An emergency handling method for clamping and fixing detached porcelain insulator conductors in power distribution networks.
By establishing a communication connection between the power distribution network operation and maintenance platform and the clamping and fixing device, the system automatically determines the location of the detached conductor and the clamping status, solving the problems of mismatch in conductor detachment handling and slippage identification in existing technologies, and improving the safety and accuracy of emergency response.
Patent Information
- Application Number
- CN202611489738.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-23
- Publication Date
- 2026-11-17
AI Technical Summary
In the existing technology, the handling method after the porcelain insulator conductor of the distribution network falls off does not match the conductor's energized state and actual load. The clamping quality lacks verification methods, and it is difficult to distinguish between wind-induced swaying and slippage, which poses a risk that the fallen conductor will fall off again.
The power distribution network operation and maintenance platform is connected to the clamping and fixing device. By collecting pressure distribution signals, electric field signals, attitude tilt angles and conductive stripe numbers, the number, position and status of the clamping and fixing device are automatically determined, so as to realize clamping quality verification and slippage identification.
It enables automated handling without requiring personnel to climb poles to assess the near-line situation, improving the safety of emergency response and the rationality of resource allocation, ensuring clamping quality, and reducing the risk of the detached conductor falling again.
Smart Images

Figure CN123121553A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power distribution line operation and maintenance technology, specifically to an emergency handling method for clamping and fixing detached porcelain insulator conductors in power distribution networks. Background Technology
[0002] In power distribution lines, conductors are secured to insulators on poles using binding or clamps. Over long-term operation, factors such as aging of the binding materials, wind loads, icing, and external damage can cause conductors to detach from the insulator's binding area. If a detached conductor remains suspended within the span and is still energized, it may pose a safety threat to pedestrians, vehicles, and nearby facilities below the line. Therefore, it is necessary to take immediate emergency measures upon discovering a detached conductor, temporarily clamping and securing it to create conditions for subsequent maintenance and restoration.
[0003] Currently, there are two main methods for dealing with detached conductors in distribution network porcelain insulators: manual pole climbing and specialized fixing tools. Manual pole climbing involves maintenance personnel carrying insulated tools to climb the pole and re-tie and fix the detached conductor. Specialized fixing tools involve using insulated operating rods or delivery equipment to send clamping and fixing devices to the detached conductor for clamping. Examples of such tools include conductor fixing tools used when replacing porcelain insulators while the power is on, and tools for adding insulating sleeves to detached conductors without power interruption.
[0004] However, the above-mentioned handling methods still have the following shortcomings: First, the handling process relies on personnel to judge the energized state of the conductor and the handling sequence on site. The number of clamping and fixing devices and the location of the clamping points are mostly determined by experience, which may not match the actual load of the detached conductor. Second, after clamping, there is a lack of means to verify the clamping quality. Abnormalities such as clamping gaps, biased clamping, and loose clamping are difficult to detect in a timely manner. Third, during the operation monitoring after clamping, both wind-induced swaying of the conductor and slippage of the conductor in the clamping device will cause changes in the device's attitude. The two are difficult to distinguish, and slippage cannot be identified in a timely and accurate manner. There is a risk that the detached conductor may slip out of the clamping device and fall again.
[0005] Therefore, the present invention provides an emergency handling method for clamping and fixing detached porcelain insulator conductors in power distribution networks. Summary of the Invention
[0006] To overcome the shortcomings of existing technologies, this invention provides an emergency handling method for clamping and fixing detached porcelain insulator conductors in power distribution networks. This method addresses the technical problems of mismatch between the handling method and the conductor's energized state and actual load, lack of verification methods for clamping quality, and difficulty in distinguishing between wind-induced swaying and slippage.
[0007] The technical solution adopted by this invention to solve its technical problem is: an emergency handling method for clamping and fixing detached porcelain insulator conductors in distribution networks, applied to a distribution network operation and maintenance platform. The distribution network operation and maintenance platform is communicatively connected to multiple clamping and fixing devices for clamping detached conductors. Each clamping and fixing device collects pressure distribution signals, electric field signals, attitude tilt angles, and conductive stripe numbers from two clamping groove surfaces. The method includes: S1. Receive distribution network line abnormality information containing abnormal line identifier and abnormal section identifier, determine the location of the fallen conductor and generate disposal order information accordingly. S2. Determine the energized state of the detached conductor based on the electric field signal; when the detached conductor is energized and there is ground fault information, determine to isolate the fault section before clamping; when the detached conductor is energized and there is no ground fault information, determine to clamp directly; when the detached conductor is de-energized, determine to handle it according to the power outage procedure, and execute step S3 after the power outage is completed. S3. Determine the number of clamping and fixing devices and the location of clamping points based on the span length, conductor type, and conductor tension at both ends of the span where the detachment location is located. S4. After clamping, receive the pressure distribution signal. When pressure peaks appear on both clamping groove surfaces and the positional deviation of the two pressure peaks is within the range determined by the size of the clamping groove surface, the clamping is deemed qualified; otherwise, a reinstallation prompt message is output. S5. After the clamping is qualified, the reference value is determined by the average value of the attitude tilt angle. When the deviation of the attitude tilt angle of any clamping and fixing device from the reference value exceeds the allowable range determined by the operating procedure, the difference in attitude tilt angle change between the clamping and fixing device and the adjacent clamping and fixing device is calculated. When the absolute value of the difference does not exceed the synchronous deviation range determined by the operating procedure and the attitude tilt angle change direction is the same, it is determined to be a wind-induced sway of the conductor and the monitoring information is output. Otherwise, the slip amount and slip direction are determined according to the change of the conductive stripe number, and the slip is confirmed in combination with the continuous change of attitude tilt angle, and the power outage processing information is output.
[0008] Preferably, in step S1, the location of the detached wire is determined according to the following steps: S11. Based on the abnormal line identifier, call the line ledger to determine the pole and tower sequence of the line corresponding to the abnormal line identifier and the porcelain insulator number corresponding to each pole and tower. S12. Based on the abnormal section identifier, determine the first and last towers in the tower sequence, and determine the span between the first and last towers and the porcelain insulator number corresponding to each span as candidate detachment locations. S13. When there are multiple candidate detachment locations, obtain the wire connection status information corresponding to each porcelain bottle number; S14. When the wire connection status information indicates that the wire is outside the binding area of the corresponding porcelain insulator, the span corresponding to the porcelain insulator number is determined as the detachment position of the detached wire; when the wire connection status information indicates that the wire is within the binding area of the corresponding porcelain insulator, the candidate detachment position corresponding to the porcelain insulator number is excluded.
[0009] Preferably, determining the charged state of the detached conductor based on the electric field signal in step S2 includes: Before delivering the clamping and fixing device, a background electric field signal covering a complete power frequency cycle is collected by a non-contact electric field sensor located at the front end of the clamping and fixing device; when the clamping and fixing device reaches the clamping position of the detached wire and does not contact the detached wire, a target electric field signal covering a complete power frequency cycle is collected by the non-contact electric field sensor. Extract the background frequency component corresponding to the rated frequency of the distribution network from the background electric field signal, and extract the target frequency component corresponding to the rated frequency of the distribution network from the target electric field signal; When the amplitude of the target frequency component is greater than the amplitude of the background frequency component, and the difference between the target frequency component and the background frequency component exceeds the allowable value of electric field change determined by the operating procedure, the detached conductor is determined to be energized; otherwise, the detached conductor is determined to be de-energized.
[0010] Preferably, step S3 is performed in the following manner: Calculate the load on the clamping and fixing device of the detached conductor based on the span length, the unit length weight determined by the conductor type, and the conductor tension at both ends of the span. The minimum positive integer not less than the quotient of the conductor load and the rated clamping load of a single clamping device shall be determined as the load requirement quantity, and the sum of the load requirement quantity and the redundancy quantity determined by the operating procedures shall be determined as the number of clamping devices. When there are multiple clamping and fixing devices, the clamping points are arranged at both ends of the span with the detachment position as the dividing position. The axial interval between adjacent clamping points on the side with greater conductor tension at both ends of the span is determined to be smaller than the axial interval between adjacent clamping points on the other side.
[0011] Preferably, in step S4, the determination of whether the clamping is qualified is performed in the following manner: When the self-locking mechanism completes locking, the initial pressure distribution signal of the two clamping groove surfaces is collected; after the verification time determined by the operating procedure, the verification pressure distribution signal of the two clamping groove surfaces is collected. When pressure peaks appear on both clamping groove surfaces in the initial pressure distribution signal and the verification pressure distribution signal, the positional deviations of the two pressure peaks are within the specified range, and the change between the initial pressure peak position and the verification pressure peak position corresponding to the same clamping groove surface is within the positional change range determined by the operating procedure, the clamping is deemed qualified. If no pressure peak appears on either of the two clamping slots in the initial pressure distribution signal or the verification pressure distribution signal, it is determined that the clamp is not clamped and a prompt message for re-delivering the clamp is output. If only one clamping slot appears in the initial pressure distribution signal or the verification pressure distribution signal, or if the positional deviation of the two pressure peaks exceeds the specified range, it is determined that the clamp is misaligned and a prompt message for adjusting the clamping position is output. If the change amount corresponding to the same clamping slot exceeds the positional change range, it is determined that the clamp is loose and a prompt message for loose clamping is output.
[0012] Preferably, after determining that the clamp is misaligned and outputting a prompt message to adjust the clamping position, the process further includes a fine-tuning process for the clamping position: The bias direction of the detached wire in the clamping groove is determined by the offset of the pressure peak position of the two clamping groove surfaces relative to the center position of the clamping groove surface. Send fine-tuning instruction information to the clamping and fixing device, the fine-tuning instruction information including an operation sequence of unlocking the self-locking mechanism, adjusting the clamping position in a direction opposite to the bias direction, and relocking; After fine-tuning, the pressure distribution signals of the two clamping slots are re-acquired and verified. Fine-tuning ends when the verification determines that the clamping is qualified; if the verification still determines that the clamping is biased, a manual handling prompt message is output.
[0013] Preferably, step S5 further includes a slip trend warning process, which specifically includes: Record the conductive stripe numbers and corresponding acquisition times for multiple acquisition cycles. Determine the slip rate for each time period based on the time interval between two adjacent changes in conductive stripe numbers and the axial spacing between adjacent conductive stripes. When the sliding rate increases segment by segment over multiple consecutive time periods, the remaining time for the detached wire to slide out of the clamping groove is determined based on the number difference between the number of the conductive stripe forming the current conductive loop and the number of the conductive stripe at the end of the clamping groove, the axial spacing, and the sliding rate of the current time period. Output slip warning information of the corresponding level according to the remaining time level determined by the operating procedure; when the remaining time is less than the emergency handling time determined by the operating procedure, output immediate power outage handling information.
[0014] Preferably, step S5 further includes a load redistribution process, which is performed in the following manner: After the clamping is qualified, the pressure distribution signal of each clamping and fixing device is continuously received. When the pressure peak of any clamping and fixing device changes from the pressure peak when the clamping is qualified to the pressure peak, the pressure change range determined by the operating procedure is exceeded, or when it is confirmed that any clamping and fixing device has slipped, the conductor tension at both ends of the span is reacquired and the conductor load of the detached conductor is recalculated. The sum of the rated clamping loads of all clamping devices other than the one that triggered the recalculation is compared with the recalculated conductor load. When the sum of the rated clamping loads is not less than the recalculated conductor load, output load redistribution normal information and keep monitoring; when the sum of the rated clamping loads is less than the recalculated conductor load, determine the number of additional clamping and fixing devices to be dispatched based on the load difference between the two, and generate supplementary dispatch information including the number of additional devices and the location of the additional clamping points.
[0015] Preferably, in step S5, the process of confirming slippage further includes electric field verification, which specifically includes: During the monitoring period, the non-contact electric field sensor is used to collect the verification electric field signal and extract the verification frequency component in the verification electric field signal that corresponds to the rated frequency of the distribution network. When the change in the conductive stripe number indicates slippage, and the change in the amplitude of the verification frequency component relative to the amplitude of the target frequency component acquired when the clamping is qualified exceeds the electric field verification range determined by the operating procedure, the slippage result is confirmed to be valid. When the change in the conductive stripe number indicates slippage but the amount of change does not exceed the electric field verification range, the conductive stripe number of subsequent acquisition cycles continues to be acquired. When the conductive stripe number remains unchanged and the change exceeds the electric field verification range, an abnormal conductive stripe detection message is output.
[0016] Preferably, in step S5, determining the reference value based on the average value of the attitude tilt angle includes: Exclude the attitude tilt angle of the acquisition cycle in which the self-locking mechanism completes locking, and determine the average value of multiple attitude tilt angles acquired within the reference duration determined by the operating procedure after that acquisition cycle as the reference value. If the attitude tilt angle is not received in any acquisition cycle within the reference duration, the attitude tilt angle supplementary acquisition information is output. The reference value is calculated again after the attitude tilt angle of each acquisition cycle within the reference duration is fully received.
[0017] This invention provides an emergency handling method for clamping and fixing detached conductors in porcelain insulators of power distribution networks. It has the following beneficial effects: 1. By determining the energized state of the detached conductor based on the electric field signal and matching the corresponding handling method, and determining the number and location of clamping and fixing devices based on the span length, conductor type, and conductor tension at both ends of the span, the handling dispatch is matched with the energized state and actual load of the detached conductor. This achieves automated handling decision-making without requiring personnel to climb the pole to judge the line, improving the safety of emergency handling and the rationality of the allocation of handling resources.
[0018] 2. By collecting pressure distribution signals from the two clamping slots twice—once when the self-locking is completed and once after the verification period—the clamping gaps, misalignment, and loosening are identified based on the pressure peak and its positional deviation. This eliminates misjudgments caused by instantaneous impacts during self-locking, achieves automatic verification of clamping quality, and prevents unqualified clamps from entering a long-term operating state.
[0019] 3. By distinguishing between wind-induced swaying and slippage of the conductor by the difference in the attitude tilt angle of adjacent clamping and fixing devices, the amount and direction of slippage are determined according to the change in the conductive stripe number, and the remaining time is extrapolated by combining the slippage rate trend to carry out graded early warning. This achieves accurate identification and early warning of slippage after handling, reducing the risk of the detached conductor falling again. Attached Figure Description
[0020] Figure 1 This is the overall flowchart of the present invention; Figure 2 This is a flowchart of the slip detection and trend warning closed loop of the present invention; Figure 3 This is a schematic diagram of the overall clamping and fixing device of the present invention; Figure 4 This is a schematic diagram showing the state of the device of the present invention holding the ceramic bottle wire.
[0021] In the diagram: 1. Hook arm; 2. Threaded screw; 3. Ring head handle; 4. Connecting bracket; 5. Insulated operating rod; 6. Grip section; 7. Locking block; 8. Porcelain insulator; 9. Wire; 10. Steel foot bolt. Detailed Implementation
[0022] Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings. However, it should be understood that these descriptions are exemplary only and are not intended to limit the scope of the invention. In the following detailed description, numerous specific details are set forth to provide a thorough understanding of the embodiments of the invention for ease of explanation. However, it will be apparent that one or more embodiments may be practiced without these specific details. Furthermore, descriptions of well-known structures and techniques are omitted in the following description to avoid unnecessarily obscuring the concept of the invention.
[0023] The terminology used herein is for the purpose of describing particular embodiments only and is not intended to limit the invention. The terms “comprising,” “including,” etc., as used herein indicate the presence of the stated features, steps, operations, and / or components, but do not exclude the presence or addition of one or more other features, steps, operations, or components.
[0024] All terms used herein (including technical and scientific terms) have the meanings commonly understood by those skilled in the art, unless otherwise defined. It should be noted that the terms used herein are to be interpreted in a manner consistent with the context of this specification, and not in an idealized or overly rigid way.
[0025] When using expressions such as "at least one of A, B and C", they should generally be interpreted in accordance with the meaning that is commonly understood by those skilled in the art (e.g., "a system having at least one of A, B and C" should include, but is not limited to, a system having A alone, a system having B alone, a system having C alone, a system having A and B, a system having A and C, a system having B and C, and / or a system having A, B and C, etc.).
[0026] like Figures 1 to 4 As shown, this invention proposes an emergency handling method for clamping and fixing detached conductors in distribution network insulators. This method is applied to a distribution network operation and maintenance platform, which is communicatively connected to multiple clamping and fixing devices for clamping detached conductors. Each clamping and fixing device collects pressure distribution signals, electric field signals, attitude tilt angles, and conductive stripe numbers from two clamping groove surfaces. The method includes: S1. Receive distribution network line abnormality information containing abnormal line identifier and abnormal section identifier, determine the location of the fallen conductor and generate disposal order information accordingly. S2. Determine the energized state of the detached conductor based on the electric field signal; when the detached conductor is energized and there is ground fault information, determine to isolate the fault section before clamping; when the detached conductor is energized and there is no ground fault information, determine to clamp directly; when the detached conductor is de-energized, determine to handle it according to the power outage procedure, and execute step S3 after the power outage is completed. S3. Determine the number of clamping and fixing devices and the location of clamping points based on the span length, conductor type, and conductor tension at both ends of the span where the detachment location is located. S4. After clamping, receive the pressure distribution signal. When pressure peaks appear on both clamping groove surfaces and the positional deviation of the two pressure peaks is within the range determined by the size of the clamping groove surface, the clamping is deemed qualified; otherwise, a reinstallation prompt message is output. S5. After the clamping is qualified, the reference value is determined by the average value of the attitude tilt angle. When the deviation of the attitude tilt angle of any clamping and fixing device from the reference value exceeds the allowable range determined by the operating procedure, the difference in attitude tilt angle change between the clamping and fixing device and the adjacent clamping and fixing device is calculated. When the absolute value of the difference does not exceed the synchronous deviation range determined by the operating procedure and the attitude tilt angle change direction is the same, it is determined to be a wind-induced sway of the conductor and the monitoring information is output. Otherwise, the slip amount and slip direction are determined according to the change of the conductive stripe number, and the slip is confirmed in combination with the continuous change of attitude tilt angle, and the power outage processing information is output.
[0027] During the execution of steps S1 to S5 above, the clamping and fixing device needs to complete the clamping of the detached wire, the acquisition of signals of the clamping state, and the controlled adjustment of the clamping position. To facilitate understanding of the operation process of the clamping and fixing device in each step, the structure of the clamping and fixing device will be explained first. Specifically, as follows... Figure 3 As shown, the clamping and fixing device includes a hook arm 1, a threaded screw 2, a ring-shaped handle 3, a connecting bracket 4, and an insulated operating rod 5. There are two hook arms 1, which are arranged symmetrically with respect to the axis of the threaded screw 2. The arm of each hook arm 1 is plate-shaped, and its end is provided with a hook facing the wire. The hooks of the two hook arms 1 are arranged facing each other to form a clamping space to accommodate the porcelain insulator 8 and the wire 9.
[0028] A threaded screw 2 passes between two hook arms 1. One end of the threaded screw 2 is integrally connected to and coaxially mounted with the ring handle 3. When the operator rotates the ring handle 3, the threaded screw 2 rotates accordingly, driving the two hook arms 1 to move towards each other to clamp the porcelain insulator 8 and the wire 9, or to move away from each other to release them. A connecting bracket 4 is located below the hook arms 1. The upper end of the insulating operating rod 5 is connected to the connecting bracket 4. The rod body of the insulating operating rod 5 has a grip section 6, allowing the operator to hold and support the entire device from a high position. The inner side of the hook arms 1 is provided with a V-shaped insulating pad, which is used to abut against the wire 9. Multiple conductive stripes are arranged at intervals on the groove surface of the V-shaped insulating pad. Each conductive stripe is numbered according to its position, and the spacing between adjacent conductive stripes is equal.
[0029] Furthermore, the two opposing grooves of the V-shaped insulating pads of the two hook arms 1 form two clamping grooves; multiple pressure sampling points are embedded in each clamping groove at intervals along the axial direction of the detached wire to collect pressure values at corresponding positions; a non-contact electric field sensor is provided at the end of the hook arm 1 facing the wire; a status sensing module, a control module, a communication module, and a power supply module are provided on the connecting bracket 4. The status sensing module is used to collect the attitude tilt angle of the clamping and fixing device, the control module is used to receive signals collected by each pressure sampling point, the non-contact electric field sensor, and the status sensing module, and communicates with the power distribution network operation and maintenance platform through the communication module, and the power supply module is used to supply power to the above-mentioned electrical components; in some embodiments, the threaded screw 2 is connected to the drive mechanism, and the drive mechanism drives the threaded screw 2 to move under the control of the control module to realize the controlled unlocking of the self-locking mechanism and the automatic adjustment of the clamping position. The drive mechanism adopts a motor-driven screw slide structure or an electric push rod structure; Specifically, each conductive stripe is a metal electrode embedded in the V-shaped insulating pad groove, and is connected to the numbering detection circuit via leads. The detached wire is a conductor. When the detached wire simultaneously presses against two adjacent conductive stripes in the clamping groove, the two conductive stripes are connected through the detached wire to form a conductive loop. The numbering detection circuit outputs the corresponding conductive stripe number based on the conductive stripe forming the conductive loop. When the detached wire slides in the clamping groove, the conductive stripe forming the conductive loop changes accordingly, and the conductive stripe number changes accordingly. Based on the above structure, such as Figure 4 As shown, in the clamped state, the wire 9 is located within the clamping space enclosed by the hook head of the hook arm 1 and is wrapped by the hook head. The porcelain insulator 8 abuts against one side of the wire 9, and the end of the porcelain insulator 8 is fixed to the crossarm by steel foot bolts 10. The threaded rod 2 is provided with a locking block 7, which constitutes part of the self-locking mechanism. After the threaded rod 2 is rotated to the clamping position, the locking block 7 locks the clamping position of the hook arm 1 to prevent the hook arm 1 from retracting and loosening under wind load.
[0030] After clamping, the hooks of the two hook arms 1 are hooked between the base of the porcelain insulator 8 and the crossarm. The clamping load on the conductor 9 is transmitted to the porcelain insulator 8 through the hook arms 1 and the threaded rod 2 and is borne by the porcelain insulator 8 and the crossarm. The insulating operating rod 5 is detachably connected to the connecting bracket 4. After clamping, the insulating operating rod 5 is removed. The clamping and fixing device maintains the clamping and fixing of the detached conductor 9 during monitoring.
[0031] In this embodiment, distribution network line anomaly information is generated by the distribution network monitoring system or distribution network operation and maintenance platform based on line operation data. This data includes feeder current, feeder voltage, grounding status, and switch operation status. Distribution network line anomaly information is generated when the feeder current or voltage exceeds the normal operating range defined in the operating procedures, or when the grounding status or switch operation status indicates a fault in the distribution line. The distribution network line anomaly information includes at least an abnormal line identifier and an abnormal section identifier. The abnormal line identifier uniquely identifies the distribution line where the anomaly occurred, and the abnormal section identifier uniquely identifies the section within that distribution line where the anomaly occurred.
[0032] In some implementations, abnormal information of distribution network lines includes abnormal line identifiers and abnormal section identifiers. The abnormal line identifier is used to uniquely identify a distribution line; the abnormal section identifier is used to uniquely identify the line section between two adjacent towers or two adjacent line monitoring points in the distribution line. The abnormal information of distribution network lines can be generated by the distribution network monitoring system based on line current, line voltage, grounding status and switch operation status, or it can be entered into the distribution network operation and maintenance platform by the personnel in charge.
[0033] In step S1 above, the location of the detached wire is determined as follows: In S11, the distribution network operation and maintenance platform stores line ledgers and section mapping tables. The line ledgers record line identifiers, tower numbers, the arrangement order of towers along the line extension direction, the span numbers between adjacent towers, insulator numbers, and the correspondence between the above information. The section mapping table records the correspondence between abnormal section identifiers and the first and last tower numbers.
[0034] In S12, when determining the location of a detachment, the distribution network operation and maintenance platform reads the corresponding tower sequence of the abnormal line based on the abnormal line identifier, and queries the corresponding first and last towers based on the abnormal section identifier. Then, it combines the span number between the first and last towers and the insulator number corresponding to each span to obtain the candidate detachment location. Each candidate detachment location includes the line identifier, span number, tower number, and insulator number.
[0035] In S13, when there is only one candidate detachment location, the distribution network operation and maintenance platform determines the candidate detachment location as the detachment location of the detached conductor. When there are multiple candidate detachment locations, the distribution network operation and maintenance platform sends each candidate detachment location as location verification information to the field terminal, and the field terminal verifies each candidate detachment location.
[0036] In S14, the field terminal obtains the field image of the corresponding insulator based on the location verification information, segments the conductor area and the insulator binding area in the field image, and extracts the center line of the conductor area. The insulator binding area refers to the groove or binding range where the conductor should be fixedly connected to the insulator. When the center line of the conductor area overlaps with the insulator binding area, conductor connection status information indicating a normal conductor connection is generated; when they do not overlap, conductor connection status information indicating that the conductor has detached from the insulator is generated; when neither the conductor area nor the insulator binding area is identified in the field image, verification failure information is generated.
[0037] The distribution network operation and maintenance platform receives conductor connection status information, verification failure information and corresponding insulator numbers. It identifies the candidate detachment locations where the indicator conductor has detached from the insulator as the detachment locations of the conductor, and excludes the candidate detachment locations where the indicator conductor is connected normally. When all candidate detachment locations are excluded or verification fails, the platform outputs location verification failure information to prompt the user to reacquire distribution network line abnormality information or re-acquire field images.
[0038] In some implementations, there are ambient electric fields, induced electric fields generated by adjacent operating lines, and electric field fluctuations caused by operating equipment around the detached conductor. Collecting an electric field signal only once at the clamping position to determine whether the detached conductor is energized can easily lead to misjudging the ambient electric field as the conductor being energized, or misjudging an energized conductor as being de-energized.
[0039] Based on this, this embodiment collects an electric field signal once before delivering the clamping and fixing device and once after reaching the clamping position. The energized state of the detached conductor is determined by comparing the components of the two signals that correspond to the rated frequency of the distribution network.
[0040] Specifically, before delivering the clamping and fixing device, the power distribution network operation and maintenance platform receives background electric field signals collected by a non-contact electric field sensor installed at the front end of the clamping and fixing device. A non-contact electric field sensor is a sensor that does not directly contact the conductor and outputs an electrical signal by sensing the intensity of the electric field in space. "Installed at the front end of the clamping and fixing device" means that the sensor is installed at the end of the clamping and fixing device facing the detached conductor, so that the distance between the sensor and the detached conductor decreases as the clamping and fixing device is delivered.
[0041] The background electric field signal refers to the electric field signal collected before the clamping and fixing device approaches the detached conductor. It is used to characterize the background electric field component in the current working environment that is unrelated to the detached conductor. The acquisition time of the background electric field signal covers a complete power frequency cycle, which refers to the AC cycle corresponding to the rated frequency of the distribution network. For example, when the rated frequency of the distribution network is 50Hz, a complete power frequency cycle is 20ms. The reason for the acquisition time covering the complete power frequency cycle is that the amplitude of the power frequency electric field signal changes with time within the cycle, and acquiring the signal only at a certain moment within the cycle will cause amplitude deviation.
[0042] When the clamping and fixing device reaches the clamping position of the detached wire but has not yet made contact with it, the non-contact electric field sensor continues to collect the target electric field signal. The target electric field signal refers to the electric field signal collected when the clamping and fixing device is near the detached wire but has not yet made electrical contact with it. If the detached wire is charged at this time, the signal collected by the sensor will include the power frequency electric field component generated by the detached wire in addition to the background electric field component. The collection time of the target electric field signal also covers a complete power frequency cycle, and the background electric field signal and the target electric field signal use the same collection period and collection time to make the two collection results comparable.
[0043] Furthermore, the distribution network operation and maintenance platform performs Fourier transforms on the background electric field signal and the target electric field signal respectively, converting the time-domain electric field signal into various frequency components. It extracts the background frequency component corresponding to the rated frequency of the distribution network from the background electric field signal, and extracts the target frequency component corresponding to the rated frequency of the distribution network from the target electric field signal. The component corresponding to the rated frequency of the distribution network reflects the power frequency electric field generated by the distribution network conductors, while the component unrelated to the rated frequency of the distribution network is excluded as an environmental interference component, thereby reducing the influence of the environmental electric field and the induced electric field on the judgment of the energized state.
[0044] The power distribution network operation and maintenance platform calculates the difference between the amplitude of the target frequency component and the amplitude of the background frequency component. When the amplitude of the target frequency component is greater than the amplitude of the background frequency component, and the difference exceeds the allowable value of electric field change determined by the operating procedure, it indicates that the power frequency electric field component detected by the clamping and fixing device after reaching the clamping position has changed relative to the background electric field component, and it is determined that the detached conductor is energized; otherwise, it is determined that the detached conductor is de-energized. The allowable value of electric field change is determined by the operating procedure based on the measurement error of the non-contact electric field sensor and the electric field fluctuation range of the working environment, and is used to eliminate the influence of measurement error and environmental electric field fluctuation on the judgment result.
[0045] It should be noted that after confirming that the detached conductor is energized, the distribution network operation and maintenance platform records the amplitude of the target frequency component as a comparison benchmark for electric field verification during the monitoring period after the clamping is qualified.
[0046] When the non-contact electric field sensor fails to collect a background electric field signal or target electric field signal covering a complete power frequency cycle, the distribution network operation and maintenance platform outputs an electric field signal resampling prompt message. It does not determine the energized state of the detached conductor based on incomplete electric field signals, thus avoiding drawing incorrect conclusions about the energized state based on signals with amplitude deviations.
[0047] In some implementations, the span length, conductor type, and conductor tension vary at different detachment locations. If clamping and fixing devices are arranged in a fixed number and at fixed intervals, there may be a mismatch between the number of devices and the conductor load, or a mismatch between the arrangement of clamping points and the stress state at both ends of the span.
[0048] Based on this, this embodiment determines the number of clamping and fixing devices according to the conductor load of the detached conductor, and adjusts the arrangement of the clamping points according to the conductor tension at both ends of the span: Specifically, the distribution network operation and maintenance platform reads the line ledger based on the location of the fallen conductor to obtain the span length and conductor type. It then queries the conductor parameter table based on the conductor type to obtain the weight per unit length of the conductor of that type. The conductor parameter table stores the correspondence between conductor type and weight per unit length. The distribution network operation and maintenance platform also obtains the conductor tension at both ends of the span. The conductor tension is collected by tension sensors installed at both ends of the span or read from the distribution network line operation record.
[0049] The power distribution network operation and maintenance platform determines the gravity load of the detached conductor based on the span length and weight per unit length, determines the unbalanced tension based on the conductor tension at both ends of the span, and calculates the conductor load acting on the clamping and fixing device using the following formula: ; Where Q represents the conductor load exerted by the detached conductor on the clamping and fixing device, in N; The value represents the weight per unit length determined by the conductor type, in N / m; L represents the span length, in m; T1 represents the conductor tension at the beginning of the span, in N; T2 represents the conductor tension at the end of the span, in N; the reason for setting the above formula is to combine the gravity load of the detached conductor with the unbalanced tension at both ends of the span into a single load value so as to compare it with the rated clamping load of a single clamping and fixing device. The units of L and |T1-T2| are both N, and the square root obtained after adding their squares is still N, so they have the same dimensions.
[0050] Furthermore, the distribution network operation and maintenance platform determines the load requirement as the minimum positive integer not less than the quotient of the conductor load and the rated clamping load of a single clamping and fixing device, which is calculated according to the following formula: ;in, This indicates the quantity of load required, expressed in units. This indicates the rated clamping load of a single clamping and fixing device, expressed in N. The rated clamping load is determined based on the nameplate parameters or type test results of the clamping and fixing device. This indicates rounding up; the reason for setting the above formula is to ensure that the total rated clamping load of all clamping and fixing devices involved in the clamping is not less than the conductor load of the detached conductor; based on this, the distribution network operation and maintenance platform determines the number of clamping and fixing devices according to the following formula: ; in, The number of clamping and fixing devices is represented by "R"; the number of redundancies determined by the operating procedures is also represented by "R". The operating procedures store the correspondence between line voltage levels and redundancy quantities. The distribution network operation and maintenance platform queries the corresponding redundancy quantity based on the voltage level of the line to which the detached conductor belongs. For example, for a 10kV distribution line, the redundancy quantity is 1; for a 10kV distribution line with higher power supply reliability requirements as determined by the operating procedures, the redundancy quantity is 2. The reason for setting the above formula is to include the redundancy quantity on top of the load requirement quantity, so that the number of clamping and fixing devices matches both the conductor load of the detached conductor and the line's operating requirements.
[0051] When determining the clamping point location, if there is only one clamping device, the distribution network maintenance platform determines the location of the detached conductor as the clamping point. If there are multiple clamping devices, the distribution network maintenance platform uses the detached conductor's location as the boundary, defining the area between the first-end tower and the boundary as the first-end arrangement area, and the area between the last-end tower and the boundary as the last-end arrangement area. Clamping points are then arranged from the boundary towards the first-end and last-end towers. The distribution network maintenance platform allocates the number of clamping devices to the first-end and last-end arrangement areas according to the ratio of the length of the first-end arrangement area to the length of the last-end arrangement area, and arranges the clamping points sequentially within each arrangement area according to the axial interval on the corresponding side. The axial interval refers to the distance between two adjacent clamping points along the axial direction of the detached conductor within the same arrangement area. The distribution network maintenance platform first determines the baseline axial interval based on the span length and the number of clamping devices. ; in The reference axial interval is indicated in meters; L indicates the span length in meters. This indicates the number of clamping and fixing devices, in units of individual units. The reason for this formula is to divide the span into corresponding arrangement intervals according to the number of clamping and fixing devices, providing a reference for adjusting the axial interval based on the conductor tension.
[0052] Subsequently, the distribution network operation and maintenance platform, based on the difference between the conductor tension at the beginning and end of the span, queries the interval adjustment amount determined by the operating procedures. The interval adjustment amount is determined by the operating procedures based on the correspondence between the conductor tension difference and the interval adjustment amount, and is less than the reference axial interval. When the conductor tension at the beginning of the span is greater than that at the end, the axial interval of the beginning area is determined as the difference between the reference axial interval and the interval adjustment amount, and the axial interval of the end area is determined as the sum of the reference axial interval and the interval adjustment amount. When the conductor tension at the end of the span is greater than that at the beginning, the axial interval of the end area is determined as the difference between the reference axial interval and the interval adjustment amount, and the axial interval of the beginning area is determined as the sum of the reference axial interval and the interval adjustment amount. When the conductor tensions at both ends of the span are equal, the interval adjustment amount is zero, and the axial intervals of both the beginning and end areas are the reference axial intervals.
[0053] Therefore, the axial spacing on the side with greater conductor tension at both ends of the span is smaller than that on the other side. Within the same arrangement length, more clamping points can be arranged on the side with greater conductor tension, so that the arrangement of clamping points matches the stress state at both ends of the span.
[0054] Furthermore, the distribution network operation and maintenance platform queries the availability status of each clamping and fixing device, selects the same number of clamping and fixing devices as the number of available clamping and fixing devices, and reads the number of the selected clamping and fixing devices. When the number of available clamping and fixing devices is less than the number of available clamping and fixing devices, an insufficient device quantity prompt message is output. When the number of available clamping and fixing devices is not less than the number of available clamping and fixing devices, a disposal order is generated and sent to the operation and maintenance terminal. The disposal order information includes the detachment location, the number of clamping and fixing devices, the clamping point location, and the number of each selected clamping and fixing device.
[0055] In some implementations, at the moment the self-locking mechanism completes locking, a momentary mechanical action occurs between the hook arm 1, the V-shaped insulating pad, and the detached wire. A pressure peak may appear at the pressure sampling point due to the momentary impact. If the clamping state is judged based solely on the pressure distribution signal collected at the moment the self-locking is completed, the momentary impact may be misjudged as normal clamping, or the gradual loosening that occurs after clamping may be missed.
[0056] Based on this, this embodiment collects the first pressure distribution signal when the self-locking mechanism completes locking, and collects the second pressure distribution signal after the verification time determined by the operating procedure, and determines the clamping state based on the two pressure distribution signals.
[0057] Specifically, multiple pressure sampling points are set in the two clamping grooves, and these points are spaced apart along the axial direction of the detached conductor. Each pressure sampling point collects the pressure value at its corresponding location and sends it along with the sampling point number to the distribution network operation and maintenance platform. The pressure distribution signal includes the sampling point number and the corresponding pressure value of each pressure sampling point. The distribution network operation and maintenance platform determines the pressure sampling point where the pressure value shows a local maximum value as the pressure peak point. A local maximum value means that the pressure value of the pressure sampling point is greater than the pressure values of the pressure sampling points on both sides of its axial direction. The sampling point number or axial coordinate corresponding to the pressure peak point is determined as the pressure peak position. The positional deviation between the two pressure peaks is the absolute value of the difference in axial coordinates between the pressure peak positions corresponding to the two clamping grooves.
[0058] When the self-locking mechanism completes locking, the distribution network operation and maintenance platform receives the initial pressure distribution signals from the two clamping slot surfaces. The locking time is determined by the moment the locking tongue inserts into the lock hole, or by the moment the locking indicator moves to a visible position outside the clamping and fixing device. After the verification period determined by the operating procedures, the distribution network operation and maintenance platform receives the verification pressure distribution signals from the two clamping slot surfaces again. The verification period is determined based on the action time of the self-locking mechanism and the pressure sampling period, and is not less than one pressure sampling period to avoid the instantaneous impact generated by the self-locking action affecting the verification pressure distribution signals.
[0059] During the judgment, the distribution network operation and maintenance platform first determines whether there is a situation in the initial pressure distribution signal and the verification pressure distribution signal where neither of the two clamping slots shows a pressure peak. When neither of the two clamping slots shows a pressure peak in either pressure distribution signal, it indicates that the detached conductor has not formed effective contact with the two clamping slots, and it is judged as clamping void. The platform then outputs a prompt message to re-deliver the clamping device, prompting the user to return the clamping device and re-deliver it.
[0060] When there is no clamping situation, the distribution network operation and maintenance platform determines whether only one clamping groove surface has a pressure peak in the initial pressure distribution signal or the verification pressure distribution signal, or whether the positional deviation of the two pressure peaks exceeds the range determined by the size of the clamping groove surface. When either situation is true, it indicates that the position of the detached conductor in the clamping groove surface deviates from the normal clamping position, which is judged as offset clamping. The platform outputs a prompt message to adjust the clamping position and records the positional offset direction of the two pressure peaks as the basis for determining the offset direction of the detached conductor during subsequent fine-tuning of the clamping position. The positional offset direction refers to the axial orientation of the pressure peak position relative to the center position of the clamping groove surface.
[0061] When both clamping slots exhibit pressure peaks and the positional deviations of the two pressure peaks are within the range defined by the clamping slot dimensions, the distribution network operation and maintenance platform further calculates the change between the initial pressure peak position and the verification pressure peak position corresponding to the same clamping slot. This change is the absolute value of the axial coordinate difference between the two pressure peak positions. When the change corresponding to either clamping slot exceeds the positional change range defined in the operating procedures, it indicates that the detached conductor has changed position relative to the clamping slot after clamping, and is judged as clamping loosening, and a clamping loosening warning message is output. The positional change range is determined based on the clamping slot dimensions, the arrangement interval of pressure sampling points, and the conductor diameter of the detached conductor. For example, the positional change range can be determined as one pressure sampling point arrangement interval.
[0062] When pressure peaks appear on both clamping groove surfaces in the initial pressure distribution signal and the verification pressure distribution signal, and the positional deviations of the two pressure peaks are within the range determined by the clamping groove surface dimensions, and the positional changes of the pressure peaks corresponding to the two clamping groove surfaces do not exceed the positional change range, the distribution network operation and maintenance platform determines that the clamping is qualified.
[0063] Through the above processing, the initial pressure distribution signal is used to confirm the clamping state when self-locking is completed, and the verification pressure distribution signal is used to confirm the clamping state after verification time. The combination of the two eliminates the interference of instantaneous impact during self-locking. Whether pressure peaks appear on the two clamping groove surfaces is used to identify clamping voids, the position deviation of pressure peaks is used to identify biased clamping, and the change in the position of pressure peaks is used to identify clamping looseness, thereby avoiding misjudgment of the clamping state caused by relying solely on a single pressure distribution signal.
[0064] In some implementations, if, upon determining that the wire is misaligned, only a prompt to adjust the clamping position is output and manual intervention is required, the operator needs to climb the pole again or reoperate the delivery device, increasing processing time and raising the risk of manual operation when the detached wire is energized. Therefore, this invention, upon determining that the wire is misaligned, automatically determines the offset direction of the detached wire based on the positional offset direction of the pressure peak, sends a fine-tuning command to the clamping and fixing device for automatic correction, and performs a re-verification after fine-tuning, forming a closed-loop adjustment process of "detection—fine-tuning—re-verification".
[0065] Specifically, the distribution network operation and maintenance platform determines the offset direction of the detached conductor within the clamping groove based on the deviation of the pressure peak positions of the two clamping groove surfaces relative to the center position of the clamping groove surface. The position offset direction refers to the axial orientation of the pressure peak position relative to the center position of the clamping groove surface, which has been recorded by the distribution network operation and maintenance platform when determining the offset. The offset direction refers to the orientation of the detached conductor within the clamping groove that deviates from the normal clamping position. When the pressure peak positions of the two clamping groove surfaces deviate to the same axial orientation, that orientation is determined as the offset direction. When the pressure peak positions of the two clamping groove surfaces deviate to opposite axial orientations, it indicates that the detached conductor has deflected within the clamping groove, and the axial orientation of the clamping groove surface with the larger pressure peak position deviation is determined as the offset direction.
[0066] Furthermore, the distribution network operation and maintenance platform generates fine-tuning instruction information based on the bias direction and sends it to the clamping and fixing device. The fine-tuning instruction information includes an operation sequence of unlocking the self-locking mechanism, adjusting the clamping position in the opposite direction to the bias direction, and relocking. It also includes an adjustment distance, which is determined based on the absolute value of the positional deviation between the two pressure peaks, for example, the adjustment distance is determined as the absolute value of the positional deviation.
[0067] After receiving the fine-tuning command, the clamping and fixing device is driven by the drive mechanism to unlock the self-locking mechanism, causing the clamping groove surface to move and adjust the distance in the opposite direction to the offset direction. The self-locking mechanism is then driven to lock again. It should be noted that this process requires the clamping and fixing device to have a controllable unlocking and position adjustment drive mechanism. This drive mechanism can be a motor-driven lead screw slide structure or an electric push rod structure.
[0068] After fine-tuning, the distribution network operation and maintenance platform re-collects the pressure distribution signals of the two clamping slots and re-verifies them according to the aforementioned method for determining clamping qualification. When the re-verification determines that the clamping is qualified, the fine-tuning process ends and the monitoring after clamping qualification begins. When the re-verification still determines that the clamping is off-center, the distribution network operation and maintenance platform accumulates the number of fine-tunings. When the number of fine-tunings has not reached the upper limit determined by the operating procedure, the offset direction is re-determined based on the position offset direction of the two pressure peaks in the re-verification and fine-tuning is performed again. When the number of fine-tunings reaches the upper limit, a manual handling prompt message is output to prompt the handling personnel to arrive at the site for handling.
[0069] Through the above processing, the pressure distribution signal serves as both the basis for determining the clamping state and as the feedback quantity for the fine-tuning process. After the clamping is off-center, the clamping position can be automatically corrected without manual approach to the detached wire. At the same time, the adjustment process is constrained by the upper limit of the number of fine-tunings to avoid getting stuck in a loop when repeated fine-tuning fails to correct the position.
[0070] In some implementations, power outage information is output only after slippage has occurred. This is a reactive measure after slippage has already happened. When slippage continues, the detached wire may slip out of the clamping slot and fall again, leaving limited time for personnel to handle the situation.
[0071] Based on this, this embodiment records the change process of the conductive stripe number during monitoring, extrapolates the remaining time for the detached wire to slide out of the clamping groove according to the change trend of the slippage rate, and issues graded warnings according to the remaining time, thus changing the slippage handling from post-event confirmation to pre-event warning: Specifically, the power distribution network operation and maintenance platform records the conductive stripe numbers and corresponding collection times for each collection cycle during the monitoring period, forming a numbered record table. The numbered record table stores the correspondence between the collection time and the conductive stripe numbers that form the conductive circuit.
[0072] The distribution network operation and maintenance platform defines the time interval between two consecutive changes in the conductive stripe number as a slip period, and determines the slip rate of each slip period according to the following formula: ;in, d represents the slip rate during the k-th slip period, in m / s; d represents the axial spacing between adjacent conductive stripes, in meters. The duration of the k-th slip period is the difference between the acquisition times corresponding to two adjacent changes in the conductive stripe number, expressed in seconds. The reason for setting the above formula is that the detached conductor moves exactly one axial distance between two adjacent changes in the number. Dividing the axial distance by the duration of the period gives the average slip rate of the detached conductor within that period.
[0073] The distribution network operation and maintenance platform sorts the slip rate of each slip period in chronological order. When the slip rate of multiple consecutive slip periods increases segment by segment, it is determined that the fallen conductor is in an accelerated slip state. The number of consecutive slip periods is determined by the operation procedure. For example, if the slip rate of three consecutive slip periods is greater than the slip rate of the previous slip period, it is determined that the slip rate increases segment by segment. When it is determined that the detached conductor is in an accelerated sliding state, the distribution network operation and maintenance platform determines the remaining time for the detached conductor to slide out of the clamping slot according to the following formula: ; in, This indicates the remaining duration, in seconds (s). This indicates the number of the end conductive stripe along the sliding direction in the clamping groove. It is dimensionless. The sliding direction is determined by the direction of change of the conductive stripe number. When the number increases, the end conductive stripe is the one with the largest number in the groove. When the number decreases, the end conductive stripe is the one with the smallest number in the groove. The 'd' represents the number of the conductive stripe that forms the current conductive loop; it is dimensionless. The 'd' represents the axial spacing between adjacent conductive stripes, in meters. The slip rate during the current slip period is expressed in m / s. The reason for setting the above formula is that the product of the number difference and the axial spacing is the remaining slip distance from the current position of the detached wire to the end of the clamping groove. Dividing it by the current slip rate gives the remaining time to slip out of the clamping groove. The number difference is dimensionless. Multiplying it by the axial spacing in m and then dividing it by the slip rate in m / s gives the remaining time in seconds, which is dimensionless.
[0074] Furthermore, the operating procedures store the correspondence between the remaining time range and the warning level. The distribution network operation and maintenance platform queries the corresponding warning level based on the remaining time and outputs the slip warning information of the corresponding level. The slip warning information includes the location of the detachment, the remaining time, and the warning level. For example, if the remaining time is not less than the first time determined by the operating procedure, a level 3 slip warning message is output; if the remaining time is less than the first time but not less than the second time determined by the operating procedure, a level 2 slip warning message is output; when the remaining time is less than the emergency handling time determined by the operating procedure, the distribution network operation and maintenance platform outputs an immediate power outage processing message, and at the same time generates on-site verification dispatch information containing the detachment location and slip direction and sends it to the operation and maintenance terminal. The emergency handling time is determined by the operating procedure based on the time required for the power outage operation and the time required for the handling personnel to arrive at the scene.
[0075] Through the above processing, the conductive stripe number is further used as the basis for predicting the slippage trend, and a graded warning of the remaining time is given in advance when the slippage rate increases step by step, so as to leave time for power outage handling and on-site verification, and to prevent the detached wire from falling again after slipping out of the clamping groove.
[0076] In some implementations, after the clamping is qualified, the stress state of the detached conductor may change due to factors such as wind load, tension release of adjacent spans, or the actual load borne by a clamping device may be transferred to other clamping devices due to slippage of a certain clamping device. If the load-bearing state of each clamping device is still evaluated according to the load when the clamping is qualified, there may be a situation where the total rated clamping load of the other clamping devices is insufficient to bear the current conductor load.
[0077] Based on this, this embodiment continuously monitors the pressure distribution signal of each clamping and fixing device after the clamping is qualified. When the pressure peak change exceeds the limit or slippage is confirmed, the conductor load is recalculated and the bearing capacity of the remaining clamping and fixing devices is evaluated. If it is insufficient, supplementary dispatch information is generated, forming a closed-loop processing process of "monitoring-evaluation-redispatch". Specifically, when the distribution network operation and maintenance platform determines that the clamping is qualified, it records the pressure peak value of each clamping and fixing device as the reference pressure peak value when the clamping is qualified; after the clamping is qualified, it continuously receives the pressure distribution signal of each clamping and fixing device, calculates the change of the current pressure peak value of each clamping and fixing device relative to the reference pressure peak value, and the change is the absolute value of the difference between the current pressure peak value and the reference pressure peak value.
[0078] When the change in pressure of any clamping and fixing device exceeds the pressure change range determined by the operating procedure, it indicates that the clamping state of the clamping and fixing device has changed, and the actual load it bears may have been transferred to other clamping and fixing devices; or when slippage is confirmed to have occurred in the aforementioned manner, it indicates that the clamping and fixing device that has slipped has reduced its ability to restrain the detached conductor; wherein the pressure change range is determined by the operating procedure based on the measurement error of the pressure sampling point and the pressure fluctuation range after the clamping is qualified.
[0079] In any of the above situations, the power distribution network operation and maintenance platform reacquires the current conductor tension collected by the tension sensors at both ends of the span, and recalculates the conductor load currently acting on the clamping and fixing device of the detached conductor in the manner described above. It should be noted that the conductor load here is calculated based on the current conductor tension, the original span length, and the weight per unit length, in order to reflect the actual stress state of the detached conductor after the load transfer.
[0080] Furthermore, the distribution network operation and maintenance platform will trigger the summation of the rated clamping loads of all clamping and fixing devices other than the recalculated clamping and fixing device to obtain the remaining total rated clamping load, and compare the remaining total rated clamping load with the recalculated conductor load; when the remaining total rated clamping load is not less than the recalculated conductor load, it indicates that the remaining clamping and fixing devices can still bear the current load of the detached conductor, and the distribution network operation and maintenance platform outputs load redistribution normal information and keeps monitoring it. The load redistribution normal information includes the detachment location, the recalculated conductor load, and the remaining total rated clamping load.
[0081] When the remaining total clamping load is less than the recalculated conductor load, the distribution network operation and maintenance platform determines the number of additional clamping and fixing devices to be dispatched according to the following formula: ;in This indicates the number of additional clamping and fixing devices required, expressed in units of one. This indicates the recalculated conductor load, in N; This indicates the remaining total clamping load, in N; This indicates the rated clamping load of a single clamping and fixing device, expressed in N; This indicates rounding up to the nearest integer.
[0082] The reason for setting the above formula is that the difference between the remaining total rated clamping load and the current conductor load is the load that needs to be supplemented. Divide this load difference by the rated clamping load of a single clamping and fixing device and round up to ensure that the total rated clamping load of each clamping and fixing device added after clamping is not less than the current conductor load.
[0083] The distribution network operation and maintenance platform determines the location of the additional clamping points based on the additional dispatch quantity. The additional clamping points are arranged within the axial interval between the existing clamping point locations according to the aforementioned method of determining the clamping point locations, and the axial interval between adjacent clamping point locations after the additional dispatch conforms to the rules for determining the baseline axial interval and the interval adjustment amount. Subsequently, supplementary dispatch information containing the additional dispatch quantity and the additional clamping point location is generated. The method of generating supplementary dispatch information is the same as that of generating the aforementioned disposal dispatch information, that is, querying the clamping and fixing devices in the available state, selecting the additional clamping and fixing devices from the available clamping and fixing devices and reading the device number, and sending the supplementary dispatch information to the operation and maintenance terminal. When the number of available clamping and fixing devices is less than the additional dispatch quantity, an insufficient device quantity prompt message is output, and power outage processing information is output simultaneously.
[0084] Through the above processing, the pressure distribution signal after the clamping is qualified is used to monitor the clamping status and as the triggering basis for load transfer. When the remaining device has insufficient bearing capacity after the load is redistributed, the gap is automatically assessed and supplementary dispatch information is generated so that the configuration of the clamping and fixing device can match the real-time stress state of the detached wire, avoiding the chain of detachment caused by load transfer after the failure of a single device.
[0085] In some implementations, the conductive stripes and their numbering detection circuits are located in the clamping groove. They are subjected to the pressure and friction of detached wires over a long period of time, which may lead to damage to the conductive stripes or failure of the numbering detection circuit. If slippage is confirmed only by the change of the conductive strip number, the number jump caused by the detection circuit failure may be misjudged as slippage, or slippage may be missed when the detection circuit fails.
[0086] Based on this, this embodiment reuses the non-contact electric field sensor at the front end of the clamping and fixing device to collect and verify the electric field signal. It utilizes the characteristic of the change in the power frequency electric field component caused by the slippage of the wire to perform cross-verification on the slippage result and provides a prompt when the conductive stripe detection is abnormal.
[0087] Specifically, after the clamping is qualified, the distribution network operation and maintenance platform continuously collects the verification electric field signal according to the collection cycle through the non-contact electric field sensor during the monitoring period. The verification electric field signal refers to the electric field signal collected during the monitoring period after the clamping is qualified, and its collection time covers a complete power frequency cycle. The distribution network operation and maintenance platform performs Fourier transform on the verification electric field signal and extracts the verification frequency component in the verification electric field signal that corresponds to the rated frequency of the distribution network.
[0088] It should be noted that when the detached wire slides axially in the clamping groove, the relative position between the detached wire and the non-contact electric field sensor changes, and the power frequency electric field strength at the sensor changes accordingly. Therefore, the amplitude of the calibration frequency component can reflect the positional change of the detached wire relative to the clamping and fixing device.
[0089] Furthermore, the distribution network operation and maintenance platform uses the amplitude of the target frequency component collected when the clamping is qualified as the comparison benchmark, and calculates the change in the amplitude of the verification frequency component relative to the comparison benchmark. This change is the absolute value of the difference between the amplitude of the verification frequency component and the comparison benchmark. The comparison benchmark is recorded by the distribution network operation and maintenance platform when it is determined that the detached conductor is energized. The electric field verification range is determined by the operating procedures based on the measurement error of the non-contact electric field sensor and the range of electric field fluctuations caused by wind-induced swaying of the conductor. This is used to eliminate the influence of wind-induced swaying and measurement error on the verification results. The range of electric field fluctuations caused by wind-induced swaying is determined by statistically analyzing the amplitude fluctuation data of the verification frequency component collected under historical wind swaying conditions.
[0090] During the verification process, when the change in the conductive stripe number indicates slippage and the amount of change exceeds the electric field verification range determined by the operating procedure, it indicates that the change in the conductive stripe number and the change in the electric field component corroborate each other. The distribution network operation and maintenance platform confirms that the slippage result is valid and outputs power outage processing information. When the conductive stripe number change indicator slips but the change amount does not exceed the electric field verification range, it indicates that the number change may be caused by a detection circuit fault or transient interference. The distribution network operation and maintenance platform will not confirm the slip and will continue to acquire conductive stripe numbers and verification electric field signals in subsequent acquisition cycles. When the conductive stripe number continues to change in the same direction in subsequent acquisition cycles, the electric field verification will be performed again. When the conductive stripe number does not change and the change amount exceeds the electric field verification range, it indicates that the electric field component reflects a change in the position of the detached conductor, but the conductive stripe detection does not output a number change. The conductive stripe detection may be malfunctioning. The distribution network operation and maintenance platform will output a conductive stripe detection anomaly message to prompt maintenance of the conductive stripe and number detection circuit. When the conductive stripe number does not change and the change amount does not exceed the electric field verification range, the distribution network operation and maintenance platform will continue monitoring.
[0091] Through the above processing, the non-contact electric field sensor is used for energization judgment before delivery and for slip verification during monitoring. The same sensor is reused in the two processing stages. The conductive stripe number and the electric field component belong to two different detection channels with different principles: mechanical contact and spatial sensing. The cross-verification of the two reduces slip misjudgment and missed judgment caused by failure or interference of a single detection channel. Furthermore, when the conductive stripe detection fails, it can be detected in time through the electric field verification results.
[0092] In some implementations, at the moment the self-locking mechanism completes locking, an instantaneous mechanical action occurs between the hook arm 1, the V-shaped insulating pad, and the detached wire. The tilt angle of the clamping and fixing device may momentarily fluctuate within the acquisition cycle. If the tilt angle of the acquisition cycle is included in the reference value, the reference value will be mixed with the transient component of the self-locking action, which cannot reflect the normal posture of the clamping and fixing device after the clamping is qualified, thus affecting the accuracy of subsequent posture deviation judgment.
[0093] Based on this, this embodiment excludes the attitude tilt angle of the acquisition cycle in which the self-locking mechanism completes locking when calculating the reference value, and determines the reference value by the average of multiple attitude tilt angles acquired within the reference duration after that acquisition cycle: Specifically, the status sensing module of the clamping and fixing device collects the attitude tilt angle of the clamping and fixing device according to the collection cycle, and sends the attitude tilt angle and the collection time to the distribution network operation and maintenance platform. The collection cycle refers to the time interval between two consecutive attitude tilt angle collections by the status sensing module. After the clamping is qualified, the distribution network operation and maintenance platform determines the collection cycle in which the self-locking mechanism completes locking. The locking time of the self-locking mechanism is determined according to the time when the lock tongue is inserted into the lock hole, or according to the time when the locking indicator moves to a visible position outside the clamping and fixing device. The distribution network operation and maintenance platform excludes the attitude tilt angle corresponding to the collection cycle, and takes the next collection cycle as the starting collection cycle to obtain multiple attitude tilt angles collected within the reference duration determined by the operation procedure. The number of attitude tilt angles involved in the calculation within the reference duration is determined by the reference duration and the collection cycle. For example, when the reference duration is ten seconds and the collection cycle is one second, the number of attitude tilt angles involved in the calculation is ten.
[0094] Furthermore, the power distribution network operation and maintenance platform sums the attitude tilt angles corresponding to each acquisition cycle within the reference duration, and then divides by the number of attitude tilt angles involved in the calculation to obtain the reference value. Since the attitude tilt angle of the acquisition cycle in which the self-locking mechanism completes locking is not included in the calculation, and the multiple attitude tilt angles within the reference duration are averaged to smooth out the random fluctuations of a single acquisition, the reference value can reflect the normal attitude state of the clamping and fixing device after the self-locking mechanism completes its action.
[0095] If no attitude tilt angle is received in any acquisition cycle within the reference duration, it indicates a communication interruption or missing acquisition. The distribution network operation and maintenance platform does not calculate the reference value based on the missing data. Instead, it sends attitude tilt angle supplementary acquisition information to the clamping and fixing device corresponding to the status sensing module to instruct it to re-acquire and transmit the attitude tilt angle of the missing acquisition cycle. When the attitude tilt angle of each acquisition cycle within the reference duration after supplementary acquisition is fully received, the reference value is calculated again in the above manner. If there are still acquisition cycles where no attitude tilt angle is received after supplementary acquisition, the distribution network operation and maintenance platform outputs an attitude acquisition anomaly prompt to check the communication link between the status sensing module and the distribution network operation and maintenance platform. This avoids inaccurate reference values due to communication interruption or missing acquisition.
[0096] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. An emergency handling method for clamping and fixing detached conductors of porcelain insulators in power distribution networks, characterized in that: The method is applied to a power distribution network operation and maintenance platform, which is communicatively connected to multiple clamping and fixing devices for holding detached conductors. Each clamping and fixing device collects pressure distribution signals, electric field signals, attitude tilt angles, and conductive stripe numbers from two clamping groove surfaces. The method includes: S1. Receive distribution network line abnormality information containing abnormal line identifier and abnormal section identifier, determine the location of the fallen conductor and generate disposal order information accordingly. S2. Determine the energized state of the detached conductor based on the electric field signal; when the detached conductor is energized and there is ground fault information, determine to isolate the fault section before clamping; when the detached conductor is energized and there is no ground fault information, determine to clamp directly; when the detached conductor is de-energized, determine to handle it according to the power outage procedure, and execute step S3 after the power outage is completed. S3. Determine the number of clamping and fixing devices and the location of clamping points based on the span length, conductor type, and conductor tension at both ends of the span where the detachment location is located. S4. After clamping, receive the pressure distribution signal. When pressure peaks appear on both clamping groove surfaces and the positional deviation of the two pressure peaks is within the range determined by the size of the clamping groove surface, the clamping is deemed qualified; otherwise, a reinstallation prompt message is output. S5. After the clamping is qualified, the reference value is determined by the average value of the attitude tilt angle. When the deviation of the attitude tilt angle of any clamping and fixing device from the reference value exceeds the allowable range determined by the operating procedure, the difference in attitude tilt angle change between the clamping and fixing device and the adjacent clamping and fixing device is calculated. When the absolute value of the difference does not exceed the synchronous deviation range determined by the operating procedure and the attitude tilt angle change direction is the same, it is determined to be a wind-induced sway of the conductor and the monitoring information is output. Otherwise, the slip amount and slip direction are determined according to the change of the conductive stripe number, and the slip is confirmed in combination with the continuous change of attitude tilt angle, and the power outage processing information is output.
2. The emergency treatment method for the conductor falling-off of the porcelain insulator according to claim 1, characterized in that: In step S1, the location of the detached wire is determined according to the following steps: S11. Based on the abnormal line identifier, call the line ledger to determine the tower sequence of the line corresponding to the abnormal line identifier and the porcelain insulator number corresponding to each tower. S12. Based on the abnormal section identifier, determine the first and last towers in the tower sequence, and determine the span between the first and last towers and the porcelain insulator number corresponding to each span as candidate detachment locations. S13. When there are multiple candidate detachment locations, obtain the wire connection status information corresponding to each porcelain bottle number; S14. When the wire connection status information indicates that the wire is outside the binding area of the corresponding porcelain insulator, the span corresponding to the porcelain insulator number is determined as the detachment position of the detached wire; when the wire connection status information indicates that the wire is within the binding area of the corresponding porcelain insulator, the candidate detachment position corresponding to the porcelain insulator number is excluded.
3. The emergency treatment method for the conductor falling of the porcelain insulator according to claim 1, characterized in that: Determining the charged state of the detached conductor based on the electric field signal in step S2 includes: Before delivering the clamping and fixing device, a background electric field signal covering a complete power frequency cycle is collected by a non-contact electric field sensor located at the front end of the clamping and fixing device; when the clamping and fixing device reaches the clamping position of the detached wire and does not contact the detached wire, a target electric field signal covering a complete power frequency cycle is collected by the non-contact electric field sensor. Extract the background frequency component corresponding to the rated frequency of the distribution network from the background electric field signal, and extract the target frequency component corresponding to the rated frequency of the distribution network from the target electric field signal; When the amplitude of the target frequency component is greater than the amplitude of the background frequency component, and the difference between the target frequency component and the background frequency component exceeds the allowable value of electric field change determined by the operating procedure, the detached conductor is determined to be energized; otherwise, the detached conductor is determined to be de-energized.
4. The emergency treatment method for the conductor falling of the porcelain insulator according to claim 1, characterized in that: Step S3 is performed in the following manner: Calculate the load on the clamping and fixing device of the detached conductor based on the span length, the weight per unit length determined by the conductor type, and the conductor tension at both ends of the span. The minimum positive integer not less than the quotient of the conductor load and the rated clamping load of a single clamping device shall be determined as the load requirement quantity, and the sum of the load requirement quantity and the redundancy quantity determined by the operating procedures shall be determined as the number of clamping devices. When there are multiple clamping and fixing devices, the clamping points are arranged at both ends of the span with the detachment position as the dividing position. The axial interval between adjacent clamping points on the side with greater conductor tension at both ends of the span is determined to be smaller than the axial interval between adjacent clamping points on the other side.
5. The emergency treatment method for the conductor falling of the porcelain insulator according to claim 1, characterized in that: In step S4, the determination of whether the clamping is qualified is performed in the following manner: When the self-locking mechanism completes locking, the initial pressure distribution signal of the two clamping groove surfaces is collected; after the verification time determined by the operating procedure, the verification pressure distribution signal of the two clamping groove surfaces is collected. When pressure peaks appear on both clamping groove surfaces in the initial pressure distribution signal and the verification pressure distribution signal, the positional deviations of the two pressure peaks are within the specified range, and the change between the initial pressure peak position and the verification pressure peak position corresponding to the same clamping groove surface is within the positional change range determined by the operating procedure, the clamping is deemed qualified. If no pressure peak appears on either of the two clamping slots in the initial pressure distribution signal or the verification pressure distribution signal, it is determined that the clamp is not clamped and a prompt message for re-delivering the clamp is output. If only one clamping slot appears in the initial pressure distribution signal or the verification pressure distribution signal, or if the positional deviation of the two pressure peaks exceeds the specified range, it is determined that the clamp is misaligned and a prompt message for adjusting the clamping position is output. If the change amount corresponding to the same clamping slot exceeds the positional change range, it is determined that the clamp is loose and a prompt message for loose clamping is output.
6. The emergency treatment method for the conductor falling-off of the porcelain insulator according to claim 5, characterized in that: After determining that the clamping is biased and outputting a prompt message to adjust the clamping position, the process also includes a fine-tuning of the clamping position: The bias direction of the detached wire in the clamping groove is determined by the offset of the pressure peak position of the two clamping groove surfaces relative to the center position of the clamping groove surface. Send fine-tuning instruction information to the clamping and fixing device, the fine-tuning instruction information including an operation sequence of unlocking the self-locking mechanism, adjusting the clamping position in a direction opposite to the bias direction, and relocking; After fine-tuning, the pressure distribution signals of the two clamping slots are re-acquired and verified. Fine-tuning ends when the verification determines that the clamping is qualified. If the re-inspection still determines that the bias is still present, a manual handling prompt message will be output.
7. The emergency treatment method for the conductor falling of the porcelain insulator according to claim 1, wherein: Step S5 further includes a slip trend warning process, which specifically includes: Record the conductive stripe numbers and corresponding acquisition times for multiple acquisition cycles. Determine the slip rate for each time period based on the time interval between two adjacent changes in conductive stripe numbers and the axial spacing between adjacent conductive stripes. When the sliding rate increases segment by segment over multiple consecutive time periods, the remaining time for the detached wire to slide out of the clamping groove is determined based on the number difference between the number of the conductive stripe forming the current conductive loop and the number of the conductive stripe at the end of the clamping groove, the axial spacing, and the sliding rate of the current time period. Output slip warning information of the corresponding level according to the remaining time level determined by the operating procedure; when the remaining time is less than the emergency handling time determined by the operating procedure, output immediate power outage handling information.
8. The emergency handling method for clamping and fixing detached porcelain insulator conductors in a power distribution network according to claim 1, characterized in that: Step S5 also includes a load redistribution process, which is performed in the following manner: After the clamping is qualified, the pressure distribution signal of each clamping and fixing device is continuously received. When the pressure peak of any clamping and fixing device changes from the pressure peak when the clamping is qualified to the pressure peak, the pressure change range determined by the operating procedure is exceeded, or when it is confirmed that any clamping and fixing device has slipped, the conductor tension at both ends of the span is reacquired and the conductor load of the detached conductor is recalculated. The sum of the rated clamping loads of all clamping devices other than the one that triggered the recalculation is compared with the recalculated conductor load. When the sum of the rated clamping loads is not less than the recalculated conductor load, output load redistribution normal information and keep monitoring. When the sum of the rated clamping loads is less than the recalculated conductor load, the number of additional clamping and fixing devices to be dispatched is determined based on the load difference between the two, and supplementary dispatch information including the number of additional devices and the location of the additional clamping points is generated.
9. The emergency treatment method for the conductor and insulator falling of the distribution network porcelain insulator according to claim 3, characterized in that: In step S5, the process of confirming slippage also includes electric field verification, which specifically includes: During the monitoring period, the non-contact electric field sensor is used to collect the verification electric field signal and extract the verification frequency component in the verification electric field signal that corresponds to the rated frequency of the distribution network. When the change in the conductive stripe number indicates slippage, and the change in the amplitude of the verification frequency component relative to the amplitude of the target frequency component acquired when the clamping is qualified exceeds the electric field verification range determined by the operating procedure, the slippage result is confirmed to be valid. When the change in the conductive stripe number indicates slippage but the amount of change does not exceed the electric field verification range, the conductive stripe number of subsequent acquisition cycles continues to be acquired. When the conductive stripe number remains unchanged and the change exceeds the electric field verification range, an abnormal conductive stripe detection message is output.
10. The emergency treatment method for the conductor and insulator falling of the distribution network insulator according to claim 1, characterized in that: The step S5, which determines the reference value based on the average value of the attitude tilt angle, includes: Exclude the attitude tilt angle of the acquisition cycle in which the self-locking mechanism completes locking, and determine the average value of multiple attitude tilt angles acquired within the reference duration determined by the operating procedure after that acquisition cycle as the reference value. If the attitude tilt angle is not received in any acquisition cycle within the reference duration, the attitude tilt angle supplementary acquisition information is output. The reference value is calculated again after the attitude tilt angle of each acquisition cycle within the reference duration is fully received.