Concrete pipeline hoisting device
By using wear-resistant flat sleeves and coating components during the lifting of concrete pipelines to reduce the friction between the lifting belt and the end of the pipe, the problem of reduced mechanical strength and safety risks of the lifting belt is solved, and the protection and safety of the lifting belt are improved.
Patent Information
- Application Number
- CN202322023576.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-07-28
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2033-07-28
AI Technical Summary
During the hoisting process, the mechanical strength of concrete pipes decreases due to friction between the lifting straps and the ends of the pipes, making it difficult to determine when to replace them, which increases safety risks.
Wear-resistant flat sleeves and covering components are used to cover the sling and contact the end of the concrete pipe to reduce friction. The position is adjusted through Velcro and locking parts. Nylon material is used to reduce replacement costs.
It effectively reduces the possibility of the lifting belt breaking during the hoisting process, improves operating safety, and reduces the replacement cost of wear-resistant components.
Smart Images

Figure CN221821645U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of building construction equipment, and in particular to a concrete pipe hoisting device. Background Art
[0002] Concrete pipes are pipes made of reinforced concrete and are commonly used for transporting fluids.
[0003] During the installation of concrete pipes, lifting equipment is required to lift the concrete pipes. Since the lifting steel cable is difficult to bend, a lifting belt is used to connect the concrete pipe and the hook of the lifting equipment during lifting. After the lifting is completed, the lifting belt can be removed. At the same time, in order to prevent the lifting belt from being pressed to the ground by the concrete pipe and difficult to remove, the lifting belt will be installed by passing through the concrete pipe.
[0004] However, concrete pipes often swing during the hoisting process, and friction will occur between the edge of the concrete pipe end and the hoisting belt, which will cause the mechanical strength of the hoisting belt to decrease. The mechanical strength of the hoisting belt is difficult to judge with the naked eye, so it is difficult to determine at what level of friction the hoisting belt needs to be replaced, which can easily cause the hoisting belt to break during the hoisting process, which can easily increase the safety risk during the operation. Utility Model Content
[0005] In order to improve safety during operation, the present application provides a concrete pipe lifting device.
[0006] The concrete pipe hoisting device provided in this application adopts the following technical solution:
[0007] A concrete pipe hoisting device comprises a hoisting belt, a covering component covered on the hoisting belt, and two movable abutment components arranged on the covering component;
[0008] The movable abutment assembly comprises a wear-resistant flat sleeve which is slidably sleeved on the covering assembly and a locking member which is arranged on the wear-resistant flat sleeve;
[0009] The locking piece is used to lock the position of the wear-resistant flat sleeve, and the wear-resistant flat sleeve is used to abut against the end of the concrete pipe.
[0010] By adopting the above technical solution, when hoisting the concrete pipe, first pass the lifting belt through the concrete pipe, and make the two wear-resistant flat sleeves respectively abut the two ends of the concrete pipe, and then hang the two ends of the lifting belt on the hooks of the lifting equipment. The covering component completely covers the lifting belt, so as to avoid the friction between the lifting belt and the inner wall of the concrete pipe. The wear-resistant flat sleeve covers the part where the lifting belt and the end of the concrete pipe abut, so as to avoid the friction between the lifting belt and the end of the concrete pipe during hoisting. Therefore, by providing the wear-resistant flat sleeve and the covering component, the lifting belt can be protected, so as to reduce the possibility of the lifting belt breaking due to friction during the hoisting process, thereby improving the safety during operation.
[0011] Meanwhile, when the position of the wear-resistant flat sleeve on the lifting belt needs to be adjusted according to the length of the concrete pipe, it is only necessary to release the locking piece and slide the wear-resistant flat sleeve.
[0012] Optionally, the covering assembly includes a wear-resistant covering strip covered on the lifting belt, and the wear-resistant flat sleeve sliding sleeve is arranged on the wear-resistant covering strip.
[0013] By adopting the above technical solution, the wear-resistant coated strip covers the lifting belt, thereby protecting the lifting belt and reducing the possibility of the mechanical strength of the lifting belt decreasing. The wear-resistant flat sleeve can slide on the wear-resistant coated strip to adjust its position on the lifting belt.
[0014] Optionally, the covering component further comprises a Velcro sub-tie and a Velcro mother-tie respectively arranged on both sides of the wear-resistant covering strip along the length direction of the wear-resistant covering strip; the Velcro sub-tie is adhered to the Velcro mother-tie.
[0015] By adopting the above technical solution, when the Velcro sub-sticker is bonded to the Velcro mother sticker, the wear-resistant coated strip can be coated on the sling. When the wear-resistant coated strip needs to be replaced, it is only necessary to release the Velcro sub-sticker and the Velcro mother sticker.
[0016] Optionally, the locking member is selected to be two locking bolts, and the two locking bolts are respectively penetrated and fixed on both sides of one end of the wear-resistant flat sleeve, and the two locking bolts clamp the wear-resistant flat sleeve on the wear-resistant coated strip.
[0017] By adopting the above technical solution, the two locking bolts can clamp the wear-resistant flat sleeve on the wear-resistant coated long strip, thereby reducing the possibility of the wear-resistant flat sleeve moving on the wear-resistant coated long strip. When the position of the wear-resistant flat sleeve on the wear-resistant coated long strip needs to be adjusted according to the length of the concrete pipe, it is only necessary to loosen the two locking bolts and slide the wear-resistant flat sleeve, and then tighten the locking bolts.
[0018] Optionally, the wear-resistant coating strip and the wear-resistant flat sleeve are both made of nylon.
[0019] By adopting the above technical solution, the nylon material has a strong wear-resistant effect and a low manufacturing cost, which can effectively reduce the cost of replacing the wear-resistant coated strips and / or the wear-resistant flat sleeves.
[0020] Optionally, a connecting component is further included, and both ends of the lifting belt are respectively provided with hanging parts, and the two hanging parts are respectively hung on the two ends of the connecting component, and the connecting component is used to connect with the lifting equipment.
[0021] By adopting the above technical solution and setting a connecting assembly, the distance between the two hanging parts can be increased, and the wrap angle at the abutment between the lifting belt and the concrete pipe can be reduced, thereby reducing the wrap angle at the abutment between the wear-resistant flat sleeve and the concrete pipe, thereby reducing the friction of the wear-resistant flat sleeve.
[0022] Optionally, the connecting assembly includes a connecting horizontal long rod, a main hook, a connecting plate and two sub-hooks; the two sub-hooks are respectively arranged at the two ends of the connecting horizontal long rod, the main hook is arranged on one side of the connecting plate, and the two ends of the connecting horizontal long rod are connected to the other side of the connecting plate through a steel cable.
[0023] By adopting the above technical solution, when hoisting the concrete pipe, it is only necessary to hang the main hook on the hook of the lifting equipment, and then hang the two hanging parts on the two sub-hooks respectively. The setting of the connecting horizontal long rod can disperse the pulling force generated during hoisting into two parts, thereby reducing the swing generated during hoisting of the concrete pipe, and further reducing the wear caused by the friction between the wear-resistant flat sleeve and the end of the concrete pipe.
[0024] Optionally, the connecting assembly also includes a connecting longitudinal rod, the middle section of the connecting longitudinal rod and the middle section of the connecting transverse rod are welded and perpendicular to each other, and reinforcing ribs are provided at the connection between the connecting transverse rod and the connecting longitudinal rod, and the two ends of the connecting longitudinal rod are respectively connected by a steel cable and a connecting plate.
[0025] By adopting the above technical solution, the reinforcing ribs are used to improve the stability of the connection between the connecting longitudinal rod and the connecting long cross rod, and the connection between the connecting longitudinal rod and the connecting plate can serve as a protective connection.
[0026] In summary, the present application includes at least one of the following beneficial technical effects:
[0027] 1. The provision of wear-resistant flat sleeves and covering components can protect the lifting belt, thereby reducing the possibility of the lifting belt breaking due to friction during the lifting process, thereby improving the safety during operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1It is a schematic diagram of the hoisting of an embodiment of the present application.
[0029] Figure 2 yes Figure 1 Enlarged schematic diagram of part A.
[0030] Figure numerals: 1. lifting belt; 11. hanging part; 2. covering assembly; 21. wear-resistant covering strip; 22. Velcro sub-stick; 23. Velcro mother stick; 3. connecting assembly; 31. connecting horizontal long rod; 32. connecting longitudinal rod; 33. main hook; 34. connecting plate; 35. sub-hook; 36. reinforcing rib; 4. movable abutment assembly; 41. wear-resistant flat sleeve; 42. locking piece. DETAILED DESCRIPTION
[0031] The following is combined with Figure 1-2 This application is described in further detail.
[0032] The embodiment of the present application discloses a concrete pipe hoisting device.
[0033] Reference Figure 1 A concrete pipe lifting device includes a lifting belt 1, a covering component 2, a connecting component 3, and two movable abutment components 4.
[0034] The two ends of the lifting belt 1 are integrally formed with a hanging part 11, and the two hanging parts 11 are respectively hung on the two ends of the connecting component 3. The connecting component 3 is used to connect with the lifting equipment. The covering component 2 is covered on the lifting belt 1, and the two movable abutting components 4 are respectively arranged at the two ends of the covering component 2.
[0035] Reference Figure 1 and Figure 2 The covering component 2 includes a wear-resistant covering strip 21, a Velcro sub-sticker 22 and a Velcro mother sticker 23. The Velcro sub-sticker 22 is fixedly connected to one side of the wear-resistant covering strip 21, and the Velcro mother sticker 23 is fixedly connected to the other side of the wear-resistant covering strip 21. The Velcro sub-sticker 22 and the Velcro mother sticker 23 are both arranged along the length direction of the wear-resistant covering strip 21. The Velcro sub-sticker 22 is attached to the Velcro mother sticker 23, so that the wear-resistant covering strip 21 is covered on the lifting belt 1.
[0036] When hoisting a concrete pipe, the hoisting belt 1 is inserted into the concrete pipe, and the wear-resistant coating strip 21 abuts between the hoisting belt 1 and the inner wall of the concrete pipe, thereby reducing the possibility of friction between the hoisting belt 1 and the inner wall of the concrete pipe, thereby reducing the wear of the hoisting belt 1. When the wear-resistant coating strip 21 is worn to a certain extent, the entire coating assembly 2 can be directly replaced.
[0037] Reference Figure 1 and Figure 2The movable abutment assembly 4 includes a wear-resistant flat sleeve 41 and a locking member 42. The wear-resistant flat sleeve 41 is slidingly mounted on one end of the wear-resistant coated strip 21, and the wear-resistant flat sleeve 41 is used to abut against the end of one end of the concrete pipe when hoisting the concrete pipe, thereby further improving the wear resistance of the lifting belt 1. The locking member 42 is arranged on the wear-resistant flat sleeve 41, and the locking member 42 is used to lock and fix the position of the wear-resistant flat sleeve 41 on the wear-resistant coated strip 21.
[0038] In the embodiment of the present application, the locking member 42 is selected to be two locking bolts, which are respectively passed through and fixed on both sides of one end of the wear-resistant flat sleeve 41, and the locking bolts are located at one end of the wear-resistant flat sleeve 41 close to the end of the lifting belt 1. The provision of the two locking bolts enables the wear-resistant flat sleeve 41 to be clamped on the wear-resistant coated strip 21, thereby reducing the possibility of the wear-resistant flat sleeve 41 moving on the wear-resistant coated strip 21. When it is necessary to adjust the position of the wear-resistant flat sleeve 41 on the wear-resistant coated strip 21 according to the length of the concrete pipe, it is only necessary to loosen the two locking bolts and slide the wear-resistant flat sleeve 41, and then tighten the locking bolts.
[0039] In the embodiment of the present application, the wear-resistant flat sleeve 41 and the wear-resistant coated strip 21 are both made of nylon. In other embodiments, the wear-resistant flat sleeve 41 and the wear-resistant coated strip 21 can also be made of polyester, polypropylene polyester fiber, or a composite material made of two or more of the above wear-resistant materials.
[0040] Reference Figure 1 and Figure 2 The connecting assembly 3 includes a connecting horizontal long bar 31, a connecting longitudinal bar 32, a main hook 33, a connecting plate 34 and two sub-hooks 35. The middle section of the connecting horizontal long bar 31 and the middle section of the connecting longitudinal bar 32 are welded, and the connecting horizontal bar and the connecting longitudinal bar 32 are perpendicular to each other. The two sub-hooks 35 are respectively fixedly connected to the two ends of the connecting horizontal long bar 31, and the two hanging parts 11 of the lifting belt 1 are respectively hung on the two sub-hooks 35.
[0041] One side edge of the connecting plate 34 is fixedly connected to both ends of the connecting horizontal long rod 31 and both ends of the connecting longitudinal rod 32 through steel cables, and a plurality of steel cables are arranged at equal intervals at the ends of the connecting plate 34 along the central axis of the connecting plate 34. The main hook 33 is fixedly connected to the middle of the other side of the connecting plate 34, and the main hook 33 is used to realize the hooking with the lifting equipment.
[0042] Compared with the two hanging parts 11 directly hanging on the hook of the starting device, the two hanging parts 11 are respectively hung on the two sub-hooks 35, which can increase the distance between the two hanging parts 11 and reduce the wrap angle between the lifting belt 1 and the end of the concrete pipe and the lifting belt 1, thereby reducing the wrap angle between the wear-resistant flat sleeve 41 and the end of the concrete pipe, and further reducing the wear of the wear-resistant flat sleeve 41 caused by friction with the end of the concrete pipe.
[0043] When the two hooking parts 11 are directly hooked to the hook of the lifting equipment for hoisting, there is only one force point, and the hoisted concrete pipe is prone to swing. By setting the connecting horizontal long rod 31 and the corresponding hook, the pulling force generated during hoisting can be dispersed into two parts, thereby reducing the swing generated during hoisting of the concrete pipe, and further reducing the wear caused by friction between the wear-resistant flat sleeve 41 and the end of the concrete pipe. By setting the connecting longitudinal rod 32 and the corresponding hook, it can be used as a safety connection.
[0044] At the same time, a reinforcing rib 36 is welded at the angle between the connecting horizontal long rod 31 and the connecting longitudinal rod 32 . The reinforcing rib 36 is triangular in shape. The provision of the reinforcing rib 36 can improve the stability of the connection between the connecting horizontal long rod 31 and the connecting longitudinal rod 32 .
[0045] The implementation principle of a concrete pipe lifting device in an embodiment of the present application is: when lifting the concrete pipe, first pass the lifting belt 1 through the concrete pipe, then hang the two hanging parts 11 on the two branch hooks 35 respectively, and then hang the hook of the lifting equipment on the main hook 33 for lifting.
[0046] In the above process, the wear-resistant coating strip 21 covers the lifting belt 1, thereby avoiding friction between the lifting belt 1 and the inner wall of the concrete pipe during lifting; the wear-resistant flat sleeve 41 covers the part of the lifting belt 1 that abuts against the end of the concrete pipe, thereby avoiding friction between the lifting belt 1 and the end of the concrete pipe during lifting. When the wear-resistant coating strip 21 and / or the wear-resistant flat sleeve 41 are damaged, they only need to be replaced, thereby protecting the lifting belt 1 and reducing the possibility of the lifting belt 1 breaking during the lifting process, thereby improving the safety during operation.
[0047] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A concrete pipe hoisting device, characterized in that: It comprises a lifting belt (1), a covering component (2) covering the lifting belt (1), and two movable abutment components (4) arranged on the covering component (2); The movable abutment assembly (4) comprises a wear-resistant flat sleeve (41) which is slidably sleeved on the covering assembly (2) and a locking member (42) which is arranged on the wear-resistant flat sleeve (41); The locking piece (42) is used to lock the position of the wear-resistant flat sleeve (41), and the wear-resistant flat sleeve (41) is used to abut against the end of the concrete pipe.
2. A concrete pipe hoisting device according to claim 1, characterized in that: The covering component (2) comprises a wear-resistant covering strip (21) covering the lifting belt (1), and the wear-resistant flat sleeve (41) sliding sleeve is arranged on the wear-resistant covering strip (21).
3. A concrete pipe hoisting device according to claim 2, characterized in that: The covering component (2) further comprises a Velcro sub-strip (22) and a Velcro mother-strip (23) respectively arranged on both sides of the wear-resistant covering strip (21) along the length direction of the wear-resistant covering strip (21); the Velcro sub-strip (22) is adhered to the Velcro mother-strip (23).
4. A concrete pipe hoisting device according to claim 2, characterized in that: The locking member (42) is selected to be two locking bolts, and the two locking bolts are respectively passed through and fixed on both sides of one end of the wear-resistant flat sleeve (41), and the two locking bolts clamp the wear-resistant flat sleeve (41) onto the wear-resistant coated strip (21).
5. A concrete pipe hoisting device according to claim 2, characterized in that: The wear-resistant coating strip (21) and the wear-resistant flat sleeve (41) are both made of nylon.
6. A concrete pipe hoisting device according to claim 4, characterized in that: It also comprises a connecting assembly (3), wherein both ends of the lifting belt (1) are respectively provided with hanging parts (11), and the two hanging parts (11) are respectively hung on the two ends of the connecting assembly (3), and the connecting assembly (3) is used to be connected to the lifting equipment.
7. A concrete pipe hoisting device according to claim 6, characterized in that: The connecting assembly (3) comprises a connecting transverse long rod (31), a main hook (33), a connecting plate (34) and two sub-hooks (35); the two sub-hooks (35) are respectively arranged at two ends of the connecting transverse long rod (31), the main hook (33) is arranged on one side of the connecting plate (34), and the two ends of the connecting transverse long rod (31) are connected to the other side of the connecting plate (34) via a steel cable.
8. A concrete pipe hoisting device according to claim 7, characterized in that: The connecting assembly (3) further comprises a connecting longitudinal rod (32), the middle section of the connecting longitudinal rod (32) and the middle section of the connecting transverse rod (31) being welded and perpendicular to each other, and a reinforcing rib (36) is provided at the connection between the connecting transverse rod (31) and the connecting longitudinal rod (32), and the two ends of the connecting longitudinal rod (32) are respectively connected by a steel cable and a connecting plate (34).