) and extend into the interior of the two adjacent support columns (1), and are detachably connected to the support column (1) through a connecting component.

5. The prefabricated large-scale construction support for pipe operations according to claim 4, characterized in that, The connecting assembly includes a pad (223) and a connecting sleeve (224). The connecting sleeve (224) is located inside the support column (1) and is threaded to one end of the diagonal brace (221) that passes through the sleeve (222). The pad (223) is clamped between the connecting sleeve (224) and the sleeve (222).

6. The prefabricated large-scale construction support for pipe operations according to claim 3, characterized in that, The horizontal support (21) is a steel beam. The two ends of the horizontal support (21) are respectively provided with lifting points (211). The lifting points (211) are arranged near the operating hole (23) and are used to remove the lifting load after the installation is completed.

7. The prefabricated large-scale construction support for pipe operations according to claim 1, characterized in that, The operating table (31) includes a mounting steel pipe (311) and a platform plate (312). The mounting steel pipe (311) is horizontally inserted through the side wall of the supporting column (1) and fixed. The platform plate (312) is horizontally laid on the mounting steel pipe (311).

8. The prefabricated large-scale construction support for pipe operations according to claim 1, characterized in that, The support column (1) is provided with multiple fall protection safety nets (33) spaced apart along its axial direction, and the fall protection safety nets (33) are located below the operating platform (31).

9. The prefabricated large-scale construction support for pipe operations according to claim 1, characterized in that, The bottom of the support column (1) is provided with a leveling joint (4). The leveling joint (4) is located below the inlet (101). The lower end of the leveling joint (4) is fixed to the foundation embedded plate and is used to adjust the installation elevation and verticality of the support column (1).

10. A construction method for a prefabricated large-scale construction scaffold for in-pipe operations, characterized in that, The method of using a prefabricated large-scale construction scaffold for in-pipe operations as described in any one of claims 1 to 9 includes the following steps: Step 1: Install the foundation embedded plate on the construction foundation; Step 2: Fix the prefabricated leveling joint (4) to the top surface of the foundation embedded plate; Step 3: Hoist and fix the standard pipe section (10) onto the leveling joint (4) as the base section; Step 4: The workers enter the interior of the support column (1) through the entrance (101) of each of the basic segments, climb the ladder (32) to the operating platform (31) at the corresponding operating hole (23), and install horizontal support members (21) and cross diagonal bracing members (22) between adjacent support columns (1) in the same standard pipe segment layer through the operating hole (23). Step 5: The standard pipe segments (10) are hoisted and spliced ​​sequentially on the top of the base segment and connected and fixed. Step 4 is repeated until the support column (1) is erected to the design height. Step 6: Lay steel beams and bottom formwork on top of the uppermost standard pipe segment (10) and carry out the upper structure concrete pouring construction; Step 7: After the construction is completed, the workers enter the interior of each of the support columns (1) again through the entrance (101), climb the ladder (32) to reach the operating platform (31) at the position of the corresponding operating hole (23), and disassemble the horizontal support (21) and the cross brace (22) in sequence through the operating hole (23). Step 8: Remove each of the standard pipe sections (10) from top to bottom to complete the overall removal of the support.