Ore pulp preparation accident treatment pond

By setting up an auxiliary tank and a filter plate in the slurry accident treatment tank, combined with the slope cleaning structure, the problems of difficulty in cleaning and serious equipment wear in the existing technology are solved, and efficient separation and cleaning of coarse aggregate and tailings are achieved, reducing costs. Labor intensity and equipment wear and tear.

CN221831738UActive Publication Date: 2024-10-15KUNMING ENG & RES INST OF NONFERROUS METALLURGY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420198387.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-27
Publication Date
2024-10-15
Estimated Expiration
2034-01-27

AI Technical Summary

Technical Problem

The existing slurry accident treatment pool has problems such as difficulty in cleaning, unstable concentration of reconstituted slurry, severe equipment wear, and high labor intensity. In particular, high-pressure water re-slurrying after mortar precipitation and hardening causes processing difficulties, and the limited operating space affects the equipment. Use and personnel operations.

Method used

Design a slurry preparation accident treatment pool, including a main pool below ground elevation and a connected auxiliary pool. The main pool is equipped with a filter plate and a slope. The auxiliary pool is equipped with a pump. After filtering through the filter plate, the sand-containing water enters the auxiliary pool. Pumped out, the deposited sand and coarse aggregate are cleaned through the slope to achieve separation of coarse aggregate, tailings and water, reducing equipment losses and human resource requirements.

Benefits of technology

It improves the cleaning efficiency, reduces equipment loss and human resource consumption, achieves efficient separation and cleaning of coarse aggregate and tailings, and simplifies the slurry accident handling process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221831738U_ABST
    Figure CN221831738U_ABST
Patent Text Reader

Abstract

The utility model provides an ore pulp preparation accident treatment pond which comprises a main pond arranged below a ground elevation, and is characterized in that an auxiliary pond communicated with the main pond is arranged beside the main pond, a filter plate is arranged at the joint of the auxiliary pond and the main pond, a pump is arranged in the auxiliary pond, and a slope for connecting the pond bottom and the ground is arranged in the main pond. Dry and wet separation of coarse aggregate, tailings and water is achieved by arranging the auxiliary pool and the filter plate beside the main pool, separated sand-containing water is pumped out of the auxiliary pool, accumulated sand and the coarse aggregate in the main pool enter and exit from a slope through mechanical equipment to be cleaned, the cleaning efficiency is improved, meanwhile, equipment loss is reduced, and manpower resources are saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a processing pool, in particular to a slurry preparation accident processing pool, belonging to the technical field of metallurgy. Background Art

[0002] In the preparation of ore pulp, the prepared slurry often overflows and leaks due to various production accidents. Therefore, a slurry preparation accident pool is generally set up during the preparation of ore pulp to timely collect various types of slurries that overflow or cannot be discharged in time. The slurry accident pool in the prior art is usually set below the ground elevation. When a certain amount of slurry is collected, it is necessary to use a slurry pump or a submersible sewage pump to send it to the treatment pool. If the mortar is precipitated and hardened, it is necessary to use high-pressure water to re-slurry. This cleaning method has problems such as difficulty in the later discharge and treatment of mortar, unstable concentration of regenerated slurry, and large wear of slurry pumps or submersible sewage pumps. In addition, after the mortar is pumped, the coarse aggregate left in the treatment pool needs to be manually cleaned. This not only increases the labor intensity of workers and reduces the cleaning efficiency, but also the limited working space is not conducive to the use of equipment and personnel operation. Therefore, it is necessary to improve the existing technology. Summary of the invention

[0003] In order to solve the problems of existing slurry accident treatment pools, such as difficulty in cleaning, unstable concentration of regenerated slurry, serious equipment loss, high labor intensity, time and labor consumption, the utility model provides a slurry preparation accident treatment pool.

[0004] The utility model is completed through the following technical scheme: a slurry preparation accident treatment pool, including a main pool arranged below the ground elevation, characterized in that a secondary pool connected to the main pool is arranged beside the main pool, a filter plate is arranged at the connection between the secondary pool and the main pool, a pump is arranged in the secondary pool, and a slope connecting the pool bottom and the ground is arranged in the main pool, so that the slurry discharged into the main pool is filtered by the filter plate, so that the sand-containing water enters the secondary pool and is pumped out of the secondary pool, and the accumulated sand and coarse aggregate deposited in the main pool are cleaned and sent out by engineering equipment entering the pool bottom through the slope, so that the dry and wet separation of coarse aggregate, tailings and water is achieved, and efficient cleaning is completed, equipment loss is reduced, and human resources are saved.

[0005] The main pool is configured as an open rectangular pool, the length, width and depth of which are set as required. An input port is provided on the side wall of one side of the main pool, and the input port is connected to the accident sludge discharge ditch so that the slurry discharged due to the accident can be collected through the main pool.

[0006] The slope is arranged between the bottom of the main pool and the ground, the slope angle is set to 10° to 25°, a step walkway is arranged in the center of the slope, the slopes on both sides of the step walkway are set as driveways, and the top surface height of the step walkway is lower than the slope surface height, so that mechanical equipment can enter and exit the main pool from the ground through the slope to clean up accumulated sand and coarse aggregate.

[0007] The auxiliary pool is configured as a rectangular pool with an open top, whose width and length are smaller than those of the main pool, and whose depth is greater than that of the main pool. A pump is disposed at the bottom of the auxiliary pool, which is connected to the outside through a sewage pipe so that the sand-containing water in the main pool can flow smoothly into the auxiliary pool through the auxiliary pool which is deeper than the main pool, thereby facilitating mechanical equipment to clean the accumulated sand and coarse aggregate in the main pool.

[0008] The pump is configured as a slurry pump or a submersible sewage pump.

[0009] A connection port is provided between the main pool and the auxiliary pool, and the connection port is provided on the pool wall between the main pool and the auxiliary pool. Vertical slots are provided on both sides of the connection port. The corresponding two sides of the filter plate are inserted into the vertical slots on both sides of the connection port. A plurality of water-permeable holes are provided on the filter plate so that coarse aggregate and tailings can be separated from water through the filter plate.

[0010] The utility model has the following advantages and effects: by adopting the above scheme, a secondary pool and a filter plate are arranged next to the main pool to realize the dry and wet separation of coarse aggregate, tailings and water; the separated sand-containing water is pumped out of the secondary pool; the accumulated sand and coarse aggregate in the main pool are cleaned by mechanical equipment entering and exiting from the slope, thereby improving the cleaning efficiency, reducing equipment loss and saving human resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a top view of the utility model;

[0012] Figure 2 for Figure 1 AA view;

[0013] Figure 3 for Figure 1 BB view. DETAILED DESCRIPTION

[0014] The following will be combined with the drawings in the embodiments to clearly and completely describe the technical solution of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on this embodiment, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model. Example

[0015] The slurry preparation accident treatment pool provided by the utility model comprises a main pool 1 arranged below the ground elevation, a secondary pool 5 connected to the main pool 1 is arranged beside the main pool 1, a filter plate 10 is arranged at the connection between the secondary pool 5 and the main pool 1, a pump 6 is arranged in the secondary pool 5, and a slope 9 connecting the pool bottom and the ground is arranged in the main pool 1, so that the slurry discharged into the main pool 1 is filtered by the filter plate 10, so that the sand-containing water enters the secondary pool 5, and is sent out of the secondary pool 5 through the pump 6, and the accumulated sand and coarse aggregate deposited in the main pool 1 are cleaned and sent out through the engineering equipment entering the pool bottom through the slope 9, so that the dry and wet separation of coarse aggregate, tailings and water is achieved, and efficient cleaning is completed, equipment loss is reduced, and human resources are saved;

[0016] The main pool 1 is a rectangular pool with an open top, and its length, width and depth are set as required. An input port 3 is provided on the side wall of one side of the main pool 1, and the input port 3 is connected to the accident sludge discharge ditch 2, so as to collect the slurry discharged due to the accident through the main pool 1;

[0017] The slope 9 is arranged between the bottom of the main pool 1 and the ground, and the slope angle is set to 10° to 25°. A step walkway 8 is arranged in the center of the slope 9, and the slopes on both sides of the step walkway 8 are set as vehicle lanes, and the top surface height of the step walkway 8 is lower than the slope surface height of the slope 9, so that engineering equipment can enter the main pool 1 from the ground through the slope 9 to clean up the accumulated sand and coarse aggregate;

[0018] The auxiliary pool 5 is set as a rectangular pool with an open top, whose width and length are smaller than those of the main pool 1, and whose depth is greater than that of the main pool 1. A pump 6 is set at the bottom of the auxiliary pool 5, and is connected to the outside through a sewage pipe 7, so that the sand-containing water in the main pool 1 can be filtered through the filter plate 10 through the auxiliary pool 5 which is deeper than the main pool 1, and then smoothly flow into the auxiliary pool 5, thereby completing the dry and wet separation, and facilitating the engineering equipment to clean the accumulated sand and coarse aggregate in the main pool 1;

[0019] Pump 6 is set as a slurry pump or a submersible sewage pump;

[0020] A connection port 4 is provided between the main pool 1 and the auxiliary pool 5. The connection port 4 is provided on the pool wall between the main pool 1 and the auxiliary pool 5. Vertical slots 11 are provided on both sides of the connection port 4. The corresponding two sides of the filter plate 10 are inserted into the vertical slots 11 on both sides of the connection port 4. A plurality of water-permeable holes are provided on the filter plate 10 so that coarse aggregate, tailings and water can be filtered and separated through the filter plate 10.

[0021] The engineering equipment is conventional excavators and forklifts.

[0022] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0023] The preferred embodiments of the utility model disclosed above are only used to help explain the utility model. The preferred embodiments do not describe all the details in detail, nor do they limit the utility model to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the utility model, so that technicians in the relevant technical field can well understand and use the utility model. The utility model is limited only by the claims and their full scope and equivalents.

Claims

1. A slurry preparation accident treatment pool, comprising a main pool located below ground level, characterized in that A secondary pool connected to the main pool is arranged beside the main pool, a filter plate is arranged at the connection between the secondary pool and the main pool, a pump is arranged in the secondary pool, and a slope connecting the pool bottom and the ground is arranged in the main pool.

2. The slurry preparation accident treatment pool according to claim 1, characterized in that The main pool is configured as a rectangular pool with an open top, and its length, width and depth are set as required. An input port is provided on the side wall of one side of the main pool, and the input port is connected to the accident sludge discharge ditch.

3. The slurry preparation accident treatment pool according to claim 1, characterized in that The slope is arranged between the bottom of the main pool and the ground, the slope angle is set to 10° to 25°, a step walkway is arranged in the center of the slope, the slopes on both sides of the step walkway are set as vehicle lanes, and the top surface height of the step walkway is lower than the slope surface height.

4. The slurry preparation accident treatment pool according to claim 1, characterized in that The auxiliary pool is configured as a rectangular pool with an open top, whose width and length are smaller than those of the main pool, and whose depth is greater than that of the main pool. A pump is disposed at the bottom of the auxiliary pool, and is connected to the outside world through a sewage pipe.

5. The slurry preparation accident treatment pool according to claim 1, characterized in that The pump is configured as a slurry pump or a submersible sewage pump.

6. The slurry preparation accident treatment pool according to claim 1, characterized in that A connection port is provided between the main pool and the auxiliary pool, and the connection port is provided on the pool wall between the main pool and the auxiliary pool. Vertical slots are provided on both sides of the connection port. The corresponding two sides of the filter plate are inserted into the vertical slots on both sides of the connection port, and the filter plate is provided with a plurality of water-permeable holes.