Power construction guardrail

By designing an adjustable electric construction guardrail structure, including fixed columns, movable collars, support rods and shrinking rods, the problems of installation stability and height adjustment of existing guardrails in different environments are solved, and flexibility in electric power construction is achieved. Usage and safety requirements.

CN221823533UActive Publication Date: 2024-10-11YUNNAN YAODA ELECTRIC POWER ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323418942.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-14
Publication Date
2024-10-11
Estimated Expiration
2033-12-14

AI Technical Summary

Technical Problem

Existing electric construction guardrails are difficult to use in different construction environments, especially when installed on unhardened soil, they have poor stability and have a fixed height, making it difficult to flexibly adjust to meet construction safety needs.

Method used

An electric construction guardrail is designed that includes a fixed column, a movable collar, a support rod and a shrink rod. The guardrail is stably fixed through the mutual cooperation of the support rod and the shrink rod, and through sliding connections and adjustable vertical and horizontal bars. structure, the height of the guardrail can be changed.

Benefits of technology

It achieves stable installation and highly flexible adjustment in different environments, and is suitable for a wider range of power construction environments to ensure construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221823533U_ABST
    Figure CN221823533U_ABST
Patent Text Reader

Abstract

The utility model discloses an electric power construction guardrail, and particularly relates to the technical field of electric power installation equipment, the electric power construction guardrail comprises two first fixing columns which are symmetrically distributed, the lower parts of the first fixing columns are slidably sleeved with movable lantern rings, the lower parts of the movable lantern rings are fixedly provided with four groups of first fixing plates which are distributed in an array; a first fixing shaft is fixedly installed on the opposite side of the first fixing plate, the stability of the building is controlled by arranging a supporting rod and a telescopic rod, a movable lantern ring is pushed downwards to open the supporting rod under the mutual cooperation of the supporting rod and the telescopic rod, the supporting rod is fixed through a first fixing plug pin, and the supporting rod can be stably placed on the ground; and the supporting rods can be opened and then inserted into the soil to fix the first fixing columns, so that the construction guardrail is fixed, the construction guardrail can be normally used when the construction guardrail meets the soil ground due to uneven ground or soft ground soil, and the construction guardrail can be applied to wider construction environments.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of electric power installation equipment, in particular to an electric power construction guardrail. Background Art

[0002] The power construction guardrail is a safety fence that needs to be set up during power construction. It is to maintain a sufficient safe distance between people and power equipment during power construction. In the process of power construction, there will be many different construction environments, and the existing construction guardrails most of the time cannot meet the requirements of use in a variety of different environments. For example, when installing construction guardrails on unhardened mud ground, it is difficult to install and set up existing construction guardrails in this situation, and there may be a situation where the terrain is high on one side and low on the other side. The height of existing guardrails is mostly fixed, and it is difficult to flexibly change their height in different environments to meet the safety needs of power construction. For this reason, we propose a power construction guardrail to solve the above problems. Utility Model Content

[0003] The purpose of the utility model is to provide a power construction guardrail to solve the problems raised in the above background technology.

[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a power construction guardrail, comprising a first fixed column, wherein the first fixed column is provided with two symmetrically distributed columns, a lower sliding sleeve of the first fixed column is provided with a movable collar, four groups of first fixed plates distributed in an array are fixedly installed on the lower part of the movable collar, a first fixed shaft is fixedly installed on the opposite side of the first fixed plate, an outer rotation sleeve of the first fixed shaft is provided with a support rod distributed in an array, a second fixed shaft is fixedly installed on the middle part of one side of the support rod, a contraction rod is rotatably installed on the outer side of the second fixed shaft, a second fixed plate is fixedly installed on the side of the second fixed shaft away from the support rod, a fixed collar is fixedly installed on the outer bottom of the first fixed column, four groups of third fixed plates corresponding to the contraction rods are fixedly installed on the outer surface of the fixed collar, a third fixed shaft is fixedly installed on the opposite side of the third fixed plate, and one end of the contraction rod away from the second fixed shaft is rotatably installed on the outside of the corresponding third fixed shaft, a plurality of second vertical rods distributed in an array are provided between the two first fixed columns, and second cross rods distributed at equal intervals are fixedly installed in the middle of the plurality of second vertical rods.

[0005] Preferably, the upper part of the first fixed column is slidably connected to the second fixed column, the top of the second fixed column is fixedly installed with a column cap, a plurality of first vertical rods corresponding to the second vertical rods are provided between the two second fixed columns, a first cross rod is fixedly installed on the upper parts of the plurality of first vertical rods, and the lower part of the first vertical rod is movably sleeved inside the top of the second vertical rod.

[0006] Preferably, a No. 1 base is fixedly installed inside the first fixed column, a No. 1 spring is fixedly installed on one side of the No. 1 base, a No. 1 fixed pin is fixedly installed on the side of the No. 1 spring away from the No. 1 base, and a side of the No. 1 fixed pin away from the No. 1 spring is movably clamped on the bottom of the first fixed column.

[0007] Preferably, a No. 2 base is fixedly installed inside the second fixing column, a No. 2 spring is fixedly installed on one side of the No. 2 base, and a No. 2 fixing pin is fixedly installed on one end of the No. 2 spring away from the No. 2 base.

[0008] Preferably, a No. 1 clamping hole for use with a No. 1 fixing pin is provided on one side of the movable ring.

[0009] Preferably, a plurality of evenly distributed No. 2 clamping holes for use with No. 2 fixing pins are provided on one side of the upper portion of the first fixing column.

[0010] Preferably, second fixing hooks distributed in an array are fixedly installed on the upper and lower ends of the first fixing column, second fixing blocks distributed symmetrically are fixedly installed on both ends of the second vertical rod, a second fixing ring is fixedly installed on the side of the second fixing block away from the second vertical rod, and the second fixing ring is movably installed on the outside of the corresponding second fixing hook.

[0011] Preferably, a first fixing hook distributed in an array is fixedly installed on the upper end of the second fixing column, a first fixing block is fixedly installed on the upper end of the first vertical rod, a first fixing ring is fixedly installed on the side of the first fixing block away from the first vertical rod, and the first fixing ring is movably installed on the outside of the corresponding first fixing hook.

[0012] Compared with the prior art, the beneficial effects of the present invention are:

[0013] 1. Control the stability of the structure by setting the support rod and the retractable rod. Push the movable ring downward to open the support rod under the cooperation of the support rod and the retractable rod, and fix it with the No. 1 fixing pin. You can put it stably on the ground, or you can open the support rod and insert it into the soil to fix the first fixing column, thereby fixing the construction guardrail. When encountering a muddy ground due to uneven ground or soft soil, it can be used normally, so that it can be applied to a wider range of power construction environments.

[0014] 2. By setting the first fixed column and the second fixed column in sliding connection, press the No. 2 fixed pin, lift the second fixed column upward, and lift the vertical rod and the horizontal rod upward under the cooperation of the first fixed hook, the first fixed ring and the first fixed block to reach the specified height, align the No. 2 fixed pin with the corresponding No. 2 card hole, and the No. 2 fixed pin pops out to fix the second fixed column, so that the height can be freely changed when the height of the construction guardrail needs to be increased to achieve the target height. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0016] Figure 1 It is a schematic diagram of the structure of the utility model.

[0017] Figure 2 It is a schematic diagram of the structural connection between the support rod and the retractable rod of the utility model.

[0018] Figure 3 For this utility model Figure 2 Enlarged view of point A in the middle.

[0019] Figure 4 It is a schematic diagram of the cross-sectional structure of the utility model.

[0020] Figure 5 For this utility model Figure 4 Enlarged view of point B in the middle.

[0021] Figure 6 It is a schematic diagram of the partial cross-section structure of the utility model.

[0022] Figure 7 For this utility model Figure 6 Enlarged view of point C in the middle.

[0023] Figure 8 For this utility model Figure 6 Enlarged view of point D in the middle.

[0024] In the figure: 1. first fixed column; 11. No. 1 base; 12. No. 1 spring; 13. No. 1 fixed pin; 14. No. 2 clamping hole; 15. second fixed hook; 2. movable ring; 21. first fixed plate; 211. first fixed axis; 22. No. 1 clamping hole; 3. support rod; 31. second fixed plate; 311. second fixed axis; 4. retractable rod; 5. fixed ring; 51. third fixed plate; 511. third fixed axis; 6. second fixed column; 61. column cap; 62. No. 2 base; 63. No. 2 spring; 64. No. 2 fixed pin; 65. first fixed hook; 7. first vertical rod; 71. first horizontal rod; 72. first fixed block; 73. first fixed ring; 8. second vertical rod; 81. second horizontal rod; 82. second fixed block; 83. second fixed ring. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0026] Example: Figure 1-8 As shown, the utility model provides a power construction guardrail, including a first fixed column 1, the first fixed column 1 is provided with two symmetrically distributed, the lower part of the first fixed column 1 is slidably sleeved with a movable ring 2, the lower part of the movable ring 2 is fixedly installed with four groups of first fixed plates 21 distributed in an array, the opposite side of the first fixed plate 21 is fixedly installed with a first fixed shaft 211, the outer rotation sleeve of the first fixed shaft 211 is provided with a support rod 3 distributed in an array, the first fixed shaft 211 can drive the support rod 3 to move up and down with the movable ring 2 by setting the first fixed shaft 211, and the support rod 3 can rotate on the outer side of the first fixed shaft 211, a second fixed shaft 311 is fixedly installed in the middle part of one side of the support rod 3, and a retractable rod 4 is rotatably installed on the outer side of the second fixed shaft 311, and the retractable rod 4 is arranged to make the support rod 3 open obliquely downward under the mutual influence of the movable ring 2 and the support rod 3 by setting the retractable rod 4, and the second fixed shaft 311 is fixed on the side away from the support rod 3. A second fixing plate 31 is fixedly installed, and the end of the retracting rod 4 close to the support rod 3 is rotatably installed on the support rod 3 by setting the second fixing shaft 311 and the second fixing plate 31. A fixing ring 5 is fixedly installed on the outer bottom of the first fixing column 1, and four groups of third fixing plates 51 corresponding to the retracting rod 4 are fixedly installed on the outer surface of the fixing ring 5. The opposite side of the third fixing plate 51 is fixedly installed with a third fixing shaft 511, and the end of the retracting rod 4 away from the support rod 3 is rotatably installed on the fixing ring 5 by setting the third fixing plate 51 and the third fixing shaft 511. The end of the retracting rod 4 away from the second fixing shaft 311 is rotatably installed on the outside of the corresponding third fixing shaft 511. A plurality of second vertical rods 8 distributed in an array are provided between the two first fixing columns 1, and second cross rods 81 distributed at equal intervals are fixedly installed in the middle of the plurality of second vertical rods 8. The second vertical rods 8 can be connected to form a whole by setting the second cross rod 81.

[0027] The upper part of the first fixed column 1 is slidably connected to the second fixed column 6, and the top of the second fixed column 6 is fixedly installed with a column cap 61. A plurality of first vertical rods 7 corresponding to the second vertical rod 8 are provided between the two second fixed columns 6, and a first cross rod 71 is fixedly installed on the upper part of the plurality of first vertical rods 7. By setting the first cross rod 71, the first vertical rods 7 can be connected into a whole. The lower part of the first vertical rod 7 is movably sleeved inside the top of the second vertical rod 8. By setting the second fixed column 6, the first vertical rod 7 and the first cross rod 71, the height of the construction guardrail can be freely adjusted.

[0028] A No. 1 base 11 is fixedly installed inside the first fixed column 1, and a No. 1 spring 12 is fixedly installed on one side of the No. 1 base 11. By setting the No. 1 base 11, one end of the No. 1 spring 12 can be fixed, and a No. 1 fixing pin 13 is fixedly installed on the side of the No. 1 spring 12 away from the No. 1 base 11. The side of the No. 1 fixing pin 13 away from the No. 1 spring 12 is movably connected to the bottom of the first fixed column 1. By setting the No. 1 spring 12, the No. 1 fixing pin 13 can be immediately popped out when it reaches the corresponding position.

[0029] A No. 2 base 62 is fixedly installed inside the second fixed column 6, and a No. 2 spring 63 is fixedly installed on one side of the No. 2 base 62. By setting the No. 2 base 62, one end of the No. 2 spring 63 can be fixed, and a No. 2 fixing pin 64 is fixedly installed on the end of the No. 2 spring 63 away from the No. 2 base 62. By setting the No. 2 spring 63, the No. 2 fixing pin 64 can be immediately popped out when it reaches the corresponding position.

[0030] A No. 1 clamping hole 22 used in conjunction with the No. 1 fixing pin 13 is provided on one side of the movable collar 2. By providing the No. 1 clamping hole 22, the No. 1 fixing pin 13 pops out through the No. 1 clamping hole 22 to fix the movable collar 2 after reaching the corresponding position.

[0031] A plurality of evenly distributed No. 2 clamping holes 14 for use with the No. 2 fixing pin 64 are provided on one side of the upper portion of the first fixing column 1. By providing the No. 2 clamping holes 14, after the second fixing column 6 is pulled to the corresponding position, the No. 2 fixing pin 64 pops out through the No. 2 clamping holes 14 to fix the second fixing column 6.

[0032] The upper and lower ends of the first fixed column 1 are respectively fixedly installed with array-distributed second fixing hooks 15, and the two ends of the second vertical rod 8 are fixedly installed with symmetrically distributed second fixing blocks 82. The second fixing block 82 is fixedly installed with a second fixing ring 83 on the side away from the second vertical rod 8. The second fixing ring 83 is movably installed on the outside of the corresponding second fixing hook 15. By arranging the second fixing hook 15, the second fixing block 82 and the second fixing ring 83, the second vertical rod 8 and the first fixed column 1 are movably installed together.

[0033] The upper end of the second fixing column 6 is fixedly installed with an array-distributed first fixing hook 65, the upper end of the first vertical rod 7 is fixedly installed with a first fixing block 72, the first fixing block 72 is fixedly installed with a first fixing ring 73 on the side away from the first vertical rod 7, and the first fixing ring 73 is movably installed on the outer side of the corresponding first fixing hook 65. By arranging the first fixing hook 65, the first fixing block 72 and the first fixing ring 73, the first vertical rod 7 and the second fixing column 6 are movably installed together.

[0034] Working principle: when it is necessary to use the electric construction guardrail, push the movable collar 2 downward to drive the support rod 3 to move downward, and the support rod 3 is opened due to the cooperation between the retracting rod 4 and the support rod 3. When the most suitable opening and closing angle is reached, the movable collar 2 encounters the No. 1 fixed pin 13 and is squeezed inward. When the No. 1 fixed pin 13 encounters the No. 1 clamping hole 22, the No. 1 fixed pin 13 is ejected under the reaction force of the No. 1 spring 12, and the movable collar 2 is clamped. At this time, the support rod 3 is fully opened and fixed, and can be placed vertically on the ground. When encountering a soft geological environment, the support rod 3 can be inserted into the ground to ensure the overall firmness. When retracting, press the No. 1 fixed pin 13, and pull the movable collar 2 upward until the support rod 3 is completely retracted. There is a second fixing hook 15 on the side of the first fixed column 1, and the second fixing ring 83 can be set on the second fixing hook 15 to complete the connection between the second vertical rod 8, the second cross bar 81 and the first fixed column 1;

[0035] When the height does not meet the requirement, you can press the No. 2 fixing pin 64 to pull the second fixing column 6 upwards so that its height meets the requirement, then align the No. 2 fixing pin 64 with the corresponding No. 2 clamping hole 14, and the No. 2 fixing pin 64 pops out under the reaction force of the No. 2 spring 63 to clamp the second fixing column 6. There is a first fixing hook 65 on the side of the second fixing column 6, and the first fixing ring 73 can be sleeved on the first fixing hook 65 to complete the connection between the first vertical rod 7, the first cross bar 71 and the second fixing column 6. When the second fixing column 6 is lifted, the first vertical rod 7 and the first cross bar 71 are driven to slide upwards under the cooperation of the first fixing hook 65, the first fixing ring 73 and the first fixing block 72.

[0036] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A power construction guardrail, comprising a first fixing column (1), Features: The first fixing column (1) is provided with two symmetrically distributed ones, the lower part of the first fixing column (1) is slidably sleeved with a movable collar (2), the lower part of the movable collar (2) is fixedly installed with four groups of first fixing plates (21) distributed in an array, the opposite side of the first fixing plate (21) is fixedly installed with a first fixing shaft (211), the outer part of the first fixing shaft (211) is rotatably sleeved with a supporting rod (3) distributed in an array, a second fixing shaft (311) is fixedly installed in the middle part of one side of the supporting rod (3), a retracting rod (4) is rotatably installed on the outer part of the second fixing shaft (311), and the second fixing shaft (311) is on the side away from the supporting rod (3). A second fixing plate (31) is fixedly installed, a fixing ring (5) is fixedly installed on the outer bottom of the first fixing column (1), four groups of third fixing plates (51) corresponding to the retractable rod (4) are fixedly installed on the outer surface of the fixing ring (5), a third fixing shaft (511) is fixedly installed on the opposite side of the third fixing plate (51), one end of the retractable rod (4) away from the second fixing shaft (311) is rotatably installed on the outside of the corresponding third fixing shaft (511), a plurality of second vertical rods (8) distributed in an array are arranged between the two first fixing columns (1), and second horizontal rods (81) distributed at equal intervals are fixedly installed in the middle of the plurality of second vertical rods (8).

2. The electric power construction guardrail according to claim 1, Features: The upper part of the first fixed column (1) is slidably connected to the second fixed column (6), the top end of the second fixed column (6) is fixedly mounted with a column cap (61), a plurality of first vertical rods (7) corresponding to the second vertical rod (8) are arranged between the two second fixed columns (6), a first cross rod (71) is fixedly mounted on the upper parts of the plurality of first vertical rods (7), and the lower part of the first vertical rod (7) is movably sleeved inside the top end of the second vertical rod (8).

3. The electric power construction guardrail according to claim 1, Features: A No. 1 base (11) is fixedly mounted inside the first fixed column (1), a No. 1 spring (12) is fixedly mounted on one side of the No. 1 base (11), a No. 1 fixed latch (13) is fixedly mounted on a side of the No. 1 spring (12) away from the No. 1 base (11), and a side of the No. 1 fixed latch (13) away from the No. 1 spring (12) is movably clamped on the bottom of the first fixed column (1).

4. The electric power construction guardrail according to claim 2, Features: A No. 2 base (62) is fixedly mounted inside the second fixed column (6), a No. 2 spring (63) is fixedly mounted on one side of the No. 2 base (62), and a No. 2 fixing pin (64) is fixedly mounted on one end of the No. 2 spring (63) away from the No. 2 base (62).

5. The electric power construction guardrail according to claim 1, Features: A No. 1 clamping hole (22) for use with a No. 1 fixing pin (13) is provided on one side of the movable sleeve ring (2).

6. The electric power construction guardrail according to claim 1, Features: A plurality of evenly distributed No. 2 clamping holes (14) for use with No. 2 fixing pins (64) are provided on one side of the upper portion of the first fixing column (1).

7. The electric power construction guardrail according to claim 1, Features: The upper and lower ends of the first fixing column (1) are respectively fixedly mounted with second fixing hooks (15) distributed in an array, the two ends of the second vertical rod (8) are fixedly mounted with second fixing blocks (82) distributed symmetrically, a second fixing ring (83) is fixedly mounted on a side of the second fixing block (82) away from the second vertical rod (8), and the second fixing ring (83) is movably mounted on the outer side of the corresponding second fixing hook (15).

8. The electric power construction guardrail according to claim 2, Features: The upper end of the second fixing column (6) is fixedly mounted with a first fixing hook (65) distributed in an array, the upper end of the first vertical rod (7) is fixedly mounted with a first fixing block (72), a side of the first fixing block (72) away from the first vertical rod (7) is fixedly mounted with a first fixing ring (73), and the first fixing ring (73) is movably mounted on the outer side of the corresponding first fixing hook (65).