A method, device and medium for scheduling high-energy-consuming loads based on demand response
By generating a load scheduling baseline chain and a dual-track synchronous simulation trajectory, the problem of unstable process buffer margin in multi-process continuous coupling scenarios was solved, realizing the reliability of high-energy-consuming load scheduling and process continuity, and ensuring the closure of demand response gaps.
Patent Information
- Application Number
- CN202611612905.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-19
- Publication Date
- 2026-11-17
AI Technical Summary
Existing demand response scheduling methods struggle to maintain the continuity of process buffer margins and close demand response gaps in scenarios with continuous coupling of multiple processes, leading to an imbalance in process support.
By collecting load process data, performing identity association and time sequence alignment, a load scheduling benchmark chain is generated. The current power is compared with the target power to generate candidate adjustment sequences. The influence propagation state is deduced along the process buffer relationship to form a dual-track synchronous deduction trajectory. Buffer occupation overlap and cross-load acceptance replacement are implemented to generate a high-energy-consuming load scheduling scheme.
This achieves stability of process buffer margin and reliability of scheduling execution during demand response, improves scheduling executability and process continuity, and ensures the closure of demand response gaps.
Smart Images

Figure CN123117730A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of industrial load dispatching technology, and in particular to a method, equipment and medium for dispatching high-energy-consuming loads based on demand response. Background Technology
[0002] With the development of digital monitoring of industrial energy consumption, time-of-use pricing, and electricity demand-side management, demand response methods for continuous production scenarios such as steel, chemical, electrolysis, and building materials are gradually shifting from manual power rationing to automatic scheduling based on load process data. Existing methods typically collect real-time power, production plans, load operating status, and response targets issued by the power grid for high-energy-consuming loads. They determine the reduction targets according to load priority, interruptible capacity, adjustment rate, and preset safety boundaries, and then issue target power curves through centralized control to enable participating loads to complete power adjustment within the specified response period, while taking into account basic production continuity and energy cost control.
[0003] Existing demand response scheduling typically relies on the adjustable power of individual high-energy-consuming loads and local operational constraints, failing to adequately consider the process continuity relationships between loads caused by material supply, process waiting, and buffer inventory. In scenarios where multiple processes are continuously coupled and the response gap needs to be shared by multiple loads, even if the adjustment content meets the power reduction requirements, imbalances may occur due to changes in the buffer margins of preceding and following processes. This is because existing processing methods mostly employ static capacity allocation or single-step power verification, failing to synchronously extrapolate from the common operating starting point to maintain the existing power consumption patterns and the propagation of process impacts after executing candidate adjustment content. Consequently, it is difficult to maintain a sustainable process buffer margin while closing the demand response gap. Summary of the Invention
[0004] In view of the aforementioned existing problems, the present invention is proposed.
[0005] Therefore, this invention provides a demand response-based high-energy-consuming load scheduling method that solves the problems of demand response gap closure and process buffer imbalance.
[0006] To solve the above-mentioned technical problems, the present invention provides the following technical solution: In a first aspect, the present invention provides a high-energy-consuming load scheduling method based on demand response, comprising: collecting load process data; performing identity association and time sequence alignment on the load process data; obtaining a load scheduling benchmark chain; comparing the current power of each high-energy-consuming load in the load scheduling benchmark chain with the corresponding demand response target power to form a power to be adjusted; placing the power to be adjusted into high-energy-consuming loads that meet the acceptance conditions; and deducing the impact propagation state after the power to be adjusted is accepted along the process buffer relationship to generate a candidate adjustment sequence; using the current power state and process buffer state in the candidate adjustment sequence as a common starting point to perform dual-track synchronous deduction to obtain the dual-track process evolution trajectory, and Along the process buffer relationship, the evolution trajectory of the dual-track process is subjected to buffer occupation overlap and cross-load acceptance replacement to form a buffer occupation migration relationship. The buffer occupation migration relationship is embedded into the subsequent acceptable buffer position and the continuous influence range is closed, generating paired trajectory deduction records. The target power trajectory is issued according to the load scheduling execution sequence. The actual power change and process buffer change after the execution of each high energy-consuming load are collected. The actual power change and process buffer change are compared with the target power trajectory to obtain the scheduling execution deviation record. The unfinished adjustment amount is supplemented and allocated according to the scheduling execution deviation record, and the actual acceptance change is backfilled into the load scheduling benchmark chain to generate a high energy-consuming load scheduling scheme.
[0007] As a preferred embodiment of the demand-response-based high-energy-consuming load scheduling method of the present invention, the specific steps for performing identity association and time-series alignment on load process data to obtain the load scheduling baseline chain are as follows: Load process data are merged according to the relationship between load objects and production process locations, and the operation information and process information corresponding to the same high energy-consuming load are bound together to generate load identity association records. Correct the time offset between different acquisition locations in the load identity association record, and match the operation information of the same high-energy-consuming load with the process information in the same operating period to generate a load scheduling baseline chain.
[0008] As a preferred embodiment of the demand response-based high-energy-consuming load scheduling method of the present invention, the current power of each high-energy-consuming load in the comparison load scheduling benchmark chain is compared with the corresponding demand response target power to form the power to be adjusted. The power to be adjusted is then placed into high-energy-consuming loads that meet the acceptance conditions, and the influence propagation state after the power to be adjusted is deduced along the process buffer relationship to generate a candidate adjustment sequence. The specific steps are as follows: Based on the load dispatching benchmark chain, compare the current power of each high-energy-consuming load with the corresponding demand response target power during the demand response period, and register the adjustment amount with the corresponding high-energy-consuming load and demand response period to generate the power to be adjusted. Each power to be adjusted is placed into the corresponding high energy-consuming load. The power position after placement is checked to see if it is within the allowable operating range. The actual acceptance conditions of each high energy-consuming load for the power to be adjusted are verified in combination with the power change process and stable operating status. The high energy-consuming loads that meet the acceptance conditions are bound to the corresponding power to be adjusted to generate a list of accepting loads. Starting from the production process location corresponding to the power to be adjusted based on the load list, the changes in material buffer occupation and process waiting status caused by the power to be adjusted are deduced step by step according to the process acceptance sequence. The remaining buffer space and allowable acceptance time of each process location in the process of influence propagation are checked, the influence propagation range and process acceptance status corresponding to the power to be adjusted are recorded, and an adjustment propagation verification form is generated. Remove the power to be adjusted from the adjustment propagation verification table that causes insufficient material buffer and excessive process waiting time. Combine the remaining power to be adjusted according to the degree of closure of the demand response target power. Arrange the adjustment contents that meet the demand response requirements according to the process buffer margin retained by each combination and the corresponding execution sequence to generate a candidate adjustment sequence.
[0009] As a preferred embodiment of the demand-response-based high-energy-consuming load scheduling method of the present invention, the step of performing dual-track synchronous deduction using the current power state and process buffer state in the candidate adjustment sequence as a common starting point to obtain the dual-track process evolution trajectory is as follows: Based on the execution start time corresponding to each candidate adjustment content in the candidate adjustment sequence, the current power status, process buffer status, material flow status and process acceptance sequence of the corresponding high energy-consuming load are extracted from the load scheduling benchmark chain. The current power status and process buffer status corresponding to the same execution start time are respectively placed into two deduction paths to generate a dual-track common starting point record. Based on the common starting point record of the two tracks, corresponding continuous simulation positions are set according to the process acceptance sequence and time sequence. The existing power consumption mode is continuously extended in one simulation path, and candidate adjustment content is placed in the corresponding simulation position of the other simulation path. The high energy-consuming load, process position and time position in the two simulation paths are bound position by position to generate a dual-track synchronous advancement sequence. According to the dual-track synchronous advancement sequence, the two simulation paths are advanced position by position according to the succession relationship of material entry, material exit and process buffer occupation, and the process state formed at each simulation position is continued to be carried over to the next simulation position, generating a dual-track state advancement record. Based on the dual-track state advancement record, the power state, material flow state, buffer occupation state, and process waiting state formed continuously in the two simulation paths according to the same high energy consumption load, the same process position, and the same time position are connected to obtain the dual-track process evolution trajectory.
[0010] As a preferred embodiment of the demand-response-based high-energy-consuming load scheduling method of the present invention, the method of implementing buffer occupation overlap and cross-load acceptance replacement on the dual-track process evolution trajectory along the process buffer relationship to form a buffer occupation migration relationship, embedding the buffer occupation migration relationship into the subsequent acceptable buffer position and closing the continuous influence range, and generating paired trajectory deduction records, the specific steps are as follows: Based on the dual-track process evolution trajectory, the buffer occupancy status corresponding to the same process position and the same time position is mapped to the same process buffer capacity range. Two buffer occupancy ranges are superimposed according to the capacity position, and common buffer occupancy, newly added buffer occupancy and available buffer position are distinguished to generate buffer occupancy overlap record. Based on the buffer space overlap record, the newly added buffer space is placed into the subsequent acceptable buffer position in sequence. When the current acceptable buffer position is insufficient to accept the newly added buffer space, the already accepted part is retained in the current process position, and the remaining buffer space is placed into the next process position to generate a buffer space acceptance record. According to the buffer occupancy acceptance record, the remaining buffer occupancy that crosses different high-energy-consuming load process positions will have its previous occupancy assignment removed and will be reassigned to the subsequent acceptable buffer positions. The newly added buffer occupancy, cross-load replacement positions and subsequent acceptable positions will be connected according to the order of acceptance to form a buffer occupancy migration relationship. Based on the buffer occupant migration relationship, the continuously migrating buffer occupants are sequentially embedded into the subsequent acceptable buffer positions. With each embedding, the subsequent acceptable buffer positions are updated. When all newly added buffer occupants are continuously accepted, the continuous influence range between the starting position and the final accepting position of the newly added buffer occupant is closed. The dual-track process evolution trajectory and the buffer occupant migration relationship are associated to generate paired trajectory deduction records.
[0011] As a preferred embodiment of the demand response-based high-energy-consuming load scheduling method of the present invention, the specific steps of selecting adjustment content that can close the demand response gap and retain process buffer margin from paired trajectory extrapolation records, combining the adjustment content with the on-site executable capability, and redistributing the unclosed adjustment amount to generate a load scheduling execution sequence are as follows: Summarize the power adjustment amount corresponding to each candidate adjustment content based on the paired trajectory simulation records, and verify the material buffer changes, process waiting changes and process acceptance changes in the candidate adjustment operation trajectory. Screen out the candidate adjustment content that cannot retain the process buffer margin after execution, and generate a closed adjustment list. Based on the closed-loop control list, check the remaining execution time before the field execution constraints of the high-energy-consuming load corresponding to each control content, arrange the control content that meets the field execution conditions, and generate the field execution verification table; According to the on-site execution verification form, the planned adjustment amount of each adjustment content is limited to the current executable adjustment range of the corresponding high energy-consuming load, and converted into an execution adjustment amount that can be issued on-site according to the minimum execution step size. The execution adjustment amount is used to deduct the demand response gap in sequence and the adjustment amount that has not yet been closed after deduction is registered to generate an unclosed adjustment amount record. Based on the unclosed regulation records, high-energy-consuming loads with remaining executable adjustment space and process buffer margins are selected from the field execution verification table. The unclosed regulation quantities are then assigned in sequence according to the order of action response and the size of the process buffer margin. The initially assigned execution regulation quantities and the reassigned execution regulation quantities are then jointly arranged according to the execution start time and process acceptance order to generate a load scheduling execution sequence.
[0012] As a preferred embodiment of the demand-response-based high-energy-consuming load scheduling method of the present invention, the steps of issuing the target power trajectory according to the load scheduling execution sequence, collecting the actual power changes and process buffer changes after the execution of each high-energy-consuming load, and comparing the actual power changes and process buffer changes with the target power trajectory to obtain the scheduling execution deviation record are as follows: According to the load scheduling execution sequence, the execution adjustment amount of each high energy-consuming load is converted into a continuous target power trajectory according to the execution start time and process acceptance order. The target power trajectory is then issued sequentially and the corresponding high energy-consuming load, process location, issuance time and execution confirmation status are registered to generate a target power issuance record. Based on the target power distribution record, starting from the moment the target power trajectory is distributed, the actual power change, actual material buffer change, actual process waiting change, and actual process acceptance change of each high-energy-consuming load after execution are collected, and corresponding records are generated to form an execution status record. Based on the execution status record, the target power trajectory is compared with the actual power change at each time step, and the expected process buffer change corresponding to the target power trajectory is checked against the actual process buffer change. The scheduling execution deviation is recorded and a scheduling execution deviation record is generated.
[0013] As a preferred embodiment of the demand-response-based high-energy-consuming load scheduling method of the present invention, the specific steps of supplementing and allocating uncompleted adjustment amounts according to scheduling execution deviation records and backfilling actual load changes into the load scheduling baseline chain to generate a high-energy-consuming load scheduling scheme are as follows: Based on the scheduling execution deviation record, summarize the unfinished adjustment amount within the same demand response period, and select high-energy-consuming loads that still have remaining executable adjustment space from the on-site execution verification table and whose actual process buffer margin can continue to accommodate power changes. Then, allocate the unfinished adjustment amount to the selected high-energy-consuming loads in sequence to generate a supplementary adjustment allocation record. Based on the supplementary adjustment allocation record, each supplementary adjustment quantity is converted into a supplementary target power trajectory and issued sequentially according to the start time of supplementary execution. The actual power change and actual process buffer change after supplementary execution are collected, and the completion status of the supplementary adjustment quantity is verified to generate a supplementary execution verification record. Based on the supplementary execution verification record, the actual changes received corresponding to the initial execution and supplementary execution are backfilled into the load dispatching baseline chain to generate the load dispatching update baseline chain; Based on the load scheduling update benchmark chain, the target power distribution record, scheduling execution deviation record, supplementary adjustment allocation record, and supplementary execution verification record are correlated according to the demand response period. The target power trajectory, actual completed adjustment amount, actual process buffer margin, and updated scheduling starting point of each high energy-consuming load are registered to generate a high energy-consuming load scheduling scheme.
[0014] In a second aspect, the present invention provides a computer device including a memory and a processor, wherein the memory stores a computer program, wherein when the computer program is executed by the processor, it implements any step of the demand-response-based high-energy-consuming load scheduling method described in the first aspect of the present invention.
[0015] Thirdly, the present invention provides a computer-readable storage medium having a computer program stored thereon, wherein: when the computer program is executed by a processor, it implements any step of the demand-response-based high-energy-consuming load scheduling method as described in the first aspect of the present invention.
[0016] The beneficial effects of this invention are as follows: by taking the current power state and process buffer state in the candidate adjustment sequence as a common starting point, the operating trajectory of the existing power consumption mode and the candidate adjustment content are deduced respectively, and the power change, buffer consumption and process influence propagation in the two trajectories are checked. This enables the simultaneous determination of the candidate adjustment content's ability to close the demand response gap and the stability of process acceptance, which is used to screen out adjustment content with buffer overdraft and influence diffusion, and retain adjustment paths with continuous acceptance conditions, thereby improving scheduling executability, process continuity and demand response closure reliability. Attached Figure Description
[0017] To more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the following description of the embodiments will be briefly introduced. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0018] Figure 1 This is a flowchart of a demand-response-based high-energy-consuming load scheduling method.
[0019] Figure 2A flowchart for generating candidate regulatory sequences.
[0020] Figure 3 This is a flowchart for paired trajectory extrapolation and load scheduling execution.
[0021] Figure 4 The flowchart is generated for scheduling execution deviation correction and high-energy-consuming load scheduling scheme. Detailed Implementation
[0022] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
[0023] Many specific details are set forth in the following description in order to provide a full understanding of the invention. However, the invention may also be practiced in other ways different from those described herein, and those skilled in the art can make similar extensions without departing from the spirit of the invention. Therefore, the invention is not limited to the specific embodiments disclosed below.
[0024] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The phrase "in one embodiment" appearing in different places in this specification does not necessarily refer to the same embodiment, nor is it a single or selective embodiment that is mutually exclusive with other embodiments.
[0025] Reference Figures 1-4 As one embodiment of the present invention, this embodiment provides a high-energy-consuming load scheduling method based on demand response, including the following steps: S1. Collect load process data, perform identity association and time sequence alignment on the load process data, obtain the load scheduling benchmark chain, compare the current power of each high energy-consuming load in the load scheduling benchmark chain with the corresponding demand response target power to form the power to be adjusted, put the power to be adjusted into the high energy-consuming loads that meet the acceptance conditions, and deduce the impact propagation state after the power to be adjusted is accepted along the process buffer relationship to generate candidate adjustment sequences.
[0026] It should be noted that when collecting load process data, the following information is continuously obtained from the power metering location, production process location, and material buffer recording location of each high-energy-consuming load: load object identifier, production process location identifier, collection location identifier, recording time, current power, target power for demand response, allowable operating range, power change process, stable operating status, operating speed, material input, material output, process buffer status, process waiting status, process acceptance status, remaining buffer space, and allowable acceptance duration. The correspondence between load objects and production process locations is recorded according to a unified collection cycle to form load process data.
[0027] The influence propagation state refers to the continuous changes in operating speed, material buffer occupancy, process waiting state, remaining buffer space, and process acceptance state caused by the placement of the power to be adjusted into the corresponding high-energy-consuming load along the production process acceptance sequence. It is used to characterize the production process location, propagation range, and acceptance boundary through which the power adjustment influence passes, providing a basis for screening out the power to be adjusted that causes insufficient buffer, excessive waiting, and interruption of process acceptance, thereby improving the executability and process continuity of the candidate adjustment sequence.
[0028] S1.1 Merge load process data according to the relationship between load objects and production process locations, and bind the operation information and process information corresponding to the same high energy-consuming load to generate load identity association records.
[0029] It should be noted that the load process data should be checked one by one according to the load object identifier, production process location identifier, data collection location identifier and recording time. Based on the pre-registered relationship between the load object and the production process location, the production process location corresponding to each load object should be found, and the load process data with the same relationship should be arranged to the location corresponding to the same high energy-consuming load.
[0030] For load process data with missing attribution relationships, the attribution location is determined according to the fixed correspondence between the collection location and the production process location. For load process data corresponding to multiple production process locations for the same load object, the actual attribution location is verified item by item according to the production process take-off order, the corresponding collection location, and the overlap of recording time periods. For load process data corresponding to multiple load objects for the same production process location, the corresponding load object is determined according to the consistency between the load object's running time and the production process location's operating time. Based on the verified attribution relationships, the operation information and process information corresponding to the same high-energy-consuming load are written into a unified load identity identifier. The operation information, process information, production process location, collection location, and recording time are bound one by one according to the unified load identity identifier. Then, the attribution relationship between the load object and the production process location, the identity binding relationship between the operation information and the process information, and the attribution relationship verification status are continuously registered to generate a load identity association record.
[0031] S1.2 Correct the time offset between different acquisition locations in the load identity association record, and match the operation information of the same high-energy-consuming load with the process information in the same operating period to generate a load scheduling baseline chain.
[0032] It should be noted that, according to the unified load identity identifier, collection location identifier and recording time in the load identity association record, the operation information and process information corresponding to the same high energy-consuming load are arranged. The load start-up, load stop, power change and process state switching times recorded by different collection locations are selected as time correction references. The recording times corresponding to the same time correction reference are compared to determine the advance and lag time of each collection location relative to the unified time reference, and the recording time is corrected accordingly.
[0033] The same high-energy-consuming load is divided into operating segments according to the corrected recording time. The operating information with the same recording time within the same operating segment is directly matched with the process information. The operating information with different collection intervals is matched with the process information according to the most recent time and the continuity of the previous and subsequent states. Finally, the operating information and process information corresponding to the time are arranged in sequence according to the unified load identity, production process location and corrected recording time to generate the load scheduling baseline chain.
[0034] It should also be noted that the load dispatching baseline chain is a time-series relationship chain formed by associating the operating information of each high-energy-consuming load with the process information of the corresponding production process location according to a unified load identity and continuous operating time. It is used to clarify the power status, process status and successive relationships of each high-energy-consuming load in different operating periods, and to provide a unified starting point for comparing the target power of demand response, determining the power to be adjusted and extrapolating the process impact, thereby improving the accuracy of load adjustment positioning and the continuity of the subsequent dispatching process.
[0035] S1.3. Based on the load dispatching benchmark chain, compare the current power of each high-energy-consuming load with the corresponding demand response target power during the demand response period, and register the adjustment amount with the corresponding high-energy-consuming load and demand response period to generate the power to be adjusted.
[0036] It should be noted that, based on the load dispatching baseline chain, the demand response period is located according to the unified load identification and the corrected recording time. The current power of each high-energy-consuming load at the start of the demand response period is extracted, and the target power of the demand response is retrieved according to the correspondence between the high-energy-consuming load and the demand response task.
[0037] Calculate the power difference between the current power and the target power of the demand response. When the current power is higher than the target power of the demand response, register the power difference as the adjustment amount that needs to be reduced. When the current power is lower than the target power of the demand response, register the power difference as the adjustment amount that needs to be increased. When the current power is equal to the target power of the demand response, register the adjustment amount as zero. According to the unified load identification, write the adjustment amount, adjustment direction, current power, target power of the demand response, demand response period and production process location into the same corresponding position, and arrange them continuously in the order of the demand response period to generate the power to be adjusted.
[0038] The expression for calculating the power difference between the current power and the target power of the demand response is: ; in, For the first The first high-energy-consuming load during the demand response period The power difference at each recording moment; For the first The high-energy-consuming load is in the first The power difference at each recording moment; For the first The high-energy-consuming load is in the first The target power of the demand response at each recorded moment; Number the high-energy-consuming loads; This refers to the recorded time within the demand response period.
[0039] S1.4. Place each power to be adjusted into its corresponding high energy-consuming load, check whether the power position after placement is within the allowable operating range, and verify the actual acceptance conditions of each high energy-consuming load for the power to be adjusted in combination with the power change process and stable operating status. Bind the high energy-consuming load that meets the acceptance conditions to the corresponding power to be adjusted, and generate a list of accepted loads.
[0040] It should be noted that, based on the high energy-consuming loads, adjustment directions, and adjustment amounts registered in the power to be adjusted, the current power of the corresponding high energy-consuming load in the load scheduling reference chain is located, and the adjustment amount is placed into the current power according to the adjustment direction to determine the power position after placement.
[0041] The installed power positions are compared item by item with the upper and lower boundaries of the allowable operating range of the corresponding high-energy-consuming loads. Power to be adjusted that exceeds the allowable operating range is screened out. For power to be adjusted that is within the allowable operating range, the power change process is tracked according to the order of the adjustment amount being installed. It is verified whether each power position is continuously within the allowable operating range during the power change process. Then, the operating status and stable operating status after the power change process ends are continuously verified to determine whether the high-energy-consuming load can maintain the installed power position during the demand response period. High-energy-consuming loads whose power change process meets the allowable operating requirements and can maintain stable operation are identified as high-energy-consuming loads that meet the actual acceptance conditions. High-energy-consuming loads that meet the actual acceptance conditions are bound to the corresponding power to be adjusted to generate a list of accepted loads.
[0042] It should also be noted that the permissible operating range is set based on the rated power of the high-energy-consuming load, the permissible power of the production process, continuous stable operation records, and safety margin. For example, if the rated power of the high-energy-consuming load is 1000 kW, the permissible power of the production process is 600 kW to 900 kW, and a safety margin of 50 kW is reserved on both the minimum and maximum power sides, then 650 kW is determined as the lower boundary of the permissible operating range, and 850 kW is determined as the upper boundary of the permissible operating range. At the same time, power ranges that have caused shutdowns, overloads, process interruptions, and insufficient buffering are eliminated, and finally, 650 kW to 850 kW is set as the permissible operating range.
[0043] The load list includes high-energy-consuming loads that meet the actual load acceptance conditions, the corresponding power to be adjusted, the adjustment direction, the adjustment amount, the power position after placement, the allowable operating range, the power change process, the stable operating status, and the power acceptance binding relationship.
[0044] S1.5. Based on the load acceptance list, starting from the production process position corresponding to the power to be adjusted, the changes in material buffer occupation and process waiting status caused by the power to be adjusted are deduced step by step according to the process acceptance sequence. The remaining buffer space and allowable acceptance time of each process position in the process of influence propagation are checked, the influence propagation range and process acceptance status corresponding to the power to be adjusted are recorded, and an adjustment propagation verification form is generated.
[0045] It should be noted that, based on the load list, the production process location corresponding to the power to be adjusted is located according to the correspondence between high energy-consuming loads and production process locations, and the power to be adjusted is set into the current operating time of the production process location. The operating speed of the production process location is adjusted according to the direction of power change.
[0046] Based on the adjusted operating speed, material input, material output, and duration, calculate the material buffer occupancy and process waiting time. Record the increase caused by the material input exceeding the material output as material buffer occupancy, and transfer the decrease caused by the material output exceeding the material input to the next production process position. Material changes are introduced step by step according to the process acceptance sequence. The material buffer occupancy is compared with the remaining buffer space, and the process waiting time is compared with the allowable acceptance time. This process continues until the material change is fully accepted. When the remaining buffer space is insufficient or the allowable acceptance time is exceeded, the impact propagation is terminated. Record the production process position through which the power to be adjusted passes, the propagation termination position, the remaining buffer space, the acceptance time, and the process acceptance status, and generate an adjustment propagation verification table.
[0047] The expression for calculating material buffer occupancy and process waiting time is: ; in, For the first The production process location is at the [number]th [location]. Material buffer occupancy formed during the simulation period; The amount of material entering per unit time is determined based on the adjusted operating speed; The amount of material output per unit time is determined based on the adjusted operating speed; For the first The duration of each simulation period; For the first The production process location is at the [number]th [location]. The process waiting time formed within each simulation period; For the first The production process location is at the [number]th [location]. The available material buffer amount that can be used to maintain material output at the start of each simulation period; Numbering the location of the production process; The time period is numbered for the simulation.
[0048] S1.6. Remove the power to be adjusted from the adjustment propagation verification table that causes insufficient material buffer and excessive process waiting time. Combine the remaining power to be adjusted according to the degree of closure of the target power of demand response. Arrange the adjustment contents that meet the demand response requirements according to the process buffer margin retained by each combination and the corresponding execution time sequence to generate a candidate adjustment sequence.
[0049] It should be noted that, according to the adjustment propagation verification form, the remaining buffer space, process waiting time and process acceptance status of each production process location are checked item by item according to the high energy-consuming load and demand response period corresponding to the power to be adjusted. Powers to be adjusted that have insufficient remaining buffer space or process waiting time exceeding the allowable acceptance time are screened out, and the remaining power to be adjusted is arranged according to the adjustment direction and demand response period.
[0050] One or more adjustment quantities are selected sequentially from the arranged power to be adjusted and accumulated. The accumulated adjustment quantity is compared with the demand response gap corresponding to the target power of the demand response. The closed combination of adjustment quantities that can completely close the demand response gap and whose deviation is within the allowable range after closure is retained. For each closed combination of adjustment quantities, the process buffer margin of the corresponding production process position after the end of the influence propagation and the execution start time of each high energy-consuming load are extracted. First, they are arranged in descending order of process buffer margin, and then in ascending order of execution start time. The high energy-consuming load, the power to be adjusted, the closed combination of adjustment quantity, the process buffer margin and the corresponding execution time sequence are continuously registered to generate a candidate adjustment sequence.
[0051] It should also be noted that the candidate adjustment sequence is a set of adjustments that can close the demand response gap, meet the process acceptance requirements, and retain the process buffer margin. These adjustments are arranged according to high energy-consuming load, power to be adjusted, process buffer margin, and execution sequence. This set is used to provide comparable execution schemes for subsequent dual-track operation simulation and adjustment content selection, thereby reducing the adjustment content that does not meet process constraints and improving the executability of demand response adjustments and the stability of process operation.
[0052] S2. Using the current power state and process buffer state in the candidate adjustment sequence as a common starting point, perform dual-track synchronous simulation to obtain the dual-track process evolution trajectory. Then, implement buffer occupation overlap and cross-load acceptance replacement on the dual-track process evolution trajectory along the process buffer relationship to form a buffer occupation migration relationship. Embed the buffer occupation migration relationship into the subsequent acceptable buffer position and close the continuous influence range to generate paired trajectory simulation records.
[0053] S2.1. Based on the candidate adjustment sequence, arrange the candidate adjustment contents in chronological order of execution start time. Using the high-energy-consuming load and production process location corresponding to the candidate adjustment contents as indexes, locate the running position corresponding to the execution start time in the load scheduling baseline chain. Extract the current power status of the high-energy-consuming load from the running position, and extract the process buffer status, material flow status, and process acceptance sequence corresponding to the same execution start time along the production process location correspondence. Check the consistency between the current power status and the process buffer status according to the execution start time, bind the current power status with the process buffer status at the same time, and then associate the material flow status sequentially according to the process acceptance sequence. Corresponding to the production process location, an execution start state correspondence is formed. The execution start time in the execution start state correspondence is used as the common time position of the two deduction paths. The current power state and process buffer state corresponding to the same high energy load are copied to the first deduction position of the two deduction paths respectively. The material flow state and process acceptance sequence are synchronously associated with the first deduction position of the two deduction paths, so that the two deduction paths have consistent high energy load, production process location, execution start time and initial process state. Then, according to the candidate adjustment content, the current power state, process buffer state, material flow state and process acceptance sequence corresponding to the two deduction paths are registered one by one to generate a dual-track common starting point record.
[0054] S2.2. Based on the dual-track common starting point record, arrange the process positions corresponding to each high-energy-consuming load according to the process acceptance sequence, and take the execution start time in the dual-track common starting point record as the first time position. Divide the time positions continuously according to the unified acquisition cycle corresponding to the load process data, and cross-correspond the process positions with the time positions to form continuous simulation positions. In the continuous simulation positions of one simulation path, maintain the existing power consumption mode corresponding to the dual-track common starting point record, and extend it position by position according to the current power status, material flow status, and process buffer status in chronological order, and inherit the status corresponding to the previous continuous simulation position to the next continuous simulation position. In the first continuous simulation of another simulation path... The candidate adjustment content corresponding to the candidate adjustment sequence is placed at the position. The current power state of the corresponding high energy-consuming load is changed according to the adjustment direction and adjustment amount in the candidate adjustment content. Then, the changed current power state is continuously associated with the subsequent process position and the subsequent time position according to the process acceptance sequence. Using the high energy-consuming load, process position and time position as corresponding conditions, the consecutive simulation positions belonging to the same high energy-consuming load, the same process position and the same time position in the two simulation paths are bound one by one, and the bound positions are connected in chronological order. The current power state, process buffer state, material flow state and candidate adjustment content placement position corresponding to the two simulation paths are registered to generate a dual-track synchronous advancement sequence.
[0055] S2.3. Based on the dual-track synchronous advancement sequence, arrange the process positions and time positions corresponding to each high-energy-consuming load according to the two simulation paths. Extract the material inflow and material outflow from the material flow status corresponding to each simulation position, and determine the process buffer occupancy corresponding to the material inflow based on the current process buffer status. When the material inflow is higher than the material outflow, continuously include the material that has not left the current process position in the process buffer occupancy of the current simulation position, and carry over the updated process buffer status to the next time position. When the material outflow is higher than the material inflow, remove the material that has left the current process position according to the process carry-over sequence. The material is transferred to the next process position, and the process buffer state after the material transfer is synchronously taken over to the next time position. The material entry, material exit and process buffer occupation are repeated in chronological order. The material flow state, process buffer state and process waiting state formed in the previous simulation position are used as the starting state for the next simulation position. Then, according to the position binding relationship in the dual-track synchronous advancement sequence, the high energy load, process position, time position, material flow state, process buffer state and process waiting state corresponding to the two simulation paths are continuously registered to generate a dual-track state advancement record.
[0056] S2.4 Based on the dual-track state advancement record, the power state, material flow state, buffer occupancy state and process waiting state in the two simulation paths are matched position by position according to high energy load, process position and time position. The state contents belonging to the same high energy load, the same process position and the same time position are grouped into the same evolution position, and the continuous evolution positions corresponding to the same high energy load are arranged in chronological order.
[0057] Starting from the first evolution position, the continuation of the power state towards the next time position is tracked along two deduction paths. The changes in material entry and exit corresponding to the power state are connected to the next evolution position. Then, the buffer occupancy state is connected according to the successive relationship of the material flow state, and the process waiting state is connected according to the continuous changes of the buffer occupancy state, forming a continuous state change segment corresponding to a single process position. According to the process succession sequence, the material exit state of the previous process position is connected to the material entry state of the next process position, and the continuous state change segments in the two deduction paths are connected along the process position to form two continuous process evolution lines. Then, based on the positional correspondence between high energy load, process position, and time position, the corresponding positions in the two continuous process evolution lines are horizontally associated, and the changes of power state, material flow state, buffer occupancy state, and process waiting state with time position and process position are continuously recorded to obtain the dual-track process evolution trajectory.
[0058] S2.5. Based on the dual-track process evolution trajectory, locate the buffer occupancy status corresponding to the two deduced paths item by item according to high energy load, process location, and time location. Retrieve the process buffer capacity range that the corresponding process location can accommodate materials. Using the starting capacity position of the process buffer capacity range as a common mapping starting point, continuously map the buffer occupancy status in the two deduced paths to the corresponding capacity position within the process buffer capacity range according to the actual occupancy amount, forming two buffer occupancy ranges. Maintaining consistency between the process location and time location, overlay the two buffer occupancy ranges position by position according to their capacity locations, and check the coverage of the two buffer occupancy ranges position by position. When the same capacity location is simultaneously covered by two buffer occupancy ranges... When the corresponding capacity location is registered as a common buffer occupant, and the capacity location is only covered by the deduction path corresponding to the candidate adjustment content, the occupied location that is added relative to the deduction path corresponding to the existing power consumption mode is continuously registered as a new buffer occupant. When there is a location within the process buffer capacity that is not covered by the new buffer occupant and can continue to receive buffer occupancy, it is continuously registered as a buffer location that can be accepted according to the propagation direction of the new buffer occupant along the process acceptance sequence. Then, the common buffer occupants, new buffer occupants and buffer locations corresponding to each process location are connected in chronological order, and associated with the corresponding high energy-consuming load, process location, time location and capacity location to generate a buffer occupant overlap record.
[0059] S2.6 Based on the buffer space overlap record, the newly added buffer space is sequentially placed into the subsequent acceptable buffer position. When the current acceptable buffer position is insufficient to accept the newly added buffer space, the already accepted part is retained in the current process position, and the remaining buffer space is placed into the next process position to generate a buffer space acceptance record.
[0060] It should be noted that, based on the buffer space overlap record, the newly added buffer space and the available buffer position corresponding to each process position are arranged in the order of process acceptance and time sequence. Starting from the starting capacity position corresponding to the newly added buffer space, the newly added buffer space is moved position by position to the available buffer position corresponding to the current process position in the continuous order of capacity position.
[0061] After each capacity location is moved in, the capacity correspondence between the remaining available buffer locations at the current process location and the newly added buffer occupants that have not yet been moved in is checked. If the available buffer locations at the current process location can continuously accommodate new buffer occupants, subsequent new buffer occupants are moved in according to the capacity location order, and the connection between the new buffer occupants and the corresponding available buffer locations at the current process location is recorded. If the available buffer locations at the current process location are insufficient to continuously accommodate new buffer occupants, the new buffer occupants that have already been moved into available buffer locations are retained at the current process location, and the last available capacity location at the current process location is used as the reference. As a dividing point, newly added buffer occupants that have not yet been accepted are arranged in order of their original capacity positions as remaining buffer occupants. The process is then moved to the next process position along the process acceptance sequence. Starting from the first acceptable buffer position corresponding to the next process position, remaining buffer occupants are placed, and the capacity position verification, continuous placement, and remaining buffer occupant transfer operations are repeated until the newly added buffer occupants are accepted along the continuous process positions. Finally, the buffer occupant acceptance record is generated by continuously registering the acceptance sequence of newly added buffer occupants, accepted portions, remaining buffer occupants, current process position, next process position, and corresponding acceptable buffer positions.
[0062] S2.7. Based on the buffer space acceptance record, arrange the newly added buffer space, the accepted portion, the remaining buffer space and the corresponding process position according to the process acceptance order, and check the high energy load attribution when the remaining buffer space extends from the current high energy load process position to the next high energy load process position.
[0063] When a remaining buffer space spans different high-energy-consuming load process locations, the last already-accepted capacity location of the previous high-energy-consuming load process location is used as the cross-load replacement location. The remaining buffer spaces still registered at the previous high-energy-consuming load process location after the cross-load replacement location are removed from their previous assignment, while maintaining the original capacity location order and acceptance sequence of the remaining buffer spaces. Following the process acceptance sequence, available buffer locations in the next high-energy-consuming load process location are retrieved. Starting from the first available buffer location that can continuously accept remaining buffer spaces, the remaining buffer spaces whose previous assignment has been removed are re-associated to subsequent available buffer locations according to capacity location order, forming cross-load re-association content. Then, starting with a newly added buffer space, the already-accepted locations in the previous high-energy-consuming load process location, the cross-load replacement locations, and the subsequent locations in the cross-load re-association content are sequentially connected. The acceptance relationships between each change in space assignment, cross-load replacement location, and subsequent available buffer locations are continuously registered according to time sequence and process acceptance sequence, forming buffer space migration relationships.
[0064] S2.8. Based on the buffer space migration relationship, arrange the continuously migrating buffer spaces, cross-load replacement positions, and subsequent available buffer positions according to the process acceptance sequence and time sequence. Starting from the starting position of the newly added buffer space, embed the continuously migrating buffer spaces position by position into the corresponding subsequent available buffer positions. After each embedding is completed, recheck the remaining capacity positions of the corresponding process positions according to the occupied capacity positions, and update the capacity positions that can still accept buffer spaces as subsequent available buffer positions. Then, use the updated subsequent available buffer positions to accept the next continuously migrating buffer space. When a continuously migrating buffer occupant passes through a cross-load replacement position, it continues to associate the subsequent acceptable buffer position corresponding to the next process position along the process acceptance sequence, while maintaining the original migration sequence of the newly added buffer occupants. When all newly added buffer occupants are continuously accepted, they are connected sequentially according to the starting position of the newly added buffer occupant, the cross-load replacement position, each embedding position and the final acceptance position, closing the continuous influence range between the starting position of the newly added buffer occupant and the final acceptance position. Then, the continuous influence range is associated with the dual-track process evolution trajectory and the buffer occupant migration relationship position by position to generate paired trajectory deduction records.
[0065] S3. Select adjustment contents from the paired trajectory simulation records that can close the demand response gap and retain the process buffer margin. Combine the adjustment contents with the field executable capabilities and redistribute the unclosed adjustment quantities to generate a load scheduling execution sequence.
[0066] S3.1 Summarize the power adjustment amount corresponding to each candidate adjustment content based on the paired trajectory deduction record, and verify the material buffer change, process waiting change and process acceptance change in the candidate adjustment operation trajectory. Screen out the candidate adjustment content that cannot retain the process buffer margin after execution, and generate a closed adjustment list.
[0067] It should be noted that, based on the paired trajectory projection records, the candidate adjustment content, high energy-consuming load, demand response period, and execution start time are classified. The power adjustment amount contained in the same candidate adjustment content is continuously collected, and the collected power adjustment amount is checked against the corresponding demand response gap. Candidate adjustment content that can complete the closure of the demand response gap is retained.
[0068] Extract material buffer changes, process waiting changes, and process acceptance changes from the candidate adjustment trajectory according to the process acceptance sequence. Verify whether there is still available buffer space after the material buffer change ends, whether the process waiting change is within the allowed acceptance time, and whether the process acceptance change is continuous. Screen out candidate adjustment contents that have exhausted available buffer space, exceeded process waiting limits, or had interrupted process acceptance. Arrange the candidate adjustment contents that have completed the demand response gap closure and retained process buffer margin after execution according to the demand response period, execution start time, and process acceptance sequence, and register the corresponding high energy load, power adjustment amount, and process buffer margin to generate a closed adjustment list.
[0069] S3.2 Based on the closed-loop control list, check the remaining execution time before the field execution constraints of the high-energy-consuming load corresponding to each control content, arrange the control contents that meet the field execution conditions, and generate the field execution verification table.
[0070] It should be noted that, based on the closed-loop control list, according to the control content, high-energy-consuming load, demand response period, and execution start time, the start-stop schedule, process switchover time, and continuous operation requirements are retrieved from the production plan record; the maintenance period is retrieved from the maintenance record; the control interval, action response time, current executable control range, and minimum execution step size are retrieved from the control parameter record; and the target power issuance status is retrieved from the operation configuration record. The retrieved content is then correlated with the corresponding high-energy-consuming load to form on-site execution constraints. Starting from the current verification time, and ending at the earliest of the following times—the end time of the demand response period, process switchover time, maintenance start time, and the next start-stop time—the remaining execution time is determined. This remaining execution time is then compared with the power adjustment time, the state stabilization time, and the control completion time. Adjustments that do not meet the on-site execution conditions include insufficient remaining execution time, conflict between the execution process and process switching or maintenance periods, failure to meet the adjustment interval, failure to meet the target power issuance conditions, and inability to complete the adjustment. Adjustments that meet all on-site execution constraints are arranged according to the execution start time, remaining execution time, and process acceptance sequence, and the corresponding high energy-consuming load, power adjustment amount, remaining execution time, on-site execution constraints, and verification status are recorded to generate an on-site execution verification form.
[0071] S3.3. Based on the on-site execution verification form, limit the planned adjustment amount of each adjustment content to the current executable adjustment range of the corresponding high energy-consuming load, and convert it into an executable adjustment amount that can be issued on-site according to the minimum execution step size. Use the executable adjustment amount to deduct the demand response gap in sequence and register the adjustment amount that has not yet been closed after deduction, and generate an unclosed adjustment amount record.
[0072] It should be noted that, based on the on-site execution verification form, the adjustment contents that meet the on-site execution conditions should be arranged according to the demand response period, execution start time, and process acceptance sequence, and the planned adjustment amount, current executable adjustment range, and minimum execution step size should be extracted for each item.
[0073] The planned adjustment amount is checked against the current executable adjustment range. If the planned adjustment amount is within the current executable adjustment range, it is retained. If the planned adjustment amount exceeds the current executable adjustment range, it is adjusted to the corresponding boundary to form a restricted adjustment amount. The number of complete minimum execution steps that the restricted adjustment amount can contain is calculated, and the execution adjustment amount that can be issued on-site is determined based on the number of complete minimum execution steps. The execution adjustment amounts are used to deduct the demand response gap item by item in the order of arrangement. After each execution adjustment amount is completed, the closure status of the demand response gap is checked, and the adjustment amount that has not been closed after deduction is continuously registered with the corresponding demand response period, the allocated high-energy-consuming load, and the remaining executable adjustment space to generate an unclosed adjustment amount record.
[0074] The expression for calculating the complete minimum number of execution steps that the constrained adjustment can contain is: ; in, For the first The high-energy-consuming load is in the first The execution adjustment quantity that can be issued on-site at any given execution moment; This is the limited adjustment amount formed after the current executable adjustment range is restricted; For the first The minimum execution step size for a high-energy-consuming load.
[0075] S3.4. Based on the unclosed regulation records, select high-energy-consuming loads with remaining executable adjustment space and process buffer margin from the field execution verification table, and accept the unclosed regulation in sequence according to the order of action response and the size of process buffer margin. Then, arrange the first-allocated execution regulation and the second-allocated execution regulation together according to the execution start time and process acceptance order to generate a load scheduling execution sequence.
[0076] It should be noted that, based on the records of unclosed regulation quantities, the regulation quantities that have not yet been closed are located according to the demand response period, and the current executable regulation range, the already executed regulation quantities, and the process buffer margin of each high energy-consuming load are checked item by item from the on-site execution verification form. High energy-consuming loads that still have remaining executable regulation space and can continue to accept power changes are retained.
[0077] High-energy-consuming loads are retained in order of action response from earliest to latest. For high-energy-consuming loads with the same action response, they are arranged in order of process buffer margin from largest to smallest. Unclosed adjustment quantities are then placed into the corresponding remaining executable adjustment space to determine the redistributed execution adjustment quantities. The initial allocation execution adjustment quantities and the redistributed execution adjustment quantities are combined to form temporary adjustment content. Using the current power state and process buffer state at the time of redistribution as a common starting point, and following the generation method of the adjustment propagation verification table and paired trajectory deduction records, the material buffer changes, process waiting changes, and process acceptance changes caused by the temporary adjustment content are re-deduced. Redistributed content that cannot retain process buffer margin, exceeds process waiting limits, or has interrupted process acceptance is filtered out. The initial allocation execution adjustment quantities and redistributed execution adjustment quantities that pass the process impact verification are jointly arranged according to the execution start time and process acceptance sequence. The execution adjustment quantity, execution start time, production process location, and process buffer margin are recorded to generate a load scheduling execution sequence.
[0078] It should also be noted that the load scheduling execution sequence is an execution list formed by combining the execution adjustment quantities of the initial allocation and subsequent allocation according to the high energy-consuming load, the execution start time, and the process acceptance sequence. It is used to clarify the adjustment quantity, execution sequence, and process acceptance relationship of each high energy-consuming load during the demand response period, providing a direct basis for target power trajectory conversion and field issuance, thereby improving the integrity of demand response gap closure and the orderliness of load adjustment execution.
[0079] S4. Issue the target power trajectory according to the load scheduling execution sequence, collect the actual power changes and process buffer changes after the execution of each high-energy-consuming load, compare the actual power changes and process buffer changes with the target power trajectory, obtain the scheduling execution deviation record, supplement and allocate the unfinished adjustment amount according to the scheduling execution deviation record, and backfill the actual received changes to the load scheduling baseline chain to generate a high-energy-consuming load scheduling scheme.
[0080] S4.1. Based on the load scheduling execution sequence, convert the execution adjustment amount of each high energy-consuming load into a continuous target power trajectory according to the execution start time and process acceptance order. Issue the target power trajectory in sequence and register the corresponding high energy-consuming load, process location, issuance time and execution confirmation status to generate a target power issuance record.
[0081] It should be noted that, according to the load scheduling execution sequence, the current power, execution adjustment amount, adjustment direction, execution start time, and process acceptance sequence corresponding to each high-energy-consuming load are extracted according to the demand response period. The current power is used as the starting point of the target power trajectory. The execution adjustment amount is gradually written into subsequent time points according to the adjustment direction. The power adjustment stage and the power maintenance stage are connected according to the power change process and stable operation status to form a target power trajectory that is continuous in time and power position. The target power trajectories are arranged from early to late according to the execution start time. Target power trajectories with the same execution start time are arranged according to the process acceptance sequence, and the target power trajectory is sent to the high-energy-consuming load at the corresponding issuance time. The reception and execution status of the target power trajectory are continuously checked. The high-energy-consuming load, process position, target power trajectory, issuance time, and execution confirmation status are registered in the same position. For target power trajectories that have not been confirmed for execution, the issuance position and re-check mark are retained to generate a target power issuance record.
[0082] S4.2 Based on the target power distribution record, starting from the time the target power trajectory is distributed, collect the actual power change, actual material buffer change, actual process waiting change, and actual process acceptance change after the execution of each high-energy-consuming load, and perform corresponding mapping to generate the execution status corresponding record.
[0083] It should be noted that, based on the target power distribution record, the execution tracking starting point is determined according to the high energy-consuming load, process location, distribution time, and execution confirmation status. Starting from the distribution time of the target power trajectory, the actual power changes corresponding to each high energy-consuming load are continuously acquired at a uniform acquisition interval. Simultaneously, the actual material buffer changes, actual process waiting changes, and actual process acceptance changes are acquired along the correspondence between the high energy-consuming load and the process location. Time correction is performed on each change according to the recording time. The actual power changes formed by the same high energy-consuming load within the same execution period are matched with the actual material buffer changes, actual process waiting changes, and actual process acceptance changes formed by the corresponding process location. For changes with interval differences in recording time, the correspondence is completed according to the most recent time and the continuity of the preceding and following states. Then, the corresponding changes are completed by continuously arranging the high energy-consuming load, process location, target power trajectory, and execution period, and the execution start time, change duration, and execution confirmation status are recorded to generate the execution status corresponding record.
[0084] S4.3. Based on the execution status record, compare the target power trajectory with the actual power change at each time step, and verify the expected process buffer change corresponding to the target power trajectory with the actual process buffer change, register the scheduling execution deviation, and generate a scheduling execution deviation record.
[0085] It should be noted that, based on the execution status co-location records, the target power trajectory and actual power changes are arranged according to high energy consumption load, process location, execution period, and recording time. Based on high energy consumption load, execution adjustment amount, execution start time, and process location, candidate adjustment contents corresponding to the target power trajectory are searched from the paired trajectory extrapolation records. The buffer occupancy status changes corresponding to the candidate adjustment contents at the same process location and the same time location are extracted. The buffer occupancy status changes are matched with the execution period of the target power trajectory to form the expected process buffer changes. Then, the expected process buffer changes are matched with the actual process buffer changes in the execution status co-location records according to the same process location and the same recording time.
[0086] Calculate the power deviation of the actual power change relative to the target power trajectory at the same recording time, and the buffer deviation of the actual process buffer change relative to the expected process buffer change. Based on the power deviation, verify the deviation direction, deviation magnitude, occurrence time, and duration. Based on the buffer deviation, verify the advance state, lag state, deviation degree, and continuity. Correlate the actual power deviation state with the actual process buffer deviation state, and register the corresponding high energy-consuming load, process location, deviation time, deviation duration, and uncompleted adjustment amount according to the order of deviation occurrence. Determine the scheduling execution deviation and generate a scheduling execution deviation record.
[0087] The expression for calculating the power deviation of the actual power change relative to the target power trajectory at the same recording time is: ; in, For the first The high-energy-consuming load is in the first Power deviation at each recording moment; For the first The high-energy-consuming load is in the first The actual power at each recorded moment; For the first The high-energy-consuming load is in the first The target power at each recording moment; Number the high-energy-consuming loads; This refers to the execution time within the demand response period.
[0088] S4.4. Based on the scheduling execution deviation record, summarize the uncompleted adjustment amount within the same demand response period, and select high-energy-consuming loads that still have remaining executable adjustment space from the on-site execution verification table and whose actual process buffer margin can continue to accommodate power changes. Then, allocate the uncompleted adjustment amount to the selected high-energy-consuming loads in sequence and generate a supplementary adjustment allocation record.
[0089] It should be noted that, based on the scheduling execution deviation record, the uncompleted adjustment quantities are collected according to the demand response period, high-energy-consuming loads, and deviation persistence. The actual power state and actual process buffer state at the end of the first execution are extracted from the execution status co-location record as the common starting point for supplementary allocation. Based on the on-site execution verification form, the remaining executable adjustment space, remaining execution time, and actual process buffer margin of each high-energy-consuming load are checked item by item. High-energy-consuming loads that cannot complete supplementary execution within the demand response period are screened out. The remaining high-energy-consuming loads are arranged according to the order of action response, the size of the actual process buffer margin, and the process acceptance order. The uncompleted adjustment quantities are then placed into the corresponding remaining executable adjustment space to form temporary supplementary adjustment content. Following the generation method of the adjustment propagation verification form, the changes in material buffer, process waiting, and process acceptance caused by the temporary supplementary adjustment content are deduced. When the temporary supplementary adjustment content involves multiple production process locations, the process impact after maintaining the current power consumption mode and executing the temporary supplementary adjustment content is compared according to the generation method of the paired trajectory deduction record. Temporary supplementary adjustments that cause insufficient process buffer, excessive process waiting time, or interruption of process continuity are screened out. The high energy-consuming load, supplementary adjustment amount, supplementary execution start time, production process location, and actual process buffer margin that have been verified are registered in the same location to generate a supplementary adjustment allocation record.
[0090] S4.5 Based on the supplementary adjustment allocation record, convert each supplementary adjustment quantity into a supplementary target power trajectory and issue it sequentially according to the start time of supplementary execution. Collect the actual power change and actual process buffer change after supplementary execution, verify the completion status of the supplementary adjustment quantity, and generate a supplementary execution verification record.
[0091] It should be noted that, based on the supplementary adjustment allocation record, the supplementary execution content is determined item by item according to the high energy-consuming load, supplementary adjustment amount, supplementary execution start time and production process location. The actual power corresponding to the supplementary execution start time is used as the trajectory starting point. The supplementary adjustment amount is continuously written into subsequent time points according to the supplementary adjustment direction and power change process, and the power adjustment stage and power maintenance stage are connected to form the supplementary target power trajectory.
[0092] The supplementary target power trajectories are arranged from earliest to latest according to the start time of supplementary execution and are sequentially sent to the corresponding high-energy-consuming loads. The time of issuance of the supplementary target power trajectory and the execution confirmation status are recorded. Starting from the time of issuance of the supplementary target power trajectory, the actual power change and actual process buffer change after supplementary execution are continuously acquired at a uniform acquisition interval, and corresponding to the high-energy-consuming load, production process location and recording time. The supplementary target power trajectory and the actual power change are compared moment by moment, and it is verified whether the actual process buffer change retains the process buffer margin. Based on this, the completion status of the supplementary adjustment is determined, and the start time of supplementary execution, supplementary target power trajectory, actual power change, actual process buffer change and completion status are recorded to generate a supplementary execution verification record.
[0093] S4.6. Based on the supplementary execution verification record, backfill the actual changes received corresponding to the initial execution and supplementary execution to the load scheduling baseline chain to generate the load scheduling update baseline chain.
[0094] It should be noted that, based on the supplementary execution verification records, the actual changes received corresponding to the supplementary execution are located according to the demand response period, high energy load, production process location, and recording time, and the actual changes received corresponding to the first execution are extracted from the execution status corresponding records along the same correspondence.
[0095] The actual changes received during the first execution and the actual changes received during the supplementary execution are arranged continuously according to the time of occurrence. The state continuity between adjacent recorded times is checked, and duplicate records, time misalignments, and state disconnections are corrected to form continuous actual changes received. According to the unified load identity and production process location, the continuous actual changes received are written into the corresponding demand response period of the load scheduling baseline chain, replacing the power status and process buffer status registered before execution, and retaining the correspondence between the target power trajectory, execution start time, actual completed adjustment amount, and actual process buffer margin. Then, the actual changes received at the end times of the first execution and the supplementary execution are used as the starting point for subsequent scheduling. The updated operation information and process information are rearranged according to high energy-consuming loads, production process locations, and recorded times to generate a load scheduling update baseline chain.
[0096] It should also be noted that the load dispatching update benchmark chain is an update sequence relationship chain formed by backfilling the actual power changes, actual process buffer changes, and actual connection relationships after the initial execution and supplementary execution into the load dispatching benchmark chain according to the unified load identity, production process location, and recording time. This is used to retain the true power status, process buffer status, and subsequent dispatching starting point of each high-energy-consuming load after execution, providing a continuous and accurate status basis for subsequent demand response adjustment, thereby avoiding the continued use of the pre-execution status and improving the accuracy and continuity of load dispatching.
[0097] S4.7 Based on the load scheduling update benchmark chain, the target power distribution record, scheduling execution deviation record, supplementary adjustment allocation record and supplementary execution verification record are correlated according to the demand response period. The target power trajectory, actual completed adjustment amount, actual process buffer margin and updated scheduling starting point of each high energy-consuming load are registered to generate a high energy-consuming load scheduling scheme.
[0098] It should be noted that, based on the load scheduling update benchmark chain, corresponding positions are established according to the demand response period, unified load identity, production process location, and recording time. First, the target power trajectory, issuance time, and execution confirmation status in the target power issuance record are written into the corresponding corresponding position. Then, the actual power deviation status, actual process buffer deviation status, and uncompleted adjustment amount in the scheduling execution deviation record are written into the same corresponding position.
[0099] Following the correspondence of incomplete adjustment amounts, the supplementary adjustment amount, supplementary execution start time, and high-energy-consuming loads in the supplementary adjustment allocation record are linked with the actual power change, actual process buffer change, and supplementary adjustment completion status in the supplementary execution verification record. The continuity of the first execution and supplementary execution in terms of time sequence, adjustment direction, and production process location is verified. Based on the completion status of the first execution and supplementary execution, the actual completed adjustment amount of each high-energy-consuming load in the corresponding demand response period is determined. The actual process buffer margin is determined according to the process buffer status corresponding to the execution end time in the load scheduling update benchmark chain. The power status and process buffer status corresponding to the execution end time are determined as the updated scheduling starting point. The target power trajectory, actual completed adjustment amount, actual process buffer margin, and updated scheduling starting point of each high-energy-consuming load are registered sequentially according to the demand response period to generate a high-energy-consuming load scheduling scheme.
[0100] This embodiment also provides a computer device applicable to the demand-response-based high-energy-consuming load scheduling method, comprising: a memory and a processor; the memory is used to store computer-executable instructions, and the processor is used to execute the computer-executable instructions to implement the demand-response-based high-energy-consuming load scheduling method proposed in the above embodiment.
[0101] The computer device can be a terminal, comprising a processor, memory, communication interface, display screen, and input devices connected via a system bus. The processor provides computing and control capabilities. The memory includes non-volatile storage media and internal memory. The non-volatile storage media stores the operating system and computer programs. The internal memory provides an environment for the operation of the operating system and computer programs stored in the non-volatile storage media. The communication interface is used for wired or wireless communication with external terminals; wireless communication can be achieved through Wi-Fi, carrier networks, NFC (Near Field Communication), or other technologies. The display screen can be an LCD screen or an e-ink screen. The input devices can be a touch layer covering the display screen, buttons, a trackball, or a touchpad on the computer device's casing, or an external keyboard, touchpad, or mouse.
[0102] This embodiment also provides a storage medium storing a computer program that, when executed by a processor, implements the demand-response-based high-energy-consumption load scheduling method proposed in the above embodiments. The storage medium can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as Static Random Access Memory (SRAM), Electrically Erasable Programmable Read-Only Memory (EEPROM), Erasable Programmable Read Only Memory (EPROM), Programmable Read-Only Memory (PROM), Read-Only Memory (ROM), magnetic storage, flash memory, magnetic disk, or optical disk.
[0103] In summary, this invention uses the current power state and process buffer state in the candidate adjustment sequence as a common starting point to deduce the operating trajectory of the existing power consumption mode and the candidate adjustment content, and verifies the power changes, buffer consumption, and process influence propagation in the two trajectories. This enables the simultaneous determination of the candidate adjustment content's ability to close the demand response gap and the stability of process acceptance, thereby filtering out adjustment content with buffer overdraft and influence diffusion, and retaining adjustment paths with continuous acceptance conditions. This improves scheduling executability, process continuity, and demand response closure reliability.
[0104] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, and all such modifications or substitutions should be covered within the scope of the claims of the present invention.
Claims
1. A high-energy-consuming load scheduling method based on demand response, characterized in that, include: Collect load process data, perform identity association and time sequence alignment on the load process data, obtain the load scheduling benchmark chain, compare the current power of each high energy-consuming load in the load scheduling benchmark chain with the corresponding demand response target power to form the power to be adjusted, put the power to be adjusted into the high energy-consuming loads that meet the acceptance conditions, and deduce the impact propagation state after the power to be adjusted is accepted along the process buffer relationship to generate candidate adjustment sequences. Using the current power state and process buffer state in the candidate adjustment sequence as a common starting point, a dual-track synchronous simulation is performed to obtain the dual-track process evolution trajectory. Buffer occupancy overlap and cross-load acceptance replacement are implemented on the dual-track process evolution trajectory along the process buffer relationship to form a buffer occupancy migration relationship. The buffer occupancy migration relationship is embedded into the subsequent acceptable buffer position and the continuous influence range is closed to generate paired trajectory simulation records. From the paired trajectory simulation records, the adjustment contents that can close the demand response gap and retain the process buffer margin are selected. The adjustment contents are combined with the field execution capabilities and the unclosed adjustment quantities are redistributed to generate the load scheduling execution sequence. Based on the load scheduling execution sequence, the target power trajectory is issued, and the actual power changes and process buffer changes after the execution of each high-energy-consuming load are collected. The actual power changes and process buffer changes are compared with the target power trajectory to obtain the scheduling execution deviation record. Based on the scheduling execution deviation record, the unfinished adjustment amount is supplemented and the actual received changes are backfilled into the load scheduling baseline chain to generate a high-energy-consuming load scheduling scheme.
2. The high-energy-consuming load scheduling method based on demand response as described in claim 1, characterized in that, The specific steps for performing identity association and time-series alignment on load process data to obtain the load scheduling baseline chain are as follows: Load process data are merged according to the relationship between load objects and production process locations, and the operation information and process information corresponding to the same high energy-consuming load are bound together to generate load identity association records. Correct the time offset between different acquisition locations in the load identity association record, and match the operation information of the same high-energy-consuming load with the process information in the same operating period to generate a load scheduling baseline chain.
3. The high-energy-consuming load scheduling method based on demand response as described in claim 2, characterized in that, The current power of each high-energy-consuming load in the comparative load scheduling benchmark chain and the corresponding demand response target power form the power to be adjusted. The power to be adjusted is placed into the high-energy-consuming loads that meet the acceptance conditions, and the impact propagation state after the power to be adjusted is deduced along the process buffer relationship to generate a candidate adjustment sequence. The specific steps are as follows: Based on the load dispatching benchmark chain, compare the current power of each high-energy-consuming load with the corresponding demand response target power during the demand response period, and register the adjustment amount with the corresponding high-energy-consuming load and demand response period to generate the power to be adjusted. Each power to be adjusted is placed into the corresponding high energy-consuming load. The power position after placement is checked to see if it is within the allowable operating range. The actual acceptance conditions of each high energy-consuming load for the power to be adjusted are verified in combination with the power change process and stable operating status. The high energy-consuming loads that meet the acceptance conditions are bound to the corresponding power to be adjusted to generate a list of accepting loads. Starting from the production process location corresponding to the power to be adjusted based on the load list, the changes in material buffer occupation and process waiting status caused by the power to be adjusted are deduced step by step according to the process acceptance sequence. The remaining buffer space and allowable acceptance time of each process location in the process of influence propagation are checked, the influence propagation range and process acceptance status corresponding to the power to be adjusted are recorded, and an adjustment propagation verification form is generated. Remove the power to be adjusted from the adjustment propagation verification table that causes insufficient material buffer and excessive process waiting time. Combine the remaining power to be adjusted according to the degree of closure of the demand response target power. Arrange the adjustment contents that meet the demand response requirements according to the process buffer margin retained by each combination and the corresponding execution sequence to generate a candidate adjustment sequence.
4. The high-energy-consuming load scheduling method based on demand response as described in claim 1 or 3, characterized in that, The process of using the current power state and process buffer state in the candidate adjustment sequence as a common starting point to perform dual-track synchronous deduction and obtain the dual-track process evolution trajectory involves the following specific steps: Based on the execution start time corresponding to each candidate adjustment content in the candidate adjustment sequence, the current power status, process buffer status, material flow status and process acceptance sequence of the corresponding high energy-consuming load are extracted from the load scheduling benchmark chain. The current power status and process buffer status corresponding to the same execution start time are respectively placed into two deduction paths to generate a dual-track common starting point record. Based on the common starting point record of the two tracks, corresponding continuous simulation positions are set according to the process acceptance sequence and time sequence. The existing power consumption mode is continuously extended in one simulation path, and candidate adjustment content is placed in the corresponding simulation position of the other simulation path. The high energy-consuming load, process position and time position in the two simulation paths are bound position by position to generate a dual-track synchronous advancement sequence. According to the dual-track synchronous advancement sequence, the two simulation paths are advanced position by position according to the succession relationship of material entry, material exit and process buffer occupation, and the process state formed at each simulation position is continued to be carried over to the next simulation position, generating a dual-track state advancement record. Based on the dual-track state advancement record, the power state, material flow state, buffer occupation state, and process waiting state formed continuously in the two simulation paths according to the same high energy consumption load, the same process position, and the same time position are connected to obtain the dual-track process evolution trajectory.
5. The high-energy-consuming load scheduling method based on demand response as described in claim 4, characterized in that, The process buffer relationship is used to perform buffer occupation overlap and cross-load replacement on the dual-track process evolution trajectory to form a buffer occupation migration relationship. The buffer occupation migration relationship is then embedded into the subsequent acceptable buffer position and the continuous influence range is closed to generate paired trajectory prediction records. The specific steps are as follows: Based on the dual-track process evolution trajectory, the buffer occupancy status corresponding to the same process position and the same time position is mapped to the same process buffer capacity range. Two buffer occupancy ranges are superimposed according to the capacity position, and common buffer occupancy, newly added buffer occupancy and available buffer position are distinguished to generate buffer occupancy overlap record. Based on the buffer space overlap record, the newly added buffer space is placed into the subsequent acceptable buffer position in sequence. When the current acceptable buffer position is insufficient to accept the newly added buffer space, the already accepted part is retained in the current process position, and the remaining buffer space is placed into the next process position to generate a buffer space acceptance record. According to the buffer occupancy acceptance record, the remaining buffer occupancy that crosses different high-energy-consuming load process positions will have its previous occupancy assignment removed and will be reassigned to the subsequent acceptable buffer positions. The newly added buffer occupancy, cross-load replacement positions and subsequent acceptable positions will be connected according to the order of acceptance to form a buffer occupancy migration relationship. Based on the buffer occupant migration relationship, the continuously migrating buffer occupants are sequentially embedded into the subsequent acceptable buffer positions. With each embedding, the subsequent acceptable buffer positions are updated. When all newly added buffer occupants are continuously accepted, the continuous influence range between the starting position and the final accepting position of the newly added buffer occupant is closed. The dual-track process evolution trajectory and the buffer occupant migration relationship are associated to generate paired trajectory deduction records.
6. The high-energy-consuming load scheduling method based on demand response as described in claim 5, characterized in that, The process involves selecting adjustment options from paired trajectory projection records that can close demand response gaps while preserving process buffer margins, combining these adjustments with on-site executable capabilities, and redistributing any unclosed adjustment amounts to generate a load scheduling execution sequence. The specific steps are as follows: Summarize the power adjustment amount corresponding to each candidate adjustment content based on the paired trajectory simulation records, and verify the material buffer changes, process waiting changes and process acceptance changes in the candidate adjustment operation trajectory. Screen out the candidate adjustment content that cannot retain the process buffer margin after execution, and generate a closed adjustment list. Based on the closed-loop control list, check the remaining execution time before the field execution constraints of the high-energy-consuming load corresponding to each control content, arrange the control content that meets the field execution conditions, and generate the field execution verification table; According to the on-site execution verification form, the planned adjustment amount of each adjustment content is limited to the current executable adjustment range of the corresponding high energy-consuming load, and converted into an execution adjustment amount that can be issued on-site according to the minimum execution step size. The execution adjustment amount is used to deduct the demand response gap in sequence and the adjustment amount that has not yet been closed after deduction is registered to generate an unclosed adjustment amount record. Based on the unclosed regulation records, high-energy-consuming loads with remaining executable adjustment space and process buffer margins are selected from the field execution verification table. The unclosed regulation quantities are then assigned in sequence according to the order of action response and the size of the process buffer margin. The initially assigned execution regulation quantities and the reassigned execution regulation quantities are then jointly arranged according to the execution start time and process acceptance order to generate a load scheduling execution sequence.
7. The high-energy-consuming load scheduling method based on demand response as described in claim 6, characterized in that, The steps are as follows: The target power trajectory is issued according to the load scheduling execution sequence; the actual power changes and process buffer changes after the execution of each high-energy-consuming load are collected; the actual power changes and process buffer changes are compared with the target power trajectory to obtain the scheduling execution deviation record. According to the load scheduling execution sequence, the execution adjustment amount of each high energy-consuming load is converted into a continuous target power trajectory according to the execution start time and process acceptance order. The target power trajectory is then issued sequentially and the corresponding high energy-consuming load, process location, issuance time and execution confirmation status are registered to generate a target power issuance record. Based on the target power distribution record, starting from the moment the target power trajectory is distributed, the actual power change, actual material buffer change, actual process waiting change, and actual process acceptance change of each high-energy-consuming load after execution are collected, and corresponding records are generated to form an execution status record. Based on the execution status record, the target power trajectory is compared with the actual power change at each time step, and the expected process buffer change corresponding to the target power trajectory is checked against the actual process buffer change. The scheduling execution deviation is recorded and a scheduling execution deviation record is generated.
8. The high-energy-consuming load scheduling method based on demand response as described in claim 1, characterized in that, The process of supplementing and allocating unfinished adjustments based on scheduling execution deviation records and backfilling actual load changes into the load scheduling baseline chain to generate a high-energy-consuming load scheduling scheme is as follows: Based on the scheduling execution deviation record, summarize the unfinished adjustment amount within the same demand response period, and select high-energy-consuming loads that still have remaining executable adjustment space from the on-site execution verification table and whose actual process buffer margin can continue to accommodate power changes. Then, allocate the unfinished adjustment amount to the selected high-energy-consuming loads in sequence to generate a supplementary adjustment allocation record. Based on the supplementary adjustment allocation record, each supplementary adjustment quantity is converted into a supplementary target power trajectory and issued sequentially according to the start time of supplementary execution. The actual power change and actual process buffer change after supplementary execution are collected, and the completion status of the supplementary adjustment quantity is verified to generate a supplementary execution verification record. Based on the supplementary execution verification record, the actual changes received corresponding to the initial execution and supplementary execution are backfilled into the load dispatching baseline chain to generate the load dispatching update baseline chain; Based on the load scheduling update benchmark chain, the target power distribution record, scheduling execution deviation record, supplementary adjustment allocation record, and supplementary execution verification record are correlated according to the demand response period. The target power trajectory, actual completed adjustment amount, actual process buffer margin, and updated scheduling starting point of each high energy-consuming load are registered to generate a high energy-consuming load scheduling scheme.
9. A computer device comprising a memory and a processor, wherein the memory stores a computer program, characterized in that, When the processor executes the computer program, it implements the steps of the demand-response-based high-energy-consuming load scheduling method according to any one of claims 1 to 8.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by the processor, it implements the steps of the demand response-based high-energy-consuming load scheduling method according to any one of claims 1 to 8.