Method for quickly building new energy automobile factory building
Through the combination of three-dimensional laser scanning and BIM model, accurate three-dimensional measurement models are generated, design is optimized, and scientific construction plans are formulated, which solves the progress and efficiency problems caused by design changes in traditional construction methods, and achieves the rapid and rapid development of new energy vehicle factories. Accurately built.
Patent Information
- Application Number
- CN202411040828.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-15
AI Technical Summary
The traditional new energy vehicle factory construction method does not match the design and site, resulting in frequent design changes during the construction process, affecting the construction progress and efficiency and increasing costs.
A three-dimensional laser scanner is used to obtain on-site data, combine BIM design models, generate three-dimensional measured models, optimize the design models, formulate construction plans and configure resources to ensure that the design is consistent with the site, and reduce rework and errors.
It improves the continuity and efficiency of construction progress, reduces resource waste and construction delays, shortens the construction cycle, and ensures the accuracy of design and the rationality of resource allocation.
Smart Images

Figure CN118967032A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of construction engineering management, and in particular to a method for rapidly constructing a new energy vehicle plant. Background Art
[0002] In the new energy vehicle industry, rapid construction of factories is one of the key requirements. Traditional factory construction methods require complex on-site measurements and multiple design adjustments, resulting in long construction periods, high costs, and prone to construction errors. These problems have seriously restricted the rapid construction and production speed of new energy vehicle factories.
[0003] In the existing technology, Building Information Modeling (BIM) technology is usually used to guide factory construction. Designers build three-dimensional design models in BIM software according to factory requirements. Since BIM models are usually based on data and assumptions in the initial design stage, which may differ from the actual on-site conditions, BIM models frequently undergo design changes during the construction process, affecting the construction progress. Summary of the invention
[0004] The present application provides a method for rapid construction of a new energy vehicle plant, which is used to avoid frequent design changes in the BIM model during the construction process, thereby speeding up the construction progress.
[0005] In the first aspect, the present application provides a method for rapid construction of a new energy vehicle factory, the method comprising: obtaining scanning point cloud data generated by a three-dimensional laser scanner after actual measurement of the factory building to be built, and obtaining a BIM design model of the factory building to be built in a BIM model library; matching the scanning point cloud data and the BIM design model to generate a three-dimensional measured model of the factory building to be built; optimizing the BIM design model based on the three-dimensional measured model to generate a target BIM design model; generating a construction plan for each construction type based on the target BIM design model, and allocating resources for each construction type based on the construction plan of each construction type.
[0006] By adopting the above technical solutions, the scanning point cloud data generated by the 3D laser scanner can accurately reflect the actual situation of the factory building to be built. The 3D measured model generated after matching with the BIM design model is more accurate, reducing adjustments and rework caused by design discrepancies with the site, thereby speeding up the construction progress. The optimized target BIM design model ensures the accuracy and reliability of the design plan, making the subsequent construction plan and resource allocation more reasonable, reducing errors and adjustments caused by design changes during the construction process, and ensuring the continuity and stability of the construction progress. Through detailed construction planning and resource allocation, it is possible to effectively avoid waste of resources and waiting time between construction types, improve construction efficiency, and shorten the construction cycle.
[0007] Optionally, the matching of the scanned point cloud data and the BIM design model to generate the three-dimensional measured model of the factory building to be built includes: importing the scanned point cloud data into three-dimensional modeling software, preprocessing the scanned point cloud data to obtain target point cloud data; importing the BIM design model into the three-dimensional modeling software, and registering the target point cloud data with the BIM design model; and reconstructing the three-dimensional measured model of the factory building to be built by a triangulation algorithm based on the registered target point cloud data and the BIM design model.
[0008] By adopting the above technical solution, the scanning point cloud data generated by the 3D laser scanner can accurately reflect the actual situation of the factory building to be built. The target point cloud data obtained after importing it into the 3D modeling software and preprocessing can ensure the accuracy and integrity of the data. By aligning the target point cloud data with the BIM design model, the difference between the two can be effectively eliminated, and the generated 3D measured model is more accurate, reducing adjustments and rework caused by inconsistencies between the design and the site, thereby speeding up the construction progress. Based on the aligned target point cloud data and BIM design model, the 3D measured model reconstructed by the triangulation algorithm can provide a reliable foundation for optimizing the BIM design model. The generated target BIM design model ensures the accuracy and reliability of the design scheme. The construction plan and resource allocation generated by the target BIM design model are more reasonable.
[0009] Optionally, optimizing the BIM design model according to the three-dimensional measured model to generate a target BIM design model includes: comparing the three-dimensional measured model with the BIM design model, marking areas in the BIM design model that do not match the three-dimensional measured model as areas to be optimized; extracting measured information of the areas to be optimized from the three-dimensional measured model; correcting the areas to be optimized in the BIM design model according to the measured information; and using the corrected BIM design model as the target BIM design model of the factory building to be built.
[0010] By adopting the above technical solution, the 3D measured model is compared with the BIM design model, the inconsistent areas are marked as areas to be optimized, and the measured information of the areas to be optimized is extracted in the 3D measured model, so that the deviations in the design model can be accurately identified and corrected. The BIM design model is corrected according to the measured information, and the generated target BIM design model is more accurate and reliable, which reduces the adjustments and rework caused by the inconsistency between the design and the site, thereby speeding up the construction progress.
[0011] Optionally, generating a construction plan for each type of construction work based on the target BIM design model includes: extracting building component information from the target BIM design model; determining the construction sequence and time nodes of each building component in combination with the building component information and the overall progress plan of the factory building to be built; and generating a construction plan for each type of construction work based on the construction sequence and time nodes of each building component.
[0012] By adopting the above technical solution, the building component information is extracted from the target BIM design model, and combined with the overall progress plan of the factory building to be built, the construction sequence and time nodes of each building component are determined, making the construction plan more scientific and systematic. The construction plan generated according to the construction sequence and time nodes of each building component ensures the coordination and cooperation of various construction types, reduces waiting time and resource waste during the construction process, and improves construction efficiency and progress continuity.
[0013] Optionally, generating a construction plan for each type of construction work according to the construction sequence and time nodes of each of the building components includes: determining the type of construction work corresponding to each building component according to the type of each building component; determining the work tasks and working hours of each type of construction work based on the construction sequence and time nodes of each building component and in combination with the type of construction work corresponding to each of the building components; acquiring the correlation between each type of construction work; generating a construction plan for each type of construction work in combination with the work tasks and time arrangements of each type of construction work and the correlation between each type of construction work.
[0014] By adopting the above technical solution, the corresponding construction work types are determined according to the types of building components to ensure that the division of labor and responsibilities of each construction work type are clear. Based on the construction sequence and time nodes of the building components, combined with the corresponding construction work types, the work tasks and working hours of each construction work type are determined to ensure the reasonable arrangement of the construction progress. By obtaining the correlation between the construction work types, the coordination and cooperation requirements between the various work types can be clarified to avoid construction delays caused by disconnection between the work types.
[0015] Optionally, according to the construction plan of each construction work type, resources are allocated to each construction work type, including: obtaining historical construction data of the factory building to be built; combining the historical construction data and the construction plan of each construction work type, and allocating resources to each construction work type, and the resource allocation includes: personnel allocation, material allocation and machinery and equipment configuration.
[0016] By adopting the above technical solution, we can obtain the historical construction data of the factory building to be built, and combine the construction plan of each construction type to allocate resources for each construction type, so as to ensure the scientific and accurate resource allocation. By using historical construction data, we can better predict and arrange the needs of personnel, materials and mechanical equipment, and avoid resource shortages or surpluses. Reasonable personnel allocation, material allocation and mechanical equipment allocation can effectively improve construction efficiency, reduce resource waste, reduce construction costs, and ensure the continuity and stability of the construction progress.
[0017] Optionally, after allocating resources for each of the construction work types, it also includes: generating a construction resource model corresponding to each of the construction work types; integrating the construction resource model of each of the construction work types with the target BIM design model to generate an integrated BIM construction model; simulating the construction process of each of the construction work types according to the integrated BIM construction model to obtain construction prediction data for each of the construction work types; comparing the construction prediction data with the preset target data of the factory building to be built to obtain a comparison result; and adjusting the integrated BIM construction model according to the comparison result until the prediction data of each of the construction work types meets the preset target data.
[0018] By adopting the above technical solution, the construction resource model of each construction type is generated and integrated with the target BIM design model to form an integrated BIM construction model, which can fully display the various resources required in the construction process. Using the integrated BIM construction model for simulation, the construction effect and possible problems of each construction type can be predicted in advance, and the construction prediction data can be obtained. By comparing the construction prediction data with the preset target data of the factory building to be built, the construction plan and resource allocation can be discovered and adjusted in time to ensure that all indicators in the construction process can meet the preset goals. By repeatedly adjusting the integrated BIM construction model until the prediction data of each construction type meets the preset target data, the construction plan can be optimized before the actual construction begins, the errors and changes in the construction process can be reduced, and the construction efficiency and quality can be improved.
[0019] In a second aspect, the present application provides a device for rapid construction of a new energy vehicle factory, the device comprising: an acquisition module, a matching module, a generation module and an output module; wherein the acquisition module is used to acquire scanning point cloud data generated by a three-dimensional laser scanner after actual measurement of the factory building to be built, and to acquire the BIM design model of the factory building to be built in the BIM model library; the matching module is used to match the scanning point cloud data and the BIM design model to generate a three-dimensional measured model of the factory building to be built; the generation module is used to optimize the BIM design model according to the three-dimensional measured model to generate a target BIM design model; the output module is used to generate a construction plan for each construction type according to the target BIM design model, and to allocate resources for each construction type according to the construction plan of each construction type.
[0020] In the third aspect, the present application provides an electronic device, adopting the following technical solution: including a processor, a memory, a user interface and a network interface, the memory is used to store instructions, the user interface and the network interface are used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes a computer program such as any of the above-mentioned methods for rapid construction of new energy vehicle factories.
[0021] In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution: storing a computer program that can be loaded by a processor and execute any of the above-mentioned methods for rapid construction of a new energy vehicle factory.
[0022] In summary, the present application includes at least one of the following beneficial technical effects: 1. Through detailed construction planning and resource allocation, it can effectively avoid resource waste and waiting time between construction jobs, improve construction efficiency and shorten the construction period; 2. Determine the corresponding construction work type according to the type of building components to ensure that each construction work type has a clear division of labor and clear responsibilities. Based on the construction sequence and time nodes of the building components, combined with the corresponding construction work types, determine the work tasks and working hours of each construction work type to ensure the reasonable arrangement of the construction progress. Obtaining the correlation between construction work types can clarify the coordination and cooperation requirements between each work type and avoid construction delays caused by disconnection between work types. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a flow chart of a method for rapid construction of a new energy vehicle plant provided in an embodiment of the present application; Figure 2 It is a structural schematic diagram of a device for rapid construction of a new energy vehicle plant provided in an embodiment of the present application; Figure 3It is a structural schematic diagram of an electronic device provided in an embodiment of the present application.
[0024] Description of reference numerals: 1000, electronic device; 1001, processor; 1002, communication bus; 1003, user interface; 1004, network interface; 1005, memory. DETAILED DESCRIPTION
[0025] In order to enable those skilled in the art to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this application, not all of the embodiments.
[0026] In the description of the embodiments of the present application, words such as "illustrative", "for example" or "for example" are used to indicate examples, illustrations or descriptions. Any embodiment or design described as "illustrative", "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "illustrative", "for example" or "for example" is intended to present related concepts in a concrete way.
[0027] Figure 1 Schematic diagram of a method for rapidly constructing a new energy vehicle plant provided in an embodiment of the present application. Figure 1 As shown, the method includes S101-S104: S101, obtaining scanning point cloud data generated by a 3D laser scanner after actual measurement of the factory building to be built, and obtaining a BIM design model of the factory building to be built in a BIM model library.
[0028] In one example, a 3D laser scanner is first used to measure the site of a factory to be built. The 3D laser scanner can quickly and accurately capture the spatial data of the site and generate high-density scanned point cloud data. These point cloud data reflect the actual situation of the site in detail, including the terrain, existing buildings and their surroundings. The reason for choosing 3D laser scanning technology is its high accuracy and high efficiency. It can complete large-area measurement work in a short time, avoiding the tedious and error-prone problems of traditional measurement methods.
[0029] After obtaining the scanned point cloud data, the next step is to obtain the BIM design model of the factory to be built from the BIM model library. The BIM design model is a three-dimensional digital model generated based on the design drawings, which contains all the design information of the factory, including detailed contents of various disciplines such as structure, architecture, and electromechanical. Obtaining the design model through the BIM model library can ensure the integrity and accuracy of the model data, and facilitate subsequent data integration and analysis.
[0030] Combining the scanned point cloud data with the BIM design model can effectively compare and analyze the actual situation on site with the design intent. In the specific operation process, the scanned point cloud data is first imported into the professional 3D modeling software, and necessary preprocessing is performed, such as denoising, filtering, and coordinate conversion, to obtain optimized target point cloud data. The preprocessed point cloud data will be clearer and more accurate, and easier to match with the BIM design model.
[0031] S102, matching the scanned point cloud data and the BIM design model to generate a three-dimensional measured model of the factory building to be built.
[0032] In one example, the scanned point cloud data and BIM design model acquired from the site are first imported into professional 3D modeling software. Selecting the right 3D modeling software is key, as it must be able to handle large-scale point cloud data and complex BIM models.
[0033] Next, the imported scanned point cloud data is preprocessed. This step includes operations such as denoising, filtering, and coordinate transformation to ensure the clarity and accuracy of the point cloud data. The preprocessed point cloud data is called target point cloud data. The purpose of preprocessing is to eliminate noise and errors in the measurement process, optimize data quality, and make it more suitable for matching with the BIM design model.
[0034] Then, the target point cloud data is registered with the BIM design model. Registration is the process of aligning data from two different sources. In the specific operation, several feature points in the point cloud data and the BIM design model are first selected as control points. These control points should be key positions that are easy to identify and clearly represented in both data. Through the registration algorithm of the 3D modeling software, these control points are matched, and then the entire point cloud data is aligned with the BIM design model. Commonly used registration algorithms include ICP (Iterative Closest Point) algorithm, etc. These algorithms can efficiently complete data alignment and ensure the accuracy of matching.
[0035] After the registration is completed, the 3D measured model of the factory to be built is reconstructed through the triangulation algorithm based on the registered target point cloud data and the BIM design model. The triangulation algorithm can convert the point cloud data into a mesh model, thereby generating a 3D measured model with geometric and topological information. This measured model not only retains the actual measurement data on site, but also incorporates the detailed information of the design model to form a highly consistent and accurate 3D model.
[0036] Based on the above embodiment, as an optional implementation, in S102, matching the scanned point cloud data and the BIM design model to generate a three-dimensional measured model of the factory building to be built specifically includes the following steps: S20-S22: S20, importing the scanned point cloud data into the three-dimensional modeling software, preprocessing the scanned point cloud data, and obtaining target point cloud data.
[0037] In one example, after importing point cloud data, the first step is to check the data to ensure the integrity and correctness of the imported data. This step includes verifying whether the coordinate system and units of the point cloud data are consistent, and checking whether there is data loss or error during the import process. If problems are found, they need to be adjusted and corrected in time to ensure the integrity of the data.
[0038] Next, the imported scanned point cloud data is preprocessed. The purpose of preprocessing is to remove noise and redundant data, optimize the quality of the point cloud data, and make it more suitable for subsequent matching and modeling steps. The preprocessing process includes the following key steps: Denoising: Use the denoising tool of the 3D modeling software to filter out noise points and isolated points in the point cloud data. Noise points are usually caused by errors in the measurement equipment or external interference. Removing these noise points can improve the clarity and accuracy of the data.
[0039] Filtering: Filter the point cloud data to remove redundant point data. For example, some environmental data irrelevant to construction may be captured during the scanning process. These data need to be removed through filtering tools to retain the core data related to construction.
[0040] Coordinate conversion: If the coordinate system of the scanned point cloud data is inconsistent with the coordinate system of the BIM design model, coordinate conversion is required. Through the coordinate conversion function of the software, the coordinate system of the point cloud data is adjusted to be consistent with the BIM design model to ensure the smooth progress of the subsequent registration process.
[0041] Data simplification: Streamline point cloud data to reduce data volume and improve processing efficiency. The simplification process includes downsampling and gridding point cloud data to reduce data volume as much as possible while maintaining accuracy, thereby improving software processing speed and efficiency.
[0042] After the above preprocessing steps, the optimized target point cloud data is obtained. The target point cloud data has higher clarity and accuracy, removes noise and redundant data, has a consistent coordinate system, and has been streamlined, making it suitable for subsequent matching and modeling steps.
[0043] S21, importing the BIM design model into the 3D modeling software, and aligning the target point cloud data with the BIM design model.
[0044] In one example, the optimized target point cloud data and the original BIM design model are first imported into professional 3D modeling software, such as Autodesk Revit or Bentley ContextCapture. After importing the data, first check whether the coordinate system and unit of the point cloud data and the BIM design model are consistent in the 3D modeling software. If not, corresponding adjustments and conversions need to be made to ensure that the two are aligned in the same coordinate system and unit. Next, the point cloud data and the BIM design model are aligned. The core of the alignment process is to match the target point cloud data with several feature points in the BIM design model. Through the matching of these control points, the position and posture of the point cloud data are adjusted to make it highly coincident with the BIM design model.
[0045] The specific operation steps are as follows: select several feature points in the target point cloud data and BIM design model as control points. These feature points should have obvious geometric features and easily identifiable positions, such as the corners of buildings, the positions of columns, the edges of doors and windows, etc.; use the registration tool of the 3D modeling software to perform preliminary matching on the selected feature points. The software will automatically calculate the translation, rotation and scaling parameters of the point cloud data based on the positional relationship of the feature points to complete the preliminary registration; after the preliminary registration, check and fine-tune the registration results. During the inspection, focus on the matching accuracy of the feature points and the overlap of the overall model. If deviations are found, the positions of the feature points can be adjusted manually, or fine-tuned through the optimization algorithm of the software to ensure the accuracy of the registration results; after completing the registration and adjustment, verify the registration results. Use the registration verification tool of the software to check the overlap and matching accuracy of the point cloud data and the BIM design model at each key position. If necessary, further fine-tuning can be performed to ensure the high accuracy and consistency of the registration results.
[0046] S22, based on the registered target point cloud data and BIM design model, reconstruct the three-dimensional measured model of the factory building to be built through the triangulation algorithm.
[0047] In one example, the triangulation algorithm in the 3D modeling software is used to triangulate the point cloud data to generate a 3D mesh model. The triangulation algorithm gradually builds a complete 3D model by connecting the points in the point cloud data into a triangular mesh, ensuring the geometric accuracy and surface smoothness of the model; in the process of generating the 3D mesh model, it is necessary to compare and adjust it according to the BIM design model to ensure the consistency of the structure and size between the reconstructed model and the design model. Through the comparison tool of the software, the difference between the reconstructed model and the design model can be viewed in real time, and corresponding adjustments and optimizations can be made; finally, the reconstructed 3D measured model is checked and verified. Through the model verification tool of the software, the integrity and accuracy of the 3D measured model are checked to ensure the high accuracy and consistency of the model in terms of geometric shape and size.
[0048] S103, optimizing the BIM design model according to the three-dimensional measured model to generate a target BIM design model.
[0049] In one example, the previously generated 3D measured model is first compared in detail with the original BIM design model. The purpose of this step is to identify the differences between the design model and the actual site. Using professional 3D modeling software such as Autodesk Revit, the 3D measured model can be intuitively overlapped with the BIM design model. In this way, inconsistencies between the two are discovered, such as deviations in structural positions, differences in component sizes, and unforeseen obstacles on site.
[0050] Next, the difference areas identified during the comparison process are marked, and these areas are the areas to be optimized. In professional 3D modeling software, these marks can be displayed intuitively through colors, annotations, etc. After marking, the detailed measured information of the areas to be optimized is extracted from the 3D measured model. This information includes precise size, position, shape and other data to ensure that the data basis for the optimization process is accurate and reliable.
[0051] Then, based on the extracted measured information, the BIM design model is corrected. In the specific operation, the relevant components in the BIM design model are adjusted to make their size, position and shape consistent with the three-dimensional measured model. Here, the editing tools in Revit can be used to accurately modify every detail in the model. For example, if the measured model shows that the position of a column deviates from the design model, the coordinates of the column need to be adjusted in the design model; if the thickness of a wall is different from the actual measurement, the thickness of the wall needs to be updated in the design model. After completing all necessary corrections, an optimized BIM design model is generated, which is the target BIM design model.
[0052] Based on the above embodiment, as an optional implementation, in S103, optimizing the BIM design model according to the three-dimensional measured model to generate the target BIM design model specifically includes: S30-S33: S30, comparing the three-dimensional measured model with the BIM design model, and marking the area in the BIM design model that is inconsistent with the three-dimensional measured model as an area to be optimized.
[0053] S31, extracting measured information of the area to be optimized in the three-dimensional measured model.
[0054] In one example, the key areas that need to be optimized are determined based on the preliminary design and actual site conditions. These areas usually include parts with complex structures, difficult construction, or large differences from the design model, such as support columns, beam connection points, equipment installation areas, etc. In the 3D modeling software, these key areas are viewed and analyzed in detail through view tools and section tools to ensure the accuracy of the annotations.
[0055] Next, in the determined area to be optimized, use the measurement tools and annotation tools of the 3D modeling software to extract detailed measured information. This measured information includes geometric dimensions, spatial positions, angle relationships, etc. The specific steps are as follows: First, select the key points and key lines of the area to be optimized, and use the software's measurement tools to measure its geometric dimensions and spatial positions point by point and line by line to ensure the accuracy and precision of each measurement point; then, record and annotate the measured data, and use the software's annotation tools to annotate the information of each measurement point on the model in the form of text or marks to ensure that the information is clear and visible, which is convenient for subsequent analysis and processing; in the process of extracting and annotating measured information, compare it with the BIM design model to identify and record the differences between the design model and the measured model. The software's comparison tool can intuitively display the deviation between the two, providing a basis for subsequent optimization.
[0056] S32: According to the measured information, the area to be optimized in the BIM design model is corrected.
[0057] In one example, the area to be optimized is located, and the part that needs to be corrected is determined by checking the difference between the measured information and the design model. Then, the geometric size, spatial position and angle relationship of the area to be optimized are adjusted using the software's editing tools to make them consistent with the measured information. For example, the size of the support column is fine-tuned, or the position of the beam connection point is adjusted. During the correction process, the accuracy of each modification step is ensured, and the changes in the model are checked in real time to ensure that the corrected model is highly consistent with the measured data.
[0058] After the correction is completed, the corrected BIM design model is verified, and the matching degree between the model and the measured information is checked again through the comparison tool of the software to ensure that the correction of all areas to be optimized is accurate. The corrected model should be able to accurately reflect the actual situation on site and eliminate the differences between design and construction.
[0059] S33, using the revised BIM design model as the target BIM design model of the factory building to be built.
[0060] S104, generating a construction plan for each type of construction work according to the target BIM design model, and performing resource allocation for each type of construction work according to the construction plan for each type of construction work.
[0061] In one example, the target BIM design model is first imported into construction management software, such as Autodesk Navisworks or Bentley Synchro. These software can perform in-depth analysis of the BIM model and generate detailed construction plans.
[0062] According to the target BIM design model, the construction plan is formulated. The construction plan needs to cover all types of construction work, including civil engineering, structure, electromechanical, decoration, etc. Using the construction simulation function in the construction management software, the construction process of each type of work can be simulated to clarify the construction sequence and time nodes of each type of work. During the simulation process, the software will automatically generate a construction schedule and Gantt chart for each type of work, helping project managers to intuitively understand the progress of the entire construction process.
[0063] In the process of formulating a construction plan, it is necessary to comprehensively consider the interdependence between various types of construction work and the actual situation of the construction site. For example, the completion of civil engineering is a prerequisite for the start of structural engineering, and mechanical and electrical installation needs to be carried out after the completion of structural engineering. Through the three-dimensional visualization function of the BIM model, conflicts and coordination problems between various types of work can be intuitively identified and resolved to ensure the feasibility and rationality of the construction plan.
[0064] After the construction plan is completed, the next step is resource allocation. Resource allocation includes construction personnel, equipment, materials and other aspects. According to the time nodes of the construction plan and the needs of each type of work, the input of construction personnel should be reasonably arranged. Construction management software can provide resource demand analysis function, and automatically calculate the number of construction personnel and the distribution of work types according to the construction task volume of each type of work. The configuration of equipment and materials also needs to be carried out according to the construction plan to ensure that the required equipment and materials can be in place in time at each construction stage without affecting the construction progress.
[0065] In the process of resource allocation, the actual conditions of the construction site and the requirements of the construction process also need to be considered. For example, the arrival and installation of certain large equipment requires a specific time window, and the stacking and management of materials need to be planned in advance. Using the spatial analysis function of the BIM model, the on-site resource layout can be optimized to avoid construction difficulties caused by site restrictions.
[0066] Based on the above embodiment, as an optional implementation, in S104, generating a construction plan for each type of construction work according to the target BIM design model specifically includes S40-S42: S40, extracting building component information from the target BIM design model.
[0067] Specifically, building component information refers to the detailed data and characteristics of each component that makes up a building, which is highly integrated and managed in BIM (Building Information Model). Building component information includes but is not limited to the following: geometric dimensions, materials, location, quantity, type, identification information (component number or label, used for identification in construction drawings and site management), and other parameters (including technical parameters such as component load capacity, fire rating, and thermal insulation performance).
[0068] S41, combining the building component information and the overall progress plan of the factory building to be built, determining the construction sequence and time nodes of each building component.
[0069] In one example, first, the building component information is imported into project management software, such as Microsoft Project or Primavera P6, which can effectively manage and schedule construction tasks. Then, according to the overall schedule, the critical path of construction and the time nodes of each stage are determined. The critical path is the longest path that affects the total duration of the project and includes all the tasks that must be completed on time in the project.
[0070] In project management software, the construction sequence of each component is arranged using the information of the building components (such as geometric dimensions, materials, and locations). For example, the basic components (such as foundations and foundation columns) should be constructed first, followed by the main structure (such as beams and slabs), followed by the secondary structure (such as interior walls and doors and windows), and finally the decoration and installation works (such as painting and equipment installation). When arranging the construction sequence, it is necessary to consider the dependencies between components and the construction process to ensure smooth connection between each process.
[0071] At the same time, the specific construction time of each building component is determined in combination with the time nodes in the overall schedule. For example, the foundation construction phase may take one month, the main structure construction phase may take two months, and the secondary structure and decoration installation phase may take one and a half months. In the project management software, the construction time nodes of each component are marked in detail to form a construction schedule.
[0072] After completing the arrangement of the construction sequence and time nodes, the construction plan is checked and optimized to ensure that the time arrangement of each stage is reasonable and feasible. For example, the Gantt chart function of the software can be used to intuitively view the time arrangement and progress of each task, make necessary adjustments and optimizations, and avoid construction period conflicts and waste of resources.
[0073] S42, generating a construction plan for each type of construction work according to the construction sequence and time nodes of each building component.
[0074] In one example, the construction sequence and time nodes of the building components determined in step S41 are imported into the project management software. Next, the tasks involved in each type of construction work are identified, and a corresponding task list is created. For example, the civil engineering type is responsible for the construction of the foundation and foundation columns, the structural type is responsible for the installation of beams and slabs, the decoration type is responsible for the construction of interior walls and doors and windows, and the decoration and installation type is responsible for painting and equipment installation.
[0075] In the project management software, specific resources and personnel are assigned to each task according to the construction sequence and time nodes, and the Gantt chart function is used to generate a construction plan for each type of construction work. The Gantt chart can intuitively display the time schedule and progress of the task, helping construction managers to effectively monitor and adjust.
[0076] Based on the above embodiment, as an optional implementation, in S42, generating a construction plan for each type of construction work according to the construction sequence and time nodes of each building component specifically includes S420-S423: S420: Determine the type of construction work corresponding to each building component according to the type of each building component.
[0077] In one example, the corresponding construction work type is determined according to the type of building component. For example, the foundation and foundation column belong to the basic components and should be the responsibility of the civil engineering work type; the beam and slab belong to the main structure and should be the responsibility of the structural work type; the interior walls and doors and windows belong to the secondary structure and should be the responsibility of the decoration work type; painting and equipment installation belong to the decoration and installation work type.
[0078] In the project management software, create a task allocation table for construction types and associate each type of building component with the corresponding construction type. For example, assign all foundation and foundation column construction tasks to the civil engineering type, assign all beam and slab construction tasks to the structural type, and assign all interior walls and doors and windows construction tasks to the decoration type.
[0079] After completing the task allocation, check and optimize the task allocation table to ensure that the task volume of each construction type is reasonable and the resource allocation is balanced. Through the resource allocation function of the project management software, ensure that the labor, equipment and materials required for each type of work can be in place on time to avoid resource conflicts and waste.
[0080] S421, based on the construction sequence and time nodes of each building component and in combination with the construction work types corresponding to each building component, determine the work tasks and working time of each construction work type.
[0081] In one example, a comprehensive task list is created in the project management software to list the work tasks of each type of construction work. For example, the tasks of civil engineering work include foundation excavation and foundation column installation; the tasks of structural work include the installation of beams and slabs; the tasks of decoration work include the construction of interior walls and doors and windows; the tasks of decoration and installation work include painting and equipment installation.
[0082] Next, assign specific working time to each task based on the construction sequence and time nodes. For example, the time nodes for foundation excavation and foundation column installation tasks are the first month of construction; the time nodes for beam and slab installation tasks are the second and third months of construction; the time nodes for interior wall and door and window construction tasks are the fourth month of construction; and the time nodes for painting and equipment installation tasks are the fifth month of construction. In the project management software, these tasks and time nodes are entered into the system to generate a detailed construction plan.
[0083] At the same time, in order to ensure the smooth execution of tasks, it is necessary to allocate corresponding resources and personnel to each task. For example, the required civil engineering workers, excavation equipment and materials are allocated to the foundation excavation task; structural workers, lifting equipment and steel are allocated to the beam and slab installation task. Through the resource allocation function of the project management software, it is ensured that the resources required for each task can be in place on time and resource conflicts and waste can be avoided.
[0084] After completing the allocation of tasks and time, use the Gantt chart function of the project management software to generate work tasks and work schedules for each type of construction work.
[0085] S422, obtaining the correlation between various types of construction work.
[0086] In one example, a detailed task dependency diagram is created in the project management software. First, the work tasks of all construction types and their corresponding time nodes are listed. Next, the predecessor and successor tasks of each task are analyzed, and these dependencies are input into the project management software. For example, the foundation column installation task is set as the successor task of the foundation excavation task, and the beam and slab installation task is set as the successor task of the foundation column installation task, and so on.
[0087] In project management software, the dependencies between tasks can be intuitively displayed through network diagrams or critical path methods (CPM). Network diagrams can clearly show the predecessor and successor tasks of each task, as well as the time and logical relationships between tasks.
[0088] S423, generating a construction plan for each type of construction work based on the work tasks and time schedule of each type of construction work and the relationship between each type of construction work.
[0089] In an example, suppose a new energy vehicle factory is being built. The main types of construction work include civil engineering, structural engineering, decoration engineering, and decoration and installation engineering. First, create a task list in the project management software, which contains the specific tasks and schedules of each type of construction work. The work tasks of civil engineering include foundation excavation and foundation column installation. The time nodes for foundation excavation are from January 1 to January 15, and the time nodes for foundation column installation are from January 16 to January 31. The time schedules of other types of work can be found in the time schedules of civil engineering, so I will not go into details here.
[0090] Next, based on the dependencies between the tasks, enter these relationships into the project management software. Foundation excavation is a predecessor task for foundation column installation, foundation column installation is a predecessor task for beam and slab installation, beam and slab installation is a predecessor task for interior wall construction, interior wall construction is a predecessor task for door and window installation, door and window installation is a predecessor task for painting, and painting is a predecessor task for equipment installation. In the project management software, a construction plan is generated using the Gantt chart function. The Gantt chart shows the start and end dates of each task and their dependencies, such as foundation excavation from January 1 to January 15, foundation column installation from January 16 to January 31, and beam and slab installation from February 1 to February 28.
[0091] Finally, the generated construction plan is checked and optimized to ensure that the time schedule of each task is reasonable and coherent. By adjusting the start and end time of the task, ensure that there is no time conflict or resource conflict. For example, if it is found that the installation task of beams and slabs may be delayed, the start time of the interior wall construction needs to be adjusted to ensure that the construction period is not affected.
[0092] Based on the above embodiment, as an optional implementation, in S104, according to the construction plan of each construction type, resource allocation for each construction type specifically includes the following steps: Obtain the historical construction data of the factory building to be built; combine the historical construction data with the construction plan of each construction type, and allocate resources for each construction type. Resource allocation includes: personnel allocation, material allocation, and mechanical equipment allocation.
[0093] In one example, historical construction data of a factory building to be built is obtained from a database. This data includes the staffing, material consumption, and mechanical equipment usage of each type of construction work in previous projects. By analyzing this historical data, the amount of resources required for each type of construction work at different stages can be identified.
[0094] Next, combine these historical construction data with the construction plan of each construction type of the current project. According to the time nodes of the construction plan, determine the resource requirements of each construction type at different stages. For example, in the early stages of the project, civil engineering may require more personnel and machinery and equipment, while in the middle and late stages of the project, decoration and installation types require more materials and professional technicians. In this way, the rationality and consistency of resource allocation can be ensured.
[0095] Then, input these resource allocation data into the project management software to generate a detailed resource allocation table. The resource allocation table clearly shows the personnel, materials and mechanical equipment required for each construction type at different time nodes. For example, the software can generate a Gantt chart to show the resource requirements and time schedule of each construction type, which is convenient for construction management personnel to monitor and adjust. The resource allocation table not only includes the resource requirements for each stage, but can also be further refined to the specific resource allocation on a daily or weekly basis to ensure the accuracy of resource scheduling.
[0096] After allocating resources for each type of construction work, the following steps are also included: Generate a construction resource model corresponding to each type of construction work; integrate the construction resource model of each type of construction work with the target BIM design model to generate an integrated BIM construction model; simulate the construction process of each type of construction work based on the integrated BIM construction model to obtain construction prediction data for each type of construction work; compare the construction prediction data with the preset target data of the factory building to be built to obtain a comparison result; based on the comparison result, adjust the integrated BIM construction model until the prediction data of each type of construction work meets the preset target data.
[0097] In one example, a corresponding construction resource model is generated for each type of construction work. The construction resource model includes the specific configuration and use plan of resources such as personnel, materials, and mechanical equipment. These models are based on historical construction data and the specific needs of the current project, and are generated through detailed data input and model generation through project management software. The construction resource model clearly displays the resource requirements of each type of construction work at different stages on the digital platform.
[0098] Next, the construction resource models of each type of construction work are integrated with the target BIM design model to generate an integrated BIM construction model. The target BIM design model contains detailed design information of the factory building to be built, including design details of various aspects such as structure, system and components. By integrating the construction resource model with the BIM design model, the coordination and optimization of design and construction resources can be achieved on a unified platform. The integrated BIM construction model not only contains design information, but also combines the resource configuration required for actual construction, making the model more comprehensive and practical.
[0099] Then, the construction process of each type of construction work is simulated based on the integrated BIM construction model. The simulation uses advanced simulation software to virtually reproduce the construction process based on the integrated BIM model. During the simulation process, the system will consider various construction conditions and restrictions, such as construction period, resource availability, construction sequence, etc., and generate construction forecast data for each type of construction work. These forecast data include construction progress, resource usage, potential problems and risks, etc., providing construction managers with comprehensive construction expectation information.
[0100] Next, the construction forecast data is compared with the preset target data of the factory building to be built. The preset target data are various construction indicators set before the project starts, such as construction period, quality standards, cost control, etc. Through the comparison, the difference between the actual construction forecast data and the preset target data can be found, and potential deviations and problems can be identified. The comparison results provide an important basis for construction management personnel to adjust construction plans and resource allocation.
[0101] According to the comparison results, the integrated BIM construction model is adjusted until the forecast data of each construction type meets the preset target data. The adjustment process may include modifying the construction sequence, optimizing resource allocation, adjusting the construction schedule, etc. After each adjustment, simulation and data comparison are performed again to gradually approach the preset target. Through continuous cycles of adjustment and optimization, the construction process will eventually reach the optimal state.
[0102] Based on the above method, the present application also discloses a device for rapid construction of a new energy vehicle plant, such as Figure 2 As shown, Figure 2 : is a schematic diagram of a structure of a device for rapid construction of a new energy vehicle plant provided in an embodiment of the present application, the device comprises: an acquisition module, a matching module, a generation module and an output module; wherein, The acquisition module is used to obtain the scanning point cloud data generated by the 3D laser scanner after the actual measurement of the factory building to be built, and to obtain the BIM design model of the factory building to be built in the BIM model library; the matching module is used to match the scanning point cloud data and the BIM design model to generate the 3D measured model of the factory building to be built; the generation module is used to optimize the BIM design model according to the 3D measured model to generate the target BIM design model; the output module is used to generate the construction plan of each construction type according to the target BIM design model, and to allocate resources for each construction type according to the construction plan of each construction type.
[0103] It should be noted that: when the device provided in the above embodiment realizes its function, only the division of the above functional modules is used as an example. In actual application, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. In addition, the device and method embodiments provided in the above embodiment belong to the same concept, and the specific implementation process is detailed in the method embodiment, which will not be repeated here.
[0104] See also Figure 3 , is a schematic diagram of the structure of an electronic device provided in an embodiment of the present application. Figure 3 As shown, the electronic device 1000 may include: at least one processor 1001 , at least one network interface 1004 , a user interface 1003 , a memory 1005 , and at least one communication bus 1002 .
[0105] The communication bus 1002 is used to realize the connection and communication between these components.
[0106] The user interface 1003 may include a display screen (Display) and a camera (Camera). Optionally, the user interface 1003 may also include a standard wired interface and a wireless interface.
[0107] The network interface 1004 may optionally include a standard wired interface or a wireless interface (such as a WI-FI interface).
[0108] Among them, the processor 1001 may include one or more processing cores. The processor 1001 uses various interfaces and lines to connect various parts in the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory 1005, and calling data stored in the memory 1005. Optionally, the processor 1001 can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field-Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor 1001 can integrate one or a combination of a central processing unit (Central Processing Unit, CPU), a graphics processing unit (Graphics Processing Unit, GPU) and a modem. Among them, the CPU mainly processes the operating system, user interface and application programs; the GPU is responsible for rendering and drawing the content to be displayed on the display screen; the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor 1001, and it can be implemented separately through a chip.
[0109] Among them, the memory 1005 may include a random access memory (Random Access Memory, RAM) and may also include a read-only memory (Read-Only Memory). Optionally, the memory 1005 includes a non-transitory computer-readable storage medium. The memory 1005 can be used to store instructions, programs, codes, code sets or instruction sets. The memory 1005 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. The memory 1005 may optionally also be at least one storage device located away from the aforementioned processor 1001. As Figure 3 As shown, the memory 1005 as a computer storage medium may include an operating system, a network communication module, a user interface module, and an application program for a method for rapid construction of a new energy vehicle plant.
[0110] exist Figure 3In the electronic device 1000 shown, the user interface 1003 is mainly used to provide an input interface for the user and obtain data input by the user; and the processor 1001 can be used to call an application program stored in the memory 1005 for a method for rapid construction of a new energy vehicle factory. When executed by one or more processors, the electronic device executes one or more of the methods described in the above embodiments.
[0111] An electronic device readable storage medium stores instructions, which, when executed by one or more processors, enable the electronic device to execute one or more of the methods described in the above embodiments.
[0112] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the order of the actions described, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required for the present application.
[0113] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0114] In the several embodiments provided in the present application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are only schematic, such as the division of the units, which is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some service interfaces, and the indirect coupling or communication connection of devices or units can be electrical or other forms.
[0115] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0116] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0117] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to execute all or part of the steps of the method described in each embodiment of the present application. The aforementioned memory includes: various media that can store program codes, such as USB flash drives, mobile hard drives, magnetic disks or optical disks.
[0118] The above is only an exemplary embodiment of the present disclosure, and the scope of the present disclosure cannot be limited thereto. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the specification and practicing the disclosure here, those skilled in the art will easily think of other embodiments of the present disclosure. This application is intended to cover any modification, use or adaptation of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the technical field not recorded in the present disclosure. The description and examples are only regarded as exemplary, and the scope and spirit of the present disclosure are defined by the claims.
Claims
1. A method for rapidly constructing a new energy vehicle plant, the method comprising: Obtain scanning point cloud data generated by a 3D laser scanner after actual measurement of the factory building to be built, and obtain a BIM design model of the factory building to be built in a BIM model library; Matching the scanned point cloud data with the BIM design model to generate a three-dimensional measured model of the factory building to be built; According to the three-dimensional measured model, the BIM design model is optimized to generate a target BIM design model; A construction plan for each type of construction work is generated according to the target BIM design model, and resources are allocated to each type of construction work according to the construction plan for each type of construction work.
2. The method for rapid construction of a new energy vehicle plant according to claim 1, characterized in that: The matching of the scanned point cloud data and the BIM design model to generate a three-dimensional measured model of the factory building to be built includes: Importing the scanned point cloud data into a three-dimensional modeling software, preprocessing the scanned point cloud data, and obtaining target point cloud data; Importing the BIM design model into the three-dimensional modeling software, and registering the target point cloud data with the BIM design model; Based on the registered target point cloud data and the BIM design model, a three-dimensional measured model of the factory building to be built is reconstructed through a triangulation algorithm.
3. The method for rapid construction of a new energy vehicle plant according to claim 1, characterized in that: The step of optimizing the BIM design model according to the three-dimensional measured model to generate a target BIM design model includes: Comparing the three-dimensional measured model with the BIM design model, marking areas in the BIM design model that are inconsistent with the three-dimensional measured model as areas to be optimized; Extracting measured information of the area to be optimized in the three-dimensional measured model; According to the measured information, the area to be optimized in the BIM design model is corrected; The revised BIM design model is used as the target BIM design model of the factory building to be built.
4. The method for rapid construction of a new energy vehicle plant according to claim 1, characterized in that: Generating a construction plan for each type of construction work according to the target BIM design model includes: Extracting building component information from the target BIM design model; Determine the construction sequence and time nodes of each building component by combining the building component information and the overall progress plan of the factory building to be built; A construction plan for each type of construction work is generated according to the construction sequence and time nodes of each of the building components.
5. The method for rapid construction of a new energy vehicle plant according to claim 4, characterized in that: The generating of a construction plan for each type of construction work according to the construction sequence and time nodes of each of the building components includes: Determining the type of construction work corresponding to each building component according to the type of each building component; Based on the construction sequence and time nodes of each of the building components, combined with the construction work types corresponding to each of the building components, determine the work tasks and working time of each of the construction work types; Obtaining the association relationship between the various types of construction work; Based on the work tasks and time arrangements of each type of construction work, as well as the relationships between each type of construction work, a construction plan for each type of construction work is generated.
6. The method for rapid construction of a new energy vehicle plant according to claim 1, characterized in that: The resource allocation for each type of construction work according to the construction plan of each type of construction work includes: Obtaining historical construction data of the factory building to be built; Combining the historical construction data with the construction plan of each construction type, resources are allocated for each construction type, and the resource allocation includes: personnel allocation, material allocation and mechanical equipment allocation.
7. The method for rapid construction of a new energy vehicle plant according to claim 1, characterized in that: After allocating resources for each type of construction work, the method further includes: Generate a construction resource model corresponding to each of the construction types; Integrate the construction resource model of each construction type with the target BIM design model to generate an integrated BIM construction model; According to the integrated BIM construction model, the construction process of each construction type is simulated to obtain construction prediction data of each construction type; Comparing the construction prediction data with the preset target data of the factory building to be built to obtain a comparison result; According to the comparison results, the integrated BIM construction model is adjusted until the predicted data of each construction work type meets the preset target data.
8. A device for rapid construction of new energy vehicle workshops, characterized in that: The device comprises: an acquisition module, a matching module, a generation module and an output module; wherein, The acquisition module is used to acquire scanning point cloud data generated by a three-dimensional laser scanner after actual measurement of the factory building to be built, and to acquire a BIM design model of the factory building to be built in a BIM model library; The matching module is used to match the scanned point cloud data with the BIM design model to generate a three-dimensional measured model of the factory building to be built; The generating module is used to optimize the BIM design model according to the three-dimensional measured model to generate a target BIM design model; The output module is used to generate a construction plan for each type of construction work according to the target BIM design model, and to allocate resources for each type of construction work according to the construction plan for each type of construction work.
9. An electronic device, characterized in that: It includes a processor, a memory, a user interface and a network interface, the memory is used to store instructions, the user interface and the network interface are used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes the method as described in any one of claims 1-7.
10. A computer-readable storage medium, characterized in that: A computer program is stored which can be loaded by a processor and execute the method according to any one of claims 1 to 7.
Citation Information
Cited By
Engineering building construction system and method based on 3D modeling
CN119180087A
Method and system for generating decoration BIM model by using personalized decoration requirements
CN120408984A
A method and system for generating a decoration BIM model by utilizing personalized decoration requirements
CN120408984B
Artificial intelligence computing power center construction management method and system
CN120805231A
Steel structure factory building modeling data processing method based on BIM technology
CN120874167A