Auxiliary pouring support for extra-large-diameter pile foundation
By designing extra-large-diameter pile foundation auxiliary pouring brackets and using annular support plates and jacking devices, the problem of unstable fixation of the funnel was solved, the funnel was stably fixed and flexibly adjusted, and construction safety and efficiency were improved.
Patent Information
- Application Number
- CN202420359660.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-26
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2034-02-26
AI Technical Summary
During the construction of long-span cable tower pile foundations, the funnel was unstable, resulting in low safety and efficiency in concrete construction. It was also heavy and inconvenient for transfer and adjustment.
Design an extra-large diameter pile foundation auxiliary pouring support, including annular support plates, jacking devices and hoisting equipment. The hoisting equipment is used to fix and adjust the position of the funnel to ensure that the funnel is stable and easy to transfer.
It achieves stable fixation and flexible adjustment of the funnel, improves construction safety and efficiency, and facilitates the transfer and storage of the funnel.
Smart Images

Figure CN221822913U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of funnel brackets, in particular to an auxiliary pouring bracket for a pile foundation with a particularly large diameter. Background Art
[0002] The construction technology of extra-large diameter pile foundation concrete has the characteristics of strong adaptability, strong earthquake resistance and convenient construction, so it is widely used in extra-large bridge projects. In the actual construction process, attention should be paid to the organization and management of concrete construction and pouring operations to ensure the quality of the project. In the construction process of large-span cable tower pile foundation, the production and construction of extra-large diameter pile foundation concrete is the key part and the main factor affecting the quality, progress and project cost of pile foundation construction.
[0003] During the pouring process, using a large concrete funnel to fill concrete can reduce the use of equipment such as sky pumps, reduce production costs, and improve production efficiency. However, the fixation of the funnel is an unknown problem, because it has to carry the inflow and outflow of concrete, so if the funnel is not fixed stably, accidents are likely to occur, and the weight of the funnel is large, so it is inconvenient to transfer and adjust.
[0004] In summary, it is necessary to design a device that is convenient for fixing and supporting the funnel for concrete pouring. Utility Model Content
[0005] The utility model aims to provide an auxiliary pouring support for a pile foundation with a particularly large diameter, which can conveniently and stably fix a funnel and conveniently rotate the funnel to adjust its position.
[0006] The embodiments of the utility model are realized through the following technical scheme: the extra-large diameter pile foundation auxiliary pouring bracket of the utility model includes a frame, an annular support plate horizontally arranged at the upper end of the frame, a funnel clamped in the support plate, a plurality of first through holes opened on the support plate, and a plurality of first jacking devices arranged on the lower side of the support plate; the first through hole is arranged below the funnel; and the first jacking device is arranged at the first through hole.
[0007] Furthermore, an annular fixing plate is provided on the outer side of the upper end of the funnel, and the fixing plate is arranged above the supporting plate; and the first through hole is arranged on the lower side of the fixing plate.
[0008] Furthermore, the first lifting device includes a first sleeve disposed at the first through hole, a first push rod threadedly connected to the first sleeve, and a first ball wheel disposed at the upper end of the first push rod; the first ball wheel is disposed in the first through hole.
[0009] Furthermore, the frame body includes a base frame which is horizontally arranged and has a frame-shaped structure, and a plurality of pillars arranged on the base frame; the upper ends of the pillars are connected to the support plate.
[0010] Furthermore, connecting rods are provided between adjacent pillars.
[0011] Furthermore, it also includes a plurality of second lifting devices, which include a second through hole opened on the base frame, a second sleeve arranged on the upper side of the second through hole, a second push rod threadedly connected to the second sleeve, and a second ball wheel arranged at the lower end of the second push rod; the second ball wheel is arranged in the second through hole.
[0012] Furthermore, a plurality of hanging rings are provided on the side of the support plate.
[0013] The technical solution of the embodiment of the utility model has at least the following advantages and beneficial effects: the large diameter pile foundation auxiliary pouring support of the utility model can directly use the lifting equipment to transport the assembled frame and support plate to the construction site when in use, or can be directly assembled on site at the construction site, and then the funnel can be directly lifted to the top of the frame by using the lifting equipment, and the funnel can be fixed by inserting it into the support plate, and the concrete pouring work can be started by connecting the pipe for conveying concrete at the lower end of the funnel, and after the pouring is completed, the frame and support plate can be completely disassembled into parts for easy transfer or storage after the funnel is taken out, and the frame, support plate and funnel can also be directly transferred to the next construction site for pouring by using the lifting equipment. During the pouring process, although the pipe for conveying concrete itself can be bent, in order to minimize bending, the funnel can be slightly lifted up by the first lifting device to make it slightly away from the support plate, and then the funnel can be manually rotated so that the mouth of the lower end of the funnel is just aligned with the place where pouring is required. In this way, not only can the funnel be stably fixed through the frame and the support plate to ensure the safety of construction, but the position of the funnel can also be easily adjusted according to needs. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.
[0015] Figure 1 A schematic diagram of the structure of a large diameter pile foundation auxiliary pouring support provided by an embodiment of the utility model;
[0016] Figure 2A schematic diagram of the structure of the frame part provided by an embodiment of the utility model;
[0017] Figure 3 A schematic structural diagram of a first lifting device provided in an embodiment of the utility model;
[0018] Figure 4 A schematic structural diagram of the second lifting device provided in an embodiment of the utility model.
[0019] Icons: 11-base frame, 12-pillar, 13-support plate, 14-first sleeve, 15-first push rod, 16-first ball wheel, 17-second sleeve, 18-second push rod, 19-second ball wheel, 110-hanging ring, 111-connecting rod, 21-funnel, 22-fixing plate. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Generally, the components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.
[0021] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0023] In the description of the present invention, it should be noted that if the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the product of the application is usually placed when used. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0024] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0025] Example
[0026] The following is further described in conjunction with specific embodiments. Figure 1 -Attached Figure 4 As shown, the extra-large diameter pile foundation auxiliary pouring support of this embodiment includes a frame, an annular support plate 13 horizontally arranged at the upper end of the frame, a funnel 21 clamped in the support plate 13, a plurality of first through holes opened on the support plate 13, and a plurality of first jacking devices arranged on the lower side of the support plate 13; the first through hole is arranged below the funnel 21; and a first jacking device is arranged at a first through hole. Specifically, when in use, the assembled frame and support plate 13 can be directly transported to the construction site using a lifting device, or directly assembled on site at the construction site, and then the funnel 21 can be directly lifted to the top of the frame using a lifting device, and inserted into the support plate 13 to fix the funnel 21, and the concrete pouring work can be started by connecting the pipeline for conveying concrete at the lower end of the funnel 21, and after the pouring is completed, the frame and support plate 13 can be completely disassembled into parts for easy transfer or storage after the funnel 21 is taken out, and the frame, support plate 13 and funnel 21 can also be directly transferred to the next construction site for pouring using a lifting device. During the pouring process, although the pipeline for conveying concrete itself can be bent, in order to minimize bending, the funnel 21 can be slightly lifted up by a first lifting device, so that it is slightly away from the support plate 13, and then the funnel 21 can be manually rotated so that the mouth of the lower end of the funnel 21 is just aligned with the place where pouring is required. In this way, not only can the funnel 21 be stably fixed by the frame and the support plate 13 to ensure the safety of the construction, but also the position of the funnel 21 can be conveniently adjusted according to needs.
[0027] In this embodiment, an annular fixing plate 22 is disposed outside the upper end of the funnel 21, and the fixing plate 22 is disposed above the support plate 13; the first through hole is disposed at the lower side of the fixing plate 22. Specifically, the funnel 21 can be better fixed by the fixing plate 22.
[0028] The first lifting device in this embodiment includes a first sleeve 14 disposed at the first through hole, a first push rod 15 threadedly connected to the first sleeve 14, and a first ball wheel 16 disposed at the upper end of the first push rod 15; the first ball wheel 16 is disposed in the first through hole. Specifically, a hexagonal hole can be provided at the end of the first push rod 15 to facilitate the use of an electric wrench to screw, and by screwing the first push rod 15, the first ball wheel 16 can be pushed upward, thereby lifting the funnel 21, and due to the support of the first ball wheel 16, the rotation of the funnel 21 is also very easy, and the funnel 21 can be rotated by only manually pushing it, and no additional structure is required in the whole process.
[0029] The frame in this embodiment includes a base frame 11 which is horizontally arranged and has a frame-shaped structure, and a plurality of pillars 12 arranged on the base frame 11; the upper ends of the pillars 12 are connected to the support plates 13. A connecting rod 111 is provided between adjacent pillars 12. It also includes a plurality of second lifting devices, which include a second through hole opened on the base frame 11, a second sleeve 17 provided on the upper side of the second through hole, a second push rod 18 threadedly connected to the second sleeve 17, and a second ball wheel 19 provided at the lower end of the second push rod 18; the second ball wheel 19 is provided in the second through hole. Specifically, the structure and principle of the second lifting mechanism are basically the same as those of the first lifting mechanism. The function of the second lifting mechanism is to lift up the frame and the funnel 21 to facilitate small-range position movement.
[0030] The side of the support plate 13 in this embodiment is provided with a plurality of hanging rings 110. Specifically, the hanging rings 110 are mainly used to connect with the hoisting equipment.
[0031] In summary, the extra-large diameter pile foundation auxiliary pouring support of this embodiment can directly use the lifting equipment to transport the assembled frame and support plate 13 to the construction site when in use, or can directly assemble on site at the construction site, and then use the lifting equipment to directly lift the funnel 21 above the frame, and insert it into the support plate 13 to fix the funnel 21, and connect the pipe for conveying concrete at the lower end of the funnel 21 to start the concrete pouring work, after the pouring is completed, the funnel 21 can be taken out and the frame and support plate 13 can be completely disassembled into parts for easy transfer or storage, or the frame, support plate 13 and funnel 21 can be directly transferred to the next construction site for pouring by using the lifting equipment. During the pouring process, although the pipe for conveying concrete itself can be bent, in order to minimize bending, the funnel 21 can be slightly lifted up by the first lifting device, so that it is slightly away from the support plate 13, and then the funnel 21 can be manually rotated so that the mouth of the lower end of the funnel 21 is just aligned with the place where pouring is required. In this way, not only can the funnel 21 be stably fixed by the frame and the support plate 13 to ensure the safety of the construction, but also the position of the funnel 21 can be conveniently adjusted according to needs.
[0032] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may be subject to various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. An auxiliary pouring support for a large diameter pile foundation, characterized in that: It comprises a frame, an annular support plate (13) horizontally arranged at the upper end of the frame, a funnel (21) clamped in the support plate (13), a plurality of first through holes opened on the support plate (13), and a plurality of first lifting devices arranged on the lower side of the support plate (13); The first through hole is arranged below the funnel (21); and the first lifting device is arranged at the first through hole.
2. The large diameter pile foundation auxiliary pouring support according to claim 1 is characterized in that: An annular fixing plate (22) is provided on the outer side of the upper end of the funnel (21), and the fixing plate (22) is arranged above the supporting plate (13); The first through hole is arranged on the lower side of the fixing plate (22).
3. The large diameter pile foundation auxiliary pouring support according to claim 1 is characterized in that: The first lifting device comprises a first sleeve (14) arranged at the first through hole, a first push rod (15) threadedly connected to the first sleeve (14), and a first ball wheel (16) arranged at the upper end of the first push rod (15); the first ball wheel (16) is arranged in the first through hole.
4. The large diameter pile foundation auxiliary pouring support according to claim 1 is characterized in that: The frame body comprises a horizontally arranged frame-shaped bottom frame (11), and a plurality of pillars (12) arranged on the bottom frame (11); the upper ends of the pillars (12) are connected to the support plate (13).
5. The large diameter pile foundation auxiliary pouring support according to claim 4, characterized in that: A connecting rod (111) is provided between adjacent pillars (12).
6. The large diameter pile foundation auxiliary pouring support according to claim 4, characterized in that: It also includes a plurality of second lifting devices, wherein the second lifting devices include a second through hole opened on the base frame (11), a second sleeve (17) arranged on the upper side of the second through hole, a second push rod (18) threadedly connected to the second sleeve (17), and a second ball wheel (19) arranged at the lower end of the second push rod (18); the second ball wheel (19) is arranged in the second through hole.
7. The large diameter pile foundation auxiliary pouring support according to claim 1, characterized in that: The side of the support plate (13) is provided with a plurality of hanging rings (110).