Efficient drainage prefabricated box girder

By setting drainage outlets and air inlets on the prefabricated box beams, the negative pressure when the train is running is used to take away water droplets and gravel, which solves the problem of weakened ballast drainage effect, achieves efficient drainage and convenient maintenance, and improves the traffic of the bridge. Security.

CN221837393UActive Publication Date: 2024-10-15FUJIAN JIETONG CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420366285.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-28
Publication Date
2024-10-15
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

After the existing low-speed railway bridges are erected, the drainage effect of the ballast weakens over time, and replacing the ballast is labor-intensive, affecting the safety and traffic efficiency of the bridge.

Method used

A high-efficiency drainage prefabricated box girder is designed. The bridge body is provided with a drainage outlet connected from top to bottom and an air inlet facing the ballast. The negative pressure generated when the train is running is used to take away water droplets and gravel and pass them through the air guide trough. and permeable panels to enhance drainage.

Benefits of technology

It effectively improves the drainage efficiency of the bridge, reduces the accumulation of gravel at the bottom of the ballast, and improves the traffic safety and maintenance convenience of the bridge.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221837393U_ABST
    Figure CN221837393U_ABST
Patent Text Reader

Abstract

The utility model discloses an efficient drainage prefabricated box girder, which belongs to the technical field of prefabricated box girders and comprises a bridge body, a roadbed surface on which railway ballasts can be laid is arranged on the bridge body, a plurality of drainage ports communicated with the roadbed surface and the outside of the bridge body from top to bottom are formed in the bridge body, a plurality of air inlets facing the railway ballasts are respectively formed in two sides of the railway ballasts, and the air inlets are formed in two sides of the bridge body. And the air inlet obliquely faces the railway ballast from bottom to top. According to the efficient drainage prefabricated box girder, negative pressure generated in the rapid running process of a train is utilized, air rapidly flowing towards railway ballasts is generated from the air inlet, water drops in gaps are taken away through high-speed air flow, and gravel in the gaps is blown away; therefore, the situation that the drainage effect of the railway ballast is rapidly reduced due to the fact that gravel is continuously stacked at the bottom of the railway ballast is effectively relieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabricated box girders, in particular to a high-efficiency drainage prefabricated box girder. Background Art

[0002] A prefabricated box girder is a prefabricated bridge component that is cast on the ground using a mold and then mechanically lifted onto the bridge pier.

[0003] After the existing low-speed railway bridges are erected, ballast is still laid first and then sleepers and rails are laid on the ballast. The ballast is a layer of gravel laid between the track and the roadbed. The weight of the train passing on the track is distributed through the contact between the gravels. At the same time, the gaps in the ballast can also guide rainwater out of the ballast and into the drainage ditch opened on the bridge, ensuring the safety of the train when running.

[0004] However, since the ballast is under pressure for a long time, the gaps between the stones at the lower end are easily embedded with smaller gravel, resulting in the weakening of the drainage effect of the ballast. Moreover, replacing the ballast placed on the bridge is extremely labor-intensive.

[0005] In view of the above problems, a technical solution is proposed to extend the drainage effect of the ballast laid on the prefabricated box girder. Utility Model Content

[0006] The utility model aims to solve the problems in the prior art and proposes a high-efficiency drainage prefabricated box beam.

[0007] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a prefabricated box girder with high-efficiency drainage, including a bridge body, a roadbed surface on which ballast can be laid, the bridge body is provided with a plurality of drainage outlets connecting the roadbed surface with the outside of the bridge body from top to bottom, and a plurality of air inlets facing the ballast are respectively provided on both sides of the ballast, the air inlets are opened on both sides of the bridge body, and the air inlets are arranged inclined from bottom to top toward the ballast.

[0008] The utility model is further configured as follows: the bridge body is fixedly connected with maintenance walkways on both sides of the roadbed surface, an air guide groove is arranged between the maintenance walkway and the roadbed surface, the opening of the air inlet close to the roadbed surface is formed below the maintenance walkway, and the air guide groove is formed with a guide surface for guiding the air blown out from the air inlet to blow laterally toward the ballast.

[0009] The utility model is further configured as follows: the height from the notch of the air guide groove to the roadbed surface is less than the distance from the upper end surface of the rail laid on the shell to the roadbed surface.

[0010] The utility model is further configured as follows: a wind deflector is provided on the bridge body extending downwardly on one side of the openings of the plurality of air inlets away from the roadbed surface.

[0011] The utility model is further configured as follows: a plurality of reinforcing ribs are arranged between the side of the air guide plate away from the air inlet and the bridge body.

[0012] The utility model is further configured as follows: two symmetrically arranged permeable plates are fixedly provided on the bridge body, the permeable plates are provided between a plurality of drainage ports and the ballast, the permeable plates are provided with a plurality of openings for blocking stones in the ballast from passing through them, and the height of the upper end surface of the permeable plate from the roadbed surface is greater than the thickness of the ballast.

[0013] In summary, the utility model has the following beneficial effects: utilizing the negative pressure generated during the rapid running of the train to generate air that flows rapidly toward the ballast from the air inlet, utilizing the high-speed gas flow to carry away the water droplets in the gap and blow away the internal gravel, thereby effectively alleviating the situation in which the drainage effect of the ballast is rapidly reduced due to the continuous accumulation of gravel at the bottom of the ballast. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 The structure of the utility model is shown in FIG. Figure 1 ;

[0015] Figure 2 The structure of the utility model is shown in FIG. Figure 2 ;

[0016] Figure 3 for Figure 2 The enlarged view of point A in the middle;

[0017] Figure 4 The structure of the utility model is shown in FIG. Figure 3 .

[0018] In the figure: 1. Bridge body; 11. Roadbed surface; 12. Air inlet; 13. Wind guide plate; 2. Maintenance walkway; 21. Guide surface; 3. Permeable board. DETAILED DESCRIPTION

[0019] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside" and "outside" indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention. Obviously, the embodiments described are only some embodiments of the present invention, rather than all embodiments.

[0020] Highly efficient drainage prefabricated box beams, such as Figures 1 to 3As shown, the bridge body 1 includes a bridge body 1. In this specific embodiment, after the bridge body 1 is formed by casting, the bridge body 1 is jointly erected in the air through two bridge piers. In order to carry two trains at the same time, the bridge body 1 is provided with a roadbed surface 11 for laying ballast. After the ballast is laid, sleepers and rails are laid on the ballast. In order to allow rainwater flowing from the gaps in the ballast to be discharged from the roadbed surface 11, the bridge body 1 is provided with a plurality of drainage outlets connecting the roadbed surface 11 with the outside of the bridge body 1 from top to bottom. In order to effectively clean up the gravel in the ballast caused by the crushing of stones, a plurality of air inlets 12 facing the ballast are respectively provided on both sides of the ballast. The air inlets 12 are opened on both sides of the bridge body 1. The air inlets 12 are arranged obliquely from bottom to top toward the ballast. In this specific embodiment, the air inlets 12 and the drainage outlets have the same structure.

[0021] Practical effect: By utilizing the negative pressure generated during the rapid travel of the train, air is generated from the air inlet 12 to flow rapidly toward the ballast, and the high-speed gas flow is utilized to carry away the water droplets in the gap and blow away the internal gravel, thereby effectively alleviating the situation in which the drainage effect of the ballast is rapidly reduced due to the continuous accumulation of gravel at the bottom of the ballast. At the same time, the ballast can be quickly dried by the flow of high-speed gas, so that water can flow to the roadbed surface 11 faster, thereby improving the drainage efficiency of the prefabricated box girder.

[0022] like Figures 1 to 3 As shown, specifically, the bridge body 1 is fixedly connected with an inspection walkway 2 on both sides of the roadbed surface 11, and the inspection walkway 2 is also formed by casting. In this specific embodiment, it is cast as a whole with the bridge body 1. An air guide groove is arranged between the inspection walkway 2 and the roadbed surface 11, and the opening of the air inlet 12 close to the roadbed surface 11 is formed below the inspection walkway 2. The air guide groove is formed with a guiding surface 21 for guiding the air blown out from the air inlet 12 to blow laterally toward the ballast. The height from the groove of the air guide groove to the roadbed surface 11 is smaller than the distance from the upper end surface of the rail laid on the shell to the roadbed surface 11. Through the guidance of the air guide groove, the high-speed air gushing out from the air inlet 12 can be blown more on the ballast. At the same time, due to the shielding of the inspection walkway 2, the disturbance of the high-speed air gushing out from the air inlet 12 by the flowing air in the upper layer of the inspection walkway 2 is effectively reduced.

[0023] like Figure 2 as well as Figure 3 As shown, since it is necessary to make the drainage of the bridge body 1 more convenient and the roadbed surface 11 flat, in order to prevent the stones on the bridge body 1 from rolling down along the air inlet 12, two symmetrically arranged permeable plates 3 are fixedly provided on the bridge body 1. The permeable plates 3 are arranged between a plurality of drainage ports and the ballast. The permeable plates 3 are provided with a plurality of openings for blocking the stones in the ballast from passing through them. The height of the upper end surface of the permeable plates 3 from the roadbed surface 11 is greater than the thickness of the ballast.

[0024] like Figure 3 as well as Figure 4As shown, in order to further increase the flow rate of the gas gushing out from the air inlet 12 when a train passes by, the bridge body 1 is provided with an air guide plate 13 extending downward on the side of the opening of the air inlet 12 away from the roadbed surface 11, and a plurality of reinforcing ribs are provided between the side of the air guide plate 13 away from the air inlet 12 and the bridge body 1.

[0025] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.

[0026] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A high-efficiency drainage prefabricated box girder, comprising a bridge body, on which a roadbed surface for laying ballast is arranged, characterized in that: The bridge body is provided with a plurality of drainage outlets connecting the roadbed surface and the outside of the bridge body from top to bottom. The two sides of the ballast are respectively provided with a plurality of air inlets facing the ballast. The air inlets are provided on both sides of the bridge body and are arranged inclined from bottom to top toward the ballast.

2. The high-efficiency drainage prefabricated box girder according to claim 1 is characterized in that: The bridge body is fixedly connected with maintenance walkways on both sides of the roadbed surface, and an air guide groove is arranged between the maintenance walkway and the roadbed surface. The opening of the air inlet close to the roadbed surface is formed below the maintenance walkway, and the air guide groove is formed with a guiding surface for guiding the air blown out from the air inlet to blow horizontally toward the ballast.

3. The high-efficiency drainage prefabricated box beam according to claim 2 is characterized in that: The height from the notch of the air guide groove to the roadbed surface is less than the distance from the upper end surface of the rail laid on the shell to the roadbed surface.

4. The high-efficiency drainage prefabricated box beam according to claim 2 is characterized in that: The bridge body is provided with a wind deflector extending downwardly on one side of the openings of the plurality of air inlets away from the roadbed surface.

5. The high-efficiency drainage prefabricated box beam according to claim 4 is characterized in that: A plurality of reinforcing ribs are arranged between the side of the air guide plate away from the air inlet and the bridge body.

6. The high-efficiency drainage prefabricated box beam according to claim 2 is characterized in that: Two symmetrically arranged permeable plates are fixedly mounted on the bridge body. The permeable plates are arranged between a plurality of drainage ports and the ballast. The permeable plates are provided with a plurality of openings for blocking stones in the ballast from passing through them. The height of the upper end surface of the permeable plate from the roadbed surface is greater than the thickness of the ballast.