Geological exploration mud circulation purification device and mud circulation purification method

The three-stage gradient purification architecture and sensor-controlled mud circulation purification device solve the problem of untimely separation of rock cuttings in the mud, improving drilling efficiency and reducing environmental impact.

CN123109575APending Publication Date: 2026-11-17INNER MONGOLIA MINING DEVELOPMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611171999.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-04
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

During geological exploration drilling, rock cuttings carried in the drilling mud are not separated in time, which leads to the deterioration of the drilling mud performance, affects drilling efficiency, and causes harm to the ecological environment.

Method used

A three-stage gradient purification architecture is adopted, including pre-sedimentation in the containment tank, static settling in the treatment chamber, and centrifugal separation in the hydrocyclone. Combined with sensors and a control system, it can achieve the step-by-step removal of solid particles with different particle sizes. Neutralizing agents or flocculants are added through the feeding chamber to optimize the mud performance.

Benefits of technology

It improves mud purification efficiency, reduces the amount of waste mud discharged, reduces the ecological impact of drilling on soil and vegetation, and ensures the safety and efficiency of drilling operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109575A_ABST
    Figure CN123109575A_ABST
Patent Text Reader

Abstract

This application discloses a geological exploration mud circulation and purification device and method, including a receiving pool, a treatment chamber, a hydrocyclone, a storage tank, a sensor group, and a controller. Through a three-stage gradient purification architecture of pre-sedimentation in the receiving pool, settling in the treatment chamber, and centrifugal separation in the hydrocyclone, solid particles of different particle sizes are removed step by step at each stage. Compared with the traditional single sedimentation tank method, it avoids the overload of a single treatment unit and improves the overall purification efficiency. The conical hydrocyclone chamber, combined with the tangential mud feeding method, uses the centrifugal force field to separate fine particles from the mud. The purified mud is directly returned to the well for recycling through the storage tank and the transfer pump, which greatly reduces the amount of waste mud discharged, thereby reducing the ecological impact of drilling operations on soil and vegetation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of geological exploration drilling technology, specifically relating to a geological exploration mud circulation and purification device and a mud circulation and purification method. Background Technology

[0002] During geological exploration drilling operations, the main functions of drilling mud (drilling fluid) include: carrying and suspending rock cuttings, cooling and lubricating the drill bit, balancing formation pressure, stabilizing the wellbore, and transmitting water power. With the continuous increase in drilling depth and the increasing number of drilling tasks in complex formations (such as shale, fractured zones, and water-sensitive formations), the requirements for drilling mud performance are also becoming higher and higher. The quality of drilling mud performance directly affects drilling efficiency, borehole quality, and construction safety.

[0003] During drilling, when drilling mud returns to the surface from the borehole, it carries a large amount of drilling cuttings. These cuttings include large rock fragments broken off from the bottom of the well, medium and fine sandy and muddy components, as well as fine and low-quality solid particles. If these solid particles cannot be separated from the drilling mud in time, it will lead to the deterioration of the drilling mud's rheological properties such as density, viscosity, and shear force, increase the circulating equivalent density, affect drilling efficiency, and in severe cases, even cause downhole accidents such as stuck drill bits or buried drill bits. In addition, if waste drilling mud containing a large amount of solid particles is discharged directly, it will cause soil compaction and vegetation damage, posing a threat to the ecological environment. Summary of the Invention

[0004] This application proposes a geological exploration drilling mud circulation and purification device and a drilling mud circulation and purification method. On the one hand, it purifies the drilling mud to improve drilling efficiency, and on the other hand, it purifies and recycles the mud to reduce waste discharge and reduce the impact on the ecological environment during the drilling process.

[0005] To achieve the above objectives, the present invention provides the following technical solution: A geological exploration mud circulation and purification device includes a receiving pool, a treatment chamber, a hydrocyclone, a storage tank, a sensor group, and a controller; The containment tank is connected to the treatment chamber via a first pipeline. A first pump body is installed on the first pipeline. The inlet of the first pipeline is located at the upper part of the containment tank. The first pump body is used to pump the sludge into the treatment chamber for sedimentation treatment. The processing chamber is connected to the hydrocyclone via a second pipeline. A second pump body is installed on the second pipeline. The inlet of the second pipeline is located at the upper part of the processing chamber. The second pump body is used to pump the slurry at the upper part of the processing chamber into the hydrocyclone. The hydrocyclone includes a conical cyclone cavity, the side wall of which is provided with a slurry inlet tangentially to its outer wall, the slurry outlet of which is located at its upper part and connected to the storage tank via a third pipeline, the storage tank being connected to a delivery pump, and the delivery pump being used to extract the purified slurry from the storage tank and send it into the return pipeline. The sensor group includes a first liquid level sensor disposed in the containment pool, a second liquid level sensor disposed in the processing chamber, and a third liquid level sensor disposed in the storage tank. The controller is electrically connected to the sensor group, the first pump body, the second pump body, and the delivery pump, respectively.

[0006] In one embodiment of this application, the sensor group further includes a temperature sensor, a concentration sensor, and a pH sensor disposed within the processing chamber. A feeding chamber is disposed on the side of the processing chamber, and the feeding chamber is connected to the processing chamber via a feeding pipeline. A feeding valve is disposed on the feeding pipeline. The controller is electrically connected to the temperature sensor, the concentration sensor, the pH sensor, and the feeding valve, respectively, and is used to control the addition of neutralizing reagent or flocculant in the feeding chamber according to the temperature, slurry concentration, and pH value within the processing chamber.

[0007] In one embodiment of this application, the inner wall of the swirling cavity is provided with a wear-resistant lining.

[0008] In one embodiment of this application, a fastening bolt is connected to the fixing block, and a stirrer is provided inside the storage tank.

[0009] In one embodiment of this application, a bracket is provided on the outer wall of the swirling cavity to improve the installation stability of the swirling cavity.

[0010] In one embodiment of this application, a slag discharge valve is provided at the bottom of the processing chamber and the cyclone chamber, respectively.

[0011] In one embodiment of this application, the slag discharge valve at the bottom of the processing chamber and the cyclone chamber is an electric slag discharge valve.

[0012] In one embodiment of this application, the control system is a PLC controller, which is electrically connected to the sensor group, the first pump body, the second pump body and the delivery pump, respectively, and is used to control the operation of the device.

[0013] A mud circulation and purification method, using the geological exploration mud circulation and purification device of this application, includes the following steps: S1: Inject the slurry to be purified returned during drilling into the containment tank; S2: The slurry in the containment tank is pumped into the treatment chamber through the first pump body on the first pipeline for static sedimentation to separate rock fragments. S3: Pump the slurry in the processing chamber into the cyclone chamber to separate the medium and fine particle impurities in the mud, and pump the separated slurry into the storage tank through the third pump body on the third pipeline; S4: The purified mud in the storage tank is pumped out by the transfer pump and sent into the return pipeline to realize the recycling of the mud.

[0014] Furthermore, in step S2, a neutralizing agent or flocculant is added to the processing chamber through the feeding chamber.

[0015] In summary, the technical solution proposed in this application has the following beneficial technical effects: This application adopts a three-stage gradient purification architecture of pre-sedimentation in the containment tank, static placement in the treatment chamber, and centrifugal separation by a hydrocyclone, so that solid particles of different particle sizes are removed step by step in each stage. Compared with the traditional single sedimentation tank method, it avoids the overload of a single treatment unit and improves the overall purification efficiency. The conical hydrocyclone chamber, combined with the tangential slurry feeding method, uses the centrifugal force field to separate fine particles from the slurry. The purified mud is directly returned to the well for recycling through storage tanks and transfer pumps, which greatly reduces the amount of waste mud discharged, thereby reducing the ecological impact of drilling operations on soil and vegetation. Attached Figure Description

[0016] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0017] Figure 1 A schematic diagram of the component connection structure of a geological exploration mud circulation and purification device provided in an embodiment of this application; Figure 2 A top view of the hydrocyclone structure of a geological exploration mud circulation and purification device provided in an embodiment of this application; Figure 3 for Figure 2 Schematic diagram of the cross-sectional structure at point AA; Figure 4 A three-dimensional structural diagram of a hydrocyclone in a geological exploration mud circulation and purification device provided in an embodiment of this application.

[0018] In the figure: 1. Container tank, 11. First pipeline, 12. First pump body, 2. Processing chamber, 21. Second pipeline, 22. Second pump body, 3. Hydrocyclone, 31. Inlet 32. Storage tank, 4. Third pipeline, 5. Conveying pump, 6. Feeding chamber, 7. Feeding pipeline, 71. Support. Detailed Implementation

[0019] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions in the embodiments of this application are described clearly and completely below. Obviously, the described embodiments are only some embodiments of this application, not all embodiments. Based on the embodiments in this application, all other embodiments obtained by those skilled in the art without creative effort are also within the scope of protection of this application.

[0020] It should be noted that in the description of this application, the terms "center", "longitudinal", "lateral", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", and "outer" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.

[0021] In this application, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection between two components. Those skilled in the art will understand the specific meaning of these terms in this application based on the specific circumstances.

[0022] In the embodiments of this application, the terms "exemplary" or "for example" are used to indicate that something is an example, illustration, or description. Any embodiment or design that is described as "exemplary" or "for example" in the embodiments of this application should not be construed as being more preferred or advantageous than other embodiments or design. Specifically, the use of the terms "exemplary" or "for example" is intended to present the relevant concepts in a specific manner.

[0023] This embodiment provides a geological exploration mud circulation and purification device, see reference. Figures 1-4 As shown, it includes a containment pool 1, a processing chamber 2, a hydrocyclone 3, a storage tank 4, a sensor group, and a controller; The container tank 1 is connected to the processing chamber 2 through a first pipeline 11. A first pump body 12 is installed on the first pipeline 11. The inlet of the first pipeline 11 is located at the upper part of the container tank 1. The first pump body 12 is used to pump the sludge into the processing chamber 2 for sedimentation treatment. The processing chamber 2 is connected to the hydrocyclone 3 through a second pipe 21. A second pump body 22 is installed on the second pipe 21. The inlet of the second pipe 21 is located at the upper part of the processing chamber 2. The second pump body 22 is used to pump the slurry at the upper part of the processing chamber 2 into the hydrocyclone 3. The hydrocyclone 3 includes a conical cyclone cavity 31. The side wall of the cyclone cavity 31 is provided with a slurry inlet 32 ​​arranged tangentially to its outer wall. The slurry outlet of the cyclone cavity 31 is located at its upper part and is connected to the storage tank 4 through a third pipeline 5. The storage tank 4 is connected to a delivery pump 6. The delivery pump 6 is used to extract the purified slurry in the storage tank 4 and send it into the return pipeline. The sensor group includes a first liquid level sensor disposed in the containment tank 1, a second liquid level sensor disposed in the processing chamber 2, and a third liquid level sensor disposed in the storage tank 4. The controller is electrically connected to the sensor group, the first pump body 12, the second pump body 22 and the delivery pump 6, respectively.

[0024] In the above embodiment, the mud entering the receiving tank 1 is pre-screened to separate large rock particles. The receiving tank 1 serves as the primary buffer unit and is connected to the processing chamber 2 via a first pipeline 11. A first pump body 12 is installed on the first pipeline 11. Furthermore, the inlet of the first pipeline 11 is located at the upper part of the receiving tank 1. The drilling mud returning carries rock fragments. If the mud is introduced from the bottom, it will agitate the solid phase that has already settled at the bottom of the tank, causing secondary suspension. If the mud is introduced from the top, it will utilize the principle of natural sedimentation due to gravity, allowing the large rock fragments to settle at the bottom of the receiving tank 1. Pre-deposition reduces the processing load on subsequent processing units. The first pump body 12 can be a slurry pump. The processing chamber 2 is an intermediate processing unit. After secondary sedimentation of the mud in the processing chamber 2, rock cuttings are deposited at the bottom of the processing chamber 2, and the upper part is a relatively clear slurry. Taking the liquid from the top can effectively avoid bringing the settled large solid particles into the hydrocyclone 3, which protects the hydrocyclone 3 from the impact and wear of large particles and improves the hydrocyclone separation efficiency. The side wall of the hydrocyclone 31 is provided with a slurry inlet 32 ​​along the tangential direction of its outer wall, and the slurry outlet is located at its upper part and connected to the storage tank 4 through the third pipeline 5. After the slurry enters the conical vortex chamber 31 tangentially at a certain pressure and flow velocity, it generates high-speed rotational motion, forming swirling turbulence. Due to the differences in particle size and density between coarse and fine particles, the centrifugal force, centripetal buoyancy, and liquid drag they experience are different. Under the combined action of centrifugal force and gravity, the coarse and heavy particles are thrown against the wall of the chamber and move spirally downwards along the cone, eventually being discharged from the bottom outlet. The fine particles and the purified slurry, due to the smaller centrifugal force, form an inner vortex in the center of the vortex chamber 31, moving upwards and being discharged through the upper overflow outlet (i.e., the slurry outlet). The storage tank 4 then... The three-pipeline 5 is connected to the slurry outlet of the hydrocyclone 3, and the storage tank 4 is connected to the transfer pump 6. The transfer pump 6 extracts the purified slurry and sends it into the return pipeline. The controller is a PLC. The controller is electrically connected to the first liquid level sensor in the container tank 1, the second liquid level sensor in the processing chamber 2, the third liquid level sensor in the storage tank 4, and the frequency converter of the pump body. When the liquid level in the container tank 1 is higher than the first preset threshold, the frequency of the first pump body 12 is started or increased; when the liquid level in the processing chamber 2 is lower than the second preset threshold, the second pump body 22 is stopped.When the liquid level in storage tank 4 is higher than the third preset threshold, the transfer pump 6 is started. That is, when the liquid level in container tank 1 reaches the high threshold, it indicates that the incoming slurry volume has increased or is close to full, and the slurry needs to be pumped into treatment chamber 2 in time to prevent overflow. When the liquid level in treatment chamber 2 is lower than the low threshold, it indicates that the incoming slurry is insufficient. If the second pump body 22 continues to run, it will cause idling and air intake, resulting in pump cavitation damage and unstable feeding of hydrocyclone 3. When the liquid level in storage tank 4 reaches the high threshold, it indicates that the purified slurry has accumulated to a certain amount, and the transfer pump 6 needs to be started to send it into the return pipeline to prevent storage tank 4 from overflowing. By setting the liquid level threshold (such as starting container tank 1 at a high level, stopping treatment chamber 2 at a low level, and starting storage tank 4 at a high level), the effective volume of each container is fully utilized, the system processing capacity is maximized, and the liquid level linkage control ensures that each pump body only runs or adjusts its speed when needed, avoiding energy loss due to ineffective operation. This application avoids resource waste; for example, during operation, the first pump 12 automatically starts when the liquid level in the containment tank 1 is higher than 1.5m; the second pump 22 automatically stops when the liquid level in the treatment chamber 2 is lower than 0.8m to prevent dry running; and the transfer pump 6 automatically starts when the liquid level in the storage tank 4 is higher than 2.0m. This application utilizes a three-stage gradient purification architecture—pre-sedimentation in the containment tank 1, settling in the treatment chamber 2, and centrifugal separation in the hydrocyclone 3—to remove solid particles of different sizes at each stage. Compared to the traditional single sedimentation tank method, this avoids overloading of a single treatment unit, improving overall purification efficiency. The conical hydrocyclone 31, combined with tangential slurry feeding, uses centrifugal force to separate fine particles from the slurry. The purified slurry is then directly returned to the well for recycling via the storage tank 4 and the transfer pump 6, significantly reducing the amount of waste slurry discharged and thus reducing the ecological impact of drilling operations on soil and vegetation.

[0025] In one embodiment of this application, the sensor group further includes a temperature sensor, a concentration sensor, and a pH sensor disposed in the processing chamber 2. A feeding chamber 7 is disposed on the side of the processing chamber 2. The feeding chamber 7 is connected to the processing chamber 2 through a feeding pipeline 71, and a feeding valve is disposed on the feeding pipeline 71. The controller is electrically connected to the temperature sensor, the concentration sensor, the pH sensor, and the feeding valve, respectively, and is used to control the addition of neutralizing reagent or flocculant in the feeding chamber 7 according to the temperature, slurry concentration, and pH value in the processing chamber 2.

[0026] In the above embodiment, a temperature sensor is used to monitor the temperature of the mud in the treatment chamber 2. The feeding chamber 7 is connected to the treatment chamber 2 via a feeding pipe 71. A feeding valve is installed on the feeding pipe 71. The feeding chamber 7 serves as a storage and dosing unit for reagents, storing neutralizing agents (used to adjust the pH value of the mud, such as lime milk or dilute sulfuric acid) and flocculants. The feeding valve (which can be an electric regulating valve) adjusts its opening under the controller's command to control the amount of reagents added. Dosing is based on real-time concentration data and avoids the problems of over- or under-dosing caused by traditional empirical dosing. Excessive flocculant will cause excessive flocculation of the mud, which will affect its fluidity. Insufficient flocculant will lead to insufficient settling of fine particles. The temperature sensor enables the control system to dynamically adjust the dosing strategy according to the actual temperature of the mud. For example, the dosing can be appropriately increased at high temperatures. The dosage is increased to compensate for the loss of flocculant activity, and appropriately reduced at low temperatures to avoid excessive flocculation. Drilling mud may become acidified or alkalized due to the formation environment during circulation. Adding a neutralizing agent through the feeding chamber 7 adjusts the mud pH to a suitable range (neutralizing the pH), protecting the drill bit from corrosion. Furthermore, the controlled addition of the equipment eliminates the need for operators to directly contact the flocculant and neutralizing agent, avoiding harm to the skin and respiratory system from chemicals. The temperature sensor is a resistance temperature sensor, and the concentration sensor is an ultrasonic concentration meter. The feeding chamber 7 contains a flocculant chamber and a neutralizing agent chamber, each connected to a feeding pipeline 71. Each feeding pipeline 71 is equipped with an electric regulating valve that adjusts its opening under controller commands to control the dosage of the chemicals.

[0027] In one embodiment of this application, the inner wall of the swirling cavity 31 is provided with a wear-resistant lining.

[0028] In the above embodiment, the high-speed rotating slurry carries coarse and heavy particles (rock fragments, sand grains, etc.). These particles are thrown towards the vessel wall under centrifugal force and move downwards along the cone in a spiral motion. During this process, the solid particles continuously generate high-speed scouring and impact wear on the inner wall of the swirling cavity 31. The wear-resistant liner is set on the inner wall surface of the swirling cavity 31, covering the entire inner wall area of ​​the swirling cavity 31. That is, the wear-resistant liner completely covers the conical inner wall surface of the swirling cavity 31, extending from the upper cylindrical section of the swirling cavity 31 to the bottom flow port of the lower cone, forming a complete wear-resistant protective layer. The material of the wear-resistant liner can be wear-resistant materials such as corundum. The liner and the outer shell are tightly bonded by adhesive or mechanical fixing. The function of the wear-resistant liner is to directly bear this scouring and wear, protect the metal outer shell of the swirling cavity 31 from being worn through, thereby extending the service life of the swirling cavity 31.

[0029] In one embodiment of this application, a stirrer is provided inside the storage tank 4.

[0030] In the above embodiment, the agitator is installed inside the storage tank 4 and mainly consists of a drive motor, a reducer, an agitator shaft, and an agitator impeller. The agitator shaft is vertically installed in the center or eccentric position of the storage tank 4, and the agitator impeller is fixed to the agitator shaft. The impeller can be an axial flow blade or a turbine blade. The agitator material is stainless steel or carbon steel with a surface coated with an anti-corrosion coating. The storage tank 4 is used to store the mud purified by the hydrocyclone 3 and to send the purified mud back to the well for recycling through the transfer pump 6. Even after separation by the hydrocyclone 3, the purified mud still contains a certain amount of fine solid particles (especially particles smaller than the separation particle size of the hydrocyclone 3). These fine particles will slowly settle due to gravity under static conditions and accumulate at the bottom of the tank. If settling occurs, the slurry density in the upper part of storage tank 4 will be lower than that in the lower part, resulting in uneven stratification of the mud's rheological properties (density, viscosity, shear stress, etc.). The agitator keeps the mud in storage tank 4 in a suspended and flowing state through continuous mechanical stirring, preventing solid particles from settling. In addition, drilling operations require the return mud to the well to have stable density and viscosity. The agitator keeps the mud in storage tank 4 in a homogeneous state, ensuring that the delivery pump 6 pumps out mud with uniform properties, thereby ensuring the stability of drilling operation parameters.

[0031] In one embodiment of this application, see [reference] Figure 4 As shown, a bracket 8 is provided on the outer wall of the swirling cavity 31 to improve the installation stability of the swirling cavity 31.

[0032] In the above embodiments, the support 8 can be a triangular support frame. The support 8 is fixed to the outer wall of the cyclone cavity 31. When the hydrocyclone 3 is working, the slurry enters the cyclone cavity 31 tangentially at a high pressure and flow rate, generating high-speed rotation within the cavity. The high-speed rotating slurry generates a large centrifugal force and impact force on the wall of the cyclone cavity 31. At the same time, the equipment itself may vibrate due to the dynamic imbalance of the rotating fluid. If the cyclone cavity 31 is not installed securely, these forces and vibrations will cause the equipment to shake, the pipe joints to loosen or even fall off, seriously affecting the separation effect and operational safety. The role of the support 8 is... The bracket 8 securely fixes the cyclone cavity 31 to the installation foundation, resisting various forces and vibrations generated during operation and ensuring the stability of the cyclone cavity 31 in the high-speed rotating flow field. In addition, the bracket 8 connects to the installation foundation, limiting the displacement and vibration of the cyclone cavity 31, protecting the integrity and sealing of the pipeline (the inlet 32 ​​and outlet connecting pipeline of the cyclone 3), avoiding environmental pollution and safety hazards caused by mud leakage. Furthermore, the bracket 8 fixes the equipment, suppresses structural vibration, reduces the overall operating noise level, and improves the working environment for on-site operators.

[0033] In one embodiment of this application, slag discharge valves are respectively provided at the bottom of the processing chamber 2 and the swirling chamber 31.

[0034] In the above embodiment, the slag discharge valve of the processing chamber 2 is installed at the lowest point of the bottom of the processing chamber 2 and is connected to the slag discharge port at the bottom of the processing chamber 2 through a flange. The slag discharge valve of the cyclone chamber 31 (i.e., the underflow valve of the hydrocyclone 3) is installed at the lower end of the cone of the cyclone chamber 31. After the processing chamber 2 is settled, large particles of rock debris and flocculent sediments accumulate at the bottom, which need to be discharged regularly to maintain the effective volume and separation effect of the processing chamber 2. The bottom of the cyclone chamber 31, i.e. the underflow port of the hydrocyclone 3, is the discharge outlet for the separated coarse and heavy particles. The timeliness and smoothness of the underflow port slag discharge are beneficial to improving the separation efficiency of the hydrocyclone 3. The slag discharge valve discharges the separated solid particles to the slag collection area through the pipeline, which is convenient for subsequent dehydration, solidification or off-site treatment.

[0035] In one embodiment of this application, the slag discharge valve at the bottom of the processing chamber 2 and the swirl chamber 31 is an electric slag discharge valve.

[0036] In the above embodiments, traditional slag discharge requires manual operation of valves, and the pressure slurry in the treatment chamber 2 and hydrocyclone 3 may splash and injure people. Electric slag discharge can realize remote control operation, that is, the operator can trigger the slag discharge valve to discharge slag through a remote manual button to ensure the safety of the staff. The slag discharge method can adopt timed slag discharge, for example, the treatment chamber 2 discharges slag once every 4 hours when the equipment is running, and the hydrocyclone 3 discharges slag once every 2 hours.

[0037] In one embodiment of this application, the control system is a PLC controller, which is electrically connected to the sensor group, the first pump body 12, the second pump body 22 and the delivery pump 6, respectively, and is used to control the operation of the device.

[0038] In the above embodiment, when the liquid level in the containment tank 1 reaches the high threshold, the PLC starts the first pump 12 to pump the slurry into the treatment chamber 2; when the liquid level in the treatment chamber 2 is lower than the low threshold, the PLC stops the second pump 22 to prevent it from running dry. This rapid response ensures that the system always operates under optimal conditions, avoiding time delays and judgment errors caused by manual operation.

[0039] A mud circulation and purification method, using the geological exploration mud circulation and purification device of this application, includes the following steps: S1: Inject the slurry to be purified returned during the drilling process into the receiving tank 1; S2: The slurry in the container tank 1 is pumped into the treatment chamber 2 through the first pump body 12 on the first pipeline 11 for static sedimentation to separate rock fragments. S3: Pump the slurry in the processing chamber 2 into the cyclone chamber 31 to separate the medium and fine particle impurities in the mud, and pump the separated slurry into the storage tank 4 through the third pump body on the third pipeline 5. S4: The purified mud in storage tank 4 is extracted by the transfer pump 6 and sent into the return pipeline to realize the recycling of mud.

[0040] In the actual implementation of this application: the method includes four sequentially executed steps, constituting a complete mud purification cycle. Step S1 is the collection and primary buffering of mud, where the drilling mud containing cuttings first enters the receiving tank 1. The receiving tank 1 serves as the first-stage buffer unit, with its inlet located at the top. Large cuttings are pre-deposited at the bottom of the tank using the principle of natural sedimentation due to gravity. Step S2 is the primary purification, where the relatively clear slurry from the upper part of the receiving tank 1 is pumped into the treatment chamber 2 by the first pump 12. In the treatment chamber 2, the slurry is allowed to settle and further... Separating rock cuttings particles; Step S3 is secondary purification, where the clarified slurry from the upper part of the treatment chamber 2 is pumped into the cyclone chamber 31, where centrifugal force is used to separate medium and fine particle impurities. The purified slurry is discharged from the slurry outlet at the upper part of the cyclone chamber 31 and enters the storage tank 4; Step S4 is mud recycling, where the purified mud in the storage tank 4 is extracted by the transfer pump 6 and sent into the return pipeline to realize the recycling of mud; The particle size distribution of solid particles in the drilling mud is wide, ranging from large rock cuttings of several millimeters to fine and inferior solid phases of several micrometers, which cannot be addressed by a single treatment method. This method effectively removes solid particles across the entire particle size range. It employs a three-stage gradient purification process: pre-sedimentation in the containment tank 1 (removing large particles >0.5mm), settling in the treatment chamber 2 (removing medium particles 0.1~0.5mm), and centrifugal separation in the hydrocyclone 3 (removing fine particles 0.02~0.1mm). This achieves graded removal of solid phases of different particle sizes. Compared to a single sedimentation tank, this method avoids overloading a single treatment unit and improves purification efficiency. Through the pre-sedimentation in steps S1 and S2, large rock fragments are separated before entering the hydrocyclone 3. The process involves pre-removal of large particles, ensuring that the hydrocyclone 3 only processes medium and fine particles from the slurry. This protects the wear-resistant lining of the hydrocyclone 3 from impact and wear by large particles and prevents coarse particles from clogging the bottom outlet of the hydrocyclone 3. Traditional drilling mud is discarded and discharged due to its high solid content after discharge. This method removes solid particles from the mud through three-stage purification. Step S4 sends the purified mud directly back into the well for recycling, reducing the amount of fresh mud preparation and the amount of waste mud discharged, thereby reducing the ecological impact of drilling operations on soil and vegetation.

[0041] Furthermore, in step S2, a neutralizing agent or flocculant is added to the processing chamber 2 through the feeding chamber 7.

[0042] The feeding chamber 7 is a reagent storage and dosing unit, located on the side of the treatment chamber 2. The feeding chamber 7 contains a flocculant chamber and a neutralizing agent chamber. The flocculant chamber stores flocculant, and the neutralizing agent chamber stores neutralizing agents (such as lime slurry for adjusting acidic slurry and dilute sulfuric acid for adjusting alkaline slurry). The flocculant chamber and neutralizing agent chamber are connected to the treatment chamber 2 via feeding pipes 71, which are equipped with feeding valves (electric regulating valves). In step S2, when sedimentation occurs in the treatment chamber 2, the feeding chamber 7 adds neutralizing agent or flocculant to the treatment chamber 2. The controller controls the reagent addition based on real-time detection data from the temperature sensor (resistive temperature sensor), concentration sensor (ultrasonic concentration meter), and pH sensor within the treatment chamber 2. For example, at high temperatures, the flocculant dosage needs to be increased, and at low temperatures, the dosage needs to be decreased. The concentration is used to determine the required amount of flocculant (the higher the concentration, the more flocculant is needed); the pH value is used to determine the required amount of neutralizing agent. The amount of neutralizing agent required varies (the further the pH deviates from neutral). The sedimentation in treatment chamber 2 mainly relies on natural gravity settling. However, for fine suspended particles, the settling speed is slow, and gravity settling alone is insufficient to effectively remove them within a limited time. The addition of flocculant causes fine particles to aggregate into larger flocs, accelerating their settling speed. The addition of neutralizing agent adjusts the pH of the mud to a suitable range (neutral or weakly alkaline), protecting the drill bit from corrosion and creating the best flocculation environment for the flocculant (most flocculants have the best flocculation effect under neutral or weakly alkaline conditions). In addition, flocculants and neutralizing agents (especially lime milk and acids) have certain irritant and harmful effects on human skin and respiratory system. The automatic dosing system eliminates the need for operators to directly contact these chemicals, avoiding the harm to human health. At the same time, the sealed feeding chamber 7 and feeding pipeline 71 also reduce dust and odor diffusion, improving the on-site working environment.

[0043] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this application, and are not intended to limit them. Although this application has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features therein. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of this application.

Claims

1. A geological exploration mud circulation and purification device, characterized in that, It includes a containment pool (1), a processing chamber (2), a hydrocyclone (3), a storage tank (4), a sensor group, and a controller; The containment tank (1) is connected to the treatment chamber (2) through a first pipeline (11). A first pump body (12) is installed on the first pipeline (11). The inlet of the first pipeline (11) is located at the upper part of the containment tank (1). The first pump body (12) is used to pump the mud into the treatment chamber (2) for sedimentation treatment. The processing chamber (2) is connected to the hydrocyclone (3) through a second pipeline (21). A second pump body (22) is installed on the second pipeline (21). The inlet of the second pipeline (21) is located at the upper part of the processing chamber (2). The second pump body (22) is used to pump the slurry at the upper part of the processing chamber (2) into the hydrocyclone (3). The hydrocyclone (3) includes a conical cyclone cavity (31), and the side wall of the cyclone cavity (31) is provided with a slurry inlet (32) arranged along the tangential direction of its outer wall. The slurry outlet (33) of the cyclone cavity (31) is located at its upper part and is connected to the storage tank (4) through a third pipeline (5). The storage tank (4) is connected to a delivery pump (6), and the delivery pump (6) is used to extract the purified slurry in the storage tank (4) and send it into the return pipeline. The sensor group includes a first liquid level sensor disposed in the containment pool (1), a second liquid level sensor disposed in the processing chamber (2), and a third liquid level sensor disposed in the storage tank (4). The controller is electrically connected to the sensor group, the first pump body, the second pump body and the delivery pump (6).

2. The geological exploration mud circulation and purification device according to claim 1, characterized in that, The sensor group also includes a temperature sensor, a concentration sensor and a pH sensor installed in the processing chamber (2). A feeding chamber (7) is provided on the side of the processing chamber (2). The feeding chamber (7) is connected to the processing chamber (2) through a feeding pipeline (71). A feeding valve is provided on the feeding pipeline (71). The controller is electrically connected to the temperature sensor, the concentration sensor and the pH sensor and the feeding valve respectively, and is used to control the addition of neutralizing reagent or flocculant in the feeding chamber according to the temperature, slurry concentration and pH value in the processing chamber.

3. The geological exploration mud circulation and purification device according to claim 1, characterized in that, The inner wall of the swirling cavity (31) is provided with a wear-resistant lining.

4. The geological exploration mud circulation and purification device according to claim 1, characterized in that, The storage tank (4) is equipped with a stirrer.

5. The geological exploration mud circulation and purification device according to claim 1, characterized in that, The outer wall of the swirling cavity (31) is provided with a support (8).

6. The geological exploration mud circulation and purification device according to claim 1, characterized in that, The bottom of the processing chamber (2) and the swirling chamber (31) are respectively equipped with slag discharge valves.

7. The geological exploration mud circulation and purification device according to claim 6, characterized in that, The slag discharge valves at the bottom of the processing chamber (2) and the swirling chamber (31) are electric slag discharge valves.

8. The geological exploration mud circulation and purification device according to any one of claims 1-7, characterized in that, The controller is a PLC controller, which is electrically connected to the sensor group, the first pump body (12), the second pump body (22) and the delivery pump (6) respectively, and is used to control the operation of the device.

9. A method for purifying sludge through circulation, characterized in that, The geological exploration mud circulation and purification device according to any one of claims 1-8 includes the following steps: S1: Inject the slurry to be purified returned during the drilling process into the containment tank (1); S2: The slurry in the container pool is pumped into the treatment chamber (2) through the first pump body (12) on the first pipeline (11) for static sedimentation to separate rock fragments; S3: Pump the slurry in the processing chamber (2) into the cyclone chamber (31) to separate the medium and fine particle impurities in the mud, and pump the separated slurry into the storage tank (4) through the third pump body (51) on the third pipeline (5); S4: The purified mud in the storage tank (4) is pumped out by the transfer pump (6) and sent into the return pipeline to realize the recycling of mud.

10. The mud circulation and purification method according to claim 9, characterized in that, In step S2, a neutralizing agent or flocculant is added to the treatment chamber (2) through the feeding chamber (7).